Oracle Primavera. P6 Resource Leveling Demo Script

Size: px
Start display at page:

Download "Oracle Primavera. P6 Resource Leveling Demo Script"

Transcription

1 Oracle Primavera P6 Resource Leveling Demo Script Script Team Information Role Name Primary Author L. Camille Frost Contributor Reviewer Geoff Roberts Manager Jeff Wiley Revision Status REVISION STATUS APPROVAL Rev Date Description Originator Reviewed Approved V1.0 9 Sep 2009 Initial Draft L. Camille Frost Geoff Roberts L. Camille Frost PRODUCT(S) Version: Primavera P6 v2 Related Documentation / Scripts Document Name Version Location Prerequisite Material / Training Prerequisite Project Management in Primavera P6 Rel. 6.2 Location Page 1 of 14

2 Contents 1. INTRODUCTION / OUTLINE / VALUE PROPOSITION SET UP / DATA REQUIREMENTS Demo Project DEMONSTRATION SCRIPT Resource Leveling Defined... 5 General... 5 Rules Leveling a Single Resource... 6 Leveling Log Advanced Leveling Options Defined... 8 Level Resource Dialog Options... 8 Leveling and Float... 9 Leveling Priorities Advanced Leveling Demonstration Activity Leveling Priority Demo Activity Leveling Priority & Activity ID Demo APPENDIX A: FREQUENTLY ASKED QUESTIONS APPENDIX B: SUPPORTING SCREEN SHOTS / ADDITIONAL INFORMATION Page 2 of 14

3 1. INTRODUCTION / OUTLINE / VALUE PROPOSITION This demonstration script is focused on Resource Leveling in the P6 thick client. Upon completion, you should be able to demonstrate the various approaches to leveling with respect to priorities. You should be able to discuss how P6 addresses conflicts or ties during the leveling process. In addition, you should be able to explain the leveling log and how to use the information to constrain activities to lock in the results of leveling that you want to retain. Much of what is covered in this demo are the topics you need to be prepared to discuss with your customers with respect to leveling but obviously that discussion may vary greatly depending upon the level of your audience. The demo itself can also be very customer dependent and data dependent, thus it is focused more on the most common areas of discussion as opposed to the actual demo. It is also worth noting that most experienced planners and schedulers use the P6 leveling algorithm as a starting point to solving their resource issues. The results are rarely just accepted at face value but rather tweaked accordingly. Having said that, it is considered an invaluable tool to use the results of the computer algorithm as a starting point to making the best decisions for the project(s). The script will include the following in order: Resource leveling defined Leveling a single resource o Leveling o Leveling log o Constraining activities Advanced resource leveling o Activity Leveling Priority o Activity ID 2. SET UP / DATA REQUIREMENTS This demo is based entirely in the P6 thick client as currently, the resource levelling capabilities do not exist in the web client. NOTE: Whatever project(s) you decide to use for this demo script, be certain to Schedule them all before you begin leveling Demo Project Because some of the leveling priorities are difficult to demo without a very controlled set of data, one suggestion would be to create two very small projects with three or four activities each, occurring simultaneously and assigned the same resource. This way, you can change leveling priorities as well as project attributes, level, and show the results. Having said that, you should reserve the more complicated leveling scenarios for the appropriate customers. In many cases, the advanced topics are discussed as opposed to proven through a demo. Page 3 of 14

4 Should you want to show examples of more complex leveling scenarios, prior to arriving at the customer site, create two simple projects similar to: The scenario you want to create is two projects occurring simultaneously with the same resource(s) required for both. In doing so, you have created a leveling conflict. You can then manipulate the leveling priorities and show how P6 responds. Here there are two projects, with the same resource assigned to each 8 hour task. Since the maximum unit / time for the resource is 8/d, the resource is overallocated. TIP: Create a project and copy it such that they are identical. NOTE: Make sure to schedule both the projects. Refer to the advanced leveling section for how to use this set up to demo the more advanced leveling priorities. Page 4 of 14

