1 CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT February 2015 Project Management Division BELOW: Collins Construction crews complete recent exterior work and await delivery of exterior siding. Collins Construction is over 75% complete with construction of the new Joe Redington Sr. JR/SR High School. The School District is anxious to move into their new high school in August New Joe Redington Sr. JR/SR High School ($65M): In February, Collins Construction completed an extensive amount of work, and is over 75% complete with construction. Collins has completed all roofing, steel erection and metal stud framing. Fire sprinkler and ceramic tile install, mechanical and electrical roughin is nearly complete. Finishes such as: sheet rocking and painting; ceramic tile, hand railings and casework install; and concrete floor polishing are progressing well. Plus, installers have begun construction of the 210,000 gallon water tank. Our project team is focused to remain on schedule to complete construction of this school by August 2015, and relieve overcrowding in Wasilla Middle School and Wasilla High School. ABOVE LEFT: Erection of the 210,000 gallon fire suppression water tank began in February. RIGHT: New basketball backboards were installed recently in preparation for March Madness at the Joe Redington Sr. JR/SR High School. Page 1 of 6
2 District-Wide Athletic Field Improvements ($6.5M): Tutka Construction has completed 99% of 2014 upgrades to the athletic fields and courts at five schools - Finger Lake, Snowshoe and Larson Elementary, Glacier View, and Houston High School. Tutka is awaiting receipt of basketball backboards to complete the play courts, and will complete seeding of the grass in the spring. In January, Stantec engineers completed the 100% design of the 2015 Athletic Fields Improvements, including: Su-Valley High, Palmer Junior Middle, Wasilla High, and Glacier View schools. These larger projects, such as the rubberized-surface track at Su-Valley, were advertised in February for construction during the summer of Houston High School Exterior Envelope Upgrades ($600K:) In February, Eklutna Services, LLC continued to work on replacement of the Houston High school exterior siding and is currently 60% complete with the work. Unfortunately, procurement issues have caused delays in the production of concrete panels, however, Eklutna plans to replace the siding in spring RIGHT: Houston High School siding is being replaced by Eklutna Services. The new panels are much more durable than the original siding. Swanson Elementary School Exterior Envelope Repairs ($260K): In 2014, Wolverine Supply replaced the damaged exterior tile. This contract work also includes replacement of the commons and library skylights, which are scheduled for replacement in The Library skylight will be replaced in March and the commons skylight in June. District-Wide Fire Alarm System Replacement ($1M): Remaining funds after replacement of fire alarm systems at 13 schools supports the replacement of fire alarm systems at five additional schools. AMC Engineers is 35% complete with designing upgrades of the fire alarm systems at Palmer High, Big Lake Elementary, Burchell High, Wasilla High, and Teeland Middle schools. After the design is complete, we will advertise for construction to begin in New Iditarod Elementary School ($25M): This project will construct a 50,605 square foot elementary school that will replace the existing outdated facility. McCool Carlson Green (MCG) was selected as the designer. This project is currently advertised for construction with bids due March 25th. Work is expected to start this spring and will be ready for occupancy by the 2016 school year. Plans for the old building have yet to be determined. Page 2 of 6
3 Design concept Willow Elementary School Roof Replacement ($1.1M): A construction contract was awarded to Earhart Roofing to replace the entire Willow Elementary School roof. During the project, some structural deficiencies were discovered that required both interior and exterior upgrades which are now complete. District Wide ADA Upgrades ($1.5M): Work includes district wide American Disabilities Act upgrades to parking lots, sidewalks, ramps, curbs, and restrooms at all middle and high schools. A design contract was awarded to Wolf Architecture with construction expected to advertise this month. Work will occur over the 2015 summer break. District Wide Roof Replacements ($6M): This project is funded by the 2011 roof bond balance. The original scope of work was completed under budget resulting in the Department of Education amending the project agreement by adding additional schools to the scope. Bezek Durst Seiser was selected as the design firm with a contract approved by the Assembly January 6, The initial roof survey has been completed with construction expected to advertise