2012 BIM Guidelines and Standards (Rev. 00) University at Albany

Size: px
Start display at page:

Download "2012 BIM Guidelines and Standards (Rev. 00) University at Albany"

Transcription

1 A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested during any point in the project and at the conclusion of each design phase. Submitting BIM files does not relieve the consultant from the responsibility of submitting final project files in the AutoCAD.DWG file format following the University s CAD Standard Guidelines. B. Office of Architecture, Engineering and Construction Management (AECM) Requirements 1. Architects shall use BIM software when directed to do so as part of the design project. Building information models shall be created that include all geometry, physical characteristics and product data needed to describe the design and construction work. All drawings and schedules required for assessment, review, bidding and construction shall be extractions from this model. 2. Structural Engineers, Mechanical, Electrical, Plumbing, Fire Protection, and Civil Engineers shall use BIM software or discipline-specific 3D modeling software. Models shall be created that include all geometry, physical characteristics and product data needed to describe the design and construction work. Drawings and schedules required for assessment, review, bidding and construction shall be extractions from this model. Software shall be capable of interfacing with the Architect s version of the software. In all cases, model building and infrastructure systems shall be developed to a level that allows the team to verify clearances, analyze conflicts/clashes and properly coordinate the work with all other aspects of the project. 3. Other Specialty Consultants shall use BIM software or discipline-specific 3D software. Models shall be created that include all geometry, physical characteristics and product data needed to describe the design and construction work. Drawings and schedules required for assessment, review, bidding and construction shall be extractions from this model. Software shall be capable of interfacing with the Architect s version of the software. In all cases, model components to a level that allows the team to verify clearances, analyze conflicts/clashes and properly coordinate the work with all other aspects of the project. C. BIM Software 1. A/E s shall use one or a combination of the following BIM software for AECM projects. a. Autodesk Revit Architecture 2011/2012 b. Autodesk Revit Structure 2011/2012 c. Autodesk Revit MEP 2011/2012 d. Autodesk Civil 3D 2011/2012 e. Autodesk NavisWorks 2011/ AECM will consider other software products subject to their capabilities, features and benefits to the Campus. 3. Note: other BIM tools may be used for analysis, specialty design, and other project needs; however final design document files must be Revit or NavisWorks compatible. D. Geo-referenced Model: A/E s shall geo-reference site plans and building models to coordinate with the Office of Campus Planning s (OCP) GIS Standards. Refer to the information on the OCP website at AECM Building Information Modeling Guidelines

2 E. Model Submittal: With submittal of documentation at the end of each design phase, A/E s shall also submit the Revit model(s) in native application's format. Any future changes to, or extractions from the model(s) will be the responsibility of the party making the changes. F. Levels of Development (LODs): The LOD descriptions identify the specific content requirements for each model element at five detailed levels of completeness. Each LOD builds upon and enhances the characteristics of the previous level. The A/E shall strive to meet the following requirements at each design phase: a. Concept / LOD 200 Concept phase elements should be modeled as generalized systems or assemblies with approximate size, quantities, location and orientation. b. Schematic (SD) / LOD 300 Elements are modeled as specific assemblies accurate in their respective size, quantities, location and orientation. c. Design Development (DD) and Construction Documents (CDs) / LOD 400 Elements are accurate in terms of size, shape, location, quantity and location with complete fabrication, assembly and detailing information with non-geometric information. d. As-Built A/E Contract Closeout / LOD 500 Model with constructed assemblies, actual and accurate in terms of size, quantities, location and orientation with non-geometric information. G. Model Object Requirements Appropriate to Phase 1. A/E s are encouraged to use electronic programming and planning tools that integrate into their BIM software to capture early cost, schedule and program information. 2. A/E s may use any method to begin the design process but shall be using a BIM or 3D model(s) at a design phase requested by the University. All information needed to describe the design shall be graphically or alphanumerically included in and derived from these models. The Campus expects A/Es to use analysis tools, static images and interactive 3D to describe the design concepts. 3. Existing conditions - A/E s shall model all existing conditions needed to explain the extent of the construction work for alterations and additions projects. The extent of modeling beyond the affected areas and the level of information to be included will be identified in the University s Scope of Services. These requirements may be stated in the project program or discussed during the project kickoff meeting. 4. Comparative Cost Analysis - A/E s shall extract quantity information using BIM software and other BIM integrated tools to support comparative costs analysis of options studied. Analysis and options may include: building perimeter, square foot zones by cost type, exterior envelope area, construction type, envelope materials, and/or others appropriate to the project. Outputs shall be converted to spreadsheets and submitted as part of the design solution justification at end of each appropriate phase. 5. Comparative Energy and Sustainability Analysis - A/E s are encouraged to use building envelope energy modeling tools integrated with the BIM software to develop comparative energy analysis. Variables shall include orientation, massing, form, sun controls, wall construction, natural ventilation, area of glass, daylighting and other factors appropriate to decision making. Modeling parameters shall be based on local climate data and actual site conditions. Output format shall clearly communicate and be appropriate to project needs and submitted as part of the design solution justification at the end of the phase. AECM Building Information Modeling Guidelines

