1 Bowmanville Marsh Habitat Restoration and Public Access Project Terms of Reference for Detailed and Conceptual Design Works December 2015

2 1.0 Background and Purpose The Bowmanville Marsh Habitat Restoration Project focuses on improving the wetland conditions and habitat opportunities within the Bowmanville Marsh, a 33-hectare Provincially Significant Lake Ontario coastal wetland located in the Municipality of Clarington, and within the 66 ha Bowmanville/Westside Conservation Area that is owned and managed by CLOCA. 12 years of monitoring data collected through the Durham Region Coastal Wetland Monitoring Project (DRCWMP) has shown that Bowmanville Marsh is in a generally poor, declining condition. The ultimate goal of the Bowmanville Marsh Habitat Restoration Project is to significantly improve the wetland conditions in the marsh by isolating the marsh from the Bowmanville Creek and controlling water levels in the marsh in a way that better mimics natural pre-regulation Lake Ontario water level fluctuation. The installation of a berm and control structure along the mouth of the wetland will be required to achieve this goal. Water level control within the Marsh will allow for both periods of low water levels to stimulate wetland plant growth (for up to 1 year in length), and periods of high water level to limit plant growth (for up to 1 year in length). Bowmanville Marsh is partially separated from Bowmanville/Soper Creek along its eastern boundary by an earthen levee. Some of this levee has been naturally created by deposition from the adjacent creek over the last century, over the same period of time, dredged material from surrounding harbor activities has also been placed on the berm. At the north limit of the Marsh, flood water from the Bowmanville/Soper Creek periodically enters the Marsh during spring freshet or significant rain event floods. Beyond the occasional flow event into the north end of the Marsh, the wetland water level is controlled by the water level of the Bowmanville/Soper Creek at the Marsh outlet (southeast limit). The creek water level is directly linked to the water level of Lake Ontario. The goal of the public access component of this project is to incorporate low impact recreation features taking into consideration the Bowmanville Marsh Habitat Restoration Project staging and access requirements for construction equipment. 1

3 Several technical studies have been completed in support of this project and are listed below: Durham Region Coastal Wetland Monitoring Project: Wetland Conditions and Management Report (Module 16 is Bowmanville Marsh) prepared by CLOCA and Environment Canada dated December Bathymetry survey completed by Canadian Wildlife Services dated April Topographic Survey completed by CLOCA dated March Digital elevation model of topographic and bathymetry surveys prepared by CLOCA dated December Bowmanville Marsh Restoration Hydrological Study prepared by CLOCA dated March Bowmanville Marsh Restoration Water Level Monitoring Study prepared by CLOCA dated A Soil Investigation for Proposed Bowmanville Marsh Investigation prepared by Soil Engineers Ltd., Dated April The investigational geotechnical study outlines the borehole and soil sampling data collected along the existing levee and within proposed berm/control structure location. The purpose of this study is to generate a detailed design for the Bowmanville Marsh Restoration Project and a concept plan for the public access component. The detailed design will include a berm and water level control structure at the mouth of Bowmanville Marsh. The proposed berm and control structure should be designed to provide a range in marsh water levels. Another previous study investigated the potential range in water levels. The maximum proposed water level will be assumed to be no greater than 75.76, which is the maximum historical high water elevation of Lake Ontario (1952) and the minimum proposed water level will be below the normal creek water levels. Lowest possible water levels within the marsh are proposed approximately once every 10 years, for the equivalent of one full growing season. A secondary berm and control structure will be required at the north limit of the Marsh to control high flow inputs to the Marsh from the Bowmanville/Soper Creek. The proposed inlet structure at the north end of the Bowmanville Marsh should also be incorporated into the detailed design. The purpose of the public access conceptual plan is to connect the existing parking lot to the berm and control structure project with an accessible trail, naturalized planting, interpretive signage, fishing nodes, kayak and canoe access and an accessible portage feature. Figure 1 presents an aerial photo of the marsh and identifies key locations. 2