this April. Construction will occur summer Dena ina Elementary School ($26M): The project scope is to design, construct and equip a new 44,000 square foot elementary school to relieve overcrowding and improve the learning opportunities for the attending students. The site for the new elementary school is adjacent to Redington middle/high school. Bettisworth North Architects have been selected to design the new school. The 95% design submittal has been reviewed by School District staff and presented to the MSBSD School Board and Borough Assembly. The completed design has been submitted to DEED. The project is currently being advertised for competitive bids and receiving a high level of interest within the contracting community. Bids are scheduled to be opened on March 11 th. Page 3 of 6
4 Flooring Replacements, 8 Schools ($3.1M): The original scope of work for construction in replacing flooring at eight schools has been completed at all eight schools. Two individual contracts were procured to complete new flooring installation at the Colony Middle School rock climbing gym and the multipurpose room at Snowshoe Elementary School. A fourth contract for replacement flooring in the multipurpose rooms at Finger Lake, Tanaina, Cottonwood Creek, and Butte Elementary Schools has been completed. Work is complete at all schools. These contracts have been closed out. A scope request for the addition of several schools has recently been sent to the State. Additional scope is being developed with MSBSD to expend the balance of bond funds. It is anticipated for new work to occur during the summer of Valley Pathways Replacement School Design and Construction ($22.5M): This 46,239 square foot state of the art facility has been accepted as Substantially Complete and is currently in its one year warranty phase. The school has been successfully opened for its first year of operation. This school boasts of visibility within which is a vast improvement from the traditional blocky inflexible spaces dated schools provide. The open and visible spaces will lend well for improved supervision and security, yet afford a comfortable and inviting environment for learning. The curriculum wing is complete with carpet, interactive white boards, wireless network abilities, document, and distance learning cameras. The school has one of the best panoramic views in the district. The exterior of the school integrates ceramic tile and metal siding in random patterns which gives a very modern yet sophisticated appearance. Two pieces of artwork from the 1% for Art program have recently been installed. More artwork is anticipated to be installed in March. Page 4 of 6
5 Flooring Replacement, 7 Schools ($685K): The purpose of this project is to replace multipurpose room floor coverings at 7 Borough schools including: Finger Lake Elementary, Goose Bay Elementary, Larson Elementary, Meadow Lakes Elementary, Trapper Creek Elementary, Wasilla Middle, and Burchell High Schools. Asbestos abatement of mastic and tile occurred at Finger Lake and Trapper Creek Elementary schools. Work is complete at all schools. Contracts have been closed. An amendment to the Project Agreement for purchase of maintenance equipment has been requested and authorized from the State. Additional scope is being developed with MSBSD to expend the balance of bond funds. It is anticipated for new work to occur during the summer of Districtwide Energy Upgrades Design, ($3.2M): This project is to perform design of various energy upgrades at 18 different Borough schools. Site assessments of all the schools are complete and a report has been produced identifying deficiencies to be prioritized by the School District. Upgrades will likely include window replacement and lighting system replacement. Thermographic imaging and analyses has been performed at all 18 schools indicating potential areas of energy loss within the structures. Districtwide HVAC Upgrades Design, ($7.1M): This project is to provide design of various HVAC upgrades at 11 different Borough schools. Site assessments are complete at all schools listed in the contract. Upgrades and enhancements to existing systems will likely include conversion of pneumatic controls to direct digital controls for heating and ventilation, boiler automation and/or modulation and augmentation of existing air handling units. A report of findings from the site assessments has been produced. Deficiencies noted will be prioritized by the MSBSD identifying specific areas of work to fit within the available construction budget. Page 5 of 6