3 6. Program and Space Validation - A/E s shall use the BIM software or other analysis tools to compare and validate stated program requirements with the actual design solution. The following shall be developed automatically from the building information model: a. Assignable Areas (ASF) and Non-assignable Areas (NaSF) measured to inside face of wall objects. b. Gross Area (GSF) measured to the outside face of wall objects. 7. Architectural Systems - Model the following architectural elements to a level that defines the design intent and accurately represents the design solution. a. Architectural Site Plan. b. Existing conditions to the extent required. c. Demolished items to the extent required. d. New interior and exterior walls. e. Floor, ceiling and roof systems. f. Elevators, stairs, ramps including railing systems. g. Casework, shelving, fireplaces and other interior architectural elements. h. Fixed furniture and other specialty equipment (food service, medical, etc); model mechanical, electrical and plumbing items that require architectural space. i. Clearance zones for handicap access, door swings, service space requirements, gauge reading, and other operational clearance must be modeled as part of all equipment and checked for conflicts with other elements. j. Wall types including openings. 8. Structural Engineering - Model the following basic structural elements such as: a. Appropriate foundation styles. b. Structural framing members. c. Load-bearing walls. 9. HVAC Systems - Model the following HVAC elements: a. Fans, VAV s, compressors, etc. b. Supply, return, exhaust, relief and outside air ductwork modeled to outside face. c. Ductwork and duct insulation (whichever is greater). d. Diffusers, grilles, louvers, hoods, radiant panels, perimeter units, wall units. e. Pipes sized at and over 2 OD; include any insulation in model. f. Clearance zones for access, door swings, service space requirements, gauge reading, and other operational clearance must be modeled as part of the HVAC equipment and checked for conflicts with other elements. 10. Electrical systems - Model the following electrical elements: a. Power. b. Interior and exterior transformers and other equipment. c. Main and distribution panels and switchgear including access clearances. d. Feeders and conduit at and over 2 OD. e. Outlets, switches, junction boxes. f. Permanently mounted lighting fixtures (moveable, plug-in fixtures need not be modeled as part of the electrical package). AECM Building Information Modeling Guidelines

4 g. Clearance zones for access, door swings, service space requirements, gauge reading, valve clearances and other operational clearance must be modeled as part of the electrical equipment for collision checking. 11. Plumbing and Fire Protection Systems - Model the following plumbing and fire protection elements: a. Waste and vents b. Piping sized at and over 2 OD; include any insulation. c. Roof and floor drains, leaders, sumps, grease interceptors, tanks, water treatments and other major items. d. Supply Piping sized at and over 2 OD include any insulation in model. e. Fixtures: sinks, toilet fixtures, water tanks, floor sinks. f. Fire protection sprinkler lines at and over 2 OD. g. Sprinkler heads. h. Stand pipes, wall hydrants, fire department connections, risers, including valve clearances. i. Clearance zones for access, service space requirements, gauge reading, valve clearances and other operational clearance must be modeled as part of the plumbing and fire protections system and checked for conflicts with other elements. 12. Specialty Consultants - Model the following specialty consultant elements to correct size and location. Extent of specialty consultant modeling shall be coordinated with the prime A/E : a. Equipment provided or specified by said consultants (Audio-Visual, Telecommunications, Data, Security, etc.). b. Rough-in connections points for power, data, communications, water service and waste, gas, steam, or other needed utilities. c. Clearance zones for access, doors swings, service space requirements, controls, gauge reading, and other operational clearance must be modeled as part of the equipment and checked for conflicts with other elements. 13. Civil Engineering Coordinate with Autodesk Civil 3D. All items must be geo-referenced such that all elements can be viewed as an overlay in the BIM model and the correct location in a GIS system. The Engineer is encouraged to model the following items: a. Existing site conditions. b. Utilities underground and overhead. c. Sediment and erosion controls. d. Trees and shrubs. e. Paving, curbs, gutters, striping. f. Site amenities or structures. g. Hazardous waste remediation H. Final Design Construction Documents Phase: A/E s shall continue development of the BIM (or 3D Models for Consulting Engineers and Specialty Consultants) created in previous phases. Maintain parametric links within the respective models to enable automatic generation of all plans, sections, elevations, custom details, schedules and 3D views. All information needed to describe the implementation documents shall be graphically or alphanumerically included in and derived from these models only. Specifications are not required to be linked in BIM. AECM Building Information Modeling Guidelines

