Session: Tue 1110 to How to Cost Load a schedule. OR Understanding the SDEF
|
|
|
- Rosemary Kennedy
- 9 years ago
- Views:
Transcription
1 Session: Tue 1110 to 1225 How to Cost Load a schedule for USACE s QCS/RMS OR Understanding the SDEF
2 (understanding the SDEF) Introduction David Long Sr. Project Controls Specialist With 20+ years of Scheduling and Cost Analysis experience on USACE funded/managed projects. Including Environmental, Bid/Construct, and Design/Build. Cost reimbursable, Time and Material, and Firm Fixed Price Contracts. It is important to understand the USACE intent and usage of a cost loaded schedule and QCS/RMS as part of the Progress Payment process. That is, your cost loaded schedule is your SOV. Therefore, it is understanding the Process and the Standard Data Exchange File (SDEF) that becomes the key to understanding how to Cost Load the Schedule.
3 (understanding the SDEF) Introduction Today s presentation is built around Primavera s P6 Version 6.2 but the principles and techniques are applicable to MS Project and other Scheduling Applications It is also based on Firm Fixed Price Contracts, however, applicable for Cost Reimbursable and T&M contracts.. Based on Actual Cost not Earned Value Firm Fixed Price vs. Cost Reimbursable Affects the source of Actual Cost not the Field used.
4 Relative Standards / Documents
5 ER
6 ER This regulation states the policy on the use of any of the various scheduling management methods. various systems (bar charts, network analysis etc.) as well as administration of contract provisions. This regulation is applicable to all USACE commands. FAR DOD FAR Supplement
7 Primavera P6 SDEF Conversion
8 Primavera P6 SDEF Conversion
9 Unified Facilities Guide Specifications (UFGS) ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS (August 2008) Change 1 08/13 Preparing Activity: USACE Superseding UFGS (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2013 ************************************************************************** SECTION PROJECT SCHEDULE ************************************************************************** NOTE: This guide specification covers the requirements for the preparation and maintenance of the project schedule for construction projects or design build construction projects.
10 Basic Reason for Cost Loading the Schedule USFG Section Paragraph 3.2 BASIS FOR PAYMENT AND COST LOADING To Get Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. That is, the cost loaded schedule is your schedule of value for progress payments. Therefore
11 Cost Loading the Schedule It is reasonable. Acceptable to the Contracting Officer. The activity scope is measurable and represents a deliverable value to the Government. All activities for a specified CLIN sums up to the CLIN value USFG Section Paragraph 3.2 BASIS FOR PAYMENT AND COST LOADING Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule. The schedule is your schedule of value for progress payments.
12 Cost Loading the Schedule The Earnings Report Budgeted Total Cost at the activity level must roll up and equal to the Contract CLINs (SubCLINS) Actual Cost is the actual cost to date for Cost Reimbursement Contract or is equal to the Earned Value for FFP Contracts (SOV Value)
13 Cost Loading the Schedule Only Resource Assignment Budget and Actual Cost are exported to QCS/RMS. That is: User Defined Cost Fields or P6 Expenses are not included in the SDEF Multiple Resource Assignments are allowed, however, it is only the Resource Assignment s total Budget and Actual Cost that are exported to QCS/RMS. Resource units, Activity Earned Value, Activity % Complete are not exported to QCS/RMS. That is: % Complete is calculated in QCS/RMS by dividing the Actual Cost by the Budget, that is, % Spent.