6 Mat-Su Career & Tech High School Addition, ($16.2M): This project includes design, construction and furnishing a new 33,060 square foot wing at Career & Technical High School. Construction of the new addition is progressing very quickly. The addition is nearly 80% complete. Interior paint is in progress, as is electrical and mechanical trim work, polishing of concrete slabs and glazing. Fully adhered roof membrane is complete. Concrete aprons, outdoor plaza, and skybridge concrete placement is complete. The interior CMU wall is completed. The five-ton bridge crane has been installed in the Transportation Lab. A new kitchen serving window has been installed in preparation for the added student population the addition will accommodate. Selection and procurement of furniture is in process. In addition, selection of artists to produce works for the installation of the 1% for Art program has begun. The new addition is scheduled to be open for the school year. Big Lake Elementary School Renovation ($800K): Phase 2 design to replace flooring, ceiling tiles/grid, lighting, and Information Technology infrastructure upgrades will be awarded to Stantec. Work will occur summer Emergency Power Generator Set and Switch Gear, 9 Schools Design Services ($180K): This project provides standby generator sets at Big Lake, Butte, Snowshoe, Swanson, and Willow Elementary Schools; Wasilla Middle School, Palmer Junior Middle School, Palmer High School, and Operations & Maintenance. Generators will facilitate normal operations during outages during the school day and will support the building during emergencies. Project is currently advertised with bids due March 16th. Restroom Renovation Design, 6 Schools ($900K): Orion Construction discovered eight locations where the designed space is not adequate for the specified sinks. These include: Pioneer Peak, Cottonwood Creek, and Snowshoe elementary schools. Work to be completed during the summer 2015 break. Page 6 of 6
Project Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT August 2015 Project Management Division New Joe Redington Sr. JR/SR High School ($65M): On August 20th, a very impressive and upbeat ribbon-cutting ceremony
More informationCAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT RIGHT: the proposed conceptual profile of the new Joe Redington Sr. JR/SR High School January 2014 Project Management Division New Knik Area Middle/High
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationMequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule
Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal
More informationFacility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components
Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development
More informationDRAPER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationHOUSTON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 59,900 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 291 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan HOUSTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationRepair Project for April 7, 2009
Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades
More informationSAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT
SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer
More informationAngelo State University Construction Report
May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning
More information17,280 square feet Overview:
CENTRAL OFFICE Located at 167 Boston Post Road, East Lyme, Connecticut, the Central Office was built in 1916 as the original Flanders Elementary School and remains connected to the current school. The
More informationMEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010
MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 To better prepare San Jose City College/ Evergreen Valley
More informationTHIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:
Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2194 ADDENDUM NUMBER ONE January 24, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM
More informationSECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request
SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table
More informationTown of Sandwich Facilities Department Summary of Building Repairs from Prior 5 7 Years List Updated August 7, 2015
Town of Sandwich Facilities Department Summary of Building Repairs from Prior 5 7 Years List Updated August 7, 2015 Town Hall Complete building restoration (state historic preservation award) High efficiency
More informationBUNKER HILL ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 98,200 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 387 WARD 5 PROPOSED PROGRAM CAPACITY 750 Site Plan BUNKER HILL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationST. MONICA FOOD PANTRY HOUSTON, TEXAS
PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,
More informationSCHOOL DISTRICT BUILDING RENOVATION 2016 Opportunity Questions and Answers
SCHOOL DISTRICT BUILDING RENOVATION 2016 Opportunity Questions and Answers WHAT IS THE ISSUE? Last year our School Board entered into a full-scale study of our educational facilities conducted by the Ohio
