The Two Most Useful Earned Value Metrics: the CPI and the TCPI

Size: px
Start display at page:

Download "The Two Most Useful Earned Value Metrics: the CPI and the TCPI"

Transcription

1 PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was originally published in the December 2008 issue of Crosstalk, and the Spring 2009 edition of the Measurable News, published by the PMI College of Performance Management (PMI-CPM). This paper is included here with the permission of the authors, who are copyright holders. The Two Most Useful Earned Value Metrics: the CPI and the TCPI By Quentin W. Fleming and Joel M. Koppelman Primavera Systems, Inc. The Project Management Institute (PMI) has just released the Fourth Edition to their world standard on project management: A Guide to the Project Management Body of Knowledge, the PMBOK Guide. Many new features have been added to this massive document among them new coverage of an earned value metric called the To-Complete Performance Index or simply the TCPI. What is the TCPI and why is it important? This article describes its purpose and utility. Whenever a project commits to the employment of earned value to help manage their effort, they are suddenly inundated with a windfall of performance metrics which are available in no other project management technique. New acronyms suddenly emerge: PV, EV, AC, SV, SPI, CV, CPI, BAC, EAC, TCPI, and on and on. i While all of these performance indicators can have value to any project, two EVM metrics in particular are critical to projects. They are the CPI and the TCPI. The CPI (Cost Performance Index) tells us what we have accomplished for what we have already spent. Did we stay within the budget, or did we overrun? By contrast, the TCPI (To-Complete Performance Index) focuses on future work: what performance levels we must achieve on the remaining work in order to meet our financial commitment to management. While most practitioners of earned value understand the utility of the CPI, most have rarely ever used the TCPI. What a pity, for the TCPI when used in conjunction with the CPI provides a powerful set of tools in the management of a single project, a program, or a full portfolio of projects. PM World Today is a free monthly ejournal - Subscriptions available at Page 1

2 Earned Value Management (EVM) the ten requirements. As a general rule, whenever a project manager makes the decision to employ earned value in the management of a project, that choice ideally should be supported by management, the stakeholders at all levels. Stakeholders must want to know the full truth. The reason: EVM performance data can be available to everyone working the project: the functions, senior management, the paying customers, all parties who have a vested interest in the success of the project. As long as everyone has a rudimentary understanding of what the EVM data means, everyone connected to the project knows what everyone else is doing. Thus, it is imperative that there be a management buy-in whenever a project manager elects to employ EVM on a project. The commitment to employing EVM requires both the compliance with certain basic requirements, and discipline on the part of everyone supporting the project. Based on our experience, we have listed below ten key requirements which must be met in order to successfully implement EVM. Some find these requirements overwhelming. See for yourself. These requirements are: 1. EVM requires that the project be fully understood, defined, and scoped to include 100% of the project effort. You need to know what constitutes 100% of the work in order to measure progress along the way. 2. EVM requires that the defined scope be decomposed, broken down into major management tasks, which are selected as points of management control ii, then planned and scheduled down to the detailed work package level. 3. EVM requires that an integrated and measurable project baseline be authorized, relating the scope of work directly to an achievable budget, then locked into a specific time-frame for performance measurement. It s called: bottom-up planning. 4. EVM requires that only authorized and budgeted work be accomplished. The effort being worked must be tightly controlled. Scope creep cannot be allowed. All changes must be managed, and not worked until specifically authorized by the project manager. 5. EVM requires that physical performance be measured (the earned value) using previously defined schedule metrics. 6. EVM requires that the values earned be related to the planned values to reflect performance against the project baseline. Earned value less the planned value represents a variance from the baseline plan. PM World Today is a free monthly ejournal - Subscriptions available at Page 2

3 7. EVM requires that the actual costs being reported be consistent with the earned value being measured, to allow for an accurate portrayal of cost performance. The relationship of values earned to actual costs reflects the true cost performance. Earned value less actual costs provides cost performance. 8. EVM requires that forecasts be made periodically (weekly, monthly) as to how much time, and how much money it will take to complete 100% of the project. 9. EVM requires that a full disclosure of actual results be made to all persons who have a vested interest in the project. All stakeholders will receive the same actual performance results. Only one set of books is allowed. 10. EVM requires that project management, in conjunction with management at all levels, and customer stakeholders, decide on the appropriate actions to be taken to stay within authorized project expectations. These ten requirements are what is needed to successfully implement earned value on any project. To the authors, these requirements constitute nothing more than following fundamental project management best practices. Now let us discuss the two, in the opinion of the authors, most important earned value indicators: the Cost Performance Index (CPI) reflecting completed performance, and the To-Complete Performance Index (TCPI) with a focus on the required future performance. What is a CPI (Cost Performance Index), and how is it used? The EVM Cost Performance Index (CPI) is a reflection of project cost efficiency. The CPI relates the physical work accomplished expressed in its budgeted value, against the actual costs incurred to accomplish the performed work. Budgets can be set with various monetary values, hours, deliverables, anything that can be measured. The issue: are we staying on target, under-running, or perhaps overrunning our costs? This concept is portrayed graphically in Figure 1. PM World Today is a free monthly ejournal - Subscriptions available at Page 3