14 Cost Loading the Schedule Role ID SUB/MTL Resource ID $$$$.Fully Burdened Cost Resource Type Nonlabor [NOTE: can use Labor or Material Resource Type] Rate Type Used with Resource or Role Rate Source Rate Source Override (allows for manual entry of Price/Unit) [NOTE: Resource or Role Rate Source can be used] Price/Unit Used if Calculate Cost form Units is Checked Budgeted Cost Budget (Price/Unit * Budget Units) Actual Units Actual Units to date (Entered value unless using Auto Compute ) Actual Cost Actual Cost to date (Entered value unless using Cal cost from units) SDEF PROG Record PROG C AUG SEP12 17SEP12 + 7
15 Cost Loading the Schedule The Earnings Report Review
16 Cost Loading the Schedule
17 Cost Loading the Schedule? SDEF ACTV Record ACTV C1040 Install Storm Water System CVIL DRNG CN W Stabilization Methods
18 Cost Loading the Schedule Direct Cost (Direct Labor include Fringe and Overhead) Any Contingency and prorated General Conditions and PMO Costs G&A and any other indirect costs excluding Bond and Insurance costs Fee / Profit (unless allowed as a separate billing line item typically Cost Re) Cost must be loaded on deliverable activities with measurable scope having value to the Government.
19
20 Cost Loading the Schedule Prep/Submit Concept Design Design Management/Support Staff (GC) Gov't Review Concept Design Prep/Submit 100% Civil Design Design Conf. Concept Design Gov't Review 100% Civil Design Construction Management/Support Staff (GC) Prep/Submit SWS Submittal Design Conf. 100% Design Prep/Submit IFC Civil Design Gov't Review/Acceptance IFC Civil Design Issue IFC Civil Design Civil and SWS Preparatory Remove Fencing Fill/Compact Sinkhole Del. Fencing Materials Install Storm Water System $ 2, $ 0.00 $ 0.00 $ 5, $ 0.00 $ 0.00 $ 0.00 $ 1, $ 0.00 $ 1, $ 0.00 $ 1, $ 0.00 $ $ 6, $ 2, $12,000.00
21 The Process Schedule Review and Reports Network Diagram Earnings Report Activity Report Logic Report Total Float Report Generate the SDEF Load SDEF into QCS [CLINs must balance with RMS] Submit to RMS Draft Prompt Payment and Application for Payment Progress Cost Loaded Schedule Payment Received Internal Approval, Compliance, and Billing Process [Signed Prompt Payment and Pay Application]
22 Understanding SDEF Requirements Cost Loaded That is: Cost to the Government. Activity Coded That is: 10 specifically defined activity codes in ER USFG Section Paragraph Approved Project Schedule Use the approved Project Schedule to measure the progress of the work Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments.
23 Understanding the SDEF Requirements Standard Activity Codes USFG Section Paragraph Standard Activity Coding Dictionary Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER , Appendix A. This exact structure is mandatory, even if some fields are not used. The SDEF format is as follows: Activity Code Field Code Length Description 1 WRKP 3 Workers per Day 2 RESP 4 Responsible Party (e.g. GC, subcontractor, USACE) 3 AREA 4 Area of Work 4 MODF 6 Modification or REA number 5 BIDI 6 Bid Item (CLIN or SubCLIN) 6 PHAS 2 Phase of Work 7 CATW 1 Category of Work 8 FOW1 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)
24 Understanding the SDEF Requirements Standard Activity Codes USFG Section Paragraph Standard Activity Coding Dictionary These activity codes were originally defined for P3 which was a flat and finite length register. Therefore, all codes had to be Use the activity coding structure defined in the Standard Data Exchange Format defined (SDEF) in the in ER order , shown Appendix and A. with This code exact length structure as is specified. mandatory, even if some fields are not used. The SDEF format is as follows: Several Tips and Tricks for P6: The order Activity is no Code longer important, in fact you do not even need to define all Fieldof them. Code Length Description 1 The Max WRKP length of 3 the Code Workers ID per is still Dayimportant, except: 2 FOW RESP 1, 2, & 43 needs Responsible to be replaced Party (e.g. with GC, just subcontractor, FOW with a USACE) code value of 3 AREA 4 Area of Work 1 to 20 characters it is not the code value that gets converted to the 4 MODF 6 Modification or REA number SDEF, it will load up to 30 characters of the Code Value Description. 5 BIDI 6 Bid Item (CLIN or SubCLIN) 6 You can PHAS use the Hierarchical 2 Phase Activity of Work Code feature in P6 What gets 7 converted CATW to the 1 SDEF is Category simple of the Work code assigned at whatever level you 8 assign FOW1 it. 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)
25 Title Sub-Title
26 Understanding the SDEF Requirements Calendars First work day = NTP +1d 7 day no holiday calendar for activities contractually assigned calendar days. Use an appropriate work week calendar for each activity as you plan to work it. Identify Weather Sensitive Installation with a weather day calendar. Plan the work then work the plan. If you do not show non work periods you cannot claim as non work days in a time impact analysis. USFG Section Paragraph Scheduled Project Completion and Activity Calendars The first scheduled work period shall be the day after NTP is received by the Contractor. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non work periods identified including weekends and holidays. Assign the Category of Work Code [CATW] Weather Sensitive Installation to those activities that are weather sensitive. Original durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non work periods on each calendar as meaning the Contractor intends to perform work during those periods.