5 I. Bidding Phase: A/E s shall update the models with all addendum, accepted alternates and/or value enhancement proposals. Republish documents and deliverable files. J. Award and Construction Phases: A/E s are encouraged to provide the final bid document Revit model to the awarded contractor in order to facilitate collaboration between the A/E, the contractor and the University. A/E s are expected to continuously maintain and update the model(s) with changes made during construction. K. Conflict Checking: A/E s shall use conflict checking software to resolve clashes between all disciplines and specialties during the design process. Hard clashes between the various elements and soft clashes between an element and a required clearance shall be identified and resolved prior to submittal. Submit the report generated by the checking software showing conflicts have been resolved. L. Other Analysis and Checking Tools: A/E s are encouraged to analyze the design using software that interacts with the model in order to confirm program and refine daylighting, natural ventilation, acoustics, code issues and design issues. M. Quantity Take-off and Cost Control: A/E s are encouraged to use quantity take-off features of the BIM and 3D tools coupled with unit costs to assist in construction cost control. N. Program and Program Verification: A/E s shall use the methodologies described above to reconfirm program. O. A/E Contract Close-out: A/E s shall submit one complete consolidated Revit model with contractor recorded changes and republish record documents to the AECM project manager. Provide LOD 500. AECM Building Information Modeling Guidelines

BIM. Guidelines & Standards for Architects, Engineers, and Contractors. Initiated: Sept. 10th, 2009. Revised: July 1st, 2015

BIM. Guidelines & Standards for Architects, Engineers, and Contractors. Initiated: Sept. 10th, 2009. Revised: July 1st, 2015 BIM Guidelines & Standards for Architects, Engineers, and Contractors Initiated: Sept. 10th, 2009 Revised: July 1st, 2015 Acknowledgements Indiana University is indebted to those many organizations that

More information

PROJECT REQUIREMENT, PR 20 VIRTUAL DESIGN & CONSTRUCTION (VDC), BUILDING INFORMATION MODEL (BIM)

PROJECT REQUIREMENT, PR 20 VIRTUAL DESIGN & CONSTRUCTION (VDC), BUILDING INFORMATION MODEL (BIM) PROJECT REQUIREMENT, PR 20 VIRTUAL DESIGN & CONSTRUCTION (VDC), BUILDING INFORMATION MODEL (BIM) A. GENERAL: 1. Summary: Design/Builder will employ VDC and BIM tools to facilitate the construction, coordination,

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

#506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist

#506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist #506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist Case #: Date: Project Name: Site Address: Application Submittal Building permit applications and plans can be submitted to the

More information

Facilities Management

Facilities Management Facilities Management June 29, 2015 THIS PAGE INTENTIONALLY LEFT BLANK University of South Florida BIM Guidelines and Standards Page 2 of 32 BIM Guidelines and Standards Table of Contents SECTION 1: BIM

More information

OPTIONAL IMAGE OR RENDERING OF BUILDING OR SITE

OPTIONAL IMAGE OR RENDERING OF BUILDING OR SITE OPTIONAL IMAGE OR RENDERING OF BUILDING OR SITE MIT BIM Execution Plan v3.2 2 MIT Project Name MIT Project Number DEVELOPED IN COLLABORATION WITH Construction Company Architect AND Engineer MIT BIM Execution

More information

CITY COLLEGE OF SAN FRANCISCO (CCSF) Building Information Modeling (BIM) Standards for Design-Bid Build Projects. CCSFBIMS Version 1.