4 Good = greater than Perfect CPI = Poor = less than Perfect EVM Cost Performance Index (CPI) = 1.0 (for every $1.00 in cost actuals you get $1.00 in earned value) Figure 1: Monitoring Earned Value Cost Performance Index (CPI) Perfect cost performance would be defined as achieving a CPI of 1.0. For every dollar spent we would get an earned value equal to one dollar. Sometimes we do better, sometimes worse. This is a particularly critical metric to track for performance less than 1.0 is a reflection of excessive costs spent against budget. Initial overruns are typically non-recoverable. Think about it: in order to recover an overrun you must under-run future work. Rarely does this happen. The same conditions which may have caused the overrun in the first place are likely to occur again and again. Sometimes the CPI will reflect values over 1.0, suggesting that an under-run of costs is occurring. Care must be taken when actuals reflect an under-run of costs to budget. Oftentimes this condition is simply the result of costs which are lagging, slow to be recorded in the organizational cost ledger. For example: we measure the earned value and give full credit, but the related costs are not reflected in the cost ledger. Reason: many/most of the project work may be performed by outside purchased labor, people who are not part of the internal labor system. Thus there can be a time mismatch between the earned value measured, and the actual payment of the purchased labor invoices. The payment of invoices generally takes more time than the recording of labor. PM World Today is a free monthly ejournal - Subscriptions available at Page 4

5 Under runs of costs are rare. And if artificially caused by lagging actual costs, the positive results can hide or offset problems that need management attention. It takes organizational discipline to make sure that earned value credits match the actual costs. Why is the CPI so important? Answer: because past performance can be used to accurately determine requirements for final performance, in order to meet financial goals. The cumulative (from the beginning) CPI has been shown to stabilize from about the 20% completion point of project performance. Empirical scientific studies by the United Sates Department of Defense on 155 actual contracts has shown that at the 20% point of project completion, the final projected results will only change by plus or minus 10%. iii What a finding! What useful data. In practical terms, one can immediately take the total authorized budget (BAC), divide it by the cumulative CPI and project the total costs of a project with an accuracy of plus or minus 10%. If management doesn t like the final cost projection, then corrective action can be taken to change the forecasted results. Few project management techniques give a comparable early-warning signal. This formula the BAC/Cumulative CPI = EAC can be used on the total project, or any sub-project, or integrated project teams to predict final results on their work. The CPI metric can be used to track periodic results (monthly, weekly, daily), or the cumulative position to see the long-term performance trends. What is a TCPI (To-Complete Performance Index), and how is it used? Whereas the CPI is an indicator of past cost performance, the TCPI has its focus on future performance. At issue: what will it take to meet the goals set by management? The TCPI works in conjunction with the CPI, and is conceptually illustrated in Figure 2. The CPI can be thought of as sunk-costs, whatever the results they cannot be altered. In the illustration shown, the cumulative CPI is at.75, for every dollar spent we only earned 75 cents of project work. If the project is exactly 50% complete, in order to stay within management s budget, we must accomplish $1.25 for every dollar in the future. Will this likely happen? Questionable at best, but highly unlikely. Opportunities for improvements are illustrated by use of the TCPI. PM World Today is a free monthly ejournal - Subscriptions available at Page 5

