THE PROJECT MANAGEMENT KNOWLEDGE AREAS
|
|
|
- Kelly Parrish
- 9 years ago
- Views:
Transcription
1 THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human Resource Management 10. Project Communications Management 11. Project Risk Management 12. Project Procurement Management ii 1996 Project Management Institute, 130 South State Road, Upper Darby, PA USA 37
2 38 NOTES
3 4 PROJECT INTEGRATION MANAGEMENT Project Integration Management includes the processes required to ensure that the various elements of the project are properly coordinated. It involves making tradeoffs among competing objectives and alternatives in order to meet or exceed stakeholder needs and expectations. While all project management processes are integrative to some extent, the processes described in this chapter are primarily integrative. Figure 4 1 provides an overview of the following major processes: 4.1 Project Plan Development taking the results of other planning processes and putting them into a consistent, coherent document. 4.2 Project Plan Execution carrying out the project plan by performing the activities included therein. 4 Overall Change Control coordinating changes across the entire project. 4.1 Project Plan Development 4.2 Project Plan Execution 4 Overall Change Control These processes interact with each other and with the processes in the other knowledge areas as well. Each process may involve effort from one or more individuals or groups of individuals based on the needs of the project. Each process generally occurs at least once in every project phase. Although the processes are presented here as discrete elements with well-defined interfaces, in practice they may overlap and interact in ways not detailed here. Process interactions are discussed in detail in Chapter 3. The processes, tools, and techniques used to integrate project management processes are the focus of this chapter. For example, project integration management comes into play when a cost estimate is needed for a contingency plan or when risks associated with various staffing alternatives must be identified. However, for a project to be completed successfully, integration must also occur in a number of other areas as well. For example: The work of the project must be integrated with the ongoing operations of the performing organization. Product scope and project scope must be integrated (the difference between product and project scope is discussed in the introduction to Chapter 5). Deliverables from different functional specialties (such as civil, electrical, and mechanical drawings for an engineering design project) must be integrated. 4.1 PROJECT PLAN DEVELOPMENT Project plan development uses the outputs of the other planning processes to create a consistent, coherent document that can be used to guide both project execution and project control. This process is almost always iterated several times. For example, the initial draft may include generic resources and undated durations while the final plan reflects specific resources and explicit dates. The project plan is used to: Guide project execution. Document project planning assumptions Project Management Institute, 130 South State Road, Upper Darby, PA USA 39
4 4.1.1 A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE Document project planning decisions regarding alternatives chosen. Facilitate communication among stakeholders. Define key management reviews as to content, extent, and timing. Provide a baseline for progress measurement and project control. Inputs Tools & Techniques Outputs.1 Other planning outputs.2 Historical information Organizational policies.4 Constraints.5 Assumptions.1 Project planning methodology.2 Stakeholder skills and knowledge Project management information system (PMIS).1 Project plan.2 Supporting detail Inputs to Project Plan Development.1 Other planning outputs. All of the outputs of the planning processes in the other knowledge areas (Section 3 provides a summary of these project planning processes) are inputs to developing the project plan. Other planning outputs include both base documents such as the work breakdown structure as well as the supporting detail. Many projects will also require application area-specific inputs (e.g., most construction projects will require a cash flow forecast)..2 Historical information. The available historical information (e.g., estimating databases, records of past project performance) should have been consulted during the other project planning processes. This information should also be available during project plan development to assist with verifying assumptions and assessing alternatives that are identified as part of this process. Organizational policies. Any and all of the organizations involved in the project may have formal and informal policies whose effects must be considered. Organizational policies which typically must be considered include, but are not limited to: Quality management process audits, continuous improvement targets. Personnel administration hiring and firing guidelines, employee performance reviews. Financial controls time reporting, required expenditure and disbursement reviews, accounting codes, standard contract provisions..4 Constraints. Constraints are factors that will limit the project management team s options. For example, a predefined budget is a constraint that is highly likely to limit the team s options regarding scope, staffing, and schedule. When a project is performed under contract, contractual provisions will generally be constraints..5 Assumptions. Assumptions are factors that, for planning purposes, will be considered to be true, real, or certain. For example, if the date that a key person will become available is uncertain, the team may assume a specific start date. Assumptions generally involve a degree of risk Project Management Institute, 130 South State Road, Upper Darby, PA USA