CITY COLLEGE OF SAN FRANCISCO (CCSF) Building Information Modeling (BIM) Standards for Design-Bid Build Projects. CCSFBIMS Version 1. CITY COLLEGE OF SAN FRANCISCO (CCSF) Building Information Modeling (BIM) Standards for Design-Bid Build Projects CCSFBIMS Version 1.0 Prepared by: CCSF Facilities Planning & Construction (FPC) Department

More information

Element D Services Plumbing

Element D Services Plumbing PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses domestic cold, hot and hot water return distribution systems within and to five feet beyond building perimeter. PART 2 - DESIGN CRITERIA 2.01 GENERAL

More information

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series Best Practices : Project Phase Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA members without endorsement

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Design Development Quality Management Phase Checklist Project Phase Checklist Series Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA

More information

(BIM) Guidelines version 1.6

(BIM) Guidelines version 1.6 Table of Contents University of Southern California Building Information Modeling (BIM) Guidelines Building Information Modeling (BIM) Guidelines version 1.6 For Design Bid Build Contracts USC Capital

More information

1 TABLE OF CONTENTS. 1. BIM Execution Plan. BIM Execution Plan- UF Minor Projects Template UF-000 2 of 20 pages. 1.1. Processes...

1 TABLE OF CONTENTS. 1. BIM Execution Plan. BIM Execution Plan- UF Minor Projects Template UF-000 2 of 20 pages. 1.1. Processes... 1 TABLE OF CONTENTS 1. BIM Execution Plan 1.1. Processes... 3 1.2. Addendum to UF Contracts... 4 1.3. Methodology... 4 1.4. Project Overview / General Information... 4 1.5. Project Collaboration Team...

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION

NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION July 2012 BIM Guidelines Michael R. Bloomberg, Mayor David J. Burney, FAIA, Commissioner David Resnick, AIA, Deputy Commissioner TABLE OF Contents Message

More information

Aurora Mall. Aurora (Denver), Colorado

Aurora Mall. Aurora (Denver), Colorado is the largest superregional mall in the city of Aurora, and it s only getting bigger and better. The mall is currently undergoing a significant interior and exterior renovation, scheduled for completion

More information

SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section)

SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section) University of North Carolina at Charlotte Design and Construction Manual Section 3, Annex J UNC Charlotte ILM Implementation Plan SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section)

More information

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 Section 1: General 1.0 Alignment with Organizational Vision In the space provided below, read

More information

Revit MEP. Autodesk Navisworks

Revit MEP. Autodesk Navisworks What is BIM? Autodesk BIM is an intelligent model-based process that helps owners and service providers achieve business results by enabling more accurate, accessible, and actionable insight throughout

More information

DRAFT BUILDING INFORMATION MODELING SCOPE OF SERVICES AND REQUIREMENTS FOR ARCHITECTS AND ENGINEERS

DRAFT BUILDING INFORMATION MODELING SCOPE OF SERVICES AND REQUIREMENTS FOR ARCHITECTS AND ENGINEERS DRAFT BUILDING INFORMATION MODELING SCOPE OF SERVICES AND REQUIREMENTS FOR ARCHITECTS AND ENGINEERS Table of Contents 1 Introduction...3 1.1. Statement of Purpose...3 1.2. BIM Competence and Responsibilities...3

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

ST. MONICA FOOD PANTRY HOUSTON, TEXAS PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,

More information

BIM GUIDE. Developed for

BIM GUIDE. Developed for BIM GUIDE Developed for BIM GUIDE Protocols and Project Execution Plan 1 Table of Contents.. Objective... P. 4.. Roles & Responsibilities... P. 5.. Contract Strategies... P. 8.. Level of Development...

More information

Olilo's AEC Design Services. SrinSoft Inc, Partners of

Olilo's AEC Design Services. SrinSoft Inc, Partners of Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,

More information

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor

More information

PLAN SUBMITTAL INFORMATION

PLAN SUBMITTAL INFORMATION PLAN SUBMITTAL INFORMATION APPLICATION FOR A BUILDING PERMIT Prior to drafting construction drawings, please check with the North Miami Beach Community Development Department concerning the following:

More information

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic

More information

TENANT DESIGN MANUAL UPDATED JULY 2015

TENANT DESIGN MANUAL UPDATED JULY 2015 TENANT DESIGN MANUAL UPDATED JULY 2015 PROJECT OVERVIEW Grapevine Mills is located at the interchange of SR 121 and Grapevine Mills Parkway. It is centrally located just 20 miles northwest of Dallas and