4 PUBLIC ACCESS

5 2.0 Study Approach The following outlines the two stage approach for the proposed restoration project: Stage 1: Detailed Design of Berm, Control Structure and Inlet Control Structure Detailed review of project background material. Site visit and project start-up meeting. Develop and present feasible design options to CLOCA and Municipality of Clarington Present design alternatives Complete detailed design of preferred design option. Finalize engineering drawings and report. Prepare construction cost estimate. Obtain approvals from applicable Municipal/Provincial/Federal Agencies. Stage 2: Conceptual Landscape Design Detailed review of project background material. Site visit and project start-up meeting. In consultation with CLOCA staff, prepare an analysis of the study area in its proposed form featuring existing infrastructure to guide the landscape design process. Develop the best options for public access based on hydrologic and hydraulic constraints; proposed berm location, bathymetry, terrestrial natural heritage data; fish data; and existing surrounding land use. Provide conceptual designs and mapping identifying public access opportunities for pedestrians, anglers, non-motorized recreational boating activities including launching and portaging, wildlife viewing and interpretation activities. Public safety design considerations. Signage and/or commemorative features to acknowledge project partners. Public Process CLOCA has included public consultation throughout the Management planning for the Bowmanville/Westside Marshes Conservation Area Master Plan, and Bowmanville Marsh Restoration Project. CLOCA will continue the commitment to public consultation through the design and development of this project. Public information sessions to showcase the design of restoration features will be arranged, financed, and managed by CLOCA. CLOCA will also work closely with staff from the Municipality of Clarington, to ensure the Restoration works compliment the municipal development of the Port Darlington waterfront parkland development. CLOCA reserves the right to administer this project in two (2) parts should they choose to do so. Please prepare the bid in two (2) parts to correspond to the above sections. 4

6 3.0 Deliverables Report submissions will be required through the study process as follows: Final Study Report with design drawings - 6 copies. The final report/drawings will also be made available to CLOCA in digital form (PDF). The consultant should also budget for a minimum of three (3) meetings with CLOCA to be held at project start-up, presentation of design alternatives, and completion of design. 4.0 Proposal Contents and Submission All proposals shall be evaluated based on the suggested methodology and work program, company experience, staffing experience, knowledge of the watershed, and cost. CLOCA reserves the right to reject any or all proposals should it be deemed in their best interest to do so. A complete proposal shall include the following information: I. A Work Plan including a brief description of the methodology should be provided. Any optional/additional work suggested in the interest of creating a better product should be identified and priced as a separate item. II. III. IV. Per Diem and Project Component Costs shall be provided as well as total costs (including GST) for all work required to complete the project Company Experience with soils analysis and borehole projects shall be identified. Please list recent similar projects and provide references. Similar information should be provided for any sub-consultants that are part of the study team. Key Staff Members that will lead the various components of the study shall be identified, and a summary of recent experience for each individual provided. Where subconsultants are proposed, list projects where the various study members worked together. The structure of the study team is to be clearly identified with one individual ultimately responsible for reporting to CLOCA. V. Any Potential Conflicts shall be listed including on-going work for development or personal interests within the area. Two copies of proposals are to be received by the Central Lake Ontario Conservation Authority by 2:00pm, January 18, Late submissions will not be accepted. 5

Restoration Planning and Development of a Restoration Bank

Restoration Planning and Development of a Restoration Bank Restoration Planning and Development of a Restoration Bank Black Creek Pioneer Village, South Theatre 8:30 a.m. to 3:30 p.m. Habitat Restoration and Environmental Monitoring Projects Section Restoration

More information

Request for Proposal

Request for Proposal Request for Proposal Business Plan for the Development of the North Bay Community Waterfront Park 1. Introduction: This Request for Proposal ( RFP ) seeks to establish a firm or consortium of firms ( Consultant

More information

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water

More information

Pioneer Park Stormwater Management Rehabilitation Project Town of Richmond Hill Engineering and Public Works Department Design, Construction and

Pioneer Park Stormwater Management Rehabilitation Project Town of Richmond Hill Engineering and Public Works Department Design, Construction and Pioneer Park Stormwater Management Rehabilitation Project Town of Richmond Hill Engineering and Public Works Department Design, Construction and Water Resources Division Presentation Outline Background

More information

Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects.

Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects. American Recovery and Reinvestment Act (ARRA) Emergency Watershed Protection Program Floodplain Easements Rhode Island Natural Resources Conservation Service Rhode Island NRCS received approximately $2.4

More information

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013. Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank

More information

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN 3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards

More information

March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633

March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633 ADDENDUM TO THE MICHELSON WATER RECLAMATION PLANT PHASE 2 & 3 CAPACITY EXPANSION PROJECT FEBRUARY 2006 FINAL ENVIRONMENTAL IMPACT REPORT AND THE SAN JOAQUIN FRESHWATER MARSH ENHANCEMENT PLAN REVISED SEPTEMBER

More information

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN 1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially

More information

West London Dyke Flood Control Structure Master Plan Appendix A

West London Dyke Flood Control Structure Master Plan Appendix A West London Dyke Flood Control Structure Master Plan Appendix A Introduction The West London Dyke runs along the west bank of the North Branch of the Thames River from Oxford Street to the forks of the

More information

Background Information: The Mamquam River Floodplain Restoration Project

Background Information: The Mamquam River Floodplain Restoration Project Background Information: The Mamquam River Floodplain Restoration Project The Mamquam River Floodplain Restoration project is being undertaken in partnership with the Squamish River Watershed Society, Fisheries

More information

San Francisco Bay Area Wetlands Restoration Program Design Review Group. Project Summary Outline

San Francisco Bay Area Wetlands Restoration Program Design Review Group. Project Summary Outline San Francisco Bay Area Wetlands Restoration Program Design Review Group Project Summary Outline The project proponent desiring to have a project considered by the Design Review Group (DRG) shall provide

More information

Halton Region Planning & Public Works Committee Meeting July 8, 2015

Halton Region Planning & Public Works Committee Meeting July 8, 2015 Acton Quarry Extension Halton Region Planning & Public Works Committee Meeting July 8, 2015 1 Proposed Extraction Area 50% Reduction The extraction area was reduced by 50% to address comments from the

More information

AN INITIATIVE TO IMPROVE

AN INITIATIVE TO IMPROVE L OW E R C A R M E L R I V E R A N D L AG O O N F L O O D P L A I N R E S TO R AT I O N A N D E N H A N C E M E N T P R O J E C T AN INITIATIVE TO IMPROVE FLOOD PROTECTION RESTORE AND PROTECT RIPARIAN

More information

Attachment 1 CARRUTHERS CREEK FLOOD MANAGEMENT and ANALYSIS DRAFT TERMS OF REFERENCE

Attachment 1 CARRUTHERS CREEK FLOOD MANAGEMENT and ANALYSIS DRAFT TERMS OF REFERENCE 1.0 INTRODUCTION In early 2010, the Town of Ajax was provided with updated floodplain mapping for Carruthers Creek, based on a Regional Storm event (i.e., Hurricane Hazel), prepared by the Toronto and

More information

How To Protect A Floodplain From Flooding

How To Protect A Floodplain From Flooding EXECUTIVE SUMMARY This Class Environmental Assessment (Class EA) was undertaken to examine alternative flood protection systems, and their environmental effects, for the elimination of the flood risk on

More information

Penticton Creek May 4, 2015 Council Meeting

Penticton Creek May 4, 2015 Council Meeting Penticton Creek May 4, 2015 Council Meeting Penticton Creek Council Meeting May 4, 2015 Penticton Creek in the Early Years Penticton Creek Council Meeting May 4, 2015 Penticton Creek Today Penticton Creek

More information

TITLE: [Name of municipality] Storm Water Abatement Feasibility Study

TITLE: [Name of municipality] Storm Water Abatement Feasibility Study TITLE: [Name of municipality] Storm Water Abatement Feasibility Study PROBLEM/NEED: [Name of watershed] is an area of [##] acres, surrounding [name of waterbody]. [Name of waterbody] has been assessed

More information

FOUR RIVERS RESTORATION PROJECT

FOUR RIVERS RESTORATION PROJECT MLTM Republic of Korea Making Every Drop Count International Workshop on Integrated Urban Water Management WATER & GREEN GROWTH FOUR RIVERS RESTORATION PROJECT Office of National River Restoration, Korea