More informationPROPOSITION E. Associated General Contractors of America San Diego Chapter September 17, 2014
PROPOSITION E Associated General Contractors of America San Diego Chapter September 17, 2014 1 Facilities Centric Bond Aging Facilities Emphasis on Technology Infrastructure School Site Safety and Security
More informationFive-Year Capital Plan Request FY 2015-16 through FY 2019-20
Section Contents Five-Year Capital Plan Request FY 2015-16 through FY 2019-20 Project Funding Type Total ($ 000s) Critical Maintenance for Community Colleges bonded $417,500 Health and Safety bonded $91,088
More informationREQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update
REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management
More informationSODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
More informationCherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016
Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Year Opened 2003 Current Square Footage 391,000 Site Acreage 86.22 cherokeetrail.cherrycreekschools.org $279,200 Asphalt and concrete
More informationNORTH PENN HIGH SCHOOL RENOVATIONS
NORTH PENN HIGH SCHOOL RENOVTIONS PRELIMINRY SCOPE, BUDGET & PHSING CONSIDERTIONS 401 EST HNCOCK STREET LNSDLE, P 19446 PREPRED BY BONNETT SSOCITES INCORPORTED 220 BLDWIN TOWER, 1510 CHESTER PIKE EDDYSTONE,
More information31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, 5.00 12, 2012
31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, 5.00 12, 2012 BOARD OF TRUSTEES OF COMMUNITY COLLEGE DISTRICT NO. 508 COUNTY OF COOK AND STATE OF ILLINOIS JOB ORDER CONTRACT
More informationMURCH ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationProject Close Out Summary
Project Close Out Summary 1. Final Cleaning and Inspection 2. Testing and Certification 3. Demonstration of Systems and Equipment 4. Inspections by Authorities Having Jurisdiction 5. O&M Manuals and As
More informationFrequently Asked Questions
Byron Area Schools Frequently Asked Questions Bond Proposal How did this come about? For several years the Byron Area Schools Board of Education has included upgrading facilities as one of the district
More informationSchool Board Proposed Capital Improvements Program. Fiscal Years 2014-2023
School Board Proposed Capital Improvements Program Fiscal Years 2014-2023 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-6 Capital Projects Description Pages 7-14 SCHOOL BOARD PROPOSED CAPITAL
More informationORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT
1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation
More informationPrint Shop/Mail Room
Chapter XVIII Print Shop/Mail Room Page 110 CHAPTER XVIII Print Shop/Mail Room ARCHITECTURAL/STRUCTURAL A. BUILDING EXTERIOR 1.0 EXTERIOR WALLS The exterior walls are comprised of stone veneer. There were
More informationSub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders
INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids
More informationAGENDA. BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room
AGENDA BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room 1. Call to order at 6:30 p.m. 2. Review of Three Year Life Safety Recommendations from EGM Architects 3. Review of
More informationNovember 3, 2015 Bond and District Additional Assistance Election Information
November 3, 2015 Bond and District Additional Assistance Election Information Proposition 432 - $22 million General Obligation Bond 150+ facility projects across all schools Building renovations and improvements
More informationCareer & Technical Education Mat-Su Borough School District. 2015-2016 Program Availability for All Students
Career & Technical Education Mat-Su Borough School District 2015-2016 Program Availability for All Students CTE Language & Outcomes Personal Learning Career Plans (PLCP) Development starting at middle
More informationBuilding Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
More informationORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT
1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.2 Water damage in many classrooms. Replace tiles. 1.1.3 Cabinets, Equipment 1.1.4 Portables
More informationCALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN
DISTRICT "SHELL" SUBMISSION DATE: 4/17/13 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 4/19/13 (delete following Hearing) KBE APPROVAL DATE: JUNE 2013 CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES
More informationBond Priorities. Repairs and Maintenance. School Safety. Capacity
Replace old windows, boilers, heating and air conditioning system. Improve accessibility for disabled persons. Keyless entry lock systems, redesign of school entrance, and wireless access throughout building.
More information48. AQUARIUM. Aquarium. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle. Total Area: No.
