EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK

Size: px
Start display at page:

Download "EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK"

Transcription

1 EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK F. Malone*, P.D. Doyle *ESB International, Ireland fergus.malone@esbi.ie ESB International, Ireland paul.d.doyle@esbi.ie Keywords: Overcurrent Protection, Coordination, IEC 61850, Directional Comparison Abstract Directional and non directional overcurrent protection are well established methods of providing either primary or backup protection on distribution networks. Compared to unit protection which only protects a specific piece of equipment, such as a transformer or feeder, overcurrent protection has the advantage of being able to provide protection to large sections of network. To do this the overcurrent protection on a network must be coordinated. On radial distribution systems this can be easily achieved, however, on a meshed or looped system it is not always possible to achieve the required coordination. For this reason overcurrent protection is sometimes unsuitable for certain applications. This paper looks at a section of 66kV distribution network for which overcurrent protection is unsuitable. The inadequacy of the standard protection scheme for the network in question is explained and possible alternatives discussed. The paper then goes through the rationale for selecting the most suitable alternative protection scheme for the section of network in question. 1 Introduction The 66kV distribution system under examination has two standard types of 66kV substations, City Tee Type and Loop Type. These standard types of 66kV substations are described in the next section. City Tee Type City Tee substations are formed when three 66kV feeders from a 220kV/66kV Bulk Supply Point (BSP) substation feed directly into three 66kV/11kV transformers in a 66kV substation. A Tee point is located on each feeder before entry to the 66kV/11kV transformers. From these three Tee points another three 66kV/11kV transformers are fed in the next substation. Again at the next substation there will be Tee point connections to the final substation on that section of 66kV network. There are no 66kV busbars in City Tee substations. The City Tee substations layout can be seen in Figure 1. BSP 66kV Busbar 1 2 For City Tee substations the primary feeder protection normally consists of feeder differential OC Relay between each substation along the circuit together with Tee point differential protection at each 3 substation. Backup protection is provided using Figure 1 City Tee Type Substations overcurrent protection located at the feeder outlet at the BSP. This overcurrent protection must coordinate with the 66kV bus coupler overcurrent protection in the BSP and also with the 11kV overcurrent protection on the 66kV/11kV transformers in each 66kV substation.

2 Loop Type Loop type substations are substations which have their own 66kV busbar, which is fed by two separate feeders. One of these two 66kV feeders will be connected directly onto the 66kV busbar in a BSP while the other will connect to a 66kV busbar in another Loop Type substation. The second 66kV feeder at this Loop Type station will then connect to a second BSP. The Loop Type substation layout can be seen in Figure 2. Loop-Type s BSP 1 66kV Busbar For Loop Type substations the primary feeder protection normally consists of feeder differential between each Loop Type substation and each DOC Relay BSP along with feeder differential between the two Loop Type substations. Backup protection is provided using directional overcurrent protection located at both ends of each of the 66kV feeders. BSP 2 66kV Busbar The directional overcurrent protection located at the BSP must coordinate with the 66kV bus Figure 2 Loop Type Substations coupler overcurrent protection in the BSP, the 66kV overcurrent protection on the feeder between the two Loop Type substations and also with the 66kV overcurrent protection on the 66kV/11kV transformers in the 66kV substation. The directional overcurrent protection at the Loop Type substations on the feeders connected to the BSPs can be set to trip very quickly as these feeders would never carry load current towards their respective BSPs, as there is always a normally-open point at some location between the two BSPs. Section of 66kV Network under Examination Before the introduction of a 220kV transmission network the 66kV network was the main transmission network for the system in question. As such all power stations were connected onto the 66kV network. Gradually over time most power stations were transferred to the 220kV network. However, the section of network under examination still has a power station connected at 66kV. In recent times load demands in the region required a connection onto the 220kV system which came in the form of a 220kV BSP. To increase operational flexibility it was decided to link the to the BSP via two 66kV feeders. As a result the 66kV network in question is quite unusual. This network can be seen in Figure 3. As can be seen in Figure 3, the two 66kV feeders between the BSP and the along with the BSP Distribution and Distribution feeders form three parallel paths between the BSP and the. Also, all three parallel paths are fully cabled and are quite short in length. It is not possible to coordinate the directional overcurrent protection on the feeders as for a fault on any particular feeder the directional overcurrent protection on all three circuits will pick up as the fault current splits between the three parallel paths. 11kV Busbar New 66kV feeders 11kV Busbar 220kV Busbar BSP 66kV Busbar 66kV Dist. OC Relay DOC Relay Figure 3 66kV Network under examination

3 Another problem is trying to coordinate the 66kV directional overcurrent protection with the 66kV bus coupler protection at both the BSP and the. For a fault on the 66kV busbar, the local 66kV bus coupler overcurrent relay should trip before the directional overcurrent protection at the BSP end of the feeders, which in turn should trip before the BSP bus coupler overcurrent protection. Likewise for a fault on the BSP 66kV busbar, the local bus coupler overcurrent relay should trip before the directional overcurrent protection at the end of the feeders, which in turn should trip before the bus coupler overcurrent protection. It is not possible to achieve both of these requirements simultaneously. In addition to this problem, the 66kV bus coupler protection in the is quite slow as a result of coordinating with slow outgoing 66kV feeders. Due to high short circuit levels on the 66kV system the timer of the bus coupler protection at the BSP cannot be increased due to the limitations of the switchgear duty. This also limits the ability to time-grade the protection on this section of network. For these reasons directional overcurrent protection is unsuitable as backup protection on this section of the 66kV network. 2 Alternative Backup Protection Schemes As a result of the issues outlined above it was decided to investigate alternative backup protection schemes for the 66kV network in question. These alternative protection schemes are outlined below. 2.1 Duplicate Feeder Differential The first alternative backup protection scheme considered was a duplicate feeder differential scheme. This would require a replication of the feeder differential scheme currently installed as primary protection but with some important alterations. 1) The communications link would have to follow a separate route. 2) An alternative protection relay manufacturer to that of the primary differential scheme would have to be used. Figure 4 shows suggested routes for the fibre-optic links between the duplicate differential relays for each feeder. It is worth noting that both the BSP circuits 1 & 2 are buried in the same trench, so in order to prevent a common mode of failure the communications channels for the backup protection scheme should follow the circuit 3 route via the 66kV Distribution. Ccts1& 2 BSP PS Comms route 66kV Dist. Figure 4 Backup Protection Communication Channels A duplicate feeder differential scheme will only provide backup protection for the 66kV feeders. As a result the backup busbar protection for each station would be compromised. Without directional overcurrent relays on the feeders the backup busbar protection for either station would be dependant on the coupler and source transformers or generators tripping out in the remote station. Ccts 1&2 Cct 3 BSP Dist. St. Comms route BSP Cct 3 Cct 3 Dist. St. PS Comms route

4 2.2 Directional Comparision Overcurrent The next scheme examined was a directional comparision overcurrent scheme. This scheme uses directional overcurrent relays on both ends of each feeder, similar to the original backup protection proposed on the network. In addition, the two directional overcurrent relays at each end of the feeder City Tee feeders Ccts 1&2 Fwd Pickup BSP 66kV Dist. Cct 3 PS Loop Type feeder DOC Relay Blocking Signal Figure 5 Directional Comparison scheme blocking signals Channels communicate with each other over fibre optic channels. A fault is determined to be internal to the feeder if the relays at each end pick up in the forward direction. This allows a permissive trip to occur, where both relays trip without any additional time delay. Near-instantaneous backup protection is provided to each cable in this way the only time delay being the relay s directional decision time plus the communication time delay. The IDMT directional overcurrent stages provide backup protection to the BSP and the in the event of a fault at either busbar not being cleared by the primary protection. Backup protection for busbar faults in the Distribution is provided by the IDMT stage of the directional overcurrent relays at the remote ends of the Distribution BSP and Distribution feeders. An extra measure is required to ensure selectivity for faults on the Loop Type 66kV feeder (as shown in Figure 5) in the event of that feeder s unit protection failing to clear the fault. As this is a Loop Type feeder, there is no instantaneous overcurrent stage enabled on the directional overcurrent relay. It is not possible to coordinate the IDMT stage of this relay with the directional overcurrent relays on circuits 1, 2 & 3, so a blocking signal is required to be sent to the appropriate relays in the event of the Loop Type feeder relay picking up for a fault in the forward direction. In the case of the City Tee 66kV feeders, it is not possible to coordinate the directional overcurrent relays on circuits 1, 2 and 3 with the City Tee directional overcurrent relays for downstream 11kV faults, so a blocking signal is also required from each of these relays in the event that they pick up in the forward direction. A simplified schematic of these blocking signals is shown in Figure 5. The existing overcurrent relays on the two 66kV transformer feeders at the Distribution have no instantaneous element, so it is not possible to coordinate the directional overcurrent relays on the Distribution outlets at the BSP and the with those relays. This problem can be solved by installing overcurrent protection which includes an instantaneous element. 2.3 IEC Blocked Overcurrent Scheme The final scheme which was looked at was a blocked overcurrent scheme utilising the IEC communication protocols [1]. This scheme involves connecting IEC compatible relays in each station via CAT-5 ethernet cable to their local Ethernet switch. The Ethernet switches are linked via fibre optic channels between the stations. This allows each relay to send and receive GOOSE (Generic Object Oriented Substation Event) messages. A GOOSE message can be sent by any relay to all the other Ethernet-connected devices in all three stations to indicate the pickup of a specific directional element. Each device that receives the message will be programmed to block the appropriate element, switch between tripping characteristics or ignore the message altogether, as appropriate. This system enables selective tripping for all faults on the 66kV network in question.

5 The following describes the operation of the system for different fault scenarios: Fault on 66kV feeders between the BSP, the and the Distribution Directional Overcurrent relays on each end of the faulted feeder pick up in the forward direction and broadcast GOOSE messages to that effect. Directional Overcurrent relays on parallel feeders are blocked from tripping. Bus coupler overcurrent relays in the BSP and the switch to slower IDMT characteristic as the fault is confirmed to be not on the busbar. Tripping is accelerated for the relay at each end of the faulted feeder. Fault on 66kV busbar of the BSP or the 11kV Busbar BSP 220kV Busbar 66kV Busbar 66kV Dist. Bus coupler overcurrent relay picks up for the fault and no blocking signal is received from a relay on any busbar outlet. So the bus coupler relay remains in its fast IDMT characteristic and trips the coupler. The overcurrent relay on any HV transformer/generator connected to the faulted busbar section trips, along with any feeder carrying fault current connected to the same section. OC Relay Ethernet Switch 11kV Busbar DOC Relay Cat 5 Cable Fibre Optic link Figure 6 IEC61850 Blocked Overcurrent Scheme Channels The healthy bus section(s) and feeder(s) remain intact and load can still be fed from the healthy bus sections. Fault on 66kV busbar of the 66kV Distribution Directional Overcurrent relays on the and BSP feeders at the Distribution pick up in the reverse direction and broadcast GOOSE messages. Directional Overcurrent relays on parallel feeders are blocked from tripping. Bus coupler overcurrent relays in the BSP and the switch to their slower IDMT characteristic as the fault is confirmed not to be on the busbar. Tripping is accelerated for the relays at each end of the feeders from the and BSP to the distribution station.

6 Fault on City/Loop-type 66kV feeders from the Directional Overcurrent relay on the faulted feeder picks up and broadcasts GOOSE message. The bus coupler switches to its slower IDMT characteristic to coordinate with the feeder relay. Directional Overcurrent relays at the BSP and the Distribution switch to slower characteristic to coordinate with the slow bus coupler overcurrent characteristic at the. The BSP bus coupler switches to its slower overcurrent characteristic to coordinate with the feeder relays. The Directional Overcurrent relay on the faulted feeder clears the fault and nothing else trips on the network. Fault on the outgoing 66kV feeders from the 66kV Distribution 66kV Directional Overcurrent relay on the faulted feeder picks up and broadcasts a GOOSE message Directional overcurrent relays on the feeders from the BSP and to the 66kV Distribution remain in their slower IDMT characteristic in order to coordinate with the downstream relay that issued the GOOSE message. 11kV fault at the or the BSP (not cleared by 11kV protection) 66kV Overcurrent relay on the 66/11kV transformers picks up in the IDMT stage. This overcurrent relay is not linked via IEC61850 so no GOOSE message is sent. Bus coupler overcurrent relay remains in its fast IDMT characteristic but this is set to coordinate with the 66/11kV transformer overcurrent relay so fault is cleared selectively. 11kV fault at 66kV Distribution (not cleared by 11kV protection) 66kV Overcurrent relay on 66/11kV transformers picks up in the IDMT stage. This relay is not linked via IEC61850 so no GOOSE message is sent. Distribution feeder directional overcurrent relays at the BSP and the pick up, but due to their high pickup current they coordinate with the 66/11kV transformers overcurrent relays for 11kV faults. Fault on HV side of the 66/11kV transformers at the / the BSP / the Distribution (not cleared by differential protection) The instantaneous element of the 66kV Overcurrent relay on the 66/11kV transformer picks up and trips straight away, clearing the fault.

7 3 Discussion This section discusses the technical merits of each scheme along with the cost and physical installation requirements. 3.1 Duplicate Feeder Differential Backup protection for the 66kV cables is instantaneous with the duplicate differential scheme. However, it would not be practical to install duplicate busbar differential protection for the 66kV busbars at the BSP, the Distribution and the. If a 66kV busbar fault occurred at the BSP, the or the Distribution and primary protection failed the 220kV transformers at the BSP and the generators at the power station would have to be disconnected by overcurrent protection in order to clear the fault. Due to the low probability of busbar faults, this may be acceptable as long as the fault clearance time is quick enough to avoid any damage to equipment. However, the short circuit duty was calculated for 66kV busbar faults and it was found that for certain faults at the Distribution 66kV busbars, the short circuit withstand of the busbar was exceeded. It may be possible to ensure the short circuit duty is kept within the busbar ratings by changing the protection settings on the existing protection in downstream substations. This is currently being investigated. Also the CT cores being used for the backup protection scheme may not meet the criteria for use in a differential scheme so may have to be replaced. Equipment Required 8x Differential Relays CTs on 8 bays for feeder differential protection. (depending on testing / suitability of existing relays) Installation Installing CTs on each end of the 66kV cables between the BSP, the Distribution and the would require outages of each 66kV feeder. The outages should be possible to organise due to the three parallel circuits connecting the BSP and the, however replacing the GIS CTs at the BSP (if the existing overcurrent CTs are unsuitable for differential protection) would not be as straightforward. Commissioning of the scheme would be relatively straightforward. 3.2 Directional Comparision Overcurrent Backup protection for the cables is similar in performance to the duplicate differential scheme, offering near-instantaneous backup protection [2]. Unlike the duplicate differential scheme, the directional overcurrent relays can also provide extra protection to the busbars at the, the BSP and the Distribution in the event of the busbar differential protection failing to clear a fault. The benefits of this backup busbar protection are: Busbar faults are cleared faster resulting in a reduced short circuit duty. This prevents any risk of damage to the busbar in the event of the busbar differential protection failing. For a busbar fault in the or the BSP, the three 66kV branches are disconnected. This allows the coupler closest to the faulted busbar section to trip and only the transformer/generator(s) connected to the faulted busbar section to trip, allowing some load to continue to be fed. For a fault at Distribution 66kV bus, only the Distribution feeders at the BSP and will be disconnected. This is a more selective busbar protection than that offered by the duplicate

8 differential scheme. With the duplicate differential scheme, both transformers in the BSP and generators in the station would trip for a busbar fault in the BSP, Distribution or the that was not cleared by primary protection. Equipment Required 3 Teleprotection devices 3x Numerical Directional Overcurrent relays. 2x Numerical Overcurrent Relays. Installation With no new instrument transformers required and only 5 relay replacements, the implementation of this scheme would be the least disruptive to the network. Commissioning would be relatively simple. An advantage of this scheme is that it makes use of the existing DOC relays that are already installed on the BSP and BSP Distribution feeders as well as the associated instrument transformers. 3.3 IEC Blocked Overcurrent Scheme This scheme offers fully selective backup protection to the BSP to and the BSP Distribution cables as well as the busbars in each station. 66kV Bus coupler relays in the BSP and the could also be coordinated with the feeder relays so the load disruption would be minimised for busbar faults that are not cleared by primary protection. Equipment Required 16x IEC61850 compatible Directional Overcurrent relays VTs on 5 generator transformer bays 3x Ethernet hubs Installation This scheme would require a directional overcurrent relay on every outlet from the busbar in each station to determine whether or not a fault lies on the busbar. This requires VTs to be installed on the generator bays in the. During a site survey, it was found that due to a lack of space in the bays of the indoor AIS compound at the, the installation of VTs would not be practical. Aside from the high cost of the equipment required and the complex commissioning associated with this option, the lack of space to install VTs in the generator bays at the means that this protection scheme is not a viable option.

9 4 Conclusions Duplicate Differential The duplicate differential protection scheme does not offer acceptable backup protection for the busbars in the BSP and Distribution. Slow fault clearance times for backup protection could potentially cause damage to the GIS equipment at the BSP or the indoor AIS equipment at the. However this may be possible to rectify pending a review of downstream substation protection with a view to speeding up the backup protection in the BSP and the. This scheme could also only be implemented if the existing CTs on the feeders between the BSP, and Distribution were tested and deemed suitable for differential protection. Pending those two criteria being fulfilled, the duplicate differential scheme would be a simple and robust option. IEC61850 blocked overcurrent scheme Implementation of the IEC61850 blocked overcurrent scheme would not be practical due to the requirement for VTs in the generator transformer bays at the. The cost of installing and commissioning this scheme would also be high due to the quantity of equipment required and the complexity of setting up the scheme. Directional Comparison Overcurrent scheme The Directional Comparison Overcurrent scheme is a viable option for the following reasons: It offers instantaneous and selective backup protection for cable faults. Clearance time for busbar faults is reasonably fast with no risk of the short circuit withstand rating being exceeded on any busbar. In the event of a busbar fault at the BSP, the or the Distribution where primary protection fails, the load and source transformers/generators on the healthy busbars can remain connected. This scheme can be implemented without installing any new instrument transformers. It also uses standard teleprotection equipment which should be relatively straightforward to commission. References [1] Hakala-Ranta, Rintamäki, Starck. Utilizing possibilities of IEC and GOOSE, CIRED 2009, Paper 0741 (2009). [2] D. Tholomier, S. Richards, A. Apostolov, Which one is better Line Differential or Directional Comparison?, DPSP 2008.

Chapter 1. Network Structures

Chapter 1. Network Structures Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Industrial Ethernet How to Keep Your Network Up and Running A Beginner s Guide to Redundancy Standards

Industrial Ethernet How to Keep Your Network Up and Running A Beginner s Guide to Redundancy Standards Redundancy = Protection from Network Failure. Redundancy Standards WP-31-REV0-4708-1/5 Industrial Ethernet How to Keep Your Network Up and Running A Beginner s Guide to Redundancy Standards For a very

More information

Local Back-up Protection for an Electric Power System

Local Back-up Protection for an Electric Power System MULTILIN GER-3178 GE Power Management Local Back-up Protection for an Electric Power System LOCAL BACK UP PROTECTION FOR AN ELECTRIC POWER SYSTEM J. BERDY TABLE OF CONTENTS Transmission Line Back-Up Protection...............................................

More information

Numerical Differential Protection

Numerical Differential Protection Numerical Differential Protection Principles and Applications Publicis Corporate Publishing 1 Introduction 8 1.1 Protection Principle 8 1.2 Numerical Differential Protection 9 2 Deflnitions 10 3 Mode of

More information

ISIO 200. Binary Input/Output (I/O) Terminal with IEC 61850 Interface

ISIO 200. Binary Input/Output (I/O) Terminal with IEC 61850 Interface ISIO 200 Binary Input/Output (I/O) Terminal with IEC 61850 Interface Compact and Easy ISIO 200 Put your Binary I/Os where you need them ISIO 200 is a simple and versatile binary I/O terminal with IEC 61850

More information

Failsafe Protection for Utility Critical Infrastructure

Failsafe Protection for Utility Critical Infrastructure Failsafe Protection for Utility Critical Infrastructure Introduction PUCs maintain a crucial part of the nation s CI that provide essential services to the public, business and government. Reliable CI

More information

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ * Teleprotection Schemes and Equipment James W. Ebrecht Young Power Equipment Scottsdale, AZ Teleprotection Schemes And Equipment ~ ~ Relay Relay Teleprotection Communications channel Teleprotection Protection

More information

Fusible Disconnect Switch

Fusible Disconnect Switch Circuit Breakers Circuit breakers are used in panelboards and switchboards to provide circuit protection and provide a means of energizing and de-energizing a circuit. Siemens Sentron molded case circuit

More information

Transmission Protection Overview

Transmission Protection Overview Transmission Protection Overview 2012 Hands-On Relay School Brian Smyth Schweitzer Engineering Laboratories Pullman, WA Transmission Line Protection Objective General knowledge and familiarity with transmission

More information

ECE 586b Course Project Report. Auto-Reclosing

ECE 586b Course Project Report. Auto-Reclosing ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1

More information

IEC 61850 in ZX Gas-insulated medium voltage switchgear

IEC 61850 in ZX Gas-insulated medium voltage switchgear IEC 61850 in ZX Gas-insulated medium voltage switchgear IEC 61850 in ZX Just as the supply of electrical power is becoming more and more important in a networked world, demands for the integration of electrical

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

Arc Terminator Active Arc-Resistant Switchgear

Arc Terminator Active Arc-Resistant Switchgear Arc Terminator Active Arc-Resistant Switchgear Increasing safety and productivity by extinguishing internal arcing faults within the switchgear. The Square D Arc Terminator from Schneider Electric offers

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

Distribution Automation Handbook. Section 8.13 Backup Protection

Distribution Automation Handbook. Section 8.13 Backup Protection Distribution Automation Handbook Section 8.13 Backup Protection 2 Contents 8.13 Backup Protection... 3 8.13.1 Introduction... 3 8.13.1.1 REQUIREMETS FOR BACKUP PROTECTIO... 3 8.13.1.2 JUSTIFICATIO OF RESERVE

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

Secure your electrical network. PACiS The Safety Solution for Healthcare Institutions

Secure your electrical network. PACiS The Safety Solution for Healthcare Institutions Secure your electrical network The Safety Solution for Healthcare Institutions Fast Secure : the solution for fault isolation and electrical network restoration in less than 500 ms 03 A Real Time System

More information

Eaton s E-Series protective relay family

Eaton s E-Series protective relay family E-Series protective relays Feeder distribution relays Motor relays Transformer relays Generator relays Eaton s E-Series protective relay family Microprocessor-based design Eaton s E-Series relay family

More information

IEC 61850: Communication Networks and Systems in Substations

IEC 61850: Communication Networks and Systems in Substations IEC 61850: Communication Networks and Systems in Substations Sistemi e strumenti per l'automazione, A. Flammini, AA2011-2012 Background I: Power Grid Sistemi e strumenti per l'automazione A. Flammini,

More information

What will MV switchgear look like in the future? by Jean-Marc Biasse

What will MV switchgear look like in the future? by Jean-Marc Biasse What will MV switchgear look like in the future? by Jean-Marc Biasse Table of contents Introduction... 2 Brief history of the technologies used in medium voltage switchgear and control gear... 4 Evolution

More information

Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring

Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring Siemens Integrated Substation Condition Monitoring System Circuit Breaker Monitoring System Description Introduction The Circuit Breaker Monitor [CBM] is only one example of the way that the Substation

More information

Electric utilities may vary in their application of end-to-end testing

Electric utilities may vary in their application of end-to-end testing An Application Case of End-to-End Relay Testing of Communication-Based Protection Schemes Using GPS-Synchronized Secondary Injection Feature by J. Ariza, Megger USA G. Ibarra, CFE, Mexico Electric utilities

More information

How To Choose A Transformer

How To Choose A Transformer Consider open loop MV network as an example source 1 source 2 NC NC NC or NO main MV switchboard A B Detail design of substation NC NC NC NO NC NC switchboard 1 switchboard 2 switchboard 3 MV MV MV LV

More information

The Application of Circuit Breakers to Reduce Downtime in Datacentres

The Application of Circuit Breakers to Reduce Downtime in Datacentres The Application of Circuit Breakers to Reduce Downtime in Datacentres Tim Campbell BEng MIET. Marketing Manager, Terasaki Electric (Europe) Ltd. Abstract Circuit breakers fulfil several functions in the

More information

SIPROTEC Protection Technology

SIPROTEC Protection Technology SIPROTEC Protection Technology The Basis for Highest Availability of Supply Siemens AG 2012. Siemens All rights reserved. AG 2012 Infrastructure and Cities Objectives of this Brochure Objective The following

More information

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Relion Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Fast substation busbar protection with IEC 61850 and GOOSE Falu Elnät AB applies new power

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

Network Structure or Topology

Network Structure or Topology Volume 1, Issue 2, July 2013 International Journal of Advance Research in Computer Science and Management Studies Research Paper Available online at: www.ijarcsms.com Network Structure or Topology Kartik

More information

Electrical Shore Connections / Cold Ironing

Electrical Shore Connections / Cold Ironing STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template

Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template Application Note Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template Author Jens Baumeister jens.baumeister@omicron.at Date

More information

APPLICATION CASE OF THE END-TO-END RELAY TESTING USING GPS-SYNCHRONIZED SECONDARY INJECTION IN COMMUNICATION BASED PROTECTION SCHEMES

APPLICATION CASE OF THE END-TO-END RELAY TESTING USING GPS-SYNCHRONIZED SECONDARY INJECTION IN COMMUNICATION BASED PROTECTION SCHEMES APPLICATION CASE OF THE END-TO-END RELAY TESTING USING GPS-SYNCHRONIZED SECONDARY INJECTION IN COMMUNICATION BASED PROTECTION SCHEMES J. Ariza G. Ibarra Megger, USA CFE, Mexico Abstract This paper reviews

More information

New standardized approach to arc flash protection

New standardized approach to arc flash protection New standardized approach to arc flash protection Samuel Dahl Juha Arvola Tero Virtala Arcteq Relays Ltd Arcteq Relays Ltd Arcteq Relays Ltd Wolffintie 36 F 11 Wolffintie 36 F 11 Wolffintie 36 F11 65200

More information

Increased power protection with parallel UPS configurations

Increased power protection with parallel UPS configurations Increased power protection with parallel UPS configurations Making the selection between Centralized Bypass and Distributed Bypass systems Janne Paananen Application Engineer, Large Systems Group Eaton

More information

Nuclear Power Plant Electrical Power Supply System Requirements

Nuclear Power Plant Electrical Power Supply System Requirements 1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, zeljko.jurkovic@nek.si Abstract Various regulations and standards require from electrical power system of the

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

Power over Ethernet technology for industrial Ethernet networks

Power over Ethernet technology for industrial Ethernet networks Power over Ethernet technology for industrial Ethernet networks Introduction Ethernet networking has grown beyond office and home usage to become a very successful protocol suite used in many industrial

More information

Advanced Protection of Distribution Networks with Distributed Generators

Advanced Protection of Distribution Networks with Distributed Generators Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School

More information

GROUP OF SPANISH ELECTRICITY COMPANIES FOR STUDIES ON IEC 61850

GROUP OF SPANISH ELECTRICITY COMPANIES FOR STUDIES ON IEC 61850 GROUP OF SPANISH ELECTRICITY COMPANIES FOR STUDIES ON IEC 61850 MINIMUM COMMON SPECIFICATION FOR SUBSTATION PROTECTION AND CONTROL EQUIPMENT IN ACCORDANCE WITH THE IEC 61850 STANDARD EDITION MODIFICATION

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 AORC Technical meeting 2014 http : //www.cigre.org C4-1012 Alarm System Improvement in the Northern Region Dispatching Center of Thailand Mr. Manu PONGKAEW, Mr. Phathom TIPSUWAN Electricity Generating

More information

CTS2134 Introduction to Networking. Module 07: Wide Area Networks

CTS2134 Introduction to Networking. Module 07: Wide Area Networks CTS2134 Introduction to Networking Module 07: Wide Area Networks WAN cloud Central Office (CO) Local loop WAN components Demarcation point (demarc) Consumer Premises Equipment (CPE) Channel Service Unit/Data

More information

25 Distribution System Automation

25 Distribution System Automation Chap25 exe 21/06/02 8:30 Page 442 Distribution System Automation Introduction 25.1 Factors influencing the application of automation to distribution networks 25.2 Primary distribution system automation

More information

Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear

Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear Index 3 Overview 4 Standard Levels 6 Monitoring & Control 7 Measurements 8 Protection & Logic

More information

Managing Relion IEDs Protection and control IED manager PCM600

Managing Relion IEDs Protection and control IED manager PCM600 Managing Relion IEDs Protection and control IED manager PCM600 Efficient management of Relion protection and control IEDs The protection and control IED manager PCM600 tool provides versatile functionalities

More information

Market Growth and New Regulations Demand Network Modernization

Market Growth and New Regulations Demand Network Modernization CASE ESB NETWORKS: POLE TOP COMMUNICATION INCREASES EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to

More information

Utility Communications FOXMAN-UN Network Management System for ABB Communication Equipment

Utility Communications FOXMAN-UN Network Management System for ABB Communication Equipment Utility Communications FOXMAN-UN Network Management System for ABB Communication Equipment A reliable & flexible communication network lies at the heart of successful electrical grid operations. A comprehensive

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination

More information

B&B ELECTRONICS WHITE PAPER. Managed Ethernet Switches - Key Features for a Powerful Industrial Network

B&B ELECTRONICS WHITE PAPER. Managed Ethernet Switches - Key Features for a Powerful Industrial Network Determinism is the assurance that control/communication will occur in a set period of time. Ethernet was nondeterministic at first, and not widely used for industrial purposes. Ethernet switches designed

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.2 Number of J-Tubes Filename ONL 15-060-T2_ J tubes_ bays_pp_v2 Version 3 - Public

More information

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks Introduction SCADA (Supervisory Controlled and Data Acquisition) controlled multi-step metalenclosed automatic capacitor

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

Developing an Agent-based Backup Protection System for Transmission Networks

Developing an Agent-based Backup Protection System for Transmission Networks Power Systems and Communications Infrastructures for the Future, Beijing, September 2002 Developing an Agent-based Backup Protection System for Transmission Networks X. R. Wang* Member IEEE, K. M. Hopkinson**

More information

Redundant Serial-to-Ethernet Data Connections for Mission-critical Devices

Redundant Serial-to-Ethernet Data Connections for Mission-critical Devices Redundant Serial-to-Ethernet Data Connections for Mission-critical Devices Daniel Lai, Moxa Product Manager daniel.lai@moxa.com The popularity of serial-to-ethernet technology has increased steadily since

More information

New Supervisory Control and Data Acquisition (SCADA) Based Fault Isolation System for Low Voltage Distribution Systems

New Supervisory Control and Data Acquisition (SCADA) Based Fault Isolation System for Low Voltage Distribution Systems International Conference on Computer and Communication Engineering (ICCCE 2010), 11-13 May 2010, Kuala Lumpur, Malaysia New Supervisory Control and Data Acquisition (SCADA) Based Fault Isolation System

More information

In this section of notes you will learn the rudiments of networking, the components of a network and how to secure a network

In this section of notes you will learn the rudiments of networking, the components of a network and how to secure a network Computer networking In this section of notes you will learn the rudiments of networking, the components of a network and how to secure a network What This Section Will And Will Not Cover What we will talk

More information

A Talari Networks White Paper. Transforming Enterprise WANs with Adaptive Private Networking. A Talari White Paper

A Talari Networks White Paper. Transforming Enterprise WANs with Adaptive Private Networking. A Talari White Paper ATalariNetworksWhitePaper TransformingEnterpriseWANswith AdaptivePrivateNetworking ATalariWhitePaper 2 TransformingEnterpriseWANwithAdaptivePrivateNetworking Introduction IT departments face pressures

More information

An Alternative Approach to Improving SAIDI and SAIFI Indicators

An Alternative Approach to Improving SAIDI and SAIFI Indicators An Alternative Approach to Improving SAIDI and SAIFI Indicators Philippe Deschamps - Schneider Electric Industries - France Jean-Christophe Orsini - Schneider Electric Industries - France Kaare Seest Rasmussen

More information

INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002

INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002 INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002 NEW GAS INSULATED SWITCHGEAR (GIS) FOR ALL MEDIUM VOLTAGE APPLICATIONS H. Fink, ABB Calor Emag Mittelspannungs GmbH; M. Hyrenbach, ABB Calor

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

SIEMENS Transmission and Distribution

SIEMENS Transmission and Distribution TITLE Long Term Maintenance and Care for S36A E. C. Wright 02/09/04 This document is to be used in conjunction with Installation, Operation and Maintenance Schedule IOMS 635. Its aim is to provide guidance

More information

Current transformer selection guide

Current transformer selection guide The selection of a current transformer is a simple task. There are four phases in the selection procedure. Current transformer selection guide KEEP IN MIND efine customer requirements based on the primary

More information

Inverter / Charger Installation General Operations and AC and DC Connections

Inverter / Charger Installation General Operations and AC and DC Connections Inverter / Charger Installation General Operations and AC and DC Connections The Inverter is just one piece. Sometimes, a tendency is to mount the inverter and batteries, and make it work It is better

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY

TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY 2 TRACTION NETWORK MONITORING AND PROTECTION SYSTEM Traction network monitoring and protection system,

More information

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars Presented By: Greg Pelster & Robert Schmid FFI Ferrie, Franzmann Industries LOW VOLTAGE SWITCHGEAR & LOW VOLTAGE

More information

Low Voltage Switchgear

Low Voltage Switchgear Arc Resistant Switchgear n Insulated and isolated bus n Separation barriers and top venting n Breaker shutters 12 SWITCHGEAR Arc resistant metal-enclosed low voltage switchgear is an optional product offering

More information

SAN Conceptual and Design Basics

SAN Conceptual and Design Basics TECHNICAL NOTE VMware Infrastructure 3 SAN Conceptual and Design Basics VMware ESX Server can be used in conjunction with a SAN (storage area network), a specialized high speed network that connects computer

More information

PD Monitor GIS. 24/7 Partial Discharge (PD) monitoring system for Gas Insulated Switchgear. Benefits NEW PRODUCT

PD Monitor GIS. 24/7 Partial Discharge (PD) monitoring system for Gas Insulated Switchgear. Benefits NEW PRODUCT NEW PRODUCT PD Monitor GIS 24/7 Partial Discharge (PD) monitoring system for Gas Insulated Switchgear For automatic, continuous monitoring of mission critical GIS assets Benefits The most cost effective

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

Market Growth and New Regulations Demand Network Modernization

Market Growth and New Regulations Demand Network Modernization CAE EB NETWORK: POLE TOP COMMUNICATION INCREAE EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to meet

More information

INSTRUCTION BOOKLET. AQ SAS Standard Arc Schemes. AQ 100 Series

INSTRUCTION BOOKLET. AQ SAS Standard Arc Schemes. AQ 100 Series INSTRUCTION BOOKLET AQ SAS Standard Arc Schemes AQ 100 Series Instruction booklet Standard arc schemes for AQ 100 series 2 (28) Revision 1.2 Date August 2011 Changes - Add trade mark to SAS. - AQ SAS scheme

More information

ISBN 978-967-5770-63-0

ISBN 978-967-5770-63-0 Assessment of Arc Flash Detection System in Distribution Network Imran bin Hussin College of Engineering, Universiti Tenaga Nasional, Malaysia. Email: imran.hussin@my.abb.com Dr Au Mau Teng College of

More information

No. 1 - The Simple Guide to SIP Trunking. City Lifeline Technology Briefing

No. 1 - The Simple Guide to SIP Trunking. City Lifeline Technology Briefing No. 1 - The Simple Guide to SIP Trunking City Lifeline Technology Briefing We ll be adding these to our website every couple of months or so, to provide you with useful and informative information on a

More information

The evolution of data connectivity

The evolution of data connectivity Leveraging the Benefits of IP and the Cloud in the Security Sector The CCTV and alarm industry has relied on analogue or Integrated Services Digital Network (ISDN) communications to provide data connectivity

More information

Bonded Resilient Broadband Internet Access

Bonded Resilient Broadband Internet Access Bonded Resilient Broadband Internet Access Fast, Reliable Broadband for Businesses with demanding needs If your business relies on broadband to stay operational, wants a better connection speed and better

More information

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories: Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission

More information

The electrical energy produced at the gen

The electrical energy produced at the gen 300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5

More information

Earth Fault Detection Basics in Theory

Earth Fault Detection Basics in Theory Earth Fault Detection Basics in Theory Author: Dipl.-Ing. Ingo Kühnen Woodward Power Solutions Krefelder Weg 47 47906 Kempen, Germany Kempen, 16.04.2010 Earth_Fault_Detection_20100416.doc page 1 1. Star

More information

Technology Solution Guide. Deploying Omnitron PoE Media Converters with Aruba Access Points and AirMesh Routers

Technology Solution Guide. Deploying Omnitron PoE Media Converters with Aruba Access Points and AirMesh Routers Technology Solution Guide Deploying Omnitron PoE Media Converters with Aruba Access Points and AirMesh Routers WARRANTY DISCLAIMER THE FOLLOWING DOCUMENT, AND THE INFORMATION CONTAINED HEREIN IS PROVIDED

More information

CLASS Voltage Regulation Scheme. 27 February 2014

CLASS Voltage Regulation Scheme. 27 February 2014 CLASS Voltage Regulation Scheme 27 February 2014 Functional Specifications and Voltage Regulation Scheme for the Autonomous Substation Controllers (ASCs) Date: 27 February 2014 Page 2 of 26 Table of Contents

More information

Power network telecommunication

Power network telecommunication www.siemens.com Power network telecommunication Teleprotection Answers for infrastructure and cities. Binary I/O The best protection against high-voltage grid failures When it comes to managing power networks,

More information

Reducing the Risk, Cost and Frequency of Production Stoppages Using Network Redundancy

Reducing the Risk, Cost and Frequency of Production Stoppages Using Network Redundancy Introduction Reducing the Risk, Cost and Frequency of Production Stoppages Using Network Redundancy By Mike Miclot, Vice President of Marketing, Industrial Solutions Division at Belden and John Mower,

More information

Advantages of Fixed Circuit Breaker Switchgear

Advantages of Fixed Circuit Breaker Switchgear Advantages of Fixed Circuit Breaker Switchgear by Lionel Mackay, EDF Energy, and Mike Adams, Schneider Electric Ltd Introduction The purpose of this paper is to review the advantages of fixed circuit breaker

More information

PROFIBUS Diagnostics and Network Monitoring Tools

PROFIBUS Diagnostics and Network Monitoring Tools PROFIBUS Diagnostics and Network Monitoring Tools Andy Verwer Verwer Training & Consultancy Ltd Dave Tomlin Hitex (UK) Ltd Outline of Presentation Briefly look at the types of problems that commonly occur

More information

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective India Core Events 2008 September 24 th 2008 1 Background Stability & Reliability Data Storage Communication

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

The ABCs of Spanning Tree Protocol

The ABCs of Spanning Tree Protocol The ABCs of Spanning Tree Protocol INTRODUCTION In an industrial automation application that relies heavily on the health of the Ethernet network that attaches all the controllers and computers together,

More information

PLANNING & IMPLEMENTING VOICE over IP

PLANNING & IMPLEMENTING VOICE over IP PLANNING & IMPLEMENTING VOICE over IP By Harry Forbes Chief Technology Officer Nexans Intelligent Enterprise Solutions White Paper Nexans Cabling Solutions August 2005 Introduction Planning and implementing

More information

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB Reprint from Aluminium World 2009, Volume 2 Emirates Aluminium starts up World s first fully integrated power distribution system from ABB Emirates Aluminium (EMAL), a joint venture between Abu Dhabi s

More information

METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV. tgood.com. Energy. Fast.

METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV. tgood.com. Energy. Fast. METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW Integral substation component

More information

Cahier technique no. 196

Cahier technique no. 196 Collection Technique... Cahier technique no. 196 Integration of local power generation in industrial sites and commercial buildings T. Hazel "Cahiers Techniques" is a collection of documents intended for

More information

Evaluation of L-PRO 4000 for End-to-End Communication Using IEC 61850 Protocol With RFL IMUX 2000 Multiplexer

Evaluation of L-PRO 4000 for End-to-End Communication Using IEC 61850 Protocol With RFL IMUX 2000 Multiplexer Evaluation of L-PRO 4000 for End-to-End Communication Using IEC 61850 Protocol With RFL IMUX 2000 Multiplexer Introduction The ERLPhase L-PRO 4000 Transmission Line Protection Relay provides standard communication-aided

More information

Module 5. Broadcast Communication Networks. Version 2 CSE IIT, Kharagpur

Module 5. Broadcast Communication Networks. Version 2 CSE IIT, Kharagpur Module 5 Broadcast Communication Networks Lesson 1 Network Topology Specific Instructional Objectives At the end of this lesson, the students will be able to: Specify what is meant by network topology

More information

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution Medium Voltage Products ZN1 12 kv arc-proof air-insulated switchgear for primary distribution ZN1 an innovative switchgear for power distribution requirements ABB ZN1 primary distribution switchgear is

More information

Availability and Disaster Recovery: Basic Principles

Availability and Disaster Recovery: Basic Principles Availability and Disaster Recovery: Basic Principles by Chuck Petch, WVS Senior Technical Writer At first glance availability and recovery may seem like opposites. Availability involves designing computer

More information

Line Monitoring and Control in Subsea Networks

Line Monitoring and Control in Subsea Networks Line Monitoring and Control in Subsea Networks This paper discusses how submerged equipment is monitored and contrasts different methods of doing this. It also considers what features are required by the

More information