How to Develop Work Breakdown Structures
|
|
|
- Edwina Lambert
- 10 years ago
- Views:
Transcription
1 How to Develop Work Breakdown Structures Michael D. Taylor
2 Copyright by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in any form or by any means -- graphic, electronic, or mechanical, including photocopying, recording, taping, or information storage and retrieval system -- without written permission of Michael D. Taylor, Systems Management Services ( 2
3 P a g e 3 WORK BREAKDOWN STRUCTURES A Work Breakdown Structure is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. 1 A Work Breakdown Structure (WBS) is a fundamental project management technique for defining and organizing the total scope of a project, using a hierarchical tree structure. The first two levels of the WBS (the root node and Level 2) define a set of planned outcomes that collectively and exclusively represent 100% of the project scope. At each subsequent level, the children of a parent node collectively and exclusively represent 100% of the scope of their parent node. A well-designed WBS describes planned outcomes instead of planned actions. Outcomes are the desired ends of the project, such as a product, result, or service, and can be predicted accurately. Actions, on the other hand, may be difficult to predict accurately. A well-designed WBS makes it easy to assign any project activity to one and only one terminal element of the WBS. TYPES OF WORK BREAKDOWN STRUCTURES Even though the term Work Breakdown Structure has been used as a label for all project scope hierarchical diagrams, there are, in practice, many types other than deliverable oriented structures. 1 A Guide to the Project Management Body of Knowledge, (Newton Square, PA: Project Management Institute, 2004).
4 P a g e 4 Verb-oriented WBS: a task-oriented WBS defines the deliverable of project work in terms of the actions that must be done to produce the deliverable. The first word in a given WBS element usually is a verb, such as, design, develop, optimize, transfer, test, etc. Noun-oriented WBS: a deliverable-oriented WBS defines project work in terms of the components (physical or functional) that make up the deliverable. In this case, the first word in a given WBS element is a noun, such as, Module A, Subsystem A, Automobile Engine, Antenna, etc. Since the nouns are usually parts of a product, this WBS type is sometimes called a Product Breakdown Structure (PBS). Deliverable-oriented WBS structures are the preferred type according to PMI s definition. Time-phased WBS: a time-phased WBS is one that is used on very long projects. It breaks the project into major phases instead of tasks. In this type, a rolling wave approach is adopted and only the near-term phase is planned in detail. Other WBS types may include organization-types, geographical-types, cost breakdown types, and profit-center types. WBS DESIGN PRINCIPLES The 100% Rule One of the most important WBS design principles is called the 100% Rule. The Practice Standard for Work Breakdown Structures (Second Edition), published by the Project Management Institute (PMI) defines the 100% Rule as follows: The 100% Rule...states that the WBS includes 100% of the work defined by the project scope and captures ALL deliverables internal, external, interim in terms of the work to be completed, including project management. The 100% rule is one of the most important principles guiding the development, decomposition and evaluation of the WBS. The rule applies at all levels within the hierarchy: the sum of the work at the child level must equal 100% of the work represented by the parent and the WBS should not include any work that falls outside the actual scope of the project, that is, it cannot include more than 100% of the work It is important to remember that the 100% rule also applies to the activity level. The work represented by the activities in each work package must add up to 100% of the work necessary to complete the work package.
5 P a g e 5 Planned Outcomes, Not Planned Actions If the WBS designer attempts to capture any action-oriented details in the WBS, he/she will likely include either too many actions or too few actions. Too many actions will exceed 100% of the parent's scope and too few will fall short of 100% of the parent's scope. The best way to adhere to the 100% Rule is to define WBS elements in terms of outcomes or results. This also ensures that the WBS is not overly prescriptive of methods, allowing for greater ingenuity and creative thinking on the part of the project participants. For new product development projects, the most common technique to assure an outcome-oriented WBS is to use a product breakdown structure (PBS). The best way to adhere to the 100% Rule is to define WBS elements in terms of outcomes or results. Feature-driven software projects may use a similar technique which is to employ a feature breakdown structure. When a project provides professional services, a common technique is to capture all planned deliverables to create a deliverableoriented WBS. Work breakdown structures that subdivide work by project phases (e.g. Preliminary Design Phase, Critical Design Phase) must ensure that phases are clearly separated by a deliverable (e.g. an approved Preliminary Design Review document, or an approved Critical Design Review document). Level 2 is the Most Important Of all the levels on a WBS, Level-2 is often the most important because it determines how actual costs and schedule data are grouped for future project cost and schedule estimating. A project manager may find it useful to know how much it took to design (major work element) a product after it had been completed so that the data can be used for future analogous estimating. In other cases, the project manager may want to know how much a major part of the product actually cost after the project was completed. For this a PBS would be used. Level-2 is therefore used to capture actuals from a project for future estimating purposes. The Four Elements in Each WBS Element Each WBS element, when completed should contain the following four items: 1. The scope of work, including any deliverables. 2. The beginning and end dates for the scope of work. 3. The budget for the scope of work. 4. The name of the person responsible for the scope of work. By using a WBS in this manner the project manager can approach a complex project and decompose it into manageable, assignable portions. There is minimal confusion among project members when this technique is used.