27 Understanding the SDEF Requirements The SDEF Records ER Part 2 SDEF SPECIFICATION, Section 6. SDEF Organization: The SDEF shall consist of the following records provided in the exact sequence shown Below: Volume Record Mandatory First Line of File Project Record Mandatory Second Line of File Calendar Record(s) Mandatory One Record Min. (one record for each calendar) Holiday Record(s) Mandatory if Holidays Used (one record for each calendar) Activity Record(s) Mandatory Records (one for every activity) Precedence Record(s) Mandatory for Precedence (one record for each pred.) Unit Cost Record(s) Mandatory for Unit Costs (scheduling application specific) Progress Record(s) Mandatory Records (one for every activity) File End Record Mandatory Last Line of Disk/File SDEF Example
28 UFGS Project Schedule Requirements [Section ] WED UFGS Project Schedule Reporting Requirements [Section ] WED
29 Thank you Q & A
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008) --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 10 (February 2010) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01.10 (January 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
Module 8: QUALITY CONTROL SYSTEM (QCS) and RESIDENT MANAGEMENT SYSTEM (RMS) Submodule 1: Introduction and Overview
Module 8: QUALITY CONTROL SYSTEM (QCS) and RESIDENT MANAGEMENT SYSTEM (RMS) Submodule 1: Introduction and Overview (Module 8 is mandatory for Contractors having Corps of Engineer contracts. It is optional
Pricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
Distribution Restriction Statement Approved for public release; distribution is unlimited.
CEMP-CP Regulation No. 415-1-15 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Construction CONSTRUCTION TIME EXTENSIONS FOR WEATHER ER 415-1-15 Distribution Restriction
AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING
AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING 1. NICRA - What is a NICRA? - Who has a NICRA? - Do I need a NICRA? - How do I get a NICRA? 2. INDIRECT
Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (February 2010) Change 1-05/15 ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01 (January 2008) UNIFIED FACILITIES
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 DATE PUBLISHED: MAY 18, 2016 TO ALL PROSPECTIVE SUBMITTERS: THE FOLLOWING CHANGES ARE MADE: REF. LOCATION DESCRIPTION OF CHANGE Attachment A Attachment
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices
Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010
Designer & Builder Symposium Construction Scheduling Glenn Saito NAVFAC Pacific Construction Division December 1, 2010 FOCUS AREAS Current processes (where implemented) Scheduling specification changes
Planning and Managing Projects with Microsoft Project Professional 2013
Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE
SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.
MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration
SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for
Oracle Primavera. P6 Resource Leveling Demo Script
Oracle Primavera P6 Resource Leveling Demo Script Script Team Information Role Name Email Primary Author L. Camille Frost [email protected] Contributor Reviewer Geoff Roberts [email protected]
CONSTRUCTION CONTRACT TERMINOLOGY
PAGE 1 ALLOWANCE - in bidding, an amount budgeted for an item for which no exact dollar amount if available; a contingency for unforeseen costs; the classification of connected parts or members according
ALLOCATE RESOURCES STEP 6 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)
ALLOCATE RESOURCES STEP 6 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) Abstract: Many Contract Documents are now requiring the use of the latest version of Primavera
CHAPTER 53 COST ACCOUNTING STANDARDS
CHAPTER 53 COST ACCOUNTING STANDARDS A. REQUIREMENTS 0F COST ACCOUNTING SYSTEMS 1. The Defense Business Operations Fund shall have a cost estimating and cost accounting system or, as needed, systems specifically
U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I
VA U.S. Department of Veterans Affairs Facilities Management Critical Path Method design DECEMBER 2012 Volume I Design Manual for & TABLE OF CONTENTS, Volume I 1. INTRODUCTION... 3 1.1. Purpose and Scope...