5 3. DEMONSTRATION SCRIPT 3.1. Resource Leveling Defined General Resource Leveling is a process that ensures resource demand does not exceed resource availability. Activities may be delayed if too few resources are available at any time during an activity s duration. Leveling enables you to determine the earliest dates an activity can be scheduled without overallocating resources. In other words, Primavera looks at the resource requirements of each activity in conjunction with each resource s availability. When a resource is assigned to more activities than their maximum allowable units / time, this is referred to as a resource conflict or more commonly, overallocation. The result of leveling in general when resources are over allocated is the activity is delayed and thus projects are delayed (take longer to complete). The resource leveling log will detail this and the schedule can then be adjusted accordingly. Imagine though that your resources are spread across multiple projects. This is where one can demonstrate the options available to customers to appropriately prioritize one project over another for example. Rules Primavera uses rules to determine the order by which activities are leveled: 1. Mandatory Constraints Leaves activities that have a mandatory Start/Finish date on their early dates Network logic may be violated 2. Topological order (relationships) Respects network logic 3. Leveling priority ( tiebreaker ) If two activities can be leveled at the same time, levelling priorities are used to break the tie. Page 5 of 14

6 3.2. Leveling a Single Resource Let s start with a very simple leveling example using a single project and a single resource. Open the project that you want to level and make sure you are in the Activities view. Click the Resource Usage Profile button and locate a resource that is overallocated (denoted by red in histogram). If you are unable to find a resource that is overallocated, add a resource that is close to overallocated to some additional activities. For this example, we ll use Ken Williams. Click Tools > Level Resources What does it mean for a resource to be overallocated? It means that they are assigned to more hours than their maximum allowable. To show where the Maximum Units / Time for your overallocated resource is click Resources and select the Units & Prices tab. You can see that for Ken Williams, the Max Units / Time is 8/d (8 hours / day). NOTE: The calendar associated with Ken Williams will tell you what type of work week he is assigned (5 day, 6 day for example). For this first example, we will level only within this project and only this resource that is overallocated. Check Preserve scheduled early and late dates, click Select Resource and check the box next to your overallocated resource. Check Log to File and make certain the file location etc. exists. Click Level. In this case, you can see that the leveling pushed some of the activities out and as a result, this particular resource is not as overallocated. Page 6 of 14

7 NOTE: If you are not seeing similar behavior, it is most likely because there are some mandatory Start / Finish dates within the project you chose that cannot be violated. In this example, there is one task to which Ken Williams is assigned that has mandatory dates and thus he is still overallocated for one of these weeks. Another (and perhaps more informative) way of looking at the results of the leveling is in a spread sheet type form. Click on Resource Usage Spreadsheet. You can now see, in this example, that Ken Williams is now only scheduled for 40 hours / week. Return to the histogram (Resource Usage Profile) view. Click on Schedule and you will see the histogram return to its original state. In order to lock in some or all of the results of the leveling, you will have to use Constraints. The best way to determine what has changed and decide what to constrain is through the Leveling Log. NOTE: In reality, the Global Change feature in P6 would be used to set these dates in the current plan as opposed to activity by activity. Leveling Log Level the project again making sure to log the results. Click Tools > Level Resources and click View Log. Close to the end of the report, look for Activities delayed due to predecessor delay and Activities delayed due to resource leveling. Page 7 of 14