6 P a g e 6 Mutually-exclusive Elements In addition to the 100% Rule, it is important that there is no overlap in scope definition between two elements of a WBS. This ambiguity could result in duplicated work or miscommunications about responsibility and authority. Likewise, such overlap is likely to cause confusion regarding project cost accounting. If the WBS element names are ambiguous, a WBS dictionary can help clarify the distinctions between WBS elements It is important that there is no overlap in scope definition between two elements of a WBS. How Far Down? The WBS is decomposed down to the work package level. A work package is the lowest level in the WBS, and is the point at which the cost and schedule for the work can be reliably estimated. 2 A question to be answered in the design of any WBS is when to stop dividing work into smaller elements. If a WBS terminal elements are defined too broadly, it may not be possible to track project performance effectively. If a WBS terminal elements are too granular, it may be inefficient to keep track of so many terminal elements, especially if the planned work is in the distant future. A satisfactory tradeoff may be found in the concept of progressive elaboration which allows WBS details to be progressively refined before work begins on an element of work. An effective limit of WBS granularity may be reached when it is no longer possible to define planned outcomes, and the only details remaining are actions One form of progressive elaboration in large projects is called rolling wave planning which establishes a regular time schedule for progressive elaboration. In reality, an effective limit of WBS granularity may be reached when it is no longer possible to define planned outcomes, and the only details remaining are actions. Unless these actions can be defined to adhere to the 100% Rule, the WBS should not be further subdivided. 2 PMBOK
7 P a g e 7 The 40-Hour Rule of Decomposition Another rule-of-thumb for determining how far down a WBS should be decomposed is called the 40 Hour Rule. Generally, when a project has been decomposed down to an element that has about 40 hours of allocated direct labor, there is no need to decompose further. The 40 Hour Rule is based on a 40-hour work week. Because of this, most WBS diagrams are not symmetrical. Some legs may go down to Level-4 while others may go down to Level-5. The 4% Rule of Decomposition Gary Heerkens suggests a 4% Rule for decomposing a WBS. With this rule a WBS is adequately decomposed when the lowest element is about 4% of the total project. 3 For a 26-week schedule, the lowest element should be about one week. For a $2.6M project, the lowest level should be about $104K. WBS Identification Numbering It is common for WBS elements to be numbered sequentially to reveal the hierarchical structure. For example Rear Wheel identifies this item as a Level 3 WBS element, since there are three numbers separated decimal point. A coding scheme also helps WBS elements to be recognized in any written context. Figure 1 WBS Construction Example The above WBS is from PMI's Practice Standard for Work Breakdown Structures (2nd Edition). This image illustrates an objective method of employing the 100% Rule during WBS construction. 3 Gary R. Heerkens, Project Management (New York, NY: McGraw-Hill Publishers, 2002) p. 103, 122.
8 P a g e 8 Figure 1 shows a WBS construction technique that demonstrates the 100% Rule quantitatively. At the beginning of the design process, the project manager has assigned 100 points to the total scope of this project, which is designing and building a custom bicycle. At WBS Level 2, the 100 total points are subdivided into seven comprehensive elements. The number of points allocated to each is a judgment based on the relative effort involved; it is NOT an estimate of duration. The three largest elements of WBS Level 2 are further subdivided at Level 3, and so forth. The largest terminal elements at Level 3 represent only 17% of the total scope of work. These larger elements may be further subdivided using the progressive elaboration technique described above. In this example, the WBS coding scheme includes a trailing "underscore" character ("_") to identify terminal elements. This is a useful coding scheme because planned project schedule activities (e.g. "Install inner tube and tire") will be assigned to terminal elements instead of parent elements. It is recommended that WBS design be initiated with interactive software (e.g. a spreadsheet) that allows automatic rolling up of point values. Another recommended practice is to discuss the point estimations with project team members. This collaborative technique builds greater insight into scope definitions, underlying assumptions, and consensus regarding the level of granularity required to manage the project. COMMON PITFALLS AND MISCONCEPTIONS A WBS is not an exhaustive list of work. It is instead a comprehensive classification of project scope. A WBS is not a project plan or a project schedule and it is not a chronological listing. It is considered poor practice to construct a project schedule (e.g. using project management software) before designing a proper WBS. This would be similar to scheduling the activities of home construction before completing the house design. Without concentrating on planned outcomes, it is very difficult to follow the 100% Rule at all levels of the WBS hierarchy. It is not possible to recover from an improperly defined WBS without starting over, so it is worthwhile to finish the WBS design before starting a project plan or project schedule. A WBS is not an organizational hierarchy. Some practitioners make the mistake of creating a WBS that shadows the organizational chart. While it is common for responsibility to be assigned to organizational elements, a WBS that shadows the organizational structure is not descriptive of the project scope and is not outcomeoriented.