More information

Water Security Agency. Plan for 2015-16. saskatchewan.ca

Water Security Agency. Plan for 2015-16. saskatchewan.ca Water Security Agency Plan for 2015-16 saskatchewan.ca Statement from the Minister I am pleased to present the Water Security Agency s Plan for 2015-16. The Honourable Scott Moe Minister Responsible for

More information

Arkansas River Corridor Vision & Master Plan

Arkansas River Corridor Vision & Master Plan A r k a n s a s R I v e r C o r r I d o r P l a n Arkansas River Corridor Vision & Master Plan July 2005 Indian Nations Council of Governments A r k a n s a s R I v e r C o r r I d o r P l a n Partnership

More information

Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013

Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 1. Design alternatives for large capital flood projects (basinlevel water retention and Interstate

More information

Briefing Paper on Lower Galveston Bay and Bayou Watersheds Lower Bay I: Armand Bayou to Moses Lake and Adjacent Bay Waters

Briefing Paper on Lower Galveston Bay and Bayou Watersheds Lower Bay I: Armand Bayou to Moses Lake and Adjacent Bay Waters Briefing Paper on Lower Galveston Bay and Bayou Watersheds Lower Bay I: Armand Bayou to Moses Lake and Adjacent Bay Waters Jim Lester, PhD. and Lisa Gonzalez Houston Advanced Research Center Galveston

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013

REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013 REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013 CENTRAL NEW YORK REGIONAL PLANNING AND DEVELOPMENT BOARD 126 NORTH SALINA

More information

Nipigon Bay. Area of Concern Status of Beneficial Use Impairments September 2010

Nipigon Bay. Area of Concern Status of Beneficial Use Impairments September 2010 Nipigon Bay Area of Concern Status of Beneficial Use Impairments September 2010 Nipigon Bay is in the most northerly area of Lake Superior. The Area of Concern takes in a large portion of Nipigon Bay and

More information

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project. The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along

More information

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:

More information

Community Workshop 5. Overarching Goals for Machado Lake Ecosystem and Wilmington Drain Multi-Use Projects

Community Workshop 5. Overarching Goals for Machado Lake Ecosystem and Wilmington Drain Multi-Use Projects City of Los Angeles Department of Public Works Bureau of Engineering Machado Lake Ecosystem Rehabilitation Project & Wilmington Drain Multi-Use Project Community Workshop 5 February 24, 2009 In association

More information

NEW BRUNSWICK DEPARTMENT OF SUPPLY AND SERVICES EEL RIVER DAM REMOVAL/ DECOMMISSIONING PROJECT

NEW BRUNSWICK DEPARTMENT OF SUPPLY AND SERVICES EEL RIVER DAM REMOVAL/ DECOMMISSIONING PROJECT NEW BRUNSWICK DEPARTMENT OF SUPPLY AND SERVICES EEL RIVER DAM REMOVAL/ DECOMMISSIONING PROJECT August 2006 Prepared by: NB Department of Environment Environment 1. INTRODUCTION This General Review Statement

More information

4.2 Buena Vista Creek Watershed

4.2 Buena Vista Creek Watershed Buena Vista Creek Watershed 4.2 Buena Vista Creek Watershed Watershed Overview The Buena Vista Creek Watershed is the fourth-largest system within the Carlsbad Hydrologic Unit. The watershed extends approximately

More information

ANGORA FIRE RESTORATION PROJECT

ANGORA FIRE RESTORATION PROJECT ANGORA FIRE RESTORATION PROJECT U.S. Forest Service LAKE TAHOE BASIN MANAGEMENT UNIT Duncan Leao Vegetation Management Planner Richard Vacirca Forest Aquatics Biologist 3 PHASES OF FIRE REHAB Phase I Rehab:

More information

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Harmony Creek subwatershed Harmony Creek subwatershed BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT April 2011 TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION. Lower Carmel River Floodplain Restoration and Enhancement Project

ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION. Lower Carmel River Floodplain Restoration and Enhancement Project ECONOMIC ANALYSIS FLOOD DAMAGE REDUCTION Lower Carmel River Floodplain Restoration and Enhancement Project I. Description of the Project and its Relationship to Other Projects in the Proposal The Lower

More information

Appendix A. Lists of Accomplishments and Project Costs. UMRWD 10 Year Plan Update. Appendix A UPPER MINNESOTA RIVER WATERSHED DISTRICT

Appendix A. Lists of Accomplishments and Project Costs. UMRWD 10 Year Plan Update. Appendix A UPPER MINNESOTA RIVER WATERSHED DISTRICT UPPER MINNESOTA RIVER WATERSHED DISTRICT Lists of Accomplishments and Project Costs 10 Year Plan Update UMRWD 10 Year Plan Update Page A 1 UMRWD LIST OF ACCOMPLISHMENTS Since its inception in 1967, the

More information

Michigan Wetlands. Department of Environmental Quality

Michigan Wetlands. Department of Environmental Quality Department of Environmental Quality Wetlands are a significant component of Michigan s landscape, covering roughly 5.5 million acres, or 15 percent of the land area of the state. This represents about

More information

Thunder Bay. Area of Concern Status of Beneficial Use Impairments September 2010

Thunder Bay. Area of Concern Status of Beneficial Use Impairments September 2010 Thunder Bay Area of Concern Status of Beneficial Use Impairments September 2010 The Thunder Bay Area of Concern extends approximately 28 km along the shoreline of Lake Superior from north of Bare Point

More information

3. The submittal shall include a proposed scope of work to confirm the provided project description;

3. The submittal shall include a proposed scope of work to confirm the provided project description; QIN Shoreline Master Program Project Summary The Shoreline Master Program (SMP) development process for the Quinault Indian Nation (QIN) includes the completion of inventory and analysis report with corresponding

More information

Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting

Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting Urban Stream Restoration Defining the Full Benefits of a Project Warren C. High MACTEC Engineering and Consulting Economics in the Decision Process Return on Investment Willingness to Pay Municipal Growth

More information

Rediscovery of Two Federally Listed Rare Plant Species in New York

Rediscovery of Two Federally Listed Rare Plant Species in New York Rediscovery of Two Federally Listed Rare Plant Species in New York Beverly Simone Kimberly J. Smith, NY Natural Heritage Program and NYS Office of Parks, Recreation, and Historic Preservation and Steve

More information

HERE COMES THE RAIN AGAIN Stormwater Management in a Changing Climate at the City of Toronto

HERE COMES THE RAIN AGAIN Stormwater Management in a Changing Climate at the City of Toronto HERE COMES THE RAIN AGAIN Stormwater Management in a Changing Climate at the City of Toronto Evergreen s Urban Watershed Forum 20 March 2015 Presented by Kurtis Elton Policy & Program Advisor, Toronto

More information

RESTORATION AND ENHANCEMENT OF SOUTHERN CALIFORNIA LAGOONS

RESTORATION AND ENHANCEMENT OF SOUTHERN CALIFORNIA LAGOONS RESTORATION AND ENHANCEMENT OF SOUTHERN CALIFORNIA LAGOONS by Hany Elwany, Ph.D. Scripps Institution of Oceanography Headwaters to Oceans Conference 25 October 2003 CE Ref #03-22 San Diego County Lagoons

More information

City of Red Wing REQUEST FOR QUALIFICATIONS. Levee Park - Riverboat & Transient Boat Dockage, Park and Promenade Improvements Professional Services

City of Red Wing REQUEST FOR QUALIFICATIONS. Levee Park - Riverboat & Transient Boat Dockage, Park and Promenade Improvements Professional Services City of Red Wing REQUEST FOR QUALIFICATIONS Levee Park - Riverboat & Transient Boat Dockage, Park and Promenade Improvements Professional Services RFQ Release Date: November 2, 2015 Statement of Qualifications

More information

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO.

