SECTION COST LOADED CRITICAL PATH SCHEDULE
|
|
|
- Ashley Hutchinson
- 9 years ago
- Views:
Transcription
1 SECTION COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in sufficient detail to show a logical sequence in which Contractor proposes to carry out all Work required under this Contract. It is the Contractor s responsibility to effectively plan, schedule, manage, and execute the Work in accordance with Contract Documents. A. Contractor shall generate a cost loaded critical path schedule using the schedule software program in use by the Authority. The Authority uses Primavera P6, Version 7 (P6). The Authority will provide an electronic file that will contain a Primavera P6 schedule development template on or before the Notice to Proceed (NTP). The Contractor shall be required to use this template as it will align with similar data structures within the Authority and Metro P6 databases. B. Contractor shall submit a hard copy of the schedule as well as an electronic computer generated back-up copy in XER format of the Level One Schedule, Baseline CPM Contract Schedule, Current CPM Contract Schedule and any other schedule submittals. The XER electronic file shall be made directly from Primavera P6, Version 7, and shall contain all files of the schedule that can be restored by the Authority for its evaluation and analysis. It is the Contractor s responsibility to ensure that all schedule submittals will be calculated in the Authority s P6 database without variance from hardcopies submitted for review. Any variance from printed reports from the Contractor s P6 environment to the calculated schedule dates within the Authority s P6 production database will be cause for rejection of the submittal. C. All construction schedules should be prepared in a Critical Path Method format capable of delineating specific data dates and physical percent complete as defined below. The level of schedule detail shall be sufficient to clearly identify key subcontractors, sequences of work, inter-relationships and interfaces with other parties and the critical path for completing the work. The Authority has the right to request further breakdown of certain activities as deemed necessary. The Contractor shall also include Authority defined key milestones and activities supporting Metro-provided goods. 1
2 D. Contractor shall incorporate Contract milestones into the CPM Contract Schedule. These are unique zero duration activities containing corresponding dates and logic ties. Designate these activities as start or finish milestones and utilize constraints of "start on or after" or "finish on or before". Each milestone activity will constrain its dependent Work. Assume Notice to Proceed (NTP) is given at day zero, for calculation of constraining dates for milestones. The use of float suppressing date constraints including start on, finish on, mandatory start, and mandatory finish are not allowed within the schedule. E. Float is not for exclusive use or benefit of either the Authority or the Contractor but is an expiring resource available to both parties on a nondiscriminatory basis. Float is used by either party, as needed to meet Contract milestone dates. Contract time extensions for Contract performance will be granted only to extent that delays or disruptions to affected Work paths exceed total float along those paths of the Current CPM Contract Schedule (updated schedule) in effect at time of delay or disruption. These delays or disruptions must also cause end date of Work to exceed current Contract date or milestone date and be beyond control and without fault or negligence of Contractor or any subcontractor at any tier. If delays or disruptions impact an already negative float path, Contractor will not receive a time extension unless and until activity with highest negative float is driven even further negative in accordance with impacting the Contract date or milestone date, and considering concurrency delays set forth in the Contract. F. Use of float suppression techniques such as preferential sequencing or logic, special lead/lag logic restraints, and extended activity times or durations shall be submitted with written justification to obtain the Authority s approval. Use of float time disclosed or implied by use of alternate float suppression techniques shall be shared to proportionate benefit of the Authority and the Contractor. Use of any network technique solely for purpose of suppressing float will be cause for rejection of schedule submittal. G. Planning units Primavera P6,scheduling software supports schedule planning units of Hours, Days, Weeks or Months. The standard time unit applied to the cost/schedule integration system is defined as days. A day as defined within Primavera P6 will span eight hours from 8AM to 5PM for all scheduled activities. Contractor will verify that all schedule start and finish dates reflect these requirements. This requirement will apply to both calendar and working days. If 2
3 for any reason the Contractor will be executing the work for activities beyond the standard specified workday (i.e. Multiple Shifts, planned Overtime, etc.), the Contractor will assign a project specific activity code as per the schedule electronic template to the affected activities. All schedule activities which meet these criteria will be readily identifiable in the Contractor schedule and the Contractor bears the burden to accurately identify all schedule activities which meet this criteria. Upon submission of any schedule update, the Authority will have the ability to effectively identify (filter) for such activities for review and analysis. Failure to accurately identify such activities accurately may result in rejection of the current schedule submittal. H. Schedule network - Use Retained Logic CPM Precedence Diagram Method of scheduling. I. Analyze in detail activities included in CPM Contract Schedule to determine activity time durations in units of project Working days. Base durations on submittal review periods, procurement lead time and duration, manufacturing times, labor (crafts), equipment, and materials required to perform each activity on a normal Work day basis. No on-site activity shall have duration of over 20 Working days except non-construction