9 P a g e 9 Short-term memory capacity should not dictate the size and span of a WBS tree structure. Some reference material suggests that each WBS level be limited to 5-9 elements because that is a theoretical limit to short-term memory. It is far more important to construct a logical grouping of planned outcomes than to worry about the limits of short-term human memory. WBS updates, other than progressive elaboration of details, require formal change control. This is another reason why a WBS should be outcome-oriented and not be prescriptive of methods. Methods can and do change frequently, but changes in planned outcomes require a higher degree of formality. If outcomes and actions are blended, change control may be too rigid for actions and too informal for outcomes. WBS Checklist The top element of the WBS is the overall deliverable of the project, and all stakeholders agree with it. The first two levels of the WBS (the root node and Level 2) define a set of planned outcomes that collectively and exclusively represent 100% of the project scope. The WBS elements are defined in terms of outcomes or results. (Outcomes are the desired ends of the project, and can be predicted accurately). Each WBS element has an identification number assigned which identifies its relative position within the structure. The WBS encompasses everything that will ultimately comprise the project deliverable, and all deliverables in the project are included. Each WBS element contains the following four items: The scope of work, including any deliverables. The beginning and end dates for the scope of work. The budget for the scope of work. The name of the person responsible for the scope of work. There is no overlap in scope definition between two elements of a WBS. The WBS is not a project plan or a project schedule, and it is not a chronological listing. In the judgment of all parties involved, the WBS has been decomposed and it is no longer possible to define planned outcomes--the only details remaining are actions. The WBS is not an exhaustive list of work. It is instead a comprehensive classification of project scope. The WBS is not an organizational hierarchy.
10 P a g e 10 In the judgment of all parties involved, the WBS is neither over-simplified or overly complex. It provides an adequate graphical or outline form for viewing the overall scope of the project. Where to Get More Information Carl L. Pritchard. Nuts and Bolts Series 1: How to Build a Work Breakdown Structure. ISBN Dennis P. Miller, Visual Project Planning & Scheduling, Second Edition (2002). ISBN (Note: This e-book is essential a facilator's guide for planning a project based on the WBS.) Gary R. Heerkens. Project Management. (New York, NY: McGraw-Hill Publishers, 2002). ISBN Gregory T. Haugan. Effective Work Breakdown Structures (The Project Management Essential Library Series). ISBN Project Management Institute. Project Management Institute Practice Standard for Work Breakdown Structures, Second Edition (2006). ISBN (Note: The Second Edition is an extensive re-write of the Practice Standard). Robert Wysocki. Effective Project Management: Traditional, Adaptive, Extreme. Indianapolis, IN: Wiley Publishing, 2003.