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO. COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO. 6 RENEWABLE ENERGY Image Source: (Word Clip Art Stock Photo, 2011) Date: May, 2015 BACKGROUND PLANNING AND DEVELOPMENT SERVICES DEPARTMENT 789

More information

What Is Rehabilitation?

What Is Rehabilitation? Location of Aggregate Operations Ready Mix Plant Locations Aggregate Locations Cement Terminal Locations What Is Rehabilitation? Rehabilitation is the treatment of land from which aggregate has been excavated

More information

Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria

Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria Memorandum TO: FROM: Michael Bergstrom and Robin Cole City of Bellevue Nancy Bird, AICP EDAW, Inc. DATE: July 23, 2008 RE: Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria

More information

Using an All lands Framework for Conservation of Ecosystem Services

Using an All lands Framework for Conservation of Ecosystem Services Using an All lands Framework for Conservation of Ecosystem Services Robert Deal USDA Forest Service - PNW Research Station, Portland, OR Nikola Smith USDA Forest Service - Pacific Northwest Region, Portland,

More information

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold CHAPTER 11 GLOSSARY OF TERMS Active Channel The channel that contains the discharge Leopold where channel maintenance is most effective, sediment are actively transported and deposited, and that are capable

More information

St. Clair College Planning Area Introduction

St. Clair College Planning Area Introduction Introduction What is the Study Area? St. Clair College Planning Area is bounded by Highway 3 to the west, Cabana Road to the north, the residential community of South Windsor to the east and Cousineau

More information

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Whitby CLOCA Whitby CLOCA LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT June 2008 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 STUDY AREA AND SCOPE... 4 3.0 METHODOLOGY...

More information

Acton Quarry Extension. Halton Region June 11, 2014

Acton Quarry Extension. Halton Region June 11, 2014 Acton Quarry Extension Halton Region June 11, 2014 1 Background Background Proposed Extraction Area Compliance with Ministry Guidelines Halton Region Official Plan Greenlands System Conveyance of Land

More information

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing

More information

Newsletter Jumbo Glacier Alpine Resort Proposal

Newsletter Jumbo Glacier Alpine Resort Proposal Newsletter Jumbo Glacier Alpine Resort Proposal August 1995 - Number 1 - Environmental Assessment Office Province of British Columbia The Jumbo Glacier Alpine Resort Proposal Pheidias Project Management

More information

Provincial Policy Statement

Provincial Policy Statement 2014 Provincial Policy Statement Under the Planning Act Ontario.ca/PPS For more copies of this document, in either English or French, please contact: Ministry of Municipal Affairs and Housing Provincial

More information

Henry Van Offelen Natural Resource Scientist MN Center for Environmental Advocacy [email protected]

Henry Van Offelen Natural Resource Scientist MN Center for Environmental Advocacy hvanoffelen@mncenter.org Henry Van Offelen Natural Resource Scientist MN Center for Environmental Advocacy [email protected] Wetland study slide Water Quality NRE goals in watershed plans Protect habitat that remains.

More information

FLOOD PLAIN DESIGNATION AND PROTECTION

FLOOD PLAIN DESIGNATION AND PROTECTION CITY OF RICHMOND FLOOD PLAIN DESIGNATION AND PROTECTION BYLAW NO. 8204 EFFECTIVE DATE - SEPTEMBER 8, 2008 CONSOLIDATED FOR CONVENIENCE ONLY This is a consolidation of the bylaws listed below. The amendment

More information

Thank you to all of our 2015 sponsors: Media Partner

Thank you to all of our 2015 sponsors: Media Partner Thank you to all of our 2015 sponsors: Media Partner Channel Naturalization: Planning and Implementation in Peel Region TRIECA March 25 & 26, 2015 Peel Region Channel Remediation Strategy An Urban Context

More information

Burnt River Black River and Gull River Flood Contingency Plan

Burnt River Black River and Gull River Flood Contingency Plan Burnt River Black River and Gull River Flood Contingency Plan Objective: The objective of this plan is to preplan and prepare for flooding events in the Burnt River, Black River and Gull River area of

More information

Coastal Engineering Indices to Inform Regional Management

Coastal Engineering Indices to Inform Regional Management Coastal Engineering Indices to Inform Regional Management Lauren Dunkin FSBPA 14 February 2013 Outline Program overview Standard products Coastal Engineering Index Conclusion and future work US Army Corps

More information

United States Army Corps of Engineers, Civil Works

United States Army Corps of Engineers, Civil Works United States Army Corps of Engineers, Civil Works Fiscal Year 2013 Federal Program Inventory May 2013 Table of Contents Introduction... 2 Program Inventory... 3 1. Navigation... 3 2. Flood Risk Management...