activities such as submittals, submittal reviews, procurement and delivery of materials or equipment, and concrete curing. All on-site construction activities will be shown in their cost loaded state, except those activities specifically identified under this Section. Durations shall be the result of definitive manpower planning by the Contractor to perform Work in consideration of Contract defined on-site Work conditions. J. In preparing the CPM Contract Schedule, the Contractor shall consider the nature and complexity of each design submittal and shall allow ample time for review, revisions or corrections. Under no circumstances will an extension of time be allowed for any submittal for which a resubmittal is required and resubmittal time was not originally scheduled. Once the need for a resubmittal is identified, a second submittal preparation and review cycle must be added to the schedule. If a CPM Contract Schedule submittal places an extraordinary labor demand on the technical reviewing staff of the Authority, Metro or any jurisdictional Third Party, the CPM Contract Schedule submittal will be rejected. The Contractor shall then prioritize the criticality of submittals, revise and resubmit the CPM Contract Schedule submittal. 3
4 K. Professional Scheduler/Project Control Engineer - Employ a full-time Professional Scheduler/Project Control Engineer with critical path method scheduling knowledge using Primavera 6.0, Version 7, and a minimum of five (5) years experience using automated scheduling systems involving one or more projects of similar scope, time, and cost. Within ten (10) calendar days of Contract Notice of Award, submit to the Authority the Professional Scheduler/Project Control Engineer s resume of experience as a construction scheduler including professional references that have had experience with individual as a construction scheduler. The Authority has the right to refuse to accept the Professional Scheduler/Project Control Engineer based upon lack of experience of similar Work as required in this Specification. If the Authority refuses to accept Professional Scheduler/Project Control Engineer proposed, the Contractor is to provide another Professional Scheduler/Project Control Engineer meeting experience requirements within two (2) weeks. 2.0 Products 2.1 Submittals Submit one original and one copy of Schedule unless specified otherwise. Provide submittals specified in this Section to the Authority for review and approval. A. Level One Schedule 1. Contractor to submit the Level One Schedule containing the first 90 day submittals, permits, equipment procurement and summary construction activities with Contractor's intended sequencing of Work within 15 calendar days after the NTP. Schedule shall contain Contractor's detailed activities for first 90 calendar days following the NTP. Update the approved Level One Schedule monthly and submit until specified Contractor's Baseline CPM Contract Schedule is approved. Include summary bars that reflect the balance of Work to be performed for remaining Interim and Contract completion milestones. 2. Contractor to submit a hard copy of the schedule as well as an electronic computer generated back-up copy in XER format of the Level One Schedule. Submit a written narrative for the Level One Schedule. The XER electronic file shall be made directly from Primavera 6.0, Version 7 4
5 (P6), and shall contain all files of the schedule that can be restored by the Authority for its evaluation and analysis. B. Schedule of Values 1. Contractor to submit partial Schedule of Values for design and construction within 15 calendar days after NTP. Identify value of Work planned for first 90 calendar days following NTP. Allocate costs to related cost accounts provided in Level One Schedule. Allocate Schedule of Values to activities to be performed in first 90 calendar days after NTP. 2. Contractor to submit a complete Schedule of Values, a breakdown of Contract price into individual cost accounts and into individual activities detailed by Contractor in Baseline CPM Contract Schedule, within 30 calendar days after the Commencement Date stated in the NTP. Cost information will be allocated to discrete activities using Resources in P6. A single project level resource will be defined and used to allocate cost to the schedule activities. These project level resources and project specific activity codes will be identified in the Primavera P6 schedule development template provided by the Authority. C. Baseline CPM Contract Schedule 1. Submit breakdown of Contract price into individual activities detailed by Contractor in Baseline CPM Contract Schedule, within 45 calendar days after NTP. Cost information will be allocated to activities in the schedule. 2. Contractor to submit cost loaded Baseline CPM Contract Schedule, containing detailed activities and intended sequencing of Work included in Contract, within 45 calendar days after NTP. Cumulative amount of cost loaded Work activities shall equal total Contract award price. 3. Contractor to include computer generated reports to show the order in which the Contractor proposes to carry out Work, to indicate restrictions of access, and availability and use of access and to show availability of Work areas, and availability and use of manpower, materials and equipment. Also include any schedule activities affected by any specified access milestones that interface with other contractors. Use the Baseline CPM Contract Schedule to plan, schedule, coordinate and execute the Work under the Contract (including activities of subcontractors, equipment vendors, and suppliers). Provide the Authority with written confirmation of 5