More information

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE Autodesk Revit LEARNING PATH FUNDAMENTALS Duration: 3 days Cost: R5 500 (excl VAT) Revit MEP Duration: 3 days Cost: R5 500 (excl VAT) Revit Structure Duration: 3 days Cost: R5 500 (excl VAT) REVIT ADVANCED

More information

RESOURCE GUIDE. A guide for implementing Building Information Modeling in State of Maryland and Washington DC public school construction projects

RESOURCE GUIDE. A guide for implementing Building Information Modeling in State of Maryland and Washington DC public school construction projects BIM RESOURCE GUIDE A guide for implementing Building Information Modeling in State of Maryland and Washington DC public school construction projects First Draft May 213 ASBO MD/DC BIM COMMITTEE MEMBERS

More information

ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015

ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 ADDENDUM NO. 1 DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 RECEIPT DATE: March 17, 2015 at 2:30 p.m. OPENING DATE: March 18,

More information

UNDERSTANDING PROJECT DESIGN CRITERIA

UNDERSTANDING PROJECT DESIGN CRITERIA Chapter II Section 1 The design of each project must be divided into phases of development that Massport reviews periodically to ensure that the Consultant has achieved all of the project s goals and objectives,

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

ESTIMATING PLUMBING, HEATING, VENTILATING, AND AIR CONDITIONING (HVAC), AND ELECTRICAL WORK

ESTIMATING PLUMBING, HEATING, VENTILATING, AND AIR CONDITIONING (HVAC), AND ELECTRICAL WORK C H A P T E R 7 ESTIMATING PLUMBING, HEATING, VENTILATING, AND AIR CONDITIONING (HVAC), AND ELECTRICAL WORK OBJECTIVES After reading this chapter and completing the review questions, you should be able

More information

2.4 Hardcopy submittals shall be provided at adequate size so that all notes are readable.

2.4 Hardcopy submittals shall be provided at adequate size so that all notes are readable. DESIGN EQUIEMENTS POJECT DELIVEABLES CHECKLISTS GENEAL INFOMATION 1.1 The following is a checklist to be used as a guide for the required deliverables for the Schematic Design phase. 1.2 Schematic Design

More information

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications

More information

BIM: FOR PROJECT MANAGERS. 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am

BIM: FOR PROJECT MANAGERS. 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am BIM: FOR PROJECT MANAGERS ANA BAKER BRANDON GARRETT 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am 1 2 3 4 BIM Overview BIM Level of Development Evolution of the Drawing Process BIM Workflow

More information

Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria

Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria Appendix B 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria 423.25 Public shelter design criteria. 423.25.1 New facilities. New educational facilities for school boards

More information

BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W

BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W Insanity: doing the same thing over and over again and expecting

More information

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering Building Information Modelling (BIM); How it Improves Building Performance R.P. Kumanayake Lecturer, Department of Civil Engineering R.M.P.S. Bandara Lecturer, Department of Mechanical Engineering Faculty

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: PHONE: PHONE: ARCHITECT/ENGINEER

More information

Certified Instructors & Curriculum

Certified Instructors & Curriculum Our Promise. TPM is dedicated to provide the most extensive and high-quality training programs to help you maximize your investment. Although the investment in time and money may seem substantial, it will

More information

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 APPLICATION for ZONING and BUILDING PERMIT APPLICATION INSTRUCTIONS:

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 8 E. DESIGN

More information

HEANEY General Contracting, Inc.

HEANEY General Contracting, Inc. HEANEY General Contracting, Inc. March 26, 2016 AAPS BID NO. 16-019-665 ADDENDUM NO. 03- PROJECT: DESCRIPTION: Ann Arbor Public Schools Mitchell Expansion Phase I Bid Pkg. 3 (MEP) Building Addition and

More information

Electrical. This section applies to the design and installation of building power distribution systems.

Electrical. This section applies to the design and installation of building power distribution systems. Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions

More information

Does Wall Township require an inspection by the building department on resale of a home?