Classification: Cluster: Location: Total Area: No. of Stories Aquarium Acreage Owned: Acquired: 1904 Most Recent Improvements: THE AQUARIUM Close to junction of Inselrhue and Loiter Way, Belle Isle Two
More informationHOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number: 300-004
HOWARD UNIVERSITY Policy Number: 300-004 Policy Title: ASSET CAPITALIZATION Responsible Officer: Chief Financial Officer Responsible Offices: Office of the Controller, Departments of Strategic Sourcing
More informationBMIC S APPETITE GUIDE EFFECTIVE JUNE 2013
The following guide is a general list of Builders Mutual s appetite for business classes residential and commercial WorkSafe workers compensation and Builders Best general liability (including trade contractors),
More informationCOMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS
COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications
More informationOHLONE COMMUNITY COLLEGE BOND MEASURE G
Monthly Report OHLONE COMMUNITY COLLEGE BOND MEASURE G Fremont, California June 2014 TABLE OF CONTENTS 1. Executive Summary 2. Safety Status 3. Schedule Status 4. Design Progress 5. Construction Progress
More informationOpening Day crowds lined streets at The Banks before, during and after the game.
Opening Day crowds lined streets at The Banks before, during and after the game. THE BANKS PROJECT MONTHLY REPORT: APRIL 2015 The Banks Monthly Report: April 2015 In April, Opening Day crowds filled Freedom
More informationSaint Cloud Business Center
Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with
More information32284 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 MAY 1, 2014
32284 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 MAY 1, 2014 BOARD OF TRUSTEES OF COMMUNITY COLLEGE DISTRICT NO. 508 COUNTY OF COOK AND STATE OF ILLINOIS JOB ORDER CONTRACT (JOC) PROJECTS
More informationDIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION
More informationAll substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.
2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other
More informationNORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008
NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008 PROGRAM AND CONSTRUCTION MANAGER SEPTEMBER 30, 2008
More informationADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED*
ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED* BID PACKAGE DESCRIPTION REQUIRED LICENSE Bid Package No. 1 Asbestos Abatement C22 or B, with ASB & HAZ Certification Bid
More informationHAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA
INITIAL YEAR BUILT 1968 BUILDING AREA 187,700 SF CURRENT PROGRAM CAPACITY N/A ENROLLMENT 2008 129 WARD 5 PROPOSED PROGRAM CAPACITY N/A Site Plan HAMILTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationBond Referendum Presentation. Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014
Bond Referendum Presentation Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014 Mr. David Fowler President Floral Park- Bellerose Mr. David Del Santo Vice-President New Hyde Park Garden City Park
More informationDAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN
DISTRICT "SHELL" SUBMISSION DATE: 11/13/12 questions 11/26/12 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 11/19/12 revised 11/26/12 (delete following Hearing) KBE APPROVAL DATE: FEBRUARY
More informationProduct description NCC Data Center
Product description NCC Data Center Concept General As one of the largest actors in the Nordic construction industry, NCC Construction plays a leading role in shaping the future of our society. After building
More informationThe work has continued on final Phase 4 and is nearing completion.
Updates-January 22, 2013 29369-Rehab Plaza Deck/Drainage Budget: $18,000,000, constr. Start 8/2009 The work has continued on final Phase 4 and is nearing completion. The main plaza area of phase 4 is now
More informationPolicy on Repair and Renovation Funding
Policy on Repair and Renovation Funding I. POLICY STATEMENT Auburn University s (the University s) Policy on Repair and Renovation Funding provides guidance and direction regarding the use of Repair and
More informationLindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1
School Facilities Evaluation Project Page 1 Executive Summary In November 1999, Alberta Infrastructure, School Facilities Branch engaged Stephens Kozak Carr and Brown Architects to conduct evaluations
More information32315 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JUNE 5, 2014
32315 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JUNE 5, 2014 BOARD OF TRUSTEES OF COMMUNITY COLLEGE DISTRICT NO. 508 COUNTY OF COOK AND STATE OF ILLINOIS JOB ORDER CONTRACT (JOC) PROJECTS
More informationTD AMERITRADE Park Omaha
TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment
More informationHow To Plan A Building
State of Nevada Department of Administration Purchasing Division Las Vegas Purchasing Warehouse Facility Condition Analysis LAS VEGAS PURCHASING WAREHOUSE 1054 South Commerce Street Las Vegas, Nevada Site
More informationBuilding Condition Assessment Report
C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses
More informationHow to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table
More informationUNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY
UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY The term capitalized fixed assets includes land, improvements to land, easements, buildings, building improvements, vehicles, machinery, furniture,
More informationCAPITAL EXPENDITURES
CAPITAL EXPENDITURES 1 CAPITAL EXPENDITURES CAPITAL EXPENDITURES PLANNING On March 1, 2010 the AmherstPelham Regional School committee adopted a policy for developing a formal capital needs planning process.
More informationSchematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL
Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 0 Overlea High School - Facility Summary Facility Opened: Auditorium Addition: Activity Room Addition: School Rated Capacity
More informationExecutive Summary. June 2005 Auke Bay Elementary School Condition Survey Report Page 4 of 228
Building History 1. The original building was built in 1968. It is essentially a 2 story building built into a hillside. A portion of the second floor steps up the hill a half level above the second floor
More informationBuilding Description Project Description Estimated Cost Notes Total Deferred
Building Description Project Description Estimated Cost Notes Total Deferred Athletic Fields & Grounds Baseball dugouts 125,000 Surface level/inground? Relamp Baseball field 16,000 Relamp Softball field
More informationNewtown and Holland Middle Schools Construction Project Bid Review
Newtown and Holland Middle Schools Construction Project Bid Review *Includes clarifications requested at 30MAR16 FACCOM Meeting (italicized) Facilities Committee Meeting March 30, 2016 (Updated March 31,
More informationSchool Facilities Referendum Recommendations
Haddonfield Public School District LONG RANGE PLANNING COMMITTEE School Facilities Referendum Recommendations NOVEMBER 19, 2015 School Facilities Referendum Recommendations Tonight s goals Presentation
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationAPPENDIX E: CAPITAL NEEDS SUMMARY
APPENDIX E: CAPITAL NEEDS SUMMARY Building A Foundation Hall Building to be replaced ARCHITECTURAL Roof Repair North Structural Wall Repair Flooring Repairs Ceiling Repairs Lighting Repairs Lighting Repairs
More informationWhy does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL?
Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? 1. BASIC FACTS: The current Abington High School building is 111,831
More informationItems in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes.
Office of Safe and Orderly Schools Facility Safety Assessment Dennis Meador, School Facilities Supervisor Mark Hobson, School Facilities Supervisor Division of School Building September 18 19, 2007 Items
More informationUNIVERSITY OF CALIFORNIA, SAN DIEGO
UNIVERSITY OF CALIFORNIA, SAN DIEGO UCSD BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ UNIVERSITY CENTERS - 0076 PHONE: (858) 822-4987 9500 GILMAN
More informationChicago Public Schools
Ames Middle School 1920 N Hamlin Ave 1997 Completed The scope of this project is to construct a new school $16,913,379 2014 Construction The intent of this project is to expand existing Ames middle school
More informationDESIGN AND CONSTRUCTION DEPARTMENT - July 2014
DESIGN AND CONSTRUCTION DEPARTMENT - Project or 1 Elementary School 46 (Aliana) AutoArch Bartlett Cocke General ors Construct a new 850 capacity elementary school in the Aliana Master Planned Community.
More informationAccounting and Administrative Manual Section 100: Accounting and Finance
No.: A-25 Page: 1 of 8 General: This policy establishes guidelines for determining when certain expenditures should be capitalized as capital assets and specifies the university s depreciation policy.