8 If we want the results of the leveling to hold, we will need to lock in the new dates (constrain the activities). In this case, Locate the activities delayed due to resource leveling. In this case, locate Activity 239 and go to the activity details. Select the status tab and put in the Primary Constraint, Start On or After. Do the same for Activity 241. Schedule the project again and if you have properly constrained the activities that were delayed, you should not see any change from the leveling results. NOTE: Primary and Secondary date restrictions can also be set from the P6 web client. NOTE: If you want to prove that these activities should now not be affected by the leveling, level again and you will not see them listed in the log as delayed activities as they were before Advanced Leveling Options Defined In this next section, we will discuss at a high level more advanced leveling techniques. Understand that you need to pick and choose according to the level and needs of your customer. Level Resource Dialog Options Click on Tools > Level Resources to bring up the leveling dialog. Automatically level resources when scheduling: As is obvious, leveling will occur each time a project is scheduled. Consider assignments in other projects with priority equal/higher than: Primavera will reduce the resource s availability by the amount of work in any of the other projects with a leveling priority equal to or higher than the value specified in the field before allocating the resource to the open project. Preserve schedule early and late dates: If marked, the project s current early and late dates are retained. If unmarked, the current scheduled early and late dates are overwritten by the leveled dates. Recalculate assignment costs after leveling: Leveling may change an activity s dates. The leveled dates may push the resource assignment into a different Effective Date, which could change the price/unit. If checked, P6 will recalculate the costs based on the new price/unit, which is based on the Effective Date of the resource assignment and the new leveled dates. Page 8 of 14

9 NOTE: The setting to Automatically level resources when scheduling is not a preferred option but rather included due to its presence within Microsoft Project. To view the rates and Effective Dates of a resource, click on Resources, locate the resource and click on the Units & Prices tab. You can see in this example for Ken Williams that he has two different rates with different Effective Dates. If an activity to which he is assigned is scheduled for 2 July 2009 and due to leveling, gets pushed to 6 Aug 2009, costs would be recalculated to the new rate if this last option is selected. Leveling and Float Leveling Priorities Preserve minimum float when leveling: Mark to delay activities with resource conflicts up to their late finish dates. Limit the float and percent overallocation as required. Next, we will focus on probably the most complicated portion of P6 resource leveling: Leveling Priorities. Two activities are ready for leveling, Primavera chooses one using the priorities you specify in the Leveling Priorities section. If you do not specify a prioritization, Primavera sorts by Activity ID. Click Add and then click in the Field Name column to see the list of priorities from which you can pick. Once selected, you would then specify Ascending or Descending. Some of those more commonly used are: Activity ID Ascending levels activities with lower IDs first. Descending levels activities with higher IDs first. Activity Leveling Priority Ascending levels lower priority activities first Descending levels higher priority activities first Page 9 of 14

10 TIP: If the Activity Leveling Priority column (or any other) is not showing and you wish to view / show it to your customer, right-click in the layout and select Columns. Move the appropriate columns to the Selected Columns side of the dialog. Early Finish Ascending levels activities with earlier, Early Finish dates first Descending levels activities with later, Early Finish dates first Early Start Ascending levels with earlier, Early Start dates first Descending levels with later, Early Start dates first There are many more priorities from which to choose. Activity Codes, for example, are one of the more common. Please consult a P6 User s Guide for descriptions of the remainder. NOTE: The ultimate tie-breaker is internally set to Task_ID. This is not a field you can view in Primavera. It is an internal database field that assigns numbers to activities based upon the order in which they were entered into the database Advanced Leveling Demonstration Refer to the script set up section for the projects / data that will be referenced in this section. Activity Leveling Priority Demo In this first scenario, note that DP1-Activity 1 and DP2-Activity 1 are scheduled for the same day with the same resource (LCF.Camille Frost) Change the Activity Leveling Priority of DP1- Activity 1 to 1-Top. Click on Tools > Level Resources: Configure as shown. Focus on adding Activity Leveling Priority / Ascending to the Leveling priorities. Click Level. Page 10 of 14

11 Review the before and after leveling with your customer. 1) Gant Chart Before: Projects start and end at same time. Resource is overallocated. After: Project 1 completes and then Project 2 starts. 2) Histogram Before: Resource overallocated. After: Resource leveled. 3) Spreadsheet Click Tools > Level Resources and click View Log to see the Leveling Log: DP2-Activity 1 was delayed because it had a lower Activity Leveling Priority than DP1-Activity 1. Page 11 of 14