Florida Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450
RICK SCOTT GOVERNOR July 30, 2012 Florida Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450 ANANTH PRASAD, P.E. SECRETARY Monica Gourdine Program Operations Engineer Federal Highway
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-28 20 02 (November 2008) ----------------------------- Preparing Activity: USACE Superseding UFGS-13729 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule
Contract No. CPM Schedule Project Id SOUTH FLORIDA WATER MANAGEMENT DISTRICT General Contractor CPM Schedule Project Name NTP DATE Data Date CONTRACT DURATION 0 ORIGINAL CONTRACT AMOUNT Date Schedule Received
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
Module 9: NAVFAC s Web-based Construction Management System (WebCM) Objectives: After completing this module, you will be able to:
Module 9: NAVFAC s Web-based Construction Management System (WebCM) Objectives: After completing this module, you will be able to: Identify functionality available in WebCM. List the benefits of WebCM.
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III
CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS Basics for Projects of All Sizes Presented by ALEXANDER F. FERRINI, III Why do I need an agreement? Why do I need an agreement? Why do I need an agreement? Design
Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015
Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015 Agenda Introductions RFP Process Types of Costs Pricing of Direct Costs Pricing
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
ITEM 639.30030002 DOCUMENT CONTROL MANAGEMENT DESCRIPTION:
DESCRIPTION: Under this item the Contractor shall provide an individual(s), designated the Document Control Specialist. The Document Control Specialist shall use a software to prepare, status, electronically
UFGS-28 33 00.00 40 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-28 33 00.00 40 (February 2014) ----------------------------------- Preparing Activity: NASA Superseding UFGS-28 33 00.00 40 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Developing Critical Path Method Scheduling (CPM)
Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest
1. Interpretation of this Schedule
Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer
Manual on Training Preparation
Project on Improvement of Local Administration in Cambodia Three Steps of Training Preparation Step 1: Work Breakdown Structure Step 2: Schedule Step 3: Budget Table of Contents Three Steps of Training
NextGEN Project Managers
Presenter Ed Coffin Product Advisor/Product Trainer/Database Consultant ConEst Software Systems [email protected] www.conest.com Estimating and Project Management The link between a well built estimate
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.20 (April 2006) Change 2-11/14 ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-02362 (August 2004) UNIFIED FACILITIES
Contract Administration
Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)
IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) Abstract: Many Contract Documents are now requiring the use of the latest version of Primavera
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
A Comparative Analysis of US Departments of Transportation Scheduling Specifications and Industry Recommended Scheduling Practices.
A Comparative Analysis of US Departments of Transportation Scheduling Specifications and Industry Recommended Scheduling Practices Salam A Abdalla A thesis submitted in partial fulfillment of the requirements
Microsoft Project Activity
Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge
Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"
Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: [email protected] Australia Software
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
NJEMs Bill ID: This is a unique identification number created by the billing software to identify this particular invoice with the responsible party.