5 PROJECT INTEGRATION MANAGEMENT Figure 4 1. Project Integration Management Overview Project Integration Management 4.1 Project Plan Development.1 Inputs.1 Other planning outputs.2 Historical information Organizational policies.4 Constraints.5 Assumptions.2 Tools and Techniques.1 Project planning.1 methodology.2 Stakeholder skills and.2 knowledge Project management information system (PMIS) Outputs.1 Project plan.2 Supporting detail 4.2 Project Plan Execution.1 Inputs.1 Project plan.2 Supporting detail Organizational policies.4 Corrective action.2 Tools and Techniques.1 General management skills.2 Product skills and.2 knowledge Work authorization system.4 Status review meetings.5 Project management.5 information system.6 Organizational procedures Outputs.1 Work results.2 Change requests 4 Overall Change Control.1 Inputs.1 Project plan.2 Performance reports Change requests.2 Tools and Techniques.1 Change control system.2 Configuration management Performance measurement.4 Additional planning.5 Project management.5 information system Outputs.1 Project plan updates.2 Corrective action Lessons learned Tools and Techniques for Project Plan Development.1 Project planning methodology. A project planning methodology is any structured approach used to guide the project team during development of the project plan. It may be as simple as standard forms and templates (whether paper or electronic, formal or informal) or as complex as a series of required simulations (e.g., Monte Carlo analysis of schedule risk). Most project planning methodologies make use of a combination of hard tools such as project management software and soft tools such as facilitated start-up meetings..2 Stakeholder skills and knowledge. Every stakeholder has skills and knowledge which may be useful in developing the project plan. The project management team must create an environment in which the stakeholders can contribute appropriately (see also Section 9, Team Development). Who contributes, what they contribute, and when will vary. For example: On a construction project being done under a lump sum contract, the professional cost engineer will make a major contribution to the profitability objective during proposal preparation when the contract amount is being determined. On a project where staffing is defined in advance, the individual contributors may contribute significantly to meeting cost and schedule objectives by reviewing duration and effort estimates for reasonableness Project Management Institute, 130 South State Road, Upper Darby, PA USA 41
6 4.1.2 A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE Project management information system (PMIS). A project management information system consists of the tools and techniques used to gather, integrate, and disseminate the outputs of the other project management processes. It is used to support all aspects of the project from initiating through closing and generally includes both manual and automated systems. 4.1 Outputs from Project Plan Development.1 Project plan. The project plan is a formal, approved document used to manage and control project execution. It should be distributed as defined in the communications management plan (e.g., management of the performing organization may require broad coverage with little detail, while a contractor may require complete details on a single subject). In some application areas, the term integrated project plan is used to refer to this document. A clear distinction should be made between the project plan and the project performance measurement baselines. The project plan is a document or collection of documents that should be expected to change over time as more information becomes available about the project. The performance measurement baselines represent a management control that will generally change only intermittently and then generally only in response to an approved scope change. There are many ways to organize and present the project plan, but it commonly includes all of the following (these items are described in more detail elsewhere): Project charter. A description of the project management approach or strategy (a summary of the individual management plans from the other knowledge areas). Scope statement, which includes the project deliverables and the project objectives. Work breakdown structure (WBS) to the level at which control will be exercised. Cost estimates, scheduled start dates, and responsibility assignments to the level of the WBS at which control will be exercised. Performance measurement baselines for schedule and cost. Major milestones and target dates for each. Key or required staff. Key risks, including constraints and assumptions, and planned responses for each. Subsidiary management plans, including scope management plan, schedule management plan, etc. Open issues and pending decisions. Other project planning outputs should be included in the formal plan based upon the needs of the individual project. For example, the project plan for a large project will generally include a project organization chart..2 Supporting detail. Supporting detail for the project plan includes: Outputs from other planning processes that are not included in the project plan. Additional information or documentation generated during development of the project plan (e.g., constraints and assumptions that were not previously known). Technical documentation such as requirements, specifications, and designs. Documentation of relevant standards. This material should be organized as needed to facilitate its use during project plan execution. 