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Applying the Work Breakdown Structure to the Project Management Lifecycle
Applying the Work Breakdown Structure to the Project Management Lifecycle Introduction Shelly A. Brotherton, PMP; Robert T. Fried, PMP; Eric S. Norman, PMP, PgMP Today, Project Managers are more frequently
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Time Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK Lewis Gray, Ph.D., PMP Abelia Fairfax, Virginia USA www.abelia.com Copyright 2002 by Abelia Corporation. All rights reserved
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
How to Craft a World-Class Work Breakdown Structure
How to Craft a World-Class Work Breakdown Structure Laura Miller, PMP [email protected] 1 Copyright Copyright 2012 2012 Hewlett-Packard Development Development Company, Company, L.P. The L.P. information
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
Project Time Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
IT/Software Project Management Core Functions
IT/Software Project Management Core Functions By: Prof. Dr. Eng. Ghazy Assassa, CMC-IMC Certified Management Consultant, Institute of Management Consultancy, UK Email: [email protected] Mobile: 0502862400
Adapted from slides by John Musser
Adapted from slides by John Musser 1 What s the difference? Plan Identify activities. No specific start and end dates. Estimate Determine the size and duration of activities. Schedule Add specific start
What is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
Chapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
Deciding the work to be Performed (Work Breakdown Structure)
Deciding the work to be Performed (Work Breakdown Structure) Goals of the Unit Understanding the transition from project goals to the project schedule Introducing the Work Breakdown Structure notation
Unit 06 Developing the Work Breakdown Structure
Unit 06 Developing the Work Breakdown Structure April 2007 Project Management Wilhelm F. Neuhäuser IBM Corporation 2007 Agenda Unit 6: Developing the Work Breakdown Structure Objectives Value of the WBS
A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE
A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE PMI Standards Committee William R. Duncan, Director of Standards Project Management Institute 130 South State Road Upper Darby, PA 19082 USA Library
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems The Work Breakdown Structure (WBS) is the foundation for project planning and control. It is the connecting
Understanding risk exposure using multiple hierarchies. Introduction
Understanding risk exposure using multiple hierarchies David Hillson PhD PMP FAPM FIRM MCMI FRSA Director, Risk Doctor & Partners Introduction Risk management is recognised as an essential contributor
Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 7 Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Credits 2 This slides are largely based on Prof. John Musser class
Work Breakdown Structures
Australian Cost Engineering Society Work Breakdown Structures Getting the fundamentals right Malcolm Sawle Melbourne February 2011 AGENDA Introduction Definitions Uses of a WBS WBS Development Process
pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Project Managing to Support Change. Cathryn Stam, PMP Tina Salaris, RN, PMP
Project Managing to Support Change Cathryn Stam, PMP Tina Salaris, RN, PMP Project Managing to Support Change Change is a constant in life People by nature do not like change Whether redesigning processes
PRINCE2, the PMBOK Guide and ISO 21500:2012. Klas Skogmar. AXELOS.com
PRINCE2, the PMBOK Guide and ISO 21500:2012 Klas Skogmar AXELOS.com White Paper September 2015 Contents Introduction 3 Relationships between PRINCE2, the PMBOK Guide and ISO 21500 4 Major differences between
Managing the Project Schedule
Managing the Project Schedule Project Skills Paul Newton www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2015. All Rights Reserved ISBN 978-1-62620-981-3
Manual on Training Preparation
Project on Improvement of Local Administration in Cambodia Three Steps of Training Preparation Step 1: Work Breakdown Structure Step 2: Schedule Step 3: Budget Table of Contents Three Steps of Training
A Comparison of PMI s PMBOK Guide Versions 4 & 3
PM WORLD TODAY FEATURED PAPER MAY 2009 A Comparison of PMI s PMBOK Guide Versions 4 & 3 By Germán Bernate The Project Management Institute PMI announced on December 31, 2008 the availability of PMBOK Version
Software Project Management I
Software Project Management I Dr. Jong Yih Kuo Dr. Chien-Hung Liu Computer Science and Information Engineering National Taipei University of Technology Course Schedule Time Topic Document 18:10~18:55 (45
Project Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
PMP Exam Prep Training - 5 Days
PMP Exam Prep Training - 5 Days (Based on the PMBOK Guide, 5 th Edition) Course Length: 5 Days Course Abstract: This workshop has a primary and a secondary goal. The primary goal is to prepare participants
Lecture Slides for Managing and Leading Software Projects. Chapter 5: Project Planning Techniques
Lecture Slides for Managing and Leading Software Projects Chapter 5: Project Planning Techniques developed by Richard E. (Dick) Fairley, Ph.D. to accompany the text Managing and Leading Software Projects
Project Management Institute STANDARD
Project Management Institute STANDARD Project Management Institute Practice Standard for Work Breakdown Structures Project Management Institute Practice Standard for Work Breakdown Structures Project Management
Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them
Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC
Creating a Publication Work Breakdown Structure
Creating a Publication Work Breakdown Structure By: Victor Clough To determine level of quality, estimate costs, assign resources and schedule milestones for your documentation project, you need precise
LECTURE 11: PROCESS MODELING
LECTURE 11: PROCESS MODELING Outline Logical modeling of processes Data Flow Diagram Elements Functional decomposition Data Flows Rules and Guidelines Structured Analysis with Use Cases Learning Objectives
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION Robert T. Hans Software Engineering Department, Tshwane University of Technology, Pretoria, South Africa [email protected] ABSTRACT
Introduction to Project Management ECE 480. Erik Goodman
Introduction to Project Management ECE 480 Erik Goodman What is Project Management? a method for organizing tasks a structured framework to help a group work productively tools to aid in task sequencing,
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
Introductory Project Management Module. Mansfield Adult Continuing Education 1 Inc
Managing Your Project: Planning & Time Introductory Project Management Module Mansfield Adult Continuing Education 1 Inc Project Management Learning Objectives Develop a working knowledge of basic project
PMP Project Management Professional Study Guide, Third Edition
PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management
Project Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION
Syed Quadri, PMP Region 5 RPM MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION 0 Project Management Background Topics to be covered: Benefits of using PM tools PMI and PMBOK Strategic Project Management
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: [email protected]
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery
Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule
1 (Image) 2 The process required to manage timely completion of the project. Project time management start with planning by the project management team (not shown as a discrete process). In small project,
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.
Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Project Planning. Project Planning. Project Planning MGMT 409 PROJECT MANAGEMENT PROJECT PLANNING: WORK BREAKDOWN STRUCTURE (WBS) (SLIDE SET 05)
MGMT 409 PROJECT MANAGEMENT PROJECT PLANNING: WORK BREAKDOWN STRUCTURE (WBS) (SLIDE SET 05) Dr. Ömer Yağız Department of Business Administration EMU Project Planning Plans are only good intentions unless
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Developing Work Breakdown Structures
Developing Work Breakdown Structures International Cost Estimating & Analysis Association June 2014 Neil F. Albert MCR, LLC [email protected] 703-506-4600 2014 MCR, LLC Distribution prohibited without express
SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE
SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE ABSTRACT Robert T. Hans Tshwane University of Technology, Pretoria, South Africa [email protected] Software project
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita
Metadata-Based Project Management System. A Case Study at M-Files Corporation Iulia Adomnita University of Tampere School of Information Sciences Computer Science M.Sc. Thesis Supervisors: Timo Poranen,
Partnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
Advanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
Using Microsoft SharePoint for Project Management
ASPE IT Training Using Microsoft SharePoint for Project Management A WHITE PAPER PRESENTED BY ASPE www.aspe-it.com 877-800-5221 Using Microsoft SharePoint for Project Management A modern Project Management
Project Delivery Process Overview
New Jersey Department of Transportation Project Delivery Process Overview Presented by the Program Management Office January, 2012 Project Delivery Process Overview The New Jersey Department of Transportation
PROJECT TIME MANAGEMENT
PROJECT TIME MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_time_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
Mindjet MindManager : A Vital Solution for Improved Project Management
Timothy G. Bolwerk, PMP [email protected] Mindjet MindManager : A Vital Solution for Improved Project Management Project managers wrestle with mountains of information. Throughout the course of
ITIL Service Lifecycles and the Project Manager
1 ITIL Service Lifecycles and the Project Manager The intersection of IT Service and Project Delivery Presented to: Kansas City Mid-America PMI Chapter Mark Thomas January 17, 2011 1 Agenda 2 Introduction
STARTING A PROJECT. Sergey V. Nesterov MD, PhD, PMP
STARTING A PROJECT Sergey V. Nesterov MD, PhD, PMP QUESTIONS to ask at the start 1. What is the situation? 2. What do you need to do? 3. Why do you need to do it? 4. What will you do? 5. How will you do
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
A COMPARISON OF PRINCE2 AGAINST PMBOK
Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the
Project Life Cycles and the WBS Part One: Typical Project Life Cycles
Project Life Cycles and the WBS Part One: Typical Project Life Cycles If you have studied the basics of project planning, you surely have learned about Work Breakdown Structures. If, for some reason, you
Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis
Expert Reference Series of White Papers Intersecting Project Management and Business Analysis 1-800-COURSES www.globalknowledge.com Intersecting Project Management and Business Analysis Daniel Stober,
PMLead. Project Management Professional. edition. Based on PMBOK Guide 4 th. www.pmlead.net
PMLead Project Management Professional Based on PMBOK Guide 4 th edition www.pmlead.net SECTION II Chapter 3 Project Management Processes Chapter 3 Project Process Groups A process is a set of interrelated
Course Overview. Course Learning Objectives
TCMG-506-6R1 University of Bridgeport Technology Management Advanced Program and Project Management ---------------------------------------------------------------------------------------------------------------------
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Module 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
SWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
D6 INFORMATION SYSTEMS DEVELOPMENT. SOLUTIONS & MARKING SCHEME. June 2013
D6 INFORMATION SYSTEMS DEVELOPMENT. SOLUTIONS & MARKING SCHEME. June 2013 The purpose of these questions is to establish that the students understand the basic ideas that underpin the course. The answers