6 Sunk Costs Status at 50% Complete Opportunity Costs TCPI 1.00 Baseline Cumulative CPI.75 Figure 2: The Relationship of Cumulative CPI versus TCPI The formula for the TCPI is: the [Work Remaining] (defined as total Budget less the earned value) divided by the [Funds Remaining]. Note in Figure 3 there are two scenarios for Funds Remaining. iv Funds remaining will focus initially on the authorized budget. Management will track performance against what it has authorized in the form of an official budget. However, once it becomes obvious that the budget is no longer achievable, the next question from management is: how much money will it cost to complete this job, called the estimate at completion (EAC). The project then stops work and makes a new forecast of what is needed to finish the job. Preparing a new EAC forecast can get emotional. Unrealistic optimism sometimes takes over, at the expense of realism. It is not uncommon for projects, when making a new EAC forecast to assume that everything will suddenly go right, and that all project risks are behind them. Thus an initial EAC may be unrealistic, unachievable. Piecemeal EACs are often the norm, where the EAC projection goes up each month as actual performance is known. PM World Today is a free monthly ejournal - Subscriptions available at Page 6

7 Using Figure 2 as an example, would an EAC requiring a future TCPI of 1.25, or 1.10 be achievable? Probably not. More likely, a TCPI of 1.0 or.90 would be reasonable. But it is painful to admit the full value of an EAC, having just acknowledged that the BAC is no longer valid. TCPI using Management s Budget at Completion Work Remaining (BAC - EV) = TCPI (BAC) Funds Remaining (BAC - AC) TCPI using the Project Manager s Estimate at Completion Work Remaining (BAC - EV) = TCPI (EAC) Funds Remaining (EAC - AC) Figure 3: Two To-Complete Performance Index (TCPI) formulas In Summary Employing the EVM technique can present a project with data not available with any other management tool. And while each metric can be useful, the authors are of the opinion that the two metrics described above are particularly useful in the management of any project, or program, or a portfolio of projects. PM World Today is a free monthly ejournal - Subscriptions available at Page 7

8 End Notes 1. This article first appeared in the December 2008 issue of Crosstalk Magazine. 2. All terms used in this article are consistent with the A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fourth Edition, published in December 2008 by the Project Management Institute, Newtown Square, PA, USA. The terms are: Planned Value, Earned Value, Actual Costs, Schedule Variance, Schedule Performance Index, Cost Variance, Cost Performance Index, Budget at Completion, Estimate at Completion, and To-Complete Performance Index. 3. The points of management control are sometimes called project teams, subprojects, or Control Account Plans (CAPs) depending on the organization. 4. Dr. David S. Christensen, Using Performace Indices to Evaluate the Estimate at Completion, The Journal of Cost Analysis of Cost Estimating and Analysis, Spring 1994, page Figures used in this article are inspired from the book Earned Value Project Management, third edition, Quentin W. Fleming and Joel M. Koppelman, published by the Project Management Institute, Newtown Square, Pennsylvania, PM World Today is a free monthly ejournal - Subscriptions available at Page 8

9 About the Authors: Quentin Fleming Author Quentin W. Fleming is a management consultant specializing in earned value. He has been a consultant to the staff at Primavera Systems, Inc. since Quentin was on the core team which updated the Project Management Institute s (PMI) PMBOK Guide Fourth Edition, released in December His personal website is Joel Koppelman Author Joel M. Koppelman is the cofounder and Chief Executive Officer (CEO) of Primavera Systems, Inc. His corporate website is Fleming and Koppelman are the co-authors of Earned Value Project Management, published in 1996 by the Project Management Institute (PMI). The Third Edition of this book was released in the fall of Over 80,000 copies have been sold by PMI worldwide. PM World Today is a free monthly ejournal - Subscriptions available at Page 9

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

Project Cost Management

Project Cost Management Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

The To Complete Performance Index

The To Complete Performance Index The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter 1.0 +1 405 364 1594 waltlipke@cox.net www.earnedschedule.com Index 1.3 1.2 TCPI vs CPI TCPI

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective

More information

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Schedule Adherence a useful measure for project management

Schedule Adherence a useful measure for project management Schedule Adherence a useful measure for project management Walt Lipke PMI Oklahoma City Chapter Abstract: Earned Value Management (EVM) is a very good method of project management. However, EVM by itself

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01 PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Expert Reference Series of White Papers. Importance of Schedule and Cost Control Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Earned Value Management Best Practices

Earned Value Management Best Practices WHITE PAPER Earned Value Management Best Practices Contents Best Practices for EVMS Use...1 Use an EVMS Description and Keep it Up to Date...1 Use EVMS on Every Project...2 When to Use EVMS on a Program...3

More information

Over the last three decades, a proven but yet

Over the last three decades, a proven but yet Earned Value Project Management A Powerful Tool for Software Projects Quentin W. Fleming and Joel M. Koppelman Primavera Systems, Inc. Earned value can provide any project manager with an early warning

More information

What is the Health of my Project?