12 Schedule the projects to return them to their unleveled state. Activity Leveling Priority & Activity ID Demo In this next scenario, change the Activity Leveling Priority of DP2- Activity 1 to 1-Top. Add a new Leveling priority: Activity ID / Ascending. Level the Projects. View the results in the Gant chart and the Log: Because DP2-Activity 1 had a higher Activity Leveling Priority, it won the tie against DP1-Activity 1. At that point, Primavera used the Activity ID and of course those starting with DP-1 got priority. You should experiment with the various leveling priorities and other leveling options discussed in this script and with dummy / easy to manipulate type data such that you are comfortable with the various outcomes prior to the customer demo. NOTE: A few notes upon conclusion: You might want to explain the importance of a Baselined project prior to leveling or any significant changes such that if results are not as expected etc. you can return to the original project easily. Page 12 of 14

13 4. APPENDIX A: FREQUENTLY ASKED QUESTIONS Question How is the performance of the P6 Resource Leveling with respect to very large projects. Response It is important to note that because the process is still managed at the desktop and not at the server, it can be time consuming for significantly large projects. Page 13 of 14

14 5. APPENDIX B: SUPPORTING SCREEN SHOTS / ADDITIONAL INFORMATION Page 14 of 14

Oracle Primavera. P6 Dashboards Demo Script

Oracle Primavera. P6 Dashboards Demo Script Oracle Primavera P6 Dashboards Demo Script Script Team Information Role Name Email Primary Author L. Camille Frost [email protected] Contributor Reviewer Richard Ring [email protected] Manager

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

Open Workbench Warrior. Beginner's Guide to Open Workbench

Open Workbench Warrior. Beginner's Guide to Open Workbench Open Workbench Warrior Beginner's Guide to Open Workbench Table of Contents Introduction...3 Open Workbench Functionality...3 Project Planning...3 Project Tracking and Management...3 Sample Project...3

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: [email protected] Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary

More information

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated.

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated. Microsoft Project Pro Steps to completing Project Pro Assignments PART B. (These instructions include all you need to know about adjusting your project in Microsoft Project Pro 2013 and may include instructions

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices

More information

Project Management: Intermediate Microsoft Project 2010

Project Management: Intermediate Microsoft Project 2010 Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project

More information

COURSE DESCRIPTION. Queries in Microsoft Access. This course is designed for users with a to create queries in Microsoft Access.

COURSE DESCRIPTION. Queries in Microsoft Access. This course is designed for users with a to create queries in Microsoft Access. COURSE DESCRIPTION Course Name Queries in Microsoft Access Audience need This course is designed for users with a to create queries in Microsoft Access. Prerequisites * Keyboard and mouse skills * An understanding

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

Resource Management with Microsoft Project Professional 2010

Resource Management with Microsoft Project Professional 2010 Resource Management with Microsoft Project Professional 2010 Greg Bailey Founder & CEO SharkPro Software [email protected] 1 Copyright 2011 SharkPro Software Corporation Microsoft Project

More information

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to

More information

Departmental Reporting in Microsoft Excel for Sage 50 Accounts

Departmental Reporting in Microsoft Excel for Sage 50 Accounts al Reporting in Microsoft Excel for Sage 50 Accounts 1 Introduction Whilst Sage 50 Accounts does already offer integrated Excel reporting functionality, we found that it was often missing the flexibility

More information

Lesson 6 - Managing Resources in a Project Plan

Lesson 6 - Managing Resources in a Project Plan Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional

More information

P6 Analytics Reference Manual

P6 Analytics Reference Manual P6 Analytics Reference Manual Release 3.2 October 2013 Contents Getting Started... 7 About P6 Analytics... 7 Prerequisites to Use Analytics... 8 About Analyses... 9 About... 9 About Dashboards... 10 Logging

More information

Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist

Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist Oracle 1z0-535 Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist Version: 6.0 QUESTION NO: 1 Select the true statement regarding Global Preferences in Primavera P6

More information

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

New Features in Primavera P6 EPPM 16.1

New Features in Primavera P6 EPPM 16.1 New Features in Primavera P6 EPPM 16.1 COPYRIGHT & TRADEMARKS Copyright 2016, Oracle and/or its affiliates. All rights reserved. Oracle is a registered trademark of Oracle Corporation and/or its affiliates.