6 concurrence of major (five percent or more of Contract amount) trade Subcontractors and Suppliers with Baseline CPM Contract Schedule, revisions and updates. 4. Contractor to provide the Authority with a means to monitor and follow progress of all phases of Work, comply with limits imposed by scope of Work, with contractually specified interim milestones and completion dates, and with constraints, restraints or sequences included in the Contract. A Primavera P6 schedule development template will be provided by the Authority. The schedule development template shall indicate activity ID and calendar naming conventions, project-specific activity codes, WBS structure, resources, schedule layouts and reports to be utilized by the Contractor. Degree of schedule detail required shall include factors to the satisfaction of the Authority, including, but not limited to, the following: a. Contract Data Requirements List (CDRL) and all other requirements as referenced in Section Submittals; b. Contract interim milestones and Contract completion date, substantial completion dates, constraints, restraints, sequences of Work indicated; c. Type of Work to be performed, and sequences; d. Purchases, manufacture, tests, delivery, and installation activities for major materials and equipment, and a separate list of major material items of equipment for which the Contractor intends to seek payment before installation; e. Deliveries of Authority furnished goods and/or materials, if any, in accordance with dates or schedule windows of such times set forth in the Contract; f. Deliveries of Contractor-furnished goods and/or materials (including spare parts, diagnostic test equipment, special tools, O&M Manuals, training handouts, As-Built documents, executed Warranties), in accordance with dates or schedule windows of such times set forth in the Contract; g. Reviews, approvals and permits required by AHJs or other Third Parties; h. Real estate acquisitions (full and partial) and easements; 6
7 i. Schedules for Subcontractor s Work, including engineering and design services; j. Assignment of responsibility for performing specific activities, including procurement management services; k. Access and availability to Work areas; l. Identification of interfaces and dependencies with preceding, concurrent and follow-on construction by other Contractors and utilities; m. Manpower loading - A single project level Resource will be defined and used to allocate man days to the schedule activities. This project level resource will be identified in the Primavera P6 schedule development template provided by the Authority. n. Cost loading as described in Section B; o. Actual tests, submission of test reports, and approval of test results; p. Testing, training, and assistance required under the Contract; q. Punch list and final cleanup; r. Identification of manpower, material, or equipment restrictions, as well as any activity requiring unusual shift Work, such as two shifts, six day weeks, specified overtime, or Work at times other than a Standard Work Day; and, s. Any cost, schedule summary organization, WBS or activity code designation requested by the Authority. D. Current CPM Contract Schedule Updates 1. Initially, upon approval of the Baseline CPM Contract Schedule, establish the Current CPM Contract Schedule from the Baseline CPM Contract Schedule. Thereafter, update the Current CPM Contract Schedule monthly with Data Date designated by the Authority. List of Data Dates will be provided by the Authority at NTP. Use updated Current CPM Contract Schedule for subsequent planning, scheduling, managing, monthly progress payments, status updating of the Contract Data Requirements List (CDRL) and execution of Work to be accomplished. 2. Participate with the Authority in periodic meetings, at least monthly, on dates directed by the Authority for purposes of reviewing changes to schedule logic and Project status. At a meeting held prior to Data Date, 7
8 provide preliminary updated Current CPM Contract Schedule that forecasts Project status through the Data Date and contains actual start and actual finish dates for activities in progress or completed, remaining durations of activities in progress, percent complete, earned value of cost-loaded activities, logic changes, new or deleted activities, and new Change Orders/Modifications. All proposed changes must be accepted by the Authority prior to incorporation into the Current CPM Contract Schedule. Once the Schedule activities are statused, Contractor shall correct all outof-sequence logic to reflect Contractor s actual work sequence. 3. Submit a stand alone portion of the network (fragnet), if current progress reflects negative float of minus 14 calendar days or more for a Contract milestone activity, as indicated by most recent Current CPM Contract Schedule. Show activities affected, date delay or disruption occurred or how productivity rates were impacted, and unmitigated impacts to schedule caused by delay or disruption. Submit similar fragnet showing Contractor's plan to mitigate delay or disruption and subsequent impacts to schedule at the Authority's request. Provide written narrative describing circumstances which caused delay or disruption and methodology used to determine extent of delay or disruption. Submission of such fragnet does not constitute permission to proceed with plan. Execute some or all of the following remedial actions, and submit a Recovery Schedule that may include: a. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog or Work. b. Increase the number of Work hours per shift, shifts per Work day, Work days per week, the amount of construction equipment, or combination of the foregoing to eliminate the backlog or Work. c. Reschedule the Work in conformance with the Specification requirements. The Recovery Schedule must be submitted in a separate P6 file for the Authority s review and approval. Failure to make a timely submittal of the Recovery Schedule may result in withholding in accordance with Sec (e) (3) of the Contract. 8