Does Wall Township require an inspection by the building department on resale of a home? Selling your home Does Wall Township require an inspection by the building department on resale of a home? No. We do not require a Certificate of Continued Occupancy on the resale of home. A Smoke Detector,

More information

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

Element Z General Design Requirements Standards and Other Requirements

Element Z General Design Requirements Standards and Other Requirements Design Phase Deliverables PART 1 - GENERAL 1.01 OVERVIEW A. The Table identified in Part 2 of this document summarizes AE deliverables and minimum level of information to be depicted on construction documents

More information

Nominal Life Expectancy for Building Components

Nominal Life Expectancy for Building Components Nominal Life Expectancy for Building Components Building System Page A. HVAC 2 B. Elevator/Escalator 6 C. Plumbing 7 D. Roofing 8 E. Electrical 10 F. Fire/Life/Safety/Security System 11 G. Interior Finishes

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

PLAN REVIEW SERVICES CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW

PLAN REVIEW SERVICES CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW PRELIMINARY BUILDING REVIEW two sets of the following: Architectural/engineering design development drawings indicating size of the building,

More information

city of edmonds development information

city of edmonds development information #B17 city of edmonds development information Commercial Kitchen Hood & Hood Fire Suppression System Permit Submittal Requirements PERMIT REQUIRED: CODES: FEES: A Commercial Kitchen Hood Mechanical Permit

More information

HOMEOWNER S PERMIT GUIDE

HOMEOWNER S PERMIT GUIDE HOMEOWNER S PERMIT GUIDE WHEN IS A PERMIT REQUIRED? Department of Development and Permits 306 Cedar Road, City Hall 2 nd Floor P.O. Box 15225 Chesapeake, VA 23328 Phone: (757) 382-6018 Fax: (757) 382-8448

More information

Building Condition Assessment Report

Building Condition Assessment Report C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses

More information

Gramercy Place Condo Association, Inc.

Gramercy Place Condo Association, Inc. Gramercy Place Condo Association, Inc. UNIT MODIFICATION REQUEST Date of Application: Name of Owner (s): Telephone: (Home) (Cell) E-Mail: Anticipated start date: Anticipated ending date: Permission is

More information

Arizona Health Care Association DISASTER PLANNING AND EMERGENCY MANAGEMENT GUIDE POST INCIDENT DAMAGE ASSESSMENT CHECKLIST

Arizona Health Care Association DISASTER PLANNING AND EMERGENCY MANAGEMENT GUIDE POST INCIDENT DAMAGE ASSESSMENT CHECKLIST It is essential to perform a Basic Damage Assessment (BDA) following an adverse event to help ensure the safety of building occupants as well as prevent additional losses from occurring. This checklist

More information

LACCD Building Information Modeling Standards For Design-Bid Build Projects

LACCD Building Information Modeling Standards For Design-Bid Build Projects LACCD Building Information Modeling Standards For Design-Bid Build Projects (LACCD BIMS) Interim Version 2.0 Prepared by: September 9, 2009 TABLE OF CONTENTS 1. INTRODUCTION 1 1.1. Overview 1.2. Main Objectives

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

WARRANTIES AND PERFORMANCE STANDARDS T A B L E O F C O N T E N T S General Provisions Introduction Warranties Effective Date of Warranties Exclusive

WARRANTIES AND PERFORMANCE STANDARDS T A B L E O F C O N T E N T S General Provisions Introduction Warranties Effective Date of Warranties Exclusive WARRANTIES AND PERFORMANCE STANDARDS T A B L E O F C O N T E N T S General Provisions Introduction Warranties Effective Date of Warranties Exclusive Warranties Time Limits for Reporting Manufacturer s

More information

City of Oviedo Commercial Shell Building Permit Application Guidelines

City of Oviedo Commercial Shell Building Permit Application Guidelines City of Oviedo Commercial Shell Building Permit Application Guidelines All permit application packages must be complete prior to acceptance. A complete application package shall include the following:

More information

Schedule B to By-law 33-2009

Schedule B to By-law 33-2009 Amended by By-law 8-2016 Note: This consolidation is prepared for convenience only. For accurate reference the original by-laws should be reviewed. Floor Area Calculation Floor area shall: Schedule B to

More information

Subpart 1. Installation. All plumbing systems must be. installed and tested according to this chapter and chapter 4715,

Subpart 1. Installation. All plumbing systems must be. installed and tested according to this chapter and chapter 4715, 4658.4500 PLUMBING SYSTEMS; NEW CONSTRUCTION. Subpart 1. Installation. All plumbing systems must be installed and tested according to this chapter and chapter 4715, the Minnesota Plumbing Code. Subp. 2.