More informationVeterans Memorial Coliseum Options Study Appendix A - Deconstruction Scope of Work and Cost Estimate August 31, 2015
Stage 1 DA.01 Fencing and cameras deployed Baseline - 3-5 years for Stage 1 for purposes of this study costs are described for a 3 year period $45,000 $0 Stage 1 DA.02 Secure all building doors and access
More informationFund 30020 Infrastructure Replacement and Upgrades
Focus Fund 30020 supports the long term needs of the County s capital assets to maximize the life of County facilities, avoid their obsolescence, and provide for planned repairs, improvements and restorations
More informationADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015
ADDENDUM NO. 1 DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 RECEIPT DATE: March 17, 2015 at 2:30 p.m. OPENING DATE: March 18,
More informationRepair and Remodeling Estimating Methods. 4th Edition. RSMeans
Brochure More information from http://www.researchandmarkets.com/reports/2214808/ Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Description: This estimating guide for repair and remodeling
More informationHartsfield-Jackson Atlanta International Airport s
Hartsfield-Jackson Atlanta International Airport s 2008-09 Closed Projects (Posted 1/6/2009) FC-3007000038C: MISCELLANEOUS BUILT-UP ROOF AND SINGLE PLY ROOF REPAIRS AT H-JAIA Furnish all labor, equipment,
More informationProgram Demand Cost Model for Alaskan Schools
Program Demand Cost Model for Alaskan Schools 14th Edition Education Support Services / Facilities 2015 Consultant Editor HMS, Inc. 4103 Minnesota Drive Anchorage, Alaska Division of School Finance &
More informationPresented by The Facilities Management Group TFMG / TFMG Architecture, PC. in conjunction with EMTEC Engineers, LLC
Presented by The Facilities Management Group TFMG / TFMG Architecture, PC in conjunction with EMTEC Engineers, LLC Why are we here today? To solicit public comments to help us create the Comprehensive
More informationHamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year
Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Printed On: 2003/04/03 St Patrick CES, 7932 Study [03.3-050 Plumbing Piping Systems] Study condition, remaining service
More informationDevelopment Services Guidelines
Dear Customer/Developer: Balcones Heights 3300 Hillcrest San Antonio, Texas 78201 210-735-9148 ext 246 Fax: 210-735-9409 Development Services Guidelines Welcome to the City of Balcones Heights, we look
More information2012 BIM Guidelines and Standards (Rev. 00) University at Albany
A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested
More informationSpringfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015)
Springfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015) What is a referendum? New Jersey school districts hold public referendum votes to seek approval
More informationPATTERSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1945 BUILDING AREA 78,300 SF CURRENT PROGRAM CAPACITY 368 ENROLLMENT 2008 463 WARD 8 PROPOSED PROGRAM CAPACITY 500 Site Plan PATTERSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationBUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES
Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE
More informationREPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PARKS, RECREATION, AND CULTURAL SERVICES DEPARTMENT
January 27, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PARKS, RECREATION, AND CULTURAL SERVICES DEPARTMENT ON WESTSYDE POOL AND COMMUNITY CENTRE ROOF REPAIR OPTIONS UPDATE PURPOSE To provide
More informationHAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION
HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION 1 AGENDA Hazelwood 1 st Planning Process High School Program Schematic Designs Schedule 2 HAZELWOOD 1 ST GOALS Life, health and safety improvements
More informationFlexible Office Space Up to 66,240 Ft 2
Flexible Office Space Up to 66,240 Ft 2 Building Description: Wide Open Large Office Complex Numerous Perimeter Offices, Conference & Break Rooms and Wide Open Office Space Throughout Can Be Modified to
More informationPresentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals
Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals Les Butler Associate Commissioner for Business and Regional
More informationDescription of Project Statewide Student Data Warehouse
Description of Project Statewide Student Data Warehouse The Department of Education (DE) uses Rebuild Iowa Infrastructure Fund funding to support critical components of Iowa s Statewide Longitudinal Data
More informationPlanning and Construction Management Services
Planning and Construction Management Services Construction Project Management Services New construction, major renovations or improvements to building structures and systems are part of the Department's
More informationAPEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT
PROJECT MANAGEMENT / SUPPORT Capital Cost Savings Construction Monitoring and Assistance In-Plant Production Assistance In-Plant Maintenance Assistance Procurement Assistance Project Cost Estimating o
More informationElectrical. This section applies to the design and installation of building power distribution systems.
Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions
More information