9 4. Before implementing any of the above actions, notify and obtain acceptance from the Authority. If such actions are accepted, incorporate revisions before next update. 5. Addition of equipment or construction forces, increasing Work hours or other methods, manner, or procedure to return to contractually required completion date will not be considered justification for a Change Order, nor be treated as acceleration where the need for a Recovery Schedule has been caused by the Contractor and/or its Subcontractors or Suppliers, at any tier. 6. When the Contractor receives a Change Order/Modification, or delays are experienced by the Contractor and a time extension is requested, submit to the Authority a written Time Impact Analysis illustrating the influence of each change or delay on the Contract milestone completion date, utilizing the latest Baseline schedule accepted by the Authority or Current CPM Contract Schedule. Include in each Time Impact Analysis a fragnet demonstrating how the Contractor proposes to incorporate the Change Order/Modification or delay into the Current CPM Contract Schedule. The fragnet shall contain a sequence of new and/or activity revisions that are proposed to be added to the Current Contract CPM Schedule in effect at the time change or delay is encountered, to demonstrate influence or delay and method for incorporating the delay, and its impact into the schedule as they are encountered. Each Time Impact Analysis shall demonstrate estimated time impact based on events of delay, date of Change Order/Modification given to the Contractor, status of design or construction at that point in time, and event time computation of activities affected by change or delay. Event times used in analysis shall be those included in latest Authority accepted version of the Current CPM Contract Schedule, in effect at time change or delay was encountered. a. Each Time Impact Analysis shall demonstrate estimated time impact based on events of delay, date of Change Order/Modification given to the Contractor, status of design or construction at that point in time, and event time computation of activities affected by change or delay. Event times used in analysis shall be those included in latest Authority 9
10 accepted version of the Current CPM Contract Schedule, in effect at time change or delay was encountered. b. Fragnets demonstrating delays caused by waiting for decisions and approvals shall not project such delays to extend later than one (1) day past the Data Date of the schedule used to analyze the impact of the delay, unless approved by the Authority. c. Each Time Impact Analysis shall demonstrate evaluation of possible concurrency between the Contractor s own delays and Owner caused delays. d. Submit each Time Impact Analysis within ten calendar days after a delay occurs. If the Contractor does not submit a Time Impact Analysis for a specific Change Order/Modification or delay within specified period of time, the Contractor will be deemed to have irrevocably waived rights to additional time and cost. e. Because float time within Current CPM Contract Schedule is jointly owned, it is acknowledged and agreed by the Contractor that Authority caused delays on the project may be offset by Authority caused time savings (including, but not limited to: critical path submittals returned in less time than allowed for in the Contract, approval of substitution requests which result in a savings of time along the critical path for the Contractor, etc.). In such an event, the Contractor will not be entitled to receive an extension of time or delay damages until the Authority caused time saving is exceeded and Contract completion date is also exceeded. f. The Authority will accept or reject each Time Impact Analysis. Upon approval, a copy of a Time Impact Analysis signed by the Authority will be returned to the Contractor for incorporation into the schedule. Incorporation of any Time Impact Analysis to the Schedule prior to acceptance of the Authority will result in an immediate rejection to the submitted Current CPM Contract Schedule prior to any detailed review of that schedule is performed by the Authority. g. Upon mutual agreement by both parties, incorporate fragnets illustrating the influence of Change Orders/Modifications and delays 10
11 into the Current CPM Contract Schedule during first update after agreement is reached. E. As-Built Schedule - As-Built Schedule is to be submitted within 90 calendar days after project substantial completion. The As-Built Schedule shall be certified by the Contractor as to how the Contract was executed. Submittal and approval of the Schedule will be a condition precedent to release withholding defined in the Contract Section F. Schedule Reviews - The Authority will review and respond to scheduling submittals within 30 calendar days after submittal. Contractor shall submit a revised schedule within seven days after receipt of the Authority's response if the Authority requires changes or additional information. G. Early Completion Schedule - Contractor agrees that in the event a proposed early completion schedule (or any subsequent update) which is found to be acceptable by the Authority, indicating a duration which is less than time allowed by Contract for completion of Work or of interim milestone, Contract completion time shall only be shortened by a Change Order/Modification to equal Contractors proposed Baseline CPM Contract Schedule duration. The Authority reserves the right to reject Early Completion Schedules without having to justify its decision to the Contractor. H. Four Week Rolling Bar Chart Schedule - Submit a weekly manpower/ construction report and progress schedule listing activities completed and in progress for the previous week and the activities scheduled for the succeeding three weeks that correlates to the Current CPM Contract Schedule. The Four Week Rolling Bar Chart Schedule shall include all activities scheduled including: activity ID, description, start and finish, total float, original duration, remaining duration, percent complete, responsible party performing the work and pertinent remarks as to activity status. I. Pay Estimate Schedule - As back-up for the Application for Progress Payments, prepare schedule of activities for all design and construction Work to be done and show status of completion. Payment will be made off the cost loaded schedule as activities are completed. Progress for payment shall be derived from the progress for Current CPM Contract Schedule Update. Pay Estimate Schedule format and content shall be in compliance with layouts and report 11
12 specifications as indicated within the Primavera P6 schedule development template provided by the Authority. 2.2 Cash Flow and Progress Curves A. Cash Flow 1. Submit with the initial Baseline CPM Contract Schedule a Cash Flow Curve of expected progress payments over the performance period. The Cash Flow Curve shall be based on the Early Dates in the Baseline Schedule. Plot curve using costs assigned to activities in the Baseline CPM Contract Schedule. 2. Update the curve with actuals from the approved monthly Application for Progress Payment and forecast progress payments and submit monthly to the Authority. The total approved progress payments and forecast progress payments must equal Contract amount including Change Orders/Modifications. Derive updated curve from updated Current CPM Contract Schedule. B. Progress Curves - Submit progress curves with Baseline CPM Contract Schedule. Show with the curves the cumulative scheduled percent complete of each phase, time-scaled in calendar days from NTP to Contract completion. The curves shall be derived from the Cash Flow Curve. Update progress curves with each monthly update of the Current CPM Contract Schedule. Include schedule, actual and forecast progress, plotted as a time-scaled curve from 0 to 100 percent. Derive schedule, actual, and forecast progress from Cash Flow Curve. 2.3 Written Narrative Reports - Include a stand-alone narrative of sufficient detail to explain basis of Contractor s submittal with each schedule submittal. A. Level One Schedule and Baseline CPM Contract Schedule Submittals - Explain determination of activity durations and describe Contractor s approach for meeting Contract milestone dates. Include as a minimum: basis and assumptions used in preparing submittal, including crew sizes, equipment requirements, and anticipated delivery dates; restraints; critical path activities; production rates; activities requiring overtime or additional shifts; holidays and other non-work days; potential problem areas; permits; coordination required with the Authority, Metro, utilities and other parties; and long lead delivery items 12
13 requiring more than 30 calendar days from order to delivery. Identify Work items that may be expedited by use of overtime or additional shifts. Identify and explain sequencing and other constraints such as manpower, material, and equipment. Include listing of holidays and special non-work days. B. Current CPM Contract Schedule Submittals - State in narrative, identification of significant schedule progress during the reporting period including progress along the critical path, progress against Contract milestones this period in terms of days ahead of or behind allowable dates, and discuss the status of major Contract material and equipment procurement. Specific requirements of narrative are as follows: 1. If updated Current CPM Contract Schedule indicates an actual or potential delay to Contract completion date or interim milestone dates as specified under the Contract or modified by Change Order/Modification, identify causes of delays, disruptions and interruptions and provide explanation of Work affected and proposed corrective action to meet milestone dates involved or to mitigate potential delays or disruptions. 2. Explain any significant schedule variances from the Baseline CPM Contract Schedule. Explain any schedule changes, including changes to the logic sequence or activity durations and the impacts to the overall Contract. Discuss any Contract schedule concerns and issues and recovery plans (if required). 3. Identify by activity number and description, activities in progress and which activities are scheduled to be completed during the next update period. 4. Identify by activity number and description, activities to be started during the month following the report period. Show Contractor's forecast early and late start and finish dates. 5. Discuss added Change Order/Modification Work items. Also identify any proposed schedule change orders submitted during the last reporting period. 6. Submit an automated database schedule analysis comparison report that identifies the changes made between the previous month Current CPM Contract Schedule and the current month Current CPM Contract Schedule. List activities started or completed during the reporting period and list and explain all changes made to the logic or planned durations. 13
14 3.0 Execution 3.1 Level One Schedule A. Show activities that will or may affect Contract milestone dates including planning, mobilization, engineering, design, permits and approvals, submittals, procurement, fabrication, and construction during first 90 calendar days after NTP. Include activities and milestones that will or may affect or be affected by activities of the Authority, Metro, utilities, and other third parties. B. Describe Contractor's approach to mobilization, procurement, design and construction during first 90 calendar days after NTP, including crew sizes, equipment and material delivery, site access, submittals and permits. 3.2 Schedule of Values A. Allocate applicable Contract costs using resources - to Contractor's detailed activities, included in Level One Schedule, to be completed or partially completed during the 90 day period following NTP. B. Submit schedule layout reports sorted by project-specific activity codes. Schedule of values format and content shall be in compliance with layouts and report specifications as indicated within the Primavera P6 schedule development template provided by the Authority. 3.3 Baseline CPM Contract Schedule The initial schedule submittal shall be an un-progressed representation of the contractor s work-plan for the initially contracted work. The accepted initial schedule shall be referred to as the Contractor s Baseline Schedule. A. Provide Contractor's detailed activities and sequencing for Work included in the Contract. Assign unique activity identification as required by Authority for each detailed activity. B. Cost sums and unit quantity sums of cost loaded activities shall equal Contract award amounts plus approved Change Order/Modification amounts. Assign General Requirement costs not specifically assigned to Work activities to level of effort activities representing entire Contract duration. Budget will be loaded utilizing Resources and shall be coded using project-specific activity codes. Budget shall equal approved Contract award amounts plus approved Change Order/Modification amounts. Approved activity budget dollar value shall equal 14
15 forecast dollar value. Submittal items may only be paid for out of General Requirements pay item. C. Indicate Contractor's best estimate for original durations, early dates, late dates, logic ties, constraint dates, and total float. Schedule activities in the sequence which Contractor intends to perform Work. D. Cost load activities for installation and testing of materials and equipment. E. Include following activity sequence for major material and equipment procurement: Submittal Preparation; Review for Approval; Review for Acceptance; and Fabricate/Deliver. Divide procurement items that may contain multiple submittals occurring at different time intervals into separate sequences that can be tracked on an individual basis. Include a minimum original duration of 30 calendar days in Review-for-Approval and Review-for-Acceptance activities. Include a minimum duration of 30 calendar days for re-review. Resubmittal activities shall contain submittal preparation activities for other material and equipment procurement (non-major). Submit for the Authority's review and approval, a listing of proposed activity codes, code values and titles for codes other than those included in the template. F. Baseline CPM Contract Schedule activity requirements are as follows: 1. Activity descriptions - Briefly convey scope and location of Work indicated. 2. Activities - Discrete items of Work accomplished under Contract that provide measurable and recognizable parts of Work. 3. Include as Contract deliverables, submittal and approval of permit applications and variances, design milestone deliverables and approvals, samples of materials, Shop Drawings, Working Drawings, Inspection and Test Plans, Safety and Security Plans, and Site Traffic Control Plans. Include activities of the Authority and Metro that may affect progress as well as those of affected utility companies and other similarly involved third parties. Include activities in the Baseline CPM Contract Schedule as stipulated in. 4. Work activities - Show duration in Workdays and include costs and manpower loading, where applicable. 5. Work activities - Durations of 20 Working days or less except for nonconstruction activities such as procurement of materials, or fabrication of 15
16 equipment. Should a Work activity require more than 20 Working days, subdivide Work activity to define appropriate Work items. 6. Critical paths defined as the sequence(s) of activities with the least amount of float. 7. Failure to include any element of Work required for performance of the Contract in Baseline CPM Contract Schedule will not excuse Contractor from completing Work required to achieve milestone completion, notwithstanding approval of Baseline CPM Contract Schedule submittals. 8. The Contractor shall allow for inclement weather in the proposed Baseline Schedule by incorporating a sequence of activities titled Rain Day Impact Allowance as the last sequence of activities prior to the Substantial Completion Milestone. No other activities may be concurrent with the Rain Allowance activity. The duration of the Rain Day Impact Allowance activity will be calculated based on the table provided in Section 9.4 of the General Provisions of the Contract. When inclement weather at the project site impacts Critical Path activities, Contractor may provide a written request for a weather impact day describing the inclement weather delay to the Critical Path activities. Upon the Authority s independent confirmation of the amount of rain fall and impact, the Contractor will be authorized to reduce the duration of the Rain Impact Allowance so that slippage to the Substantial Completion Milestone due to rain is recovered. Excusable, non-compensable time extensions will be granted for inclement weather impact to the Substantial Completion Milestone only after the weather impact affecting the critical path work has exhausted the allotted cumulative Rain Day Impact Allowance Current CPM Contract Schedule When commencing new Work associated with a Change Order/Modification, incorporate Work into the Current CPM Contract Schedule submittal as new activities after discussion with and acceptance by the Authority concerning how a change will be placed into proposed revised Contract CPM Schedule. After an official Change Order/Modification has been issued for Work, add it to the schedule. Change Orders/Modifications added to the schedule are cost loaded with corresponding cost account, activity description, and costs. The activity ID identifies the number of the 16
17 change. Time extensions may not be incorporated into schedule for changes or delays without an approved Change Order/Modification. Zero duration activities may be added until time extensions are executed. 3.5 Fragnets A. Submit revised Current CPM Contract Schedule within seven (7) calendar days of request, if current progress reflects negative float of minus 14 days or more for a Contract milestone activity, or submittal of Current CPM Contract Schedule no longer represents Contractor s actual prosecution of Work. B. Properly connect to, and constrain by, previously existing predecessor and successor activities, as applicable, activities of revised portion(s) of schedule. Band impacted activities in separate networks (fragnets), indicating specific delay or impact issue and submit to the Authority for review. Combine accepted fragnets into Current CPM Contract Schedule. C. Subject to the requirements of Contract time extensions will be granted only to the extent that equitable time adjustments for activity or activities affected exceed total or remaining float along critical path of activities at time of actual delay, or at time Change Order/Modification was issued. 3.6 Variance Reports Submit a monthly comparison of consecutive updated Current CPM Contract Schedules. Include: A. Activity I.D. number code and description B. Previous scheduled early start/finish dates. C. Current scheduled early start/finish dates. D. Working days remaining to complete the activity. E. Percentage complete of the activity. F. Remaining total float of each activity. G. Reason for the delay and mitigation measures to be implemented, in the narrative. 3.7 As-Built Schedule The final schedule submittal shall be considered the As-Built schedule for the project. 17
18 4.0 Electronic Submission of Schedules 4.1 Schedule Format XER The Contractor shall submit all project schedules in a standard Primavera XER electronic format. This format can be produced with Primavera P6 version 7. Creating Primavera P6 XER import files from any software other than P6 version 7 must provide exact calculations that can be verified between between printed reports in the contractors system and the values in the Authority s PMIS database. Other import formats from other Primavera software including P3 versions 2.0, 3.0 and 3.1 as well as all versions of Primavera SureTrak are NOT acceptable for schedule submittals. 5.0 Measurement and Payment 5.1 Physical Progress Measurement A. This Section is intended to inform Contractor how the Authority will calculate Physical progress. Physical progress will be measured as the sum of earned dollar values of activities identified as representing physical construction divided by Physical Progress Budget. Physical progress budget is defined as summed dollar values of cost loaded activities identified as representing physical construction in approved cost loaded Baseline CPM Contract Schedule. Determine percent complete for cost-loaded activities as follows: for activities loaded with Contract unit quantities, calculate percent complete by dividing units of Work in place by total units of Work forecast; for activities loaded with lump sum costs, calculate percent complete by estimating percent of Work in place. Only activities representing physical progress (Work in place) will be included in physical progress calculation. B. Monthly Application for Progress Payment schedule submission pay estimate, showing updated activity, and cost data in accordance with requirements of this Section and the Contract, and an updated Current CPM Contract Schedule, will be the basis upon which progress payments and requests are reviewed for approval by the Authority. All Work activities shall be distinguishable between the prime Contractor and subcontractors, inclusive of baseline work, Contract modifications and retention withheld in accordance with Contract Terms and Conditions. The Application for Progress Payment will be processed in accordance with the terms in the Contract Document Article
19 5.2 Payment Payment for Work of this Section shall be included in the Contractor LSFP. END OF SECTION 19
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE
SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.
Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
Construction Project Scheduling: Keys to Success
View the online version at http://us.practicallaw.com/0-574-8625 Construction Project Scheduling: Keys to Success KELLY M. HEUER AND JAMES G. ZACK, JR., NAVIGANT CONSULTING, INC., WITH PRACTICAL LAW REAL
MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration
SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON
1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent
California Department Of Transportation. Class # G0C094
California Department Of Transportation ADVANCED CPM SCHEDULING WITH SURETRAK Class # G0C094 ADVANCED CPM SCHEDULING WITH SURETRAK September 2003 SureTrak is a registered trademark of Primavera Systems,
PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...
CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........
U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I
VA U.S. Department of Veterans Affairs Facilities Management Critical Path Method design DECEMBER 2012 Volume I Design Manual for & TABLE OF CONTENTS, Volume I 1. INTRODUCTION... 3 1.1. Purpose and Scope...
SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule
Contract No. CPM Schedule Project Id SOUTH FLORIDA WATER MANAGEMENT DISTRICT General Contractor CPM Schedule Project Name NTP DATE Data Date CONTRACT DURATION 0 ORIGINAL CONTRACT AMOUNT Date Schedule Received
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008) --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS
Design Consultant Project Management Requirements
Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information
Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document
How To Use P6 For A Project Scheduling System
Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
Table 2-1: Elements of the Project Management Plan
2 PROJECT MANAGEMENT [NTA: DB Project Management requirements drop off at Project Opening and the O&M management requirements start. In Book 2A address projects that have periods of no DB or O&M Phase
S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.
S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. 1803.1 All SCHEDULES A General Requirements This section contains
CHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
Dashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
Developing Critical Path Method Scheduling (CPM)
Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest
MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Contract / Construction Management. November 2006
Contract / Construction Management November 2006 Presentation Outline I. Introduction Project Management II. Contract/Construction Management Stage 1: Construction Period Stage 2: Defects Liability Period
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Common File Server The secure common file server provided by the Department for storage of all contract documents.
DESCRIPTION: Under this item the Contractor shall prepare, status, electronically file and send all project correspondence, Shop Drawings, Requests For Information, meeting minutes, and schedule narratives
ITEM 639.30030002 DOCUMENT CONTROL MANAGEMENT DESCRIPTION:
DESCRIPTION: Under this item the Contractor shall provide an individual(s), designated the Document Control Specialist. The Document Control Specialist shall use a software to prepare, status, electronically
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
General Terms and Conditions
General Terms and Conditions 1. ACCEPTANCE Seller acknowledges and agrees that these General Terms and Conditions are incorporated in, and a part of, this contract and each purchase order. Purchase order
Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015
Donald R. McNatty, PSP FAACE November 18, 2015 1 Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order to preserve the quality of the audio for all attendees.
AACE International Recommended Practices
AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,
Reviewing a Baseline Schedule
Reviewing a Baseline Schedule by Ron Winter, PSP July 21, 2014 Copyright Ron Winter Consulting, 2014 OVERVIEW The accepted, initial schedule is often referred to as the baseline schedule. The use of this
Region of Waterloo Stage 1 Light Rail Transit Project. Design and Construction Performance Output Specifications Article 19 Project Schedule
Region of Waterloo Stage 1 Light Rail Transit Project Design and Construction Performance Output Specifications Article 19 Project Schedule Table of Contents 19.1 General Requirements... 19-1 19.2 Project
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Section 100 Contractor Quality Control Program
7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and
1. Interpretation of this Schedule
Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer
Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010
Designer & Builder Symposium Construction Scheduling Glenn Saito NAVFAC Pacific Construction Division December 1, 2010 FOCUS AREAS Current processes (where implemented) Scheduling specification changes
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
SCHEDULE OO CE NETWORK TRANSITION
SCHEDULE OO CE NETWORK TRANSITION 1. INTERPRETATION 1.1 Purpose of this Schedule This Schedules outlines the terms and conditions with respect to the CE Transition, including the procedures, terms and
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner
SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 -
Jefferson Science Associates, LLC 600 Progress Status Project Control System Manual Revision 7-44 - 600 Progress Status This chapter of the JSA Project Control System Manual explains how the status of
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Construction Claims Prevention Richard J. Long, P.E.
Implementation Consulting
Implementation Consulting Service Description Document August 2009 Table of Contents 1. Introduction...2 2. Eligibility and Prerequisite...2 3. Service Features and Deliverables...2 4. Customer Responsibilities...3
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table
PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)
TABLE OF CONTENTS Page 1 of 18 PURPOSE 2 SCOPE 2 DEFINITION 2 ORGANIZATION AND RESPONSIBILITIES 2 Organization and Function 2 Integration of Control Functions 5 7 Introduction 7 Planning and Scheduling
SCHEDULE AND BUDGETING
PROJECT CONTROLS The right combination of software management tools, proper initial project set-up, timely and accurate data input, continuous tracking of progress, a meaningful reporting structure, strong
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Layton Construction Co., Inc. Quality Management Manual
Layton Construction Co., Inc QUALITY MANAGEMENT PLAN 1 Layton Construction Co., Inc. Quality Management Manual [ 2015 ] PHOENIX PHOENIX BOISE BOISE IRVINE IRVINE SALT LAKE CITY SALT ORLANDO LAKE CITY HAWAII
CONSTRUCTION CONTRACT TERMINOLOGY
PAGE 1 ALLOWANCE - in bidding, an amount budgeted for an item for which no exact dollar amount if available; a contingency for unforeseen costs; the classification of connected parts or members according
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 For PROJECT : Renovation and Repair of Atlanta Jewish Academy
DCMA 14-Point Assessment Metrics
DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,
ADMINISTRATIVE PROCEDURES
ADMINISTRATIVE PROCEDURES FOR SMALL BUSINESS CONSTRUCTION CONTRACTS HARRISBURG, PENNSYLVANIA MAY 2014 EDITION DEPARTMENT OF GENERAL SERVICES BUREAU OF CONSTRUCTION ADMINISTRATIVE PROCEDURES TABLE OF CONTENTS
LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster
Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
Chapter 4: Contractor Quality Control
Chapter 4: Contractor Quality Control Seattle District, NWS Last updated: 05FEB14 Chapter 4 Contractor Quality Control 1. GENERAL. Contractor is responsible for quality control and shall establish and
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices
Project Management Procedures
1201 Main Street, Suite 1600 Columbia, South Carolina 29201 Project Management Procedures Start Up The grant becomes effective upon return of one copy of the grant award executed by the Chief Executive
Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs
Agenda Topics: 1. Oracle/Primavera buyout Within the last year, Oracle bought Primavera. Primavera support has been tailored to Oracle s standard. stead of initially speaking to a support representative,
PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7
PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities
THIS AGREEMENT is made effective as of this day of in the year of.
STANDARD FORM OF CONSTRUCTION MANAGEMENT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER (Where the basis of payment is Cost of the Work with a guaranteed maximum price) THIS AGREEMENT is made effective
300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
MASTER AGREEMENT FOR PROJECT THE DEKALB COUNTY BOARD OF EDUCATION. Dated:
MASTER AGREEMENT FOR PROJECT MANAGEMENT SERVICES BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND Dated: T A B L E O F C O N T E N T S ARTICLE 1 DEFINITIONS... 1 ARTICLE 2 REPRESENTATIONS... 4 2.1 Specific
An Introduction to the Management Principles of Scheduling
College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923
CONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
REAL ESTATE DEVELOPMENT AND MANAGEMENT CONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PROJECT NO: (Project Number) STATE FLAIR CODE: (Payment Code) PROJECT NAME AND LOCATION: (Project
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses
BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
PROJECT MANUAL INCLUDING SPECIFICATIONS FOR OXNARD SCHOOL DISTRICT EDUCATIONAL SERVICE CENTER DATA ROOM ALTERATION. Oxnard, CA
PROJECT MANUAL INCLUDING SPECIFICATIONS FOR OXNARD SCHOOL DISTRICT Oxnard, CA Client Project Number: ARCHITECT MVE INSTITUTIONAL, INC. 3 MacArthur Place, Suite 850 Santa Ana, CA 92707 Telephone: 949.809.3380
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:
