OHLONE COMMUNITY COLLEGE BOND MEASURE G

Size: px
Start display at page:

Download "OHLONE COMMUNITY COLLEGE BOND MEASURE G"

Transcription

1 Monthly Report OHLONE COMMUNITY COLLEGE BOND MEASURE G Fremont, California June 2014

2 TABLE OF CONTENTS 1. Executive Summary 2. Safety Status 3. Schedule Status 4. Design Progress 5. Construction Progress 6. Closeout Progress 7. Project Budgets 8. DSA Summary OHLONE BOND MEASURE G PROGRAM June

3 Activities Highlighted: Shotcrete Site Visit Synthetic Turf Site Visit Ohlone Construction Blog Citizens Bond Oversight Committee (CBOC) 1. Executive Summary June was a time to visit other campuses in order to evaluate products and processes under consideration for use on the Fremont Campus. On June 10, members of the Executive Core Team visited Stanford University with Gilbane, and Cannon Design, to review installed shotcrete finishes. The visit validated budgeted concrete finishes as acceptable for the Academic Core Buildings project, as well as confirmed the aesthetic expectations of the team. On June 27, the Athletic Fields project team including Ohlone Director of Facilities, Ohlone Women s Soccer Coach, Verde Design, and Gilbane, visited Saratoga High School to view an installed synthetic turf assembly specified for the project. The visit provided an opportunity to discuss field performance and maintenance with the SHS Principal, take temperature readings of the turf surface, and refine the desired synthetic turf specification. With the kickoff of summer construction projects, the Fremont campus has been busy with various activities in multiple locations. In order to assist faculty, staff, students and campus visitors with information on changing conditions, such as parking, access, closures, and outages, Gilbane has been assisting in providing adequate signage as well as updates to the Ohlone Campus Construction Blog and other social media. The quarterly Citizens Bond Oversight Committee meeting was held on June 16, with a tour of Fremont projects prior to the meeting. The tour included the South Parking Structure and the Swing Space modular classrooms under construction, as well as the completed Building 9 gymnasium floor refinishing and energy conservation light replacement projects. Committee members who attended were complimentary of the construction progress, reported that the tour was informative, and requested that additional tours be provided in the future. OHLONE BOND MEASURE G PROGRAM June

4 2. Safety Safety Observations: THIS MONTH TOTAL February May Man-hours Worked 10,518 18,516 Recordable Incidents 0 0 OSHA Inspections 0 0 South Parking Structure Barricade Predictive Solutions One (1) Predictive Solutions safety inspections was conducted in June on the South Parking Structure, including 6 separate observations. 3. Schedule Status OHLONE BOND MEASURE G PROGRAM June

5 4. Project Design Progress Athletic Fields Rendering Project 6101 Athletic Fields The project team is preparing for a scope and budget reconciliation meeting with the executive staff in early July. The District intends to use a Lease-Leaseback delivery method for the Athletic Fields. Five firms responded to the RFQ; a short list of three firms has been identified to receive the RFP. RFP responses are due July 21. Project 6102 Roof Repair/Replacement The design kick off meeting was held in June with the design firm, Gilbane, and the Smith Center User Group. Potholing to determine existing roof conditions will begin in July. Smith Center Roof Arts Building Stanford Site Visit Project 6105A Academic Core Buildings The hazardous material consultant has provided their 75% draft documents for review, as well as their draft conceptual cost estimate for hazardous material abatement. The FF&E kickoff meeting for development of the Academic Core Building Furniture Standards was conducted with college staff and faculty. A LEED coordination meeting was held on June 10, 2014, confirming the project is still on track in regard to LEED goals. Acoustic reverberation time measurements were conducted within the existing Building 2 music facilities in order to assess the existing acoustical environments in the rehearsal facilities. This information will inform the design for the new Academic Core Building. Also on June 10, 2014, the District and Gilbane attended a site visit to the Stanford Campus, Central Plant Project to review different finish levels for shotcrete walls so direction could be provided to the design team regarding acceptable levels of finish for the Academic Core Buildings. OHLONE BOND MEASURE G PROGRAM June

6 ACB West Elevation Newark Greenhouse Project 6105A Academic Core Buildings (Con t) Soft demolition of Buildings 1, 2 and 8, which allows for the start of new construction, is still anticipated to begin in early 2015, with hard demolition starting in late May 2015, and new building construction beginning August Project 7105 Newark Greenhouse DSA Backcheck was conducted June 30, Bid documents are being reviewed and the work will be advertised for bid upon receipt of the DSA approved documents. The most recent cost estimate by the Architect is well within budget. A contract is anticipated to be presented to the Board for approval at the the September Board meeting, with construction starting shortly thereafter. OHLONE BOND MEASURE G PROGRAM June

7 5. Project Construction Progress Site Utility Infrastructure Site Utility Infrastructure Fremont Swing Space Project 6104 Site Utility Infrastructure Improvements Ghilotti Construction continues with the construction of Phase 1A, Summer Work 2014, with the installation of the sanitary sewer, low voltage, 12KV, and medium pressure gas. St. Francis Electric is preparing for the shutdown of Building 3 for conduit termination and shutdown of Substation 2 for conduit, circuit breaker and conductor installation on July 3, Due to the encounter of unforeseen existing underground utilities and additional bedrock, Ghilotti Construction is experiencing delays in the installation of the sanitary sewer. Owner/Contractor coordination meetings have occurred over the last month to ensure Phase 1A, Summer Work 2014, will stay on schedule to complete August 15, 2014, despite the delays. Project 6105B Swing Space Project Redgwick completed all their punchlist work in June, with their final Change Order (#2) to be processed in August. On June 3, 2014 Guerra began Swing Space Connections Package Phase I. On June 14, 2014, Mobile Modular delivered the last Swing Space Phase I portable buildings at both the Fremont and Newark Campuses. On June 26, 2014, DLR submitted the Fremont Swing Space Phase II documents to DSA. The Newark Swing Space Phase II documents have been with DSA since May 5, On June 20, 2014 IBI submitted their Swing Space classroom furniture layout plans for both Fremont and Newark. IBI will continue to work with Gilbane and District purchasing regarding rooms requiring furniture. IBI has begun their furniture layout for the Swing Space Phase II portables. Newark Swing Space OHLONE BOND MEASURE G PROGRAM June

8 South Parking Structure Project 6110 Parking Structures South Parking Structure Overaa continues mass excavation of the structure and is expected to complete the first week of July. The installation of the new fire line was completed on June 20, The footing excavation for the structure began on June 24, The rebar for the footing will start on July 14, The project is 21 days behind schedule and Overaa continues to work on a recovery schedule. They have been working longer shifts and weekends to make up for the delay. South Parking Structure Project 6133 Bird (Swallow) Environmental Alternatives Exclusion means and methods are being developed for the bat colony that is overwintering in Buildings 2 and 8. This work will be scheduled for July, A bat emergence survey will be performed by qualified biologists. The work will identify areas of bat colonies and assist in the development of exclusion methods. Six areas within Buildings 2 and 8 have been identified to house bats during the bird netting installation. Building 1 will be surveyed to confirm status. Bat exclusion means and methods include the installation of netting and one way doors and the potential of netting the entire roof structure. Cliff swallows being seasonal, will leave the Campus this winter. Active nest prevention will be performed when the cliff swallows return in Data Center Relocation Data Center Relocation Project 6142A Data Center Relocation Fire suppression work is proceeding, interior framing and drywall is complete. Ceiling work is 90% complete. Communication racks and server racks seismic attachment and anchor installation observation and testing is in progress. The Contractor did not achieve the June 30 completion date. There is approximately five weeks of schedule float for the data center cutover, which still supports completion of all work prior to start of Fall Semester. The project team is reviewing needs for AT&T fiber service and coordinating with Project 6104 to reduce redundancy. OHLONE BOND MEASURE G PROGRAM June

9 Newark Overflow Parking Project 7102 Newark Overflow Parking The Contractor began construction on June 16, The temporary east parking lot was constructed in seven working days and is open for use. Construction of the permanent west parking lot valley gutters and curbs have begun. Installation of the storm drain inlets and gutters resulted in a determination that the existing grade height was 7 to 12 too low. Adjustments are being made to the concrete curbs and subgrade levels to accommodate this grade differential. Changes to the scope of work include removal and reinstallation of the existing ticket machine in parking lot A and installation of bollards at the entrance to the temporary east parking lot. Prop 39 Projects Newark Valley Gutter Framing The Loop Road and Pool Area Lighting is currently in progress. Buildings 5, 6 and 9 down light retrofit is also in progress and is on schedule. Samples of the latest product offerings in the LED replacement bulbs have been received and have been installed for review for potential use in the future. Scope of work and the Form B for Prop 39 projects has been developed and submitted to PG&E and the Chancellors Office. Building 9 Gym Floor Refinishing Gym Floor Logo Gym floor refinishing was completed June 18, and will cure until July 7 when it will be available for use. OHLONE BOND MEASURE G PROGRAM June

10 Quick Fix Project Summary Building 22 Fire Alarm Site Signage Gamma Builders completed tracing all devices back to the old Grinnell Fire Alarm Panel and completed building the new Siemens Fire Alarm Panel. Gamma Builders will continue installing devices at the basement of Building 22. Summer 2014 maps have been reviewed and approved by Ohlone and will go to vendors for shop drawings. Signage will be in place prior to start of summer classes. Mechanical Repairs Building 22 HVAC study is complete and on hold until Academic Core Building design is complete for HVAC controls. Construction repair of Building 19 Sanitary Sewer completed June OHLONE BOND MEASURE G PROGRAM June

11 6. Project Closeout Progress Building 5 Renovation of Room 5101 Construction is complete and in close out. Building 27 Presidents Conference Room Wall Project Construction is complete and in close out. Building 6 Fire Alarm DSA Completion Notification was received June 2, Building 9 Concrete ADA Curb Cuts Construction is complete and in close out. Geo-coil Repairs (Newark) 90 day letter was sent June 2, 2014 All required documents have been uploaded to the DSA Box. Additional fee check has been sent. Certification and Closeout letter is expected in July. Project 9101 Photovoltaic Energy Generating System - Newark All documentation is submitted and DSA closeout is pending. On June 17, 2014, DSA requested additional fees in order to complete their final closeout review. The District is in the process of cutting the check. Borrego claim against the District still pending. OHLONE BOND MEASURE G PROGRAM June

12 7. Active Project Budgets Project # Project Name Budget Total Contracts Transactions Unencumbered Balance 6101 Athletic Fields $12,527,901 $1,377,772 $463,989 $11,150, Roof Repair/Replacement $3,377,306 $205,701 $15,440 $3,171, Site Utility Infrastructure $15,285,804 $4,844,186 $3,826,231 $10,441, Academic Core Buildings $133,978,079 $23,079,939 $7,828,744 $110,898, Parking, Road, & Site $3,784,893 $404,543 $390,933 $3,380, Plaza & Landscape $7,654,444 $274,544 $260,083 $7,379, Parking Structures $36,835,013 $23,536,584 $3,813,494 $13,298, Renovate Building 9 $15,370,364 $42,806 $4,307 $15,327, Bird (Swallow) Environmental Alternatives $549,120 $190,363 $161,200 $358, Site Security Systems $1,445,600 $150,318 $93,982 $1,295, Hyman Hall Renovations $5,256,000 $924,941 $414,072 $4,331, Newark Additional Parking $1,031,739 $759,828 $62,609 $271, Newark Greenhouse $623,680 $121,516 $60,508 $502, Renewable Energy $31,330,689 $19,073,948 $18,313,482 $12,256, IT Infrastructure $2,275,000 $2,236,598 $2,226,037 $38, Instructional Technology $1,560,000 $1,550,901 $1,443,745 $9, FF&E $9,000,000 $392,658 $131,882 $8,607, QF: Imminent Failure $5,347,175 $4,860,417 $3,910,056 $486, QF: Safety & Accessibility $2,224,313 $2,006,788 $1,262,310 $217, QF: Way-finding/Landscape $1,056,000 $125,642 $109,419 $930, Energy Efficiency Projects $1,026,714 $19,339 $8,608 $1,007, Program Contingency $11,100,845 $805,782 $805,782 $10,295, Planning Assessments & Program Management $16,602,156 $4,104,134 $27,283,984 $12,498,022 $90,428,102 Contracts Amendments Transactions Contract Balance $44,872,997 $50,525,429 $4,971,325 OHLONE BOND MEASURE G PROGRAM June

13 8. DSA Summary DESIGN/CONSTRUCTION PHASE SUBMISSION REC'D PROJECT NAME MEASURE DSA # PLANNED ACTUAL PERMIT 6101 Athletic Fields G TBD 11/12/ Roof Repair/Replacement G TBD 10/15/2014 Civil/Infrastructure Upgrade - Water 6104 System Improvements G /27/2014 Civil/Infrastructure Upgrade - Utility 6104 Infrastructure Upgrade G /1/ A Academic Core Buildings G TBD 9/13/ B Swing Space Portables - Increment 1 G /11/ B Swing Space Portables - Increment 2 G /26/ South Parking Structure Increment 1 G /10/ South Parking Structure Increment 2 G /23/ A Data Center Relocation G /27/ Newark Parking Lot G /11/ Newark Greenhouse G /1/ Building 22 Fire Alarm G /30/2013 CLOSEOUT PHASE SUBMISSION DSA PROJECT NAME MEASURE DSA # PLANNED ACTUAL CLOSED Science Classroom Building 16 A /3/ Photovoltaic Generation - Newark G / Building 6 Fire Alarm G /2/ Geocoil Repair G /29/2014 OHLONE BOND MEASURE G PROGRAM June

The work has continued on final Phase 4 and is nearing completion.

The work has continued on final Phase 4 and is nearing completion. Updates-January 22, 2013 29369-Rehab Plaza Deck/Drainage Budget: $18,000,000, constr. Start 8/2009 The work has continued on final Phase 4 and is nearing completion. The main plaza area of phase 4 is now

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008

NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008 NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008 PROGRAM AND CONSTRUCTION MANAGER SEPTEMBER 30, 2008

More information

Angelo State University Construction Report

Angelo State University Construction Report May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning

More information

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 To better prepare San Jose City College/ Evergreen Valley

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT Los Angeles Trade Technical College PROGRESS REPORT NOVEMBER 2013

LOS ANGELES COMMUNITY COLLEGE DISTRICT Los Angeles Trade Technical College PROGRESS REPORT NOVEMBER 2013 1.0 EXECUTIVE SUMMARY 1.1 Campus Program Summary There are seven (7) projects in pre-design and programming; five (5) are in design; and six (6) in construction. A summary of the Trade-Tech construction

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM GB2 OFFICE OF THE PRESIDENT TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For the Meeting of May 15, 2013 ACTION ITEM APPROVAL OF THE BUDGET AND APPROVAL OF DESIGN FOLLOWING ACTION PURSUANT TO

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Lindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1

Lindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1 School Facilities Evaluation Project Page 1 Executive Summary In November 1999, Alberta Infrastructure, School Facilities Branch engaged Stephens Kozak Carr and Brown Architects to conduct evaluations

More information

Schedule B to By-law 33-2009

Schedule B to By-law 33-2009 Amended by By-law 8-2016 Note: This consolidation is prepared for convenience only. For accurate reference the original by-laws should be reviewed. Floor Area Calculation Floor area shall: Schedule B to

More information

Capital Projects Town Hall Meeting

Capital Projects Town Hall Meeting Capital Projects Town Hall Meeting Planning, Architectural & Engineering Services September 15, 2014 Agenda Project Updates Recently Completed and in Construction Projects in Design Projects in Planning

More information

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT 1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.2 Water damage in many classrooms. Replace tiles. 1.1.3 Cabinets, Equipment 1.1.4 Portables

More information

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal

More information

Building Condition Assessment Report

Building Condition Assessment Report C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses

More information

Policy on Repair and Renovation Funding

Policy on Repair and Renovation Funding Policy on Repair and Renovation Funding I. POLICY STATEMENT Auburn University s (the University s) Policy on Repair and Renovation Funding provides guidance and direction regarding the use of Repair and

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

Repair Project for April 7, 2009

Repair Project for April 7, 2009 Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades

More information

Project Management Division

Project Management Division CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT February 2015 Project Management Division BELOW: Collins Construction crews complete recent exterior work and await delivery of exterior siding. Collins

More information

1. Upon receipt of a signed Budgetary Estimate, including an index number, the work of creating a Project begins as follows:

1. Upon receipt of a signed Budgetary Estimate, including an index number, the work of creating a Project begins as follows: Project Development Revised 4/17/13 Process PROJECT INITIATION PHASE 1. Upon receipt of a signed Budgetary Estimate, including an index number, the work of creating a Project begins as follows: PRE-DESIGN

More information

CAPITAL PROGRAM SERVICES Capital Improvement Program

CAPITAL PROGRAM SERVICES Capital Improvement Program TABLE OF CONTENTS CAPITAL PROGRAM SERVICES Capital Improvement Program SEPTEMBER 2012 MONTHLY REPORT PROGRAM OVERVIEW Project Management & Quality Management Design and Bidding Controls MWSBE Bond Progress

More information

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011 Facility Services Section Page Recharge Services, Maintenance and Construction PURPOSE 1 of 6 The purpose of this policy is to set forth standards for chargeable services for maintenance and construction

More information

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx.

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx. cityoflavernia@lavernia-tx.gov Commercial New/Remodel Building Requirements This document is not meant to modify any Federal or State laws or City Ordinances. It is intended to be informative and to be

More information

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows: Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2194 ADDENDUM NUMBER ONE January 24, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer

More information

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1 REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

Facilities Operations Customer Service Standards WORK ORDER PRIORITIES

Facilities Operations Customer Service Standards WORK ORDER PRIORITIES Facilities Operations Customer Service Standards WORK ORDER PRIORITIES In order to provide fair and consistent maintenance service to all University faculty, staff and students, a work priority system

More information

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management

More information

DRAPER ELEMENTARY SCHOOL

DRAPER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

32284 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 MAY 1, 2014

32284 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 MAY 1, 2014 32284 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 MAY 1, 2014 BOARD OF TRUSTEES OF COMMUNITY COLLEGE DISTRICT NO. 508 COUNTY OF COOK AND STATE OF ILLINOIS JOB ORDER CONTRACT (JOC) PROJECTS

More information

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School Introduction Background The Duke School of Nursing building offers a new three-story state of the art facility that has helped strengthen the quality and integrity of the School of Nursing at Duke. The

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES All searches and notifications on Bid4Michigan are based on National Institute of Government Purchasing (NIGP) codes. It

More information

HOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number: 300-004

HOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number: 300-004 HOWARD UNIVERSITY Policy Number: 300-004 Policy Title: ASSET CAPITALIZATION Responsible Officer: Chief Financial Officer Responsible Offices: Office of the Controller, Departments of Strategic Sourcing

More information

ENVIRONMENTAL HEALTH & SAFETY 6 East Dr., Amherst MA 01002-5000

ENVIRONMENTAL HEALTH & SAFETY 6 East Dr., Amherst MA 01002-5000 AMHERST COLLEGE ENVIRONMENTAL HEALTH & SAFETY 6 East Dr., Amherst MA 01002-5000 Michael Zlogar April 11, 2001 Assistant Fire Chief Amherst Fire Department 68 North Pleasant St. Amherst, MA 01004 FIRE ALARM

More information

Schedule B to By-law 33-2009 Part A Fees Payable for Permits

Schedule B to By-law 33-2009 Part A Fees Payable for Permits Floor Area Calculation Floor area shall: Part A Fees Payable for Permits (Effective January 1, 2015) a) be calculated by measuring to the outer face of exterior walls and to the centre of party walls or

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 7 E. DESIGN

More information

Development Services Guidelines

Development Services Guidelines Dear Customer/Developer: Balcones Heights 3300 Hillcrest San Antonio, Texas 78201 210-735-9148 ext 246 Fax: 210-735-9409 Development Services Guidelines Welcome to the City of Balcones Heights, we look

More information

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL?

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? 1. BASIC FACTS: The current Abington High School building is 111,831

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

Product description NCC Data Center

Product description NCC Data Center Product description NCC Data Center Concept General As one of the largest actors in the Nordic construction industry, NCC Construction plays a leading role in shaping the future of our society. After building

More information

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT 1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

Dear Keller High School Families,

Dear Keller High School Families, Dear Keller High School Families, As we near the close of the 2014-15 school year, I am so proud of our community of learners for committing to the vision of KHS and its Tradition of Excellence! I would

More information

Lincoln Public Schools. 15 Attachments (separately bound) Schematic Design. 15.1 Schematic Design Project Manual

Lincoln Public Schools. 15 Attachments (separately bound) Schematic Design. 15.1 Schematic Design Project Manual 15 Attachments (separately bound) 15.1 Project Manual - Table of Contents - Outline Specifi cations 15.2 Drawings (half size) - Drawing List Section 15.3 15.1 Project Manual Separately bound and being

More information

NOTICE TO CONTRACTORS

NOTICE TO CONTRACTORS NOTICE TO CONTRACTORS Notice is hereby given that San Luis Obispo County Community College District, ( District ) is accepting sealed Informal Bidding Prequalification Applications and Formal Bidding Prequalification

More information

KIEWIT CM/GC Enabling/Utilities

KIEWIT CM/GC Enabling/Utilities South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 john.todd@kiewit.com General

More information

Single Family Residential Building Permit Questions & Answers

Single Family Residential Building Permit Questions & Answers Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday

More information

Frequently Asked Questions

Frequently Asked Questions Byron Area Schools Frequently Asked Questions Bond Proposal How did this come about? For several years the Byron Area Schools Board of Education has included upgrading facilities as one of the district

More information

Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11

Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11 Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11 Introduction Constructing new commercial or residential space can be a complicated

More information

Rio Hondo Community College District Measure A General Obligation Bonds Performance Audit July 1, 2012 through June 30, 2013 With Report of

Rio Hondo Community College District Measure A General Obligation Bonds Performance Audit July 1, 2012 through June 30, 2013 With Report of July 1, 2012 through June 30, 2013 With Report of Independent Auditors Table of Contents PAGE REPORT OF INDEPENDENT AUDITORS 1 PERFORMANCE AUDIT Objectives 2 Scope of the Audit 2 Background Information

More information

APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT

APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT PROJECT MANAGEMENT / SUPPORT Capital Cost Savings Construction Monitoring and Assistance In-Plant Production Assistance In-Plant Maintenance Assistance Procurement Assistance Project Cost Estimating o

More information

University of Northern Iowa Facilities Services

University of Northern Iowa Facilities Services University of Northern Iowa Facilities Services February 2013 Page 1 Table of Contents: 3 General Service Information 3 Maintenance Services 4 Non-Maintenance Services 5 Area Maintenance Program 6 Carpentry

More information

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3 TOWN OF SIDNEY Multi-Family, Commercial, Industrial and Institutional Building Permit Guide The information provided is intended as a guide only and does not replace current bylaws and regulations. Complete

More information

Public Building Commission of Chicago. Board Meeting August 20, 2013

Public Building Commission of Chicago. Board Meeting August 20, 2013 Public Building Commission of Chicago Board Meeting August 20, 2013 Board Meeting August 20, 2013 Recent Events Enrico Tonti Elementary School Kindergarten Modular Opening August 5, 2013 Board Meeting

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM GB6 Office of the President TO MEMBERS OF THE COMMITTEE ON : For Special Meeting of ACTION ITEM APPROVAL OF PHASE 1 OF THE UTILITY LINE REMEDIATION PROJECT RELATED TO THE MISSION BAY DILLER BUILDING, ROCK

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012 Geo-Thermal

More information

Chicago Public Schools

Chicago Public Schools Ames Middle School 1920 N Hamlin Ave 1997 Completed The scope of this project is to construct a new school $16,913,379 2014 Construction The intent of this project is to expand existing Ames middle school

More information

The City of Basehor, Kansas

The City of Basehor, Kansas The City of Basehor, Kansas Residential and Miscellaneous Permits This list provides general information regarding permit requirements for various residential construction and maintenance activities. The

More information

Every Student I Every Day I Every Possibility

Every Student I Every Day I Every Possibility For the Facilities Master Plan March 4, 2015 1 Introduction This has been prepared to describe a proposed process to be implemented in order to develop comprehensive Facility Master Plans for all schools

More information

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS Rhode Island Department of Education School Building Authority 255 Westminster Street, Providence, RI 02909 Telephone (401)222-4600 Website: www.ride.ri.gov

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, 5.00 12, 2012

31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, 5.00 12, 2012 31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, 5.00 12, 2012 BOARD OF TRUSTEES OF COMMUNITY COLLEGE DISTRICT NO. 508 COUNTY OF COOK AND STATE OF ILLINOIS JOB ORDER CONTRACT

More information

PROJECT UPDATES: 1.01 Cox Building Annex - Andy Doran (3 min)

PROJECT UPDATES: 1.01 Cox Building Annex - Andy Doran (3 min) PROJECT UPDATES: 1.01 Cox Building Annex - Andy Doran (3 min) 1. Hensel Phelps (HPCC) substantially completed work on October 31, 2013. 2. The A/E Team completed their Punch walk on October 31, 2013. 3.

More information

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are: When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory

More information

Design and Construction Planning Process Strongsville City Schools

Design and Construction Planning Process Strongsville City Schools Design and Construction Planning Process Strongsville City Schools THANK YOU. OUR TEAM 50+ years experience Headquartered in Akron, Ohio Full-service A&E firm Over 400 professionals Employee owned OUR

More information

Capital Project Delivery Handbook

Capital Project Delivery Handbook Capital Project Delivery Handbook Volume One Facilities Planning & Construction 1 FACILITIES PLANNING & CONSTRUCTION 3/8/09 2 FACILITIES PLANNING & CONSTRUCTION 1. WELCOME TO FACILITIES PLANNING & CONSTRUCTION...

More information

November 3, 2015 Bond and District Additional Assistance Election Information

November 3, 2015 Bond and District Additional Assistance Election Information November 3, 2015 Bond and District Additional Assistance Election Information Proposition 432 - $22 million General Obligation Bond 150+ facility projects across all schools Building renovations and improvements

More information

Development Services Guidelines

Development Services Guidelines Dear Customer/Developer: Balcones Heights 3300 Hillcrest San Antonio, Texas 78201 210-735-9148 ext 246 Fax: 210-735-9409 Development Services Guidelines Welcome to the City of Balcones Heights, we look

More information

CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division

CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT RIGHT: the proposed conceptual profile of the new Joe Redington Sr. JR/SR High School January 2014 Project Management Division New Knik Area Middle/High

More information

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project March, 2015

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project March, 2015 Addendum 1: Changes to the Draft IS/MND Text and Figures Introduction This summary presents minor corrections and revisions made to the Draft IS/MND initiated by the public, staff and/or consultants based

More information

Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR)

Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR) Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR) Version 1.2 9/30/2010 Table of Contents IVR Instructions...3 Initial Entry Instructions...3 Permit Access Instructions

More information

WYTHEVILLE COMMUNITY COLLEGE

WYTHEVILLE COMMUNITY COLLEGE WYTHEVILLE COMMUNITY COLLEGE Director of Facility Planning and Maintenance Position Description: The Director of Facility Maintenance directs, manages, and supervises all aspects of facility planning,

More information

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table

More information

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION 1 AGENDA Hazelwood 1 st Planning Process High School Program Schematic Designs Schedule 2 HAZELWOOD 1 ST GOALS Life, health and safety improvements

More information

City of San Diego Residential Photovoltaic Systems Inspection Guidelines

City of San Diego Residential Photovoltaic Systems Inspection Guidelines City of San Diego Residential Photovoltaic Systems Inspection Guidelines The purpose of inspections by DSD staff is to ensure compliance with the California Electrical Code (CEC), other applicable codes

More information

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital June 21, 2007 The Grossmont Healthcare District (GHD) will accept proposals for Architectural and Engineering

More information

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

2012 BIM Guidelines and Standards (Rev. 00) University at Albany A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested

More information

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes The graduate has reliably demonstrated the ability to 1. analyze a client's needs

More information

Please fill out and return the attached bid form to Jeremy Smith by Monday January 18, 2016 by 11 AM.

Please fill out and return the attached bid form to Jeremy Smith by Monday January 18, 2016 by 11 AM. December 23, 2015 Berkeley County School District - Energy Upgrades Electrical Bid Package Request For Proposal CMTA Contact: Jeremy Smith Email: jsmith@cmtaegrs.com Phone: 502-326-3085 Cell Phone: 859-421-9603

More information

The University of Akron Main Campus Biennium 1 July 2016- June 2018. Priority Project Budget Description 1 Electrical Infrastructure Loop

The University of Akron Main Campus Biennium 1 July 2016- June 2018. Priority Project Budget Description 1 Electrical Infrastructure Loop The University of Akron Main Campus Biennium 1 July 2016- June 2018 1 Electrical Infrastructure Loop $2,400,000 Scope: Replace center campus deteriorated 4,160 volt cable and duct bank with 23,000 volt

More information

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule

More information

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES A Residential Owner s Guide to PERMITS CITY OF Elgin PLANNING & NEIGHBORHOOD SERVICES CITY OF Elgin A Residential Owner s Guide Welcome! This booklet has been prepared to provide residential property owners

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents

Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents Primary Author: Laura McCluskey 4801 N Career Ave Sioux Falls, SD

More information

HEANEY General Contracting, Inc.

HEANEY General Contracting, Inc. HEANEY General Contracting, Inc. March 26, 2016 AAPS BID NO. 16-019-665 ADDENDUM NO. 03- PROJECT: DESCRIPTION: Ann Arbor Public Schools Mitchell Expansion Phase I Bid Pkg. 3 (MEP) Building Addition and

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED*

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED* ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED* BID PACKAGE DESCRIPTION REQUIRED LICENSE Bid Package No. 1 Asbestos Abatement C22 or B, with ASB & HAZ Certification Bid

More information

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered

More information

Reference Guide for Obtaining Permits and Utility Services For New Construction

Reference Guide for Obtaining Permits and Utility Services For New Construction Reference Guide for Obtaining Permits and Utility Services For New Construction (Revised 04-2012) Table of Contents City Offices Telephone Numbers...1 Application for Utilities...2 Building Permits New

More information

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or 9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org Construction Permitting Guidelines for Businesses Moving into Existing Buildings in Culver City If your business is moving into an existing

More information

PLAN SUBMITTAL INFORMATION

PLAN SUBMITTAL INFORMATION PLAN SUBMITTAL INFORMATION APPLICATION FOR A BUILDING PERMIT Prior to drafting construction drawings, please check with the North Miami Beach Community Development Department concerning the following:

More information

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities At Macau International Airport (RFQ-198) Section 6 Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA

More information

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PARKS, RECREATION, AND CULTURAL SERVICES DEPARTMENT

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PARKS, RECREATION, AND CULTURAL SERVICES DEPARTMENT January 27, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PARKS, RECREATION, AND CULTURAL SERVICES DEPARTMENT ON WESTSYDE POOL AND COMMUNITY CENTRE ROOF REPAIR OPTIONS UPDATE PURPOSE To provide

More information

Enhancements to Streamlined (k) Limited Repair Program

Enhancements to Streamlined (k) Limited Repair Program U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT WASHINGTON, DC 20410-8000 ASSISTANT SECRETARY FOR HOUSING- FEDERAL HOUSING COMMISSIONER December 29, 2005 MORTGAGEE LETTER 2005-50 TO: ALL APPROVED MORTGAGEES

More information

UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNIVERSITY OF CALIFORNIA, SAN DIEGO UNIVERSITY OF CALIFORNIA, SAN DIEGO UCSD BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ UNIVERSITY CENTERS - 0076 PHONE: (858) 822-4987 9500 GILMAN

More information

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor

More information

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0. Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M

More information