NJEMs Bill ID: This is a unique identification number created by the billing software to identify this particular invoice with the responsible party. Assessment Types SF (Oversight Spill Fund) or DF (Oversight
DEPARTMENT OF THE ARMY U.S. Army Corps of Engineers Washington, DC 20314-1000. Construction CONTRACTOR SUBMITTAL PROCEDURES TABLE-OF CONTENTS
CECW-CE Regulation No. 415-1-10 Paragraph DEPARTMENT OF THE ARMY U.S. Army Corps of Engineers Washington, DC 20314-1000 Construction CONTRACTOR SUBMITTAL PROCEDURES TABLE-OF CONTENTS ER 415-1-10 30 April2012
Norsouth Construction Company of Georgia, Inc. Bid Information and Requirements To Whom it May Concern:
Norsouth Construction Company of Georgia, Inc. Bid Information and Requirements To Whom it May Concern: Norsouth Construction Company of Georgia, Inc. is dedicated to the highest standards of integrity
Are You Looking to Sell Your Products & Services to the US Government? Overview
Are You Looking to Sell Your Products & Services to the US Government? What You Need to Know About Accounting, Compliance, and Reporting! 1 FICPA Overview The US Government is the largest consumer of goods
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...
INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT
LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step
J.R. Huston Enterprises, Inc.
From: POC: J.R. Huston Enterprises, Inc. Jim Huston, 303-794-9597, [email protected], www.jrhuston.biz Rev date: 12-29-2004 Format: Topic/title: MS Word How to Calculate Labor Burden *********************************
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-27 52 32.00 10 (October 2007) ---------------------------------- Preparing Activity: USACE Superseding UFGS-27 52 32.00 10 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
TECHNICAL INFORMATION MEMORANDUM 93-5 AUGUST 19, 1993
STATE OF DELAWARE DEPARTMENT OF FINANCE DIVISION OF REVENUE CARVEL STATE BUILDING 820 N. FRENCH STREET P.O. BOX 8911 WILMINGTON, DELAWARE 19899-8911 DIVISION OF REVENUE TECHNICAL INFORMATION MEMORANDUM
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Project Execution - PM Elements
Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status
CHAPTER 6 PROJECT CASH FLOW
CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Cracking the ICE: Ensuring a Compliant Incurred Cost Submission. Carlos Alvarado, VP, FP&A
Cracking the ICE: Ensuring a Compliant Incurred Cost Submission Carlos Alvarado, VP, FP&A Agenda Introduction Incurred Cost Proposal ICE Model Leveraging Reporting Applications Inadequacy Letters Q&A 2
DEPARTMENT OF THE ARMY ER 1110-1-8162 U.S. Army Corps of Engineers CECW-CE Washington, DC 20314-1000
DEPARTMENT OF THE ARMY ER 1110-1-8162 U.S. Army Corps of Engineers CECW-CE Washington, DC 20314-1000 Regulation 31 January 2014 No. 1110-1-8162 Engineering and Design DESIGN AND CONSTRUCTION POLICY FOR
SAFETY IN NAVFAC-SE ACQUISITIONS. Presented by Tina Dancy 29 June 2012
SAFETY IN NAVFAC-SE ACQUISITIONS Presented by Tina Dancy 29 June 2012 Safety Evaluation Factor Increase in mishaps/fatalities triggered need for standard and consistent evaluation approach across NAVFAC
THE DCAA AUDIT BECOMING DCAA COMPLIANT
THE DCAA AUDIT Created to oversee government spending on behalf of the American tax-payer, the Defense Contract Audit Agency (DCAA) is responsible for supervising all Department of Defense (DoD) contracts.
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
Guidelines: Project Schedule Project Management Office (PMO)
Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and
Design Consultant Project Management Requirements
Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-02 81 00 (February 2010) ----------------------------- Preparing Activity: USACE Superseding UFGS-02 81 00 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 30 00 (August 2015) ----------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 30 00 (November 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-27 05 14.00 10 (April 2006) -------------------------------- Preparing Activity: USACE Superseding UFGS-27 05 14.00 10 (April 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
The Implementation Advance Planning Document (IAPD)
The Implementation Advance Planning Document (IAPD) 1 You are here APD Overview Planning APD Implementation APD RFPs and Procurement APD Updates System Testing Regulation Getting to Go Live Project Management
USACE NAVFAC Sample QA/QC Plan 20 selected pages (out of )
USACE NAVFAC Sample QA/QC Plan 20 selected pages (out of ) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: First Time Quality 410 451 8006 Pat [Pick the date]