Evaluation of Compaction Reaming Process and Assessment of Associated Reduced Drilling Fluid Usage During Horizontal Directional Drilling

Size: px
Start display at page:

Download "Evaluation of Compaction Reaming Process and Assessment of Associated Reduced Drilling Fluid Usage During Horizontal Directional Drilling"

Transcription

1 North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T2-01 Evaluation of Compaction Reaming Process and Assessment of Associated Reduced Drilling Fluid Usage During Horizontal Directional Drilling Sarkar Sayem, Trenchless Technology Center, Louisiana Tech University, Ruston, LA Chris Bartlett, Trenchless Technology Center, Louisiana Tech University, Ruston, LA Xuanchen Yan, Trenchless Technology Center, Louisiana Tech University, Ruston, LA Steven Aaron, Trenchless Technology Center, Louisiana Tech University, Ruston, LA Erez Allouche, Trenchless Technology Center, Louisiana Tech University, Ruston, LA Floyd Gunsaulis, Charles Machine Works, Perry, OK ABSTRACT The utilization of adequate amount of drilling fluid is widely recognized as a critical factor in the successful completion of a HDD crossing. At the same time, the overall price tag is influenced by the volume of drilling fluid usage. With contractors under pressure to keep per foot cost as low as possible, the practice of constructing a borehole 1.3 to 1.5 times the diameter of the pipe product of 24 in. or less, should be re-examined. The research work reported in this paper aimed at development and testing a new method that can reduce drilling fluid usage during HDD installations by up to 33%. Five (5) full-scale HDD bores were constructed. Two of the bores followed traditional installation procedures while the remaining three bores utilized a newly developed partial compaction reamer. Data collected during the installations included in-situ soil characteristics, borehole geometry, pulling force, borehole pressure, required thrust and torque, changes in the in-situ soil pressure immediately outside of the bore path, and the characteristics of the drilling fluids and cuttings. The analyzed test data is presented in tabular and graphical formats, and discussed in the context of installation time, risk and cost. A demonstration project in the New Orleans area where this new reaming technology is currently been considered as a means to address the requirements of the USACE is also described. 2. INTRODUCTION Drilling fluid plays an important role in calculating drilling fluid drag effect and skin friction coefficient during directional drilling operation [1]. Drilling fluids also contribute to the overall price tag associated with horizontal directional drilling (HDD) operations. With contractors under pressure to keep per foot cost as low as possible, the practice of constructing a borehole 1.5 times the diameter of NPS24 and lower to ensure an annular void for returning of drilling fluids should be re-examined as the disposal of the cutting returns is becoming increasingly more difficult and costly. This research was aimed at full scale testing of a new cutting head/reamer technology that could reduce drilling fluid use by up to 35%. The construction was initiated with pilot drilling of 4.5 in. borehole with a standard drill bit. The drill bit was advanced through the borehole by rotating and pushing forward assisted by drilling fluid pumped out at a rate of 50 gpm with a drilling fluid pressure capacity up to 1,500 psi. through the nozzle located at the drill bit. The relatively high pressure of flow facilitates the transportation of the cuttings out of the borehole and maintained the borehole Paper TA-T

2 pressure. To ensure the proper drilling fluid mix design, drilling fluids in the mixing tank, and the returns were sampled and tested on a regular basis throughout the installation. The diameter of the pilot hole was then enlarged with a larger diameter reamer, depending on the targeted diameter of the borehole. This step was accomplished in two steps in the new method of compaction reaming process. After attaining the target diameter of the borehole, the product pipe was attached to the drill string and pulled back into the borehole at a constant speed sufficient for the removal of the cuttings out of the borehole. A custom-made load cell developed by Baumert and Allouche (2002) and tested at University of Western Ontario was used to record the pull load and borehole pressure at the location of the pull head [2]. Vibrating earth pressure cells were placed to collect the data of horizontal ground movement due to the compaction process. Data was also collected from the gauge of the rig to cross check the data collected by the load cell. 3. METHODOLOGY This paper presents a full-scale field study which was performed on a newly developed cutting head/reamer technology designed to minimize drilling fluid usage during HDD installation in deformable clay soil (CL) above the ground water level. The objective of the study was to determine the volume of drilling fluid usage, pull force and torque during the product pipe pull back operation, pull load at the product s pull head, borehole pressure at the pull head and ground movements at the immediate vicinity of the bore for each bore. To accomplish the above described research plan, the experimental program outlined in Table 1 was executed. Table 1. Test Matrix (Design of Experiments) Test Series Method Used Fluid Medium 1 2 Using Traditional Reamer 1.30 x pipe diameter Using Partial Compaction Reamer 1.08 x pipe diameter Drilling Fluid 300 Drilling Fluid 300 Drilling Fluid 300 Drilling Fluid 300 Drilling Fluid 300 Length of the Bore Number of Test ft. Total Number of Tests 5 The product pipe was 9 in. DR18 FPVC pipe. Test Series 1 was used to establish the baseline values associated with current construction practices. Test Series 2 was performed using a new method or process of partial compaction. Information about the tentative borehole profile is given in Table 2 and the tentative drilling path in Figure 1. Table 2. Tentative Borehole Information Parameters Value Drilled Length (ft.) 300 Target Depth (ft.) 8 Approach Angle (%) 15 Exit Angle (%) 15 Maximum build angle per 10 ft. rod ( ) Paper TA-T

3 Figure 1. Drill path Data collected consisted of the site layout, soil characterization, borehole profiles, drilling mud formulations, durations of the pilot bore and pull back operations, and the pull force and torque recorded at the drill rig. The axial pull force applied to the product pipe and borehole pressure at the location of the pull head were also recorded using a custom-built load cell. Changes in soil horizontal pressure at the immediate vicinity of the pilot bore were recorded using vibrating-wires earth pressure cells. 4. TEST SERIES 1. (INSTALLATION WITH TRADITIONAL REAMING METHOD) The pilot bore was drilled using a standard 4.5 in. wide plain duckbill bit, while both the pre-ream and the pull-back operations were conducted using a 12 in. diameter paddle reamer (Figure 2). Figure 2. Pilot bore drilling (left) and product pull (right) The drilling plan called for the construction of a stable borehole in the soil formation. During the pilot boring the drilling rod was pushed at a rate of 4-5 minutes per 10 ft. of rod, and the pump s output was kept between 4.8 and 6 gpm (~ 60% efficiency), while the viscosity of the drilling fluid was 50. During the back reaming operation, the product pipe was pulled at a rate of 9-10 minutes per 10 ft. rod. The pump s output was gpm (~ 70% efficiency), while the viscosity of the drilling fluid was 40. The installation cover was determined to be 8 ft. to 9 ft. in order to minimize the risk of frac-out during the installation. A mud pit (9-ft deep) was excavated to provide access needed for removal of the returns and borehole tools (e. g., reamers, pig, and load cell). A backhoe and a mini excavator were used during the pull-back operation to maintain the minimum bending radius allowed by the pipe product manufacturer during the installation (Figure 3). Paper TA-T

4 Figure 3. Drilling plan at the site Based on test results, the drilling fluid formulation and the reaming advancement rates were adjusted for maximum compatibility with local soil conditions. The pulling load and torque measured at the rig were recorded for the pilot bore, pre-ream, and pipe product pull-back operations for each drill rod (i.e., the average thrust and torque values per each 10-ft length of borehole construction or product installation). 5. TEST SERIES 2. (INSTALLATION USING PARTIAL COMPACTION REAMING METHOD) In this method, the 4.5 in. diameter of pilot hole was enlarged in two different steps, pre-reaming and partial compaction reaming. An additional step of Pigging was introduced to ensure the borehole is free of spoils prior to compaction reaming and product pull back. In case of Borehole #3 and Borehole #4, pilot drilling of 4.5 in. borehole was followed by an 8 in. pre-reaming operation. The drill bit was replaced with an 8 in. diameter paddle reamer (6 in. in case of Borehole #5), and the reamer was pulled back to the rig, enlarging the borehole, while at the same time removing the cuttings from the borehole and eliminating some of the profile deviations created during drilling of the pilot bore. Following the pre-reaming operation, a pig or ball device (Figure 4) of same or somewhat smaller diameter of paddle reamer was attached to the drill string and pushed toward the entry point at a speed of 1 minute per rod. The objective of this step was to clean the borehole by displacing or purging the remaining cuttings out of the borehole. Required torque and thrust for this stage were found to be very low even though no drilling fluid was used. Figure 4. Pigging with Pig or Ball device After the pigging device reached the entry pit, it was replaced by the partial compaction reamer. This reamer has two radius; major diameter of 9.75 in., minor diameter of 5 in.(figure 6). When the reamer was pushed through the borehole with controlled thrust and torque, the 8 in. borehole was gradually enlarged to 9.75 in diameter with the Paper TA-T

5 advancement of the reamer. A minimal amount of drilling fluid was supplied through the fluid port located at the reamer face for lubrication during this process. For data collection, a load cell was attached to the compaction reamer using a swivel connection. The pipe product attached to an internal pull head, was then connected to the load cell (i.e., the diameter of the pull-head was equal to the OD of the product pipe) (Figure 6). The use of an internal pull-head ensured lower friction with the borehole wall while maximizing the available annular space. The pull-back process was found to be faster as no additional time was needed to allow the cuttings to flow out of the borehole. Figure 5. Partial Compaction Reamer Figure 6. Partial compaction reaming and product pull assembly A lubrication system was introduced to lubricate the product pipe during compaction reaming and product pull back operation (Figure 7). This system consisted of a perforated pipe which was fed via a 200 L barrel filled with drilling fluid. The gravity driven flow of drilling fluid from the barrel through the perforated pipe supplies the required drilling fluid for pipe lubrication. This system was placed at the entry pit of product pipe to ensure that the pipe entering the borehole is lubricated as there was not enough cuttings flow to lubricate the product pipe at the pullback stage. Paper TA-T

6 Figure 7. Product Pipe lubrication system 6. DATA ANALYSIS The pull-back force and mud pressure, were compared to the horizontal distance travelled (Figure 7), which revealed similar trends suggested that mud-pressure form an internal component in the pull-back force as proposed by Baumert, Allouche and Moore (2004) [2]. Figure 8. Pull back force (lbf) and mud pressure during product pull operation (Load cell measurement at pull head) In this research, the HDD method was used to construct boreholes with diameter equal to either 1.33 (traditional method) or 1.08 (partial compaction method) times the pipe outside diameter. From Figure 8 it can be seen that in the traditional method (Bores #1 and #2), the maximum thrust force ranged between 10,000 and 13,000 lbf, whereas the corresponding range in partial compaction method (Bore #4 and Bore #5) was 8,000 to 10,000 lbf (BH #3 is excluded from consideration due to the presence of a horizontal curve in the bore path). Considering the variability associated with deviations in the path of the borehole (and thus friction force between the pipe product and the borehole wall), the results implies that using the partial compaction method does not increase the required pull load during product installation. Paper TA-T

7 Figure 9. Required thrust (lbf) at rig during product pull operation (rig gauge) Similarly Figure 10 shows that the torque force developed during the traditional installation method (BH #1 and BH #2) was 2.5 to 3.2 times higher than that of partial compaction method (BH #3, BH #4, and BH #5), on average. Increase in compaction level (1.75 in. to 3.75 in.) resulted in 23% increase in torque and similar thrust force recorded during the 1.75 in. compaction. Summarizing on thrust force and torque (Figure 8 & Figure 10), it can be conclude that enlarging the hole by compaction (1.08 times) is as efficient as enlarging it by a factor of Moreover 114% increase in compaction level is attainable by increasing 23% torque without any significant increase in thrust force, given that the soil cover is enough to prevent any frac-out and crack along the borehole alignment. Figure 10. Torque (lb-ft.) during the product pull operation (at rig gauge) Utilizing the compaction reamer, enlarging the hole 1.08 times the pipe OD rather than 1.33, the pulling force at the pull head was comparable to that measured using the traditional method (Figure 11). The reason of comparatively less pulling force to the pull-head can be explained by focusing on the inside borehole condition. During the compaction method, though the borehole was smaller than that of the traditional method, it was comparatively cleaner due to cuttings and spoils removal with the borehole pigging operation. Moreover, the compaction force squeezed the borehole wall toward outside which added the extra advantage of preventing further collapsing of materials from the borehole wall into the bore path. This practice also leaves a smaller void around the installed pipe which will reduce the risk of future surface settlement immediate above the bore path. Paper TA-T

8 Figure 11. Thrust (lbf) at the pull-head during product pull (load cell) The added level of cleanness associated with the partial compaction seems to also result in a similar level of mud pressure during the product pipe pull-back installation. Figure 12 shows that the mud pressure during the compaction reaming method (BH #4) was similar to that recorded during BH #1 and BH #2, and didn t cross the critical pressure for frac-out. Increasing the compaction level from 1.75 to 3.75, resulted in increased downhole drilling fluid pressure (from an average downhole drilling fluid pressure of 21 psi to 37 psi), as well as two fracout occurrence. Though the fluid release happened in the case of BH #5, in both cases the maximum mud pressure never crossed that value of traditional method. So the compaction method in our case enabled a frac-out free HDD installation as long as the compaction level is in within a pre-determined level. According to present case, it can be recommended that any compaction level of greater than 1.2 times but less than 1.6 times the initial borehole diameter may yield a frac-out free installation. Figure 12. Mud pressure (psi.) during product pull Earth pressure cells (EPCs) were deployed to observe any change in the horizontal soil pressure due to the partial compaction reaming process. During the first two bore of compaction (1.75 in. compaction level) the readings recorded by the EPCs is shown in Figure 12. No meaningful change in stress level was recorded due to the approach and passing of the partial compaction reamer across the position of the EPCs. Paper TA-T

9 Figure 13. Earth pressure recorded by EPCs at 24 in. and 30 in. from final bore wall The reading recorded by the EPCs during Borehole #5, when the compaction level was 3.75 in., are shown in Figure 14. The EPC located at 23 in. recorded a spike of 1.7 psi (4.2 psi to 5.9 psi) and the EPC at 29 in. from the borehole wall experienced a spike of 0.9 psi (4.2 psi to 5.1 psi) during the passing of the compaction reamer. This level of increase in horizontal earth pressure is considered to be minor and should not adversely affect existing utilities within 30 in. of the newly installed pipe. Figure 14. Earth pressure recorded for 3.75 in. compaction level Figure 15 presents the volume of drilling fluids that were utilized during the pre-ream and pull-back phases for each of the five boreholes. It can be seen that the utilization of the compaction reamer resulted in approximately 32% reduction in the volume of drilling fluid used. The increase in compaction level from 1.75 in. to 3.75 in was expected to further reduce the usage of drilling fluid (total reduction ~40%),) according to the calculation based on Baroid Technology Inc. formula. But the adverse ground condition along the bore path #5, (a buried iron pipe and other artifacts from previous research projects) required an amount of drilling fluid greater than anticipated to clean the bore during the pre-reaming stage. Paper TA-T

10 Figure 15. Comparison of drilling fluid usage (gals) (excluding the pilot bore operation) In terms of productivity, deployment of the partial compaction method somewhat increased the total installation time due to the additional activities (pre-ream and pigging operations) (Figure 16). These activities were found to represent an average increase of minutes per linear foot of borehole length (87 minutes, 116 minutes, and 91 minutes for Bores #3, #4, and #5, respectively), which can be considered acceptable in view of the benefits associated with this installation procedure 7. CONCLUSION Figure 16. Comparison of time (minutes) duration (based on real installation time) An analysis of small non engineered commercial horizontal directional drilling (HDD) installations was presented by Baumert et al.2003, where an important observation made was that a clean borehole was not achieved in the majority of these installations [3]. In partial compaction reaming method, the additional stage of pigging which pushes out the solid cuttings settled at the bottom of the borehole, ensures a clean annular space before compaction and product pull stage. The advancement of the compaction reamer left the borehole with a thin layer of drilling fluid (from drilling fluid used in lubrication of reamer) on the walls of the bore. These two steps will help the contractors to attain clean borehole conditions. From this point of view, the compaction method will allow the contractor to predict the pulling force more accurately which is important for proper rig sizing which in turn saves cost in mobilizing and operation of the machine (Baik et al. 2003) [4]. Paper TA-T

11 This study evaluated the performance of the compaction reamer only for two different compaction levels (1.75 in. and 3.75 in). Based on these two cases, it can be concluded that the thrust and torque, downhole mud pressure, and horizontal stresses near the borehole wall is closely depended on the compaction level and the initial borehole diameter to be enlarged. Future study could be performed, for further understanding of the behavior of this partial compaction reamer, with boreholes of larger diameter, and different compaction levels of 1in., 2 in, and 3 in. 8. REFERENCES [1] Michael E. Baumert, Erez N. Allouche, and Ian D. Moore. (2005), Drilling fluid considerations in design of engineered horizontal directional drilling installations. International Journal of Geomechanics, December 1, 2005, Vol. 5, No.4. [2] Michael E Baumert, Erez N Allouche, Ian D. Moore.(2004), Experimental Investigation of Pull Loads and Borehole Pressures during Horizontal Directional Drilling Installations. Canadian Geotechnical Journal, 2004, 41(4): , /t [3] Baumert, M. E., and Allouche, E. N. (2002). Methods for estimating pipe pullback loads for horizontal directional drilling (HDD) crossings. J. Infrastruct. Syst., 8(1), [4] Baik, H., Dulcy, M. A., and Gokhale, S. (2003), A decision support system for horizontal directional drilling. Tunn, Undergr. Space Technol., 18(1), Paper TA-T

Drilling Problems. pull

Drilling Problems. pull Drilling Problems Pipe Sticking Lost Circulation Hole Deviation Pipe Failures Borehole Instability Mud Contamination Formation Damage Hole Cleaning H S General Equipment & Personnel Pipe Sticking Can not

More information

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering. ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical

More information

DIRECTIONAL DRILLING

DIRECTIONAL DRILLING DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation

More information

Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures

Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 TM1-T2-04 Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures

More information

DIRECTIONAL DRILLING BEST PRACTICES. Planning & Construction Considerations COMMITMENT & INTEGRITY DRIVE RESULTS

DIRECTIONAL DRILLING BEST PRACTICES. Planning & Construction Considerations COMMITMENT & INTEGRITY DRIVE RESULTS DIRECTIONAL DRILLING BEST PRACTICES Planning & Construction Considerations Today s presenters will be: Dennis M. Walsh, PE Sr. Project Manager Woodard & Curran Daniel D Eletto, PE Manager, Project Engineering

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

New advances in planning a bore Software helps take out the guesswork

New advances in planning a bore Software helps take out the guesswork New advances in planning a bore Software helps take out the guesswork Written By: Greg Ehm, Technical Writer Two Rivers Marketing, Des Moines, Iowa Provided By: Vermeer Corporation Pella, Iowa Horizontal

More information

DETERMINATION OF SAFE PULLING LOADS ON FUSIBLE PVC PIPE DURING HORIZONTAL DIRECTIONAL DRILLING INSTALLATIONS

DETERMINATION OF SAFE PULLING LOADS ON FUSIBLE PVC PIPE DURING HORIZONTAL DIRECTIONAL DRILLING INSTALLATIONS North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 DETERMINATION OF SAFE PULLING LOADS ON FUSIBLE PVC PIPE DURING HORIZONTAL DIRECTIONAL

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

More information

WELL COMMANDER Versatile multi-cycle ball-activated drilling valve for mitigating downhole hazards

WELL COMMANDER Versatile multi-cycle ball-activated drilling valve for mitigating downhole hazards WELL COMMANDER Versatile multi-cycle ball-activated drilling valve for mitigating downhole hazards Note: Operating instructions updated July 2014 WELL COMMANDER: Versatile multicycle ball-activated drilling

More information

WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW

WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-02 WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW Mark Oberschmidt, P.E., Stantec,

More information

DecisionSpace Well Engineering Software

DecisionSpace Well Engineering Software DATA SHEET DecisionSpace Well Engineering Software DecisionSpace Drilling & Completions Key features Configure the right tools to drill any type of well Dramatically simple to use, complete complex fluids

More information

Positive Displacement Motors (PDM)

Positive Displacement Motors (PDM) Positive Displacement Motors (PDM) 2 www.micon-drilling.de phone +49.5144.493671 MICON Downhole-Tools GmbH Breite Horst 19 29336 Nienhagen Germany Tel. +49.5144.493671 Fax +49.5144.493677 service@micon-drilling.de

More information

Trenchless Methods for Service and Mainline Pipe Rehab and New Install

Trenchless Methods for Service and Mainline Pipe Rehab and New Install Trenchless Methods for Service and Mainline Pipe Rehab and New Install Eddie Ward TT Technologies, Inc. Tennessee Gas Association Distribution & Operations Conference April 9 th 11 th Murfreesboro, TN

More information

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES SECOND EDITION PIPEJACKING AND MICROTUNNELING NEW VERSION AUGUST 2005 1 OVERVIEW Pipe jacking and microtunnelling, including pilot

More information

CONTINGENCY PLANNING for HIGH-RISK HDD CONSTRUCTION

CONTINGENCY PLANNING for HIGH-RISK HDD CONSTRUCTION North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper F-1-05 CONTINGENCY PLANNING for HIGH-RISK HDD CONSTRUCTION David J. Tanzi, P.E., BCEE

More information

Geometry and dimensional tolerances of engine bearings

Geometry and dimensional tolerances of engine bearings Geometry and dimensional tolerances of engine bearings Dr. Dmitri Kopeliovich (Research & Development Manager.) 1. Hydrodynamic lubrication Engine bearings operate mostly in the hydrodynamic regime of

More information

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,

More information

GUIDELINE FOR HAND HELD SHEAR VANE TEST

GUIDELINE FOR HAND HELD SHEAR VANE TEST GUIDELINE FOR HAND HELD SHEAR VANE TEST NZ GEOTECHNICAL SOCIETY INC August 2001 CONTENTS Page 1.0 Introduction 2 2.0 Background 2 3.0 Recommended Practice 3 4.0 Undrained Shear Strength 3 5.0 Particular

More information

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598 Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

KWANG SING ENGINEERING PTE LTD

KWANG SING ENGINEERING PTE LTD KWANG SING ENGINEERING PTE LTD 1. INTRODUCTION This report represents the soil investigation works at Aljunied Road / Geylang East Central. The objective of the soil investigation is to obtain soil parameters

More information

SECTION 33 05 23.13 HORIZONTAL DIRECTIONAL DRILLING (HDD)

SECTION 33 05 23.13 HORIZONTAL DIRECTIONAL DRILLING (HDD) SECTION 33 05 23.13 HORIZONTAL DIRECTIONAL DRILLING (HDD) PART 1: GENERAL 1.01 SCOPE A. Furnish all labor, materials, tools and equipment as necessary to construct a pipeline crossing by the horizontal

More information

Plug and Abandonment Forum

Plug and Abandonment Forum Plug and Abandonment Forum Developments in Non-Traditional Plug and Abandonment Methods Thomas Ferg ConocoPhillips Norway June 13, 2013 Efficient P&A Thoughts - Do as Much as Possible Without a Rig Remove

More information

E-Line and Braided Line. E-Line Open Hole wireline

E-Line and Braided Line. E-Line Open Hole wireline E-Line and Braided Line E-Line Open Hole wireline Braided Line More strength Less feel Harder to seal Much harder to fish Braided line stronger (2800 to 3500 lb working strength, but less feel when fishing

More information

Morgan County Quality Water District Water Main Flood Damage Repair Project

Morgan County Quality Water District Water Main Flood Damage Repair Project North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show TM1-T5-02 Morgan County Quality Water District Water Main Flood Damage Repair Project Nathan Ferguson, Farnsworth Group,

More information

TruTrak Automated directional drilling system

TruTrak Automated directional drilling system D r i l l i n g a n d E v a l u a t i o n TruTrak Automated directional drilling system Answering the need for improved drilling precision and efficiency Simple wells are not so simple anymore While 2D

More information

Module 9: Basics of Pumps and Hydraulics Instructor Guide

Module 9: Basics of Pumps and Hydraulics Instructor Guide Module 9: Basics of Pumps and Hydraulics Instructor Guide Activities for Unit 1 Basic Hydraulics Activity 1.1: Convert 45 psi to feet of head. 45 psis x 1 ft. = 103.8 ft 0.433 psi Activity 1.2: Determine

More information

Applying a circular load. Immediate and consolidation settlement. Deformed contours. Query points and query lines. Graph query.

Applying a circular load. Immediate and consolidation settlement. Deformed contours. Query points and query lines. Graph query. Quick Start Tutorial 1-1 Quick Start Tutorial This quick start tutorial will cover some of the basic features of Settle3D. A circular load is applied to a single soil layer and settlements are examined.

More information

Carlon Bore-Gard and Boreable Multi-Gard Raceway

Carlon Bore-Gard and Boreable Multi-Gard Raceway Carlon Bore-Gard and Boreable Multi-Gard Raceway Bore-Gard Schedule 40 Bore-Gard Schedule 80 Boreable Multi-Gard Type 40 www.carlonsales.com 231 Bore-Gard Trenchless Raceway Carlon Bore-Gard Trenchless

More information

Optimizing Tank Cleaning Operations

Optimizing Tank Cleaning Operations Optimizing Tank Cleaning Operations Choosing the best way to thoroughly clean your tanks while minimizing use of costly chemicals, water and manual labor can be challenging. There are several things you

More information

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for: HANDOUT REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition RETAINING WALLS Fifth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering

More information

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting? Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

Guidelines for Pipe Bursting

Guidelines for Pipe Bursting Guidelines for Pipe Bursting TTC Technical Report #2001.02 Jadranka Simicevic Raymond L. Sterling Prepared for: U.S. Army Corps of Engineers Engineering Research and Development Center (ERDC) 3909 Halls

More information

AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy

AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy The City of Kitchener, Ontario, Canada, was in a dilemma. After repeated breakdowns

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362 California Department of Transportation Doyle Drive Test Program Deep Soil Mixing (DSM) /Cutter Soil Mixing (CSM) Testing Report By Malcolm Drilling Company, Inc. 3524 Breakwater Ave., Suite 108 Hayward,

More information

Program COLANY Stone Columns Settlement Analysis. User Manual

Program COLANY Stone Columns Settlement Analysis. User Manual User Manual 1 CONTENTS SYNOPSIS 3 1. INTRODUCTION 4 2. PROBLEM DEFINITION 4 2.1 Material Properties 2.2 Dimensions 2.3 Units 6 7 7 3. EXAMPLE PROBLEM 8 3.1 Description 3.2 Hand Calculation 8 8 4. COLANY

More information

Pump Ratio and Performance Charts

Pump Ratio and Performance Charts Pump Ratio and Performance Charts Concept and Theory Training Table of Contents Introduction... 1 Overview... 1 How to use this Module... 2 Learning Objectives...2 Text...2 Charts, Illustrations...2 Progress

More information

Sewer systems: Failures and rehabilitation

Sewer systems: Failures and rehabilitation Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Unit 24: Applications of Pneumatics and Hydraulics

Unit 24: Applications of Pneumatics and Hydraulics Unit 24: Applications of Pneumatics and Hydraulics Unit code: J/601/1496 QCF level: 4 Credit value: 15 OUTCOME 2 TUTORIAL 2 HYDRAULIC AND PNEUMATIC CYLINDERS The material needed for outcome 2 is very extensive

More information

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES WATER & SEWER REHAB TECHNOLOGIES NORTH VANCOUVER PIPE BURST REQUIRES CAREFUL PLANNING Close proximity to storage silos, poor ground conditions and clogged storm sewer pipe puts trenchless contractor to

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines: Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections

More information

Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City Wide Program

Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City Wide Program North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T3-05 Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

Dewatering - Time and Cost Relief by way of Trenchless Construction

Dewatering - Time and Cost Relief by way of Trenchless Construction North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,

More information

Flowtite Jacking Pipe

Flowtite Jacking Pipe U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe

More information

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Nature of Services The company has a long history of performance of tests of piles and pile groups under a variety

More information

Sanitary Sewer Design, Installation and Inspection in Small Rural Community

Sanitary Sewer Design, Installation and Inspection in Small Rural Community Sanitary Sewer Design, Installation and Inspection in Small Rural Community Submitted by: First name, Last name OACETT Membership #: 000000 Submitted to: OACETT 10 Four Seasons Place, Suite 404 Toronto,

More information

Composite Drill Pipe Perfect Fit for Short-Radius Drilling

Composite Drill Pipe Perfect Fit for Short-Radius Drilling American Oil & Gas Reporter Article Composite Drill Pipe Perfect Fit for Short-Radius Drilling With much of the nation's "easy-to-produce" oil and gas gone, many U.S. companies are looking for lower cost

More information

2005 WJTA American Waterjet Conference August 21-23, 2005 Houston, Texas Paper SAFE WATERJET CLEANING OF STEEL PROCESS LINES

2005 WJTA American Waterjet Conference August 21-23, 2005 Houston, Texas Paper SAFE WATERJET CLEANING OF STEEL PROCESS LINES 25 WJTA American Waterjet Conference August 21-23, 25 Houston, Texas Paper SAFE WATERJET CLEANING OF STEEL PROCESS LINES D. Wright, J. Wolgamott, G. Zink StoneAge, Inc. Durango, Colorado, U.S.A. ABSTRACT

More information

Mercury is poured into a U-tube as in Figure (14.18a). The left arm of the tube has crosssectional

Mercury is poured into a U-tube as in Figure (14.18a). The left arm of the tube has crosssectional Chapter 14 Fluid Mechanics. Solutions of Selected Problems 14.1 Problem 14.18 (In the text book) Mercury is poured into a U-tube as in Figure (14.18a). The left arm of the tube has crosssectional area

More information

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,

More information

Guidelines for Earthquake Bracing Residential Water