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

Excel 2010: Create your first spreadsheet

Excel 2010: Create your first spreadsheet Excel 2010: Create your first spreadsheet Goals: After completing this course you will be able to: Create a new spreadsheet. Add, subtract, multiply, and divide in a spreadsheet. Enter and format column

More information

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

Scheduling Software User s Guide

Scheduling Software User s Guide Scheduling Software User s Guide Revision 1.12 Copyright notice VisualTime is a trademark of Visualtime Corporation. Microsoft Outlook, Active Directory, SQL Server and Exchange are trademarks of Microsoft

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Using Microsoft Office to Manage Projects

Using Microsoft Office to Manage Projects (or, Why You Don t Need MS Project) Using Microsoft Office to Manage Projects will explain how to use two applications in the Microsoft Office suite to document your project plan and assign and track tasks.

More information

CPM Scheduling with Primavera Unifier

CPM Scheduling with Primavera Unifier CPM Scheduling with Primavera Unifier Don McNatty, PSP March 26, 2014 2014 Technical Webinar Series Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order

More information

MS Project 2007 Quick Guide

MS Project 2007 Quick Guide MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration

More information

Manager's Guide to TimeIPS

Manager's Guide to TimeIPS Manager's Guide to TimeIPS A training and reference guide for Managers using the TimeIPS time and attendance system. For more information, please contact WorkSmart Systems. To Log in, please go to your

More information

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado

More information

MICROSOFT PROJECT 2010 - II

MICROSOFT PROJECT 2010 - II MICROSOFT PROJECT 2010 - II Course Material This 2-day course is for intermediate and advanced users of the MS Project scheduling application who want to increase their capabilities managing projects in

More information

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010.

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010. Page 1 of 8 Excel 2010 Home > Excel 2010 Help and How-to > Getting started with Excel Search help More on Office.com: images templates Basic tasks in Excel 2010 Here are some basic tasks that you can do

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

To create a histogram, you must organize the data in two columns on the worksheet. These columns must contain the following data:

To create a histogram, you must organize the data in two columns on the worksheet. These columns must contain the following data: You can analyze your data and display it in a histogram (a column chart that displays frequency data) by using the Histogram tool of the Analysis ToolPak. This data analysis add-in is available when you

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: [email protected] Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

Intellect Platform - Tables and Templates Basic Document Management System - A101

Intellect Platform - Tables and Templates Basic Document Management System - A101 Intellect Platform - Tables and Templates Basic Document Management System - A101 Interneer, Inc. 4/12/2010 Created by Erika Keresztyen 2 Tables and Templates - A101 - Basic Document Management System

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

WEBFOCUS QUICK DATA FOR EXCEL

WEBFOCUS QUICK DATA FOR EXCEL WEBFOCUS QUICK DATA FOR EXCEL BRIAN CARTER INFORMATION BUILDERS SUMMIT 2008 USERS CONFERENCE JUNE 2008 Presentation Abstract: Even with the growing popularity and evolvement of Business Intelligence products

More information

PROMASTAR Instructor-led Professional Training Services

PROMASTAR Instructor-led Professional Training Services PROMASTAR Instructor-led Professional Training Services Primavera P6 Professional Fundamentals Rel 8.3 Primavera P6 Professional Fundamentals Rel 8.3 Page 1 Oracle Primavera Learning Experience Learning

More information

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities

More information

Master Scheduling Best Practices for Schools Using Secondary Scheduling

Master Scheduling Best Practices for Schools Using Secondary Scheduling Chancery SMS Version 6.3 and higher for Schools Using Secondary Scheduling January 2006 CSL - 12647 The Chancery SMS Documentation Team: Sarah Hewson, Karin Jensen, Linda MacShane, Sharon Russell, Trish