More information

RE: Docket # COE 2010 0035; ZRIN 0710 ZA05 Submitted via email to [email protected] and Rulemaking Portal at www.regulations.gov.

RE: Docket # COE 2010 0035; ZRIN 0710 ZA05 Submitted via email to NWP2012@usace.army.mil and Rulemaking Portal at www.regulations.gov. April 18, 2011 U.S. Army Corps of Engineers Attn: CECW CO R 441 G Street, N.W. Washington, DC 20314 1000 RE: Docket # COE 2010 0035; ZRIN 0710 ZA05 Submitted via email to [email protected] and Rulemaking

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Throughout the Plan 1. There is a fundamental need for the revised plan to address how

More information

Photo by Jeff Thibodeau, Helios Land Design

Photo by Jeff Thibodeau, Helios Land Design SECTION 11 REFERENCES Photo by Jeff Thibodeau, Helios Land Design PUBLIC REVIEW DRAFT Cape Cod Commission, Affordable Housing Funds, Memo from Paul Ruchinskas to County Commissioners, January 4, 2006.

More information

Post-Flood Assessment

Post-Flood Assessment Page 1 of 7 Post-Flood Assessment CHAPTER 4 AGENCY COORDINATION Agency coordination is an essential element for the operation of the flood management systems in the Central Valley. Due to the nature of

More information

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby 7. 5 A d v a n t a g e s a n d D i s a d v a n t a g e s Table 22 summarizes the advantages and disadvantages of each option based on the evaluation of Table 16. Dillon Consulting Limited Page 75 Table

More information

St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m.

St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m. St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m. City Council Study Session Room City of Longmont Civic Center, 350 Kimbark Street, Longmont Minutes 1. Introductions a. Jeff Crane

More information

THE 4 MAJOR RIVERS RESTORATION PROJECT

THE 4 MAJOR RIVERS RESTORATION PROJECT MLTM Republic of Korea WATER IN THE GREEN ECONOMY IN PRACTICE: TOWARDS RIO+20 WATER & GREEN GROWTH THE 4 MAJOR RIVERS RESTORATION PROJECT Office of National River Restoration, Korea 3 to 5 October 2011

More information

One Major Six Concentrations. Department of Environmental Conservation University of Massachusetts Amherst

One Major Six Concentrations. Department of Environmental Conservation University of Massachusetts Amherst One Major Six Concentrations Natural Resources Conservation Undergraduate Major Department of Environmental Conservation University of Massachusetts Amherst Conserving Earth s biological diversity and

More information

How To Rehabilitate A Dam In A Lake Dike

How To Rehabilitate A Dam In A Lake Dike Herbert Hoover Dike Rehabilitation Reach 1 Construction Reaches 2 and 3 Major Rehabilitation Report Briefing Purpose Provide a status update of the HHD rehabilitation project and a description of the upcoming

More information

Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE

Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE Introductions Brett Long, PE Project Permitting & Construction Oversight Chris Streb, PE Project Designer & Construction Oversight Assistance WHO WE ARE

More information

I.I. 2015-16 Action Plan. Canada-US Cooperation in the Salish Sea: Environment Environnement ft EA~ United s tates. Canada Canada,,.