4.2 PROJECT PLAN EXECUTION Project plan execution is the primary process for carrying out the project plan the vast majority of the project s budget will be expended in performing this process. In this process, the project manager and the project management team must coordinate Project Management Institute, 130 South State Road, Upper Darby, PA USA
7 PROJECT INTEGRATION MANAGEMENT and direct the various technical and organizational interfaces that exist in the project. It is the project process that is most directly affected by the project application area in that the product of the project is actually created here. Inputs Tools & Techniques Outputs.1 Project plan.2 Supporting detail Organizational policies.4 Corrective action.1 General management skills.2 Product skills and knowledge Work authorization system.4 Status review meetings.5 Project management.5 information system.6 Organizational.5 procedures.1 Work results.2 Change requests Inputs to Project Plan Execution.1 Project plan. The project plan is described in Section The subsidiary management plans (scope management plan, risk management plan, procurement management plan, etc.) and the performance measurement baselines are key inputs to project plan execution..2 Supporting detail. Supporting detail is described in Section Organizational policies. Organizational policies are described in Section Any and all of the organizations involved in the project may have formal and informal policies which may affect project plan execution..4 Corrective action. Corrective action is anything done to bring expected future project performance into line with the project plan. Corrective action is an output of the various control processes as an input here it completes the feedback loop needed to ensure effective project management Tools and Techniques for Project Plan Execution.1 General management skills. General management skills such as leadership, communicating, and negotiating are essential to effective project plan execution. General management skills are described in Section Product skills and knowledge. The project team must have access to an appropriate set of skills and knowledge about the project product. The necessary skills are defined as part of planning (especially in resource planning, Section 7.1) and are provided through the staff acquisition process (described in Section 9.2). Work authorization system. A work authorization system is a formal procedure for sanctioning project work to ensure that work is done at the right time and in the proper sequence. The primary mechanism is typically a written authorization to begin work on a specific activity or work package. The design of a work authorization system should balance the value of the control provided with the cost of that control. For example, on many smaller projects, verbal authorizations will be adequate..4 Status review meetings. Status review meetings are regularly scheduled meetings held to exchange information about the project. On most projects, status review meetings will be held at various frequencies and on different levels (e.g., the project management team may meet weekly by itself and monthly with the customer)..5 Project management information system. The project management information system is described in Section Project Management Institute, 130 South State Road, Upper Darby, PA USA 43
8 A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE.6 Organizational procedures. Any and all of the organizations involved in the project may have formal and informal procedures useful during project execution. 4.2 Outputs from Project Plan Execution.1 Work results. Work results are the outcomes of the activities performed to accomplish the project. Information on work results which deliverables have been completed and which have not, to what extent quality standards are being met, what costs have been incurred or committed, etc. is collected as part of project plan execution and fed into the performance reporting process (see Section 10 for a more detailed discussion of performance reporting)..2 Change requests. Change requests (e.g., to expand or contract project scope, to modify cost or schedule estimates, etc.) are often identified while the work of the project is being done. 4 OVERALL CHANGE CONTROL Overall change control is concerned with (a) influencing the factors which create changes to ensure that changes are beneficial, (b) determining that a change has occurred, and (c) managing the actual changes when and as they occur. Overall change control requires: Maintaining the integrity of the performance measurement baselines all approved changes should be reflected in the project plan, but only project scope changes will affect the performance measurement baselines. Ensuring that changes to the product scope are reflected in the definition of the project scope (the difference between