More information

Outlook Rules and Alerts

Outlook Rules and Alerts Outlook Rules and Alerts Utilizing Outlook Rules and Alerts to help you organize and prioritize your e-mail. Table of Contents: 1. Tackling Your In-box 2. Outlook Rules and Alerts 3. Examples 4. Rule Set-up

More information

How To Build An Intranet In Sensesnet.Com

How To Build An Intranet In Sensesnet.Com Sense/Net 6 Evaluation Guide How to build a simple list-based Intranet? Contents 1 Basic principles... 4 1.1 Workspaces... 4 1.2 Lists... 4 1.3 Check-out/Check-in... 5 1.4 Version control... 5 1.5 Simple

More information

WORKING IN TEAMS WITH CASECOMPLETE AND MICROSOFT VISUAL SOURCE SAFE. Contents

WORKING IN TEAMS WITH CASECOMPLETE AND MICROSOFT VISUAL SOURCE SAFE. Contents WORKING IN TEAMS WITH CASECOMPLETE AND MICROSOFT VISUAL SOURCE SAFE Contents Working in Teams with CaseComplete... 2 Need an introduction to how version control works?... 2 Exclusive Checkout... 3 Multiple

More information

CHAPTER 11: SALES REPORTING

CHAPTER 11: SALES REPORTING Chapter 11: Sales Reporting CHAPTER 11: SALES REPORTING Objectives Introduction The objectives are: Understand the tools you use to evaluate sales data. Use default sales productivity reports to review

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT 8. COMPUTER TOOLS FOR PROJECT MANAGEMENT The project management is a complex activity that requires among others: Information intercourse referred to the project, information that is in big amounts more

More information

Reviewing Resource Leveled Schedules Using P6

Reviewing Resource Leveled Schedules Using P6 Reviewing Resource Leveled Schedules Using P6 by Ron Winter, PSP Fellow of AACE International Copyright July 8, 2015 1 Abstract Standard CPM schedule review techniques are insufficient to review automatically

More information

1. Interpretation of this Schedule

1. Interpretation of this Schedule Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer

More information

Tips on exporting your Oracle Apps reports to Excel. Introduction

Tips on exporting your Oracle Apps reports to Excel. Introduction Tips on exporting your Oracle Apps reports to Excel Introduction Oracle E-Business Suite provides users with a host of standard reports. Quite often I have found that exporting reporting information to

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Volume FIRST WALKTHROUGH. The 10-Minute Guide to Using Newsletter Services. First Walkthrough: the 10-Minute Guide

Volume FIRST WALKTHROUGH. The 10-Minute Guide to Using Newsletter Services. First Walkthrough: the 10-Minute Guide Volume 1 FIRST WALKTHROUGH The 10-Minute Guide to Using Newsletter Services First Walkthrough: the 10-Minute Guide Table of Contents Step - 1... 3 Sign-up for an account... 3 Step 2... 4 Authenticate your

More information

Editor Manual for SharePoint Version 1. 21 December 2005

Editor Manual for SharePoint Version 1. 21 December 2005 Editor Manual for SharePoint Version 1 21 December 2005 ii Table of Contents PREFACE... 1 WORKFLOW... 2 USER ROLES... 3 MANAGING DOCUMENT... 4 UPLOADING DOCUMENTS... 4 NEW DOCUMENT... 6 EDIT IN DATASHEET...

More information

Microsoft Query, the helper application included with Microsoft Office, allows

Microsoft Query, the helper application included with Microsoft Office, allows 3 RETRIEVING ISERIES DATA WITH MICROSOFT QUERY Microsoft Query, the helper application included with Microsoft Office, allows Office applications such as Word and Excel to read data from ODBC data sources.