More information

TABLE OF CONTENTS 1 2 APPENDIX A. MPA BIM USES EXISTING CONDITIONS MODELING DESIGN AND BUILDING SYSTEM AUTHORING ANALYSIS AND REPORTING

TABLE OF CONTENTS 1 2 APPENDIX A. MPA BIM USES EXISTING CONDITIONS MODELING DESIGN AND BUILDING SYSTEM AUTHORING ANALYSIS AND REPORTING APPEN DIX A // MPA BIM GU ID ELINE S 1 EXISTING CONDITIONS MODELING 1.1 BIM Project Site Modeling Also Infrastructure Modeling 1.2 Surrounding Site Modeling 1.3 Existing Conditions Laser Scanning 1.4 Existing

More information

WESTERN MICHIGAN UNIVERSITY

WESTERN MICHIGAN UNIVERSITY WESTERN MICHIGAN UNIVERSITY Facilities Management Department DeVon Miller Building Commissioning Administrator 1 INTRODUCTION DeVon C. Miller, CPMP, LEED AP Building Commissioning Administrator Engineering

More information

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles

More information

PDmB, Inc. Definitions

PDmB, Inc. Definitions Page 1 of 11 Definitions S Satisfactory Meets industry standards for proper material and installation NP Not Present Condition or item was not present at time of inspection NI Not Inspected Condition or

More information

Execution Plan Template Design Modeling

Execution Plan Template Design Modeling Execution Plan Template Design Modeling NEW CONSTRUCTION By signature below, this Execution Plan is herewith adopted and incorporated into the Agreement, dated, for Professional Design Services between

More information

Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals

Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals Les Butler Associate Commissioner for Business and Regional

More information

South Carolina Home Inspector Standards of Practice

South Carolina Home Inspector Standards of Practice South Carolina Home Inspector Standards of Practice The following Standards provide guidelines for the Residential Home Inspector and outline what the Residential Home Inspector should observe, identify,

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 7 E. DESIGN

More information

How To Use Building Information Modeling (Bim)

How To Use Building Information Modeling (Bim) LACCD Building Information Modeling Standards (LACCD BIMS) Prepared by: March 3, 2016 DISCLAIMER THE INSTRUCTIONS, STANDARDS AND GUIDELINES CONTAINED IN THE LOS ANGELES COMMUNITY COLLEGE DISTRICT BUILDING

More information

Building Information Modeling Guidelines and Standards for Architects and Engineers

Building Information Modeling Guidelines and Standards for Architects and Engineers Version 1.1 Building Information Modeling Guidelines and Standards for Architects and Engineers 9/4/2013 Version 1.1 (revised 4/28/2014) Page ii Acknowledgement At this time, the NYC School Construction

More information

ESTIMATE ORIG. ESTIMATE: TOTAL: $204,249 DATE: 01/15/08 DESCRIPTION OF WORK QUANTITY DIVISION TOTAL

ESTIMATE ORIG. ESTIMATE: TOTAL: $204,249 DATE: 01/15/08 DESCRIPTION OF WORK QUANTITY DIVISION TOTAL PARTITIONS REGULAR WALLS 9' HIGH 214 LF TENANT DEMISING WALL 150 LF INTERIOR FURRED WALLS 9' 86 LF OFFICE DEMISING WALL 98 LF DOUBLE FRAME RADIUS WALL 18 LF RADIUS SOFFITS 172 LF SOFFIT 76 LF FINISH NEW

More information

Acumen Enterprises, Inc.

Acumen Enterprises, Inc. Hourly rates Discount w/o Rebate Electrician $78.00 10% $70.20 $70.73 HVAC Technician $78.00 10% $70.20 $70.73 Insulator $42.00 10% $37.80 $38.08 Sheet Metal Worker $74.00 10% $66.60 $67.10 Plumber/Pipefitter

More information

City of St. Charles Basement Finish or Remodel

City of St. Charles Basement Finish or Remodel City of St. Charles Basement Finish or Remodel Building & Code Enforcement Division 2 East Main Street St. Charles IL 60174 630.377.4406 (Office) 630.443.4638 (Fax) http://www.stcharlesil.gov Please direct

More information

Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company

Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company 1 Why BIM? Excessive Re-Work and Waste TURNER INNOVATION SERIES May 2012 BIM for Design, Preconstruction, & Construction Brian Krause Manager, Integrated Building Solutions bkrause@tcco.com Value Value

More information

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Boggarm S. Setty, P.E., Fellow ASHRAE Setty & Associates, Ltd. 3040 Williams Drive, Suite 600, Fairfax,