product and project scope is discussed in the introduction to Chapter 5). Coordinating changes across knowledge areas as illustrated in Figure 4 2. For example, a proposed schedule change will often affect cost, risk, quality, and staffing. Inputs Tools & Techniques Outputs.1 Project plan.2 Performance reports Change requests.1 Change control system.2 Configuration.2 management Performance measurement.4 Additional planning.5 Project management information system.1 Project plan updates.2 Corrective action Lessons learned 4.1 Inputs to Overall Change Control.1 Project plan. The project plan provides the baseline against which changes will be controlled (see Section 4.1.1)..2 Performance reports. Performance reports (described in Section 10) provide information on project performance. Performance reports may also alert the project team to issues which may cause problems in the future. Change requests. Change requests may occur in many forms oral or written, direct or indirect, externally or internally initiated, and legally mandated or optional Project Management Institute, 130 South State Road, Upper Darby, PA USA
9 PROJECT INTEGRATION MANAGEMENT Figure 4 2. Coordinating Changes Across the Entire Project Performance Reporting Overall Change Control Subsidiary Change Control Scope Change Control Schedule Change Control Cost Change Control Quality Control Risk Change Control Contract Administration 4.2 Tools and Techniques for Overall Change Control.1 Change control system. A change control system is a collection of formal, documented procedures that defines the steps by which official project documents may be changed. It includes the paperwork, tracking systems, and approval levels necessary for authorizing changes. In many cases, the performing organization will have a change control system that can be adopted as is for use by the project. However, if an appropriate system is not available, the project management team will need to develop one as part of the project. Many change control systems include a change control board (CCB) responsible for approving or rejecting change requests. The powers and responsibilities of a CCB should be well-defined and agreed upon by key stakeholders. On large, complex projects, there may be multiple CCBs with different responsibilities. The change control system must also include procedures to handle changes which may be approved without prior review; for example, as the result of emergencies. Typically, a change control system will allow for automatic approval of defined categories of changes. These changes must still be documented and captured so that they do not cause problems later in the project..2 Configuration management. Configuration management is any documented procedure used to apply technical and administrative direction and surveillance to: Identify and document the functional and physical characteristics of an item or system. Control any changes to such characteristics. Record and report the change and its implementation status. Audit the items and system to verify conformance to requirements [1]. In many application areas, configuration management is a subset of the change control system and is used to ensure that the description of the project product is correct and complete. However, in some application areas, the term configuration management is used to describe any rigorous change control system Project Management Institute, 130 South State Road, Upper Darby, PA USA 45
10 4.2 A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE Performance measurement. Performance measurement techniques such as earned value (described in Section ) help to assess whether variances from the plan require corrective action..4 Additional planning. Projects seldom run exactly according to plan. Prospective changes may require new or revised cost estimates, modified activity sequences, analysis of risk response alternatives, or other adjustments to the project plan..5 Project management information system. Project management information systems are described in Section Outputs from Overall Change Control.1 Project plan updates. Project plan updates are any modification to the contents of the project plan or the supporting detail (described in Sections and 4.1.2, respectively). Appropriate stakeholders must be notified as needed..2 Corrective action. Corrective action is described in Section Lessons learned. The causes of variances, the reasoning behind the corrective action chosen, and other types of lessons learned should be documented so that they become part of the historical database for both this project and other projects of the performing organization Project Management Institute, 130 South State Road, Upper Darby, PA USA
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
PROJECT HUMAN RESOURCE MANAGEMENT
9 PROJECT HUMAN RESOURCE MANAGEMENT Project Human Resource Management includes the processes required to make the most effective use of the people involved with the project. It includes all the project
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
Managing IT Projects. Chapter 2 The PMI Framework
Managing IT Projects Chapter 2 The PMI Framework The PMI Framework The Project Management Institute,USA is an internationally acclaimed organization Devoted to Creation & sharing of knowledge in the area
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: [email protected]
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.
Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management
PBL: Project Management. Competency: Project Definition
Competency: Project Definition 1. Define project management and the context of modern project management. 2. Describe how to manage projects throughout the five major process groups. 3. Define the characteristics
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Certification Preparation Course LATVIKON (R.E.P.)Centre
PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional
A COMPARISON OF PRINCE2 AGAINST PMBOK
Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the
Project Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
Project Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Computing Services Network Project Methodology
Computing Services Network Project Prepared By: Todd Brindley, CSN Project Version # 1.0 Updated on 09/15/2008 Version 1.0 Page 1 MANAGEMENT PLANNING Project : Version Control Version Date Author Change
Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012
Minnesota Health Insurance Exchange Project (MNHI) Deliverable Definition Document (DDD) For Project Plan Date: 07-31-2012 11/9/2012 1:18 PM Page 1 of 8 1. High Level Deliverable Description The Project
Recognition of Prior Learning (RPL) Kit. BSB51407 Diploma of Project Management
Recognition of Prior Learning (RPL) Kit BSB51407 Diploma of Project Management Applicant: Date: Diploma of Project Management RPL Kit 1 Applicant declaration: I have completed the following RPL application
Positive Train Control (PTC) Program Management Plan
Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information
output: communications management plan
Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
Project Management Office (PMO)
Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition
A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) February 2010 Version 1.12 Copyright: Australian Institute of Project Management Document
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
Project Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University
Project Management Institute (PMBOK 2000) PMP Preparation Worksheet
Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against
PMP Short Notes Based on PMBOK Guide fifth edition By Dilip Chaturvedi,PMP Email id: [email protected] To know about our training schedule, please visit www.justpmp.com 1. Communication is more complex
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
PROJECT QUALITY MANAGEMENT
8 PROJECT QUALITY MANAGEMENT Project Quality Management includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It includes all activities of the
State of Michigan (SOM) August 2013. Department of Technology, Management & Budget
State of Michigan (SOM) PROJECT MANAGEMENT KEY TERMS, DEFINITIONS AND ACRONYMS August 2013 Department of Technology, Management & Budget Table of Contents Table of Contents Key Terms, Definitions, and
Software Project Management Plan (SPMP)
Software Project Management Plan (SPMP) The basic template to be used is derived from IEEE Std 1058-1998, IEEE Standard for Software Project Management Plans. The following is a template for the SPMP.
THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT
THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT GERARD M. HILL CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Croup, an informa business
Making project management indispensable for business results. Project Management 101
Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Errata 1 st Printing. Errata 2 nd Printing
Errata 1 st Printing NOTE: The following errata only pertain to the first printing of the PMBOK Guide Fifth Edition. In order to verify the print run of your book (or PDF), refer to the bottom of the copyright
PROJECT PLAN TEMPLATE
Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Management/Information Technology PROJECT PLAN TEMPLATE Document Revision Draft
Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices
: A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
Project Time Management an essential element to project success
Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series The Roles, Responsibilities and Skills in Project Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
Project Management Competency Standards
BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply
Truly Managing a Project and Keeping Sane While Wrestling Elegantly With PMBOK, Scrum and CMMI (Together or Any Combination)
Truly Managing a Project and Keeping Sane While Wrestling Elegantly With PMBOK, Scrum and CMMI (Together or Any Combination) Neil Potter The Process Group Lead Appraiser / Improvement Coach Organization
Project Cost Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
PM Planning Configuration Management
: a Project Support Function As stated throughout the Project Planning section, there are fundamental components that are started during the pre-performance stage of the project management life cycle in
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Using Microsoft SharePoint for Project Management
ASPE IT Training Using Microsoft SharePoint for Project Management A WHITE PAPER PRESENTED BY ASPE www.aspe-it.com 877-800-5221 Using Microsoft SharePoint for Project Management A modern Project Management
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
ICT Project Management
THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE PUBLIC SERVICE MANAGEMENT ICT Project Management A Step-by-step Guidebook for Managing ICT Projects and Risks Version 1.0 Date Release 04 Jan 2010 Contact
The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)
The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) 11/17/07 Introduction Editor's Note: We liked so much of this book that we asked for the author's permission to quote
Project Knowledge Areas
From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.
5.1 Project Control Overview
5.1 Project Control Overview Project Control is a formal process in project management. In most respects, there is not a lot of room for creativity in the Control Phase of project management. The PMBOK
Software Project Management I
Software Project Management I Dr. Jong Yih Kuo Dr. Chien-Hung Liu Computer Science and Information Engineering National Taipei University of Technology Course Schedule Time Topic Document 18:10~18:55 (45