More information

An Introduction to Excel s Pivot Table

An Introduction to Excel s Pivot Table An Introduction to Excel s Pivot Table This document is a brief introduction to the Excel 2003 Pivot Table. The Pivot Table remains one of the most powerful and easy-to-use tools in Excel for managing

More information

Primavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC

Primavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC Primavera P6 102 Training Manual Prepared by Bill Pepoon, Managing Partner Construction Science, LLC 1 Day I Introduction Setting up a new Project Activities Activity Types Activity Durations Work Breakdown

More information

An Introduction to Excel Pivot Tables

An Introduction to Excel Pivot Tables An Introduction to Excel Pivot Tables EXCEL REVIEW 2001-2002 This brief introduction to Excel Pivot Tables addresses the English version of MS Excel 2000. Microsoft revised the Pivot Tables feature with

More information

Business Reports. ARUP Connect

Business Reports. ARUP Connect Business Reports ARUP Connect User Manual November 2015 Table of Contents Business Reports... 4 Quick Reference... 4 View Reports... 5 My Reports Tab... 5 Open a Report... 5 Save a Report... 5 Modify My

More information

PERCEPTION PERT-PAC Using Microsoft Project 2000

PERCEPTION PERT-PAC Using Microsoft Project 2000 PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000

More information

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

User's Guide. ver.7.1.0. RSRicksoft. www.ricksoft.jp

User's Guide. ver.7.1.0. RSRicksoft. www.ricksoft.jp User's Guide ver.7.1.0 RSRicksoft www.ricksoft.jp Table of Contents Chapter 1 To begin with... 2 1. 1 Terms and Concept...2 1. 1. 1 Ticket... 2 1. 1. 2 "Phase" Tickets... 2 1. 1. 3 Ticket's Parent-Child

More information

Gmail Merge. Step 1: Writing the actual e mail

Gmail Merge. Step 1: Writing the actual e mail Gmail Merge Step 1: Writing the actual e mail 1. Open Gmail. 2. Click Compose. 3. Paste the e mail being sent to the population or students, etc. 4. To personalize the message, create keys like

More information

Sample book with only two chapters

Sample book with only two chapters PLANNING AND CONTROL USING ORACLE PRIMAVERA P6 Versions 8.2 to 15.1 EPPM WEB Enterprise Portfolio Project Management Planning and Progressing Project Schedules With and Without Roles and Resources in an

More information

Getting Started with Excel 2008. Table of Contents

Getting Started with Excel 2008. Table of Contents Table of Contents Elements of An Excel Document... 2 Resizing and Hiding Columns and Rows... 3 Using Panes to Create Spreadsheet Headers... 3 Using the AutoFill Command... 4 Using AutoFill for Sequences...

More information

Resources Management

Resources Management Resources Management. Introduction s we have seen in network scheduling, the basic inputs to criticalpath analysis are the individual project activities, their durations, and their dependency relationships.

More information

Chapter-15 -------------------------------------------- Replication in SQL Server

Chapter-15 -------------------------------------------- Replication in SQL Server Important Terminologies: What is Replication? Replication is the process where data is copied between databases on the same server or different servers connected by LANs, WANs, or the Internet. Microsoft

More information

Chapter 9 Creating Reports in Excel

Chapter 9 Creating Reports in Excel Chapter 9 Creating Reports in Excel One of the most powerful features of Standard & Poor s Research Insight is its ability to communicate with Microsoft Excel through Active-X Technology. Excel requests

More information

Time & Expense Entry WalkThrough

Time & Expense Entry WalkThrough PRACTICE CS Time & Expense Entry WalkThrough Version 2014.x.x TL 27573a (01/16/2015) Copyright Information Text copyright 2004-2015 by Thomson Reuters. All rights reserved. Video display images copyright

More information

1-Step Appraisals Jewelry Appraisal Software

1-Step Appraisals Jewelry Appraisal Software User Guide for 1-Step Appraisals Jewelry Appraisal Software Version 5.02 Page Table of Contents Installing 1-Step Appraisals... Page 3 Getting Started... Page 4 Upgrading from a Previous Version... Page

More information

Primavera P6 Exercise Worksheet

Primavera P6 Exercise Worksheet Primavera P6 Exercise Worksheet P6 Exercise Worksheet Preparing for the Exercises Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use

More information

SAP BusinessObjects Financial Consolidation Web User Guide

SAP BusinessObjects Financial Consolidation Web User Guide SAP BusinessObjects Financial Consolidation Document Version: 10.0 Support Package 18 2016-02-19 SAP BusinessObjects Financial Consolidation Web User Guide Content 1 General user functions....12 1.1 To

More information

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans

More information

Infor LN Service User Guide for Service Scheduler Workbench

Infor LN Service User Guide for Service Scheduler Workbench Infor LN Service User Guide for Service Scheduler Workbench Copyright 2015 Infor Important Notices The material contained in this publication (including any supplementary information) constitutes and contains

More information

QUICK START GUIDE RESOURCE MANAGERS. Last Updated: 04/27/2012

QUICK START GUIDE RESOURCE MANAGERS. Last Updated: 04/27/2012 QUICK START GUIDE RESOURCE MANAGERS Last Updated: 04/27/2012 Table of Contents Introduction... 3 Getting started... 4 Logging into Eclipse... 4 Setting your user preferences... 5 Online help and the Eclipse

More information

RapidResponse Training Catalog

RapidResponse Training Catalog RapidResponse Training Catalog Contents About RapidResponse Training... 4 RapidResponse Roles... 4 Consumers... 5 Contributors... 6 Contributors + RapidResponse Applications... 6 Authors... 8 Basic Authors...

More information

University of Sunderland. Microsoft Project. Basic Guide

University of Sunderland. Microsoft Project. Basic Guide University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks

More information

Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102

Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Interneer, Inc. Updated on 2/22/2012 Created by Erika Keresztyen Fahey 2 Workflow - A102 - Basic HelpDesk Ticketing System

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE Planning and Progressing a Single Project Schedule With and Without Resources In An Established Project Environment BY PAUL EASTWOOD HARRIS Eastwood

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.

More information

To launch the Microsoft Excel program, locate the Microsoft Excel icon, and double click.

To launch the Microsoft Excel program, locate the Microsoft Excel icon, and double click. EDIT202 Spreadsheet Lab Assignment Guidelines Getting Started 1. For this lab you will modify a sample spreadsheet file named Starter- Spreadsheet.xls which is available for download from the Spreadsheet

More information

Using Ad-Hoc Reporting

Using Ad-Hoc Reporting Using Ad-Hoc Reporting The purpose of this guide is to explain how the Ad-hoc reporting function can be used to produce Management Information from client and product data held in the Key. The guide will

More information

Jolly Server Getting Started Guide

Jolly Server Getting Started Guide JOLLY TECHNOLOGIES Jolly Server Getting Started Guide The purpose of this guide is to document the creation of a new Jolly Server in Microsoft SQL Server and how to connect to it using Jolly software products.

More information

Microsoft Excel 2010 Training. Use Excel tables to manage information

Microsoft Excel 2010 Training. Use Excel tables to manage information Microsoft Excel 2010 Training Use Excel tables to manage information Overview: Help with data management In this course, you ll learn how to manage information by using tables in Excel. Tables make it

More information

Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide

Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Margy Girdzius Director, Partner Enablement WWA&C Objective & Audience Objective Help you prepare to take the

More information

Creating a Resource Library

Creating a Resource Library IT Session 3: Resourcing Creating a Resource Library It is possible within the software to include resources as you go on, but it is better to set up a separate resource library and link this to your developing

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

Calc Guide Chapter 9 Data Analysis

Calc Guide Chapter 9 Data Analysis Calc Guide Chapter 9 Data Analysis Using Scenarios, Goal Seek, Solver, others Copyright This document is Copyright 2007 2011 by its contributors as listed below. You may distribute it and/or modify it

More information

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create.

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create. What is Excel? Applies to: Excel 2010 Excel is a spreadsheet program in the Microsoft Office system. You can use Excel to create and format workbooks (a collection of spreadsheets) in order to analyze

More information