More information

Report for. Dick and Jane Homeowner. 1234 Lovers Lane, Houston, Texas 77000

Report for. Dick and Jane Homeowner. 1234 Lovers Lane, Houston, Texas 77000 Report for Dick and Jane Homeowner 1234 Lovers Lane, Houston, Texas 77000 March 17, 2004 I NI NP R Inspection Item I. STRUCTURAL SYSTEMS o o o A. Foundations (If all crawl space areas are not inspected,

More information

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing

More information

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Printed On: 2003/04/03 St Patrick CES, 7932 Study [03.3-050 Plumbing Piping Systems] Study condition, remaining service

More information

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS Rhode Island Department of Education School Building Authority 255 Westminster Street, Providence, RI 02909 Telephone (401)222-4600 Website: www.ride.ri.gov

More information

City of Elk River BASEMENT Office Use Only

City of Elk River BASEMENT Office Use Only City of Elk River BASEMENT Office Use Only Fire and Building Safety Division (FABS) Building Permit Application Notes Scan Permit Total Date Permit # PID # $ Site Address Suite/Unit Structure Type Single

More information

Transition to 3D Fabrication Workflows

Transition to 3D Fabrication Workflows Autodesk Autodesk Fabrication Solutions Transition to 3D Fabrication Workflows Autodesk is committed to the use of Building Information Modeling (BIM) to drive integrated and connected data across the

More information

Element D Services Plumbing

Element D Services Plumbing Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.

More information

Design and Construction Design Phase Deliverables

Design and Construction Design Phase Deliverables Design and Construction Design Phase Deliverables Notes: 1. The Architect or Engineer of record shall submit this document along with the deliverables for the project at the end of each design phase for

More information

Element D Services Heating, Ventilating, and Air Conditioning

Element D Services Heating, Ventilating, and Air Conditioning Load Calculation Criteria PART 1 - GENERAL 1.01 OVERVIEW A. This section includes requirements for calculating HVAC cooling and heating loads. B. Load calculations must be performed in accordance with

More information

2301.1 Scope: Communications and Electronic Systems addressed in this section include:

2301.1 Scope: Communications and Electronic Systems addressed in this section include: Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and

More information

Realizing the Future of Sustainable Design through BIM and Analysis

Realizing the Future of Sustainable Design through BIM and Analysis MEP ENGINEERING Realizing the Future of Sustainable Design through BIM and Analysis By Robert E Middlebrooks, AIA In the United States, buildings are responsible for almost half of all annual green house

More information

Schedule B to By-law 33-2009 Part A Fees Payable for Permits

Schedule B to By-law 33-2009 Part A Fees Payable for Permits Floor Area Calculation Floor area shall: Part A Fees Payable for Permits (Effective January 1, 2015) a) be calculated by measuring to the outer face of exterior walls and to the centre of party walls or

More information

CAD Standards Guideline For Facility Documentation and Construction Projects

CAD Standards Guideline For Facility Documentation and Construction Projects CAD Standards Guideline For Facility Documentation and Construction Projects Implemented March 2010 Page 1 of 9 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4.

More information

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client Order of Magnitude Mechanical Estimating Justin Apprill, P.E. Topics for Today Estimate Goals A Concept for Accurate Conceptual Estimating HVAC Systems Common System Types and Rules of Thumb Pricing Example

More information

CAD Standards Guideline For Facility Documentation and Construction Projects

CAD Standards Guideline For Facility Documentation and Construction Projects CAD Standards Guideline For Facility Documentation and Construction Projects Page 1 of 12 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4. External References 5.

More information

BUILDING SAFETY UNIT

BUILDING SAFETY UNIT POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential

More information

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman.

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman. Building Type Building Code Whitley Classroom Buildings BOCA, UBC, SBCCI, NEC, ADA Structural Support Outrigger construction standard, Whitley model classrooms. Main support beams to be 12 11.8# per lineal

More information

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

BUILDING INFORMATION MODELING SCOPE OF SERVICES AND REQUIREMENTS FOR CONSTRUCTION CONTRACTOR IN A DESIGN- BID-BUILD PROCESS

BUILDING INFORMATION MODELING SCOPE OF SERVICES AND REQUIREMENTS FOR CONSTRUCTION CONTRACTOR IN A DESIGN- BID-BUILD PROCESS BUILDING INFORMATION MODELING SCOPE OF SERVICES AND REQUIREMENTS FOR CONSTRUCTION CONTRACTOR IN A DESIGN- BID-BUILD PROCESS Final Version March 16, 2011 TABLE OF CONTENTS Page Contents 1. Introduction...

More information