What is the Health of my Project? WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

Earned Schedule Leads to Improved Forecasting

Earned Schedule Leads to Improved Forecasting Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion

More information

Assessing Schedule Performance with Earned Value

Assessing Schedule Performance with Earned Value FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative

More information

Abstract. Earned Value Management Basics

Abstract. Earned Value Management Basics Earned Schedule: A Breakthrough Extension to Earned Value Management Kym Henderson Education Director, Project Management Institute, Sydney Australia Chapter Abstract Earned Schedule (ES) analysis is a

More information

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS The 4 th edition of the Interdisciplinarity in Engineering International Conference Petru Maior University of Tîrgu Mureş, Romania, 2009 PROJECT MOITORIG AD COTROL USIG BURDOW CHARTS Attila Vajda Sysgenic

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

ONCE UPON A TIME there was a young man who wanted to

ONCE UPON A TIME there was a young man who wanted to Earned Value Project Management... an Introduction Earned value is a project management technique that is emerging as a valuable tool in the management of all projects, software projects in particular.

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION. David S. Christensen, Ph.D.

USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION. David S. Christensen, Ph.D. USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION David S. Christensen, Ph.D. College of Business Southern Utah University 351 West, Center Street Cedar

More information

Since 1985, the Test Program Set (TPS) development

Since 1985, the Test Program Set (TPS) development Applying Management Reserve to Software Project Management Walter H. Lipke Oklahoma City Air Logistics Center, Directorate of Aircraft Maintenance, Software Division Today s standard of practice for managing

More information

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

Using Earned Value Management Concepts to Improve Commercial Project Performance

Using Earned Value Management Concepts to Improve Commercial Project Performance Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the

More information

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

Is Poor Project Management a Crime?

Is Poor Project Management a Crime? WHITE PAPER Is Poor Project Management a Crime? Earned Value and the Sarbanes Oxley Act Table of Contents Introduction...1 The Relationship Between SOX and EVMS...2 Earned Value Explained...2 Proper Statistical

More information

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

CVR/IT Consulting LLC

CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com info@cvr-it.com Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value

More information

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource

More information

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

Chapter 5: Project Cost Management

Chapter 5: Project Cost Management Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism

New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism A Presentation at the Third Caribbean & Latin American Conference On Project Management, 21 23 May 2003 Denis F. Cioffi,

More information

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)

More information

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.

More information

plans based on actual cost, schedule and technical progress of work [1, 9].

plans based on actual cost, schedule and technical progress of work [1, 9]. An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan

More information

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by: Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

Metrics for Agile Projects:

Metrics for Agile Projects: Metrics for Agile Projects: Finding the right tools for the job Agile project managers have a wide range of metrics to choose from when it comes to tracking the progress of Agile projects. By understanding

More information

Predicting progress on your project

Predicting progress on your project www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The

More information

Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE

Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE Schedule Adherence and Rework Walt Lipke, PMI Oklahoma City Chapter Abstract. When project performance is such that the product is delivered with expected functionality at the time and price agreed between

More information

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,

More information

A Framework for Project Metrics

A Framework for Project Metrics A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics

More information

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating: , Fourth Edition Parallels between Cost and Time estimating: There are strong parallels between cost estimating and time estimating so you should have experienced some déjà vu when you first read it. In

More information

Chapter 3: Project Cost Management

Chapter 3: Project Cost Management Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...

More information

Project Cost Management

Project Cost Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within

More information

Young Hoon Kwak Associate Professor School of Business The George Washington University

Young Hoon Kwak Associate Professor School of Business The George Washington University Project Management in Government: An Introduction to Earned Value Management (EVM) Improving Performance Series Young Hoon Kwak Associate Professor School of Business The George Washington University Frank

More information

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP) Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office

More information

performance management system that is based on Earned Schedule Management.

performance management system that is based on Earned Schedule Management. The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created

More information

Training Seminars. Description. Core Courses: The core courses consist of the following:

Training Seminars. Description. Core Courses: The core courses consist of the following: Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Earned-Value Benchmarks for Re-baselining Your Project

Earned-Value Benchmarks for Re-baselining Your Project 500 Thoreau Street Concord, MA 01742 USA +978.369.9009 info@newleafpm.com ($39.95 for 4 PDUs; $59.95 for 6 PDUs) Earned-Value Benchmarks for Re-baselining Your Project Handy benchmarks to help you re-baseline

More information

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11. Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management

More information

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study 2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT 7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information