I.I. 2015-16 Action Plan. Canada-US Cooperation in the Salish Sea: Environment Environnement ft EA~ United s tates. Canada Canada,,. Canada-US Cooperation in the Salish Sea: 2015-16 Action Plan I.I Environment Environnement ft EA~ United s tates tl...w~ Environmental Protection Canada Canada,,. Agency Fifteen Years of International

More information

Mer Bleue Wetland Management Plan: Executive Summary National Capital Commission National Capital Greenbelt 202-40 Elgin Street Ottawa, Ontario K1P

Mer Bleue Wetland Management Plan: Executive Summary National Capital Commission National Capital Greenbelt 202-40 Elgin Street Ottawa, Ontario K1P Mer Bleue Wetland Management Plan: Executive Summary National Capital Commission National Capital Greenbelt 202-40 Elgin Street Ottawa, Ontario K1P 1C7 March 2007 PREFACE The Mer Bleue Wetland Management

More information

Appendix B: Cost Estimates

Appendix B: Cost Estimates Appendix B: Estimates This appendix presents the estimated costs of the monitoring and supplemental research components presented in Section 3 of this document. A 20% quality assurance and quality control

More information

HARBOR INFRASTRUCTURE INVENTORIES Port Austin Harbor, Michigan

HARBOR INFRASTRUCTURE INVENTORIES Port Austin Harbor, Michigan HARBOR INFRASTRUCTURE INVENTORIES Port Austin Harbor, Michigan Harbor Location: Port Austin Harbor is located at the tip of the thumb of Michigan, about 80 miles northeast of Saginaw, MI Authority: Rivers

More information

Recognizing Wetlands. For additional information contact your local U.S. Army Corps of Engineers office. Pitcher plant.

Recognizing Wetlands. For additional information contact your local U.S. Army Corps of Engineers office. Pitcher plant. US Army Corps of Engineers For additional information contact your local U.S. Army Corps of Engineers office. 1998 Edition Recognizing Wetlands Pitcher plant The information presented here will help you

More information

COASTAL APPLICATION FOR A MAJOR SITING PERMIT

COASTAL APPLICATION FOR A MAJOR SITING PERMIT Frank M. Rabauliman Administrator Commonwealth of the Northern Mariana Islands OFFICE OF THE GOVERNOR Bureau of Environmental and Coastal Quality Division of Coastal Resources Management Gualo Rai Center

More information

TABLE OF CONTENTS. Page. Executive Summary

TABLE OF CONTENTS. Page. Executive Summary TABLE OF CONTENTS Executive Summary Page i-ii Chapter 1: Purpose, Introduction and Background 1 Chapter 2: The Planning Process 4 Map 1: Naturally Reproducing Trout & Wilderness Trout Streams 13 Chapter

More information

Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016

Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016 Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016 James L. McIntire Washington State Treasurer Summary The State of Washington offered green bonds to investors in September 2015, with approximately

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

Integrated Restoration Prioritization

Integrated Restoration Prioritization Integrated Restoration Prioritization Habitat Restoration and Environmental Monitoring Projects Section Restoration Services Division Definition Restoration Prioritization is a process of combining various

More information

Navigating the Credit River by Canoe, Kayak, Raft and Tubes

Navigating the Credit River by Canoe, Kayak, Raft and Tubes Navigating the Credit River by Canoe, Kayak, Raft and Tubes NOTE: Credit Valley Conservation does not endorse navigation of the river, trespassing nor suggests that it is a safe recreational activity.

More information

Haynes Recreation Center, Laredo, TX. Data Matrix and Sustainability Benchmarks

Haynes Recreation Center, Laredo, TX. Data Matrix and Sustainability Benchmarks Haynes Recreation Center, Laredo, TX Data Matrix and Sustainability Benchmarks (Updated Spring 2010) 1 Standard Benchmarks BENCHMARKS UNITS PRE PROJECT GOAL Property value (pre/post) Assessed or redevelopment

More information

The 25 Year Saskatchewan Water Security Plan. February 2013

The 25 Year Saskatchewan Water Security Plan. February 2013 The 25 Year Saskatchewan Water Security Plan February 2013 OUTLINE Challenges The Plan The Agency Implications for Agriculture Water Security Plan Development Consultation in 2011 with 174 individuals

More information

The answers to some of the following questions are separated into two major categories:

The answers to some of the following questions are separated into two major categories: Following the recent flooding events for Front Range communities in Colorado, property owners, communities, and the National Flood Insurance Program are being presented with some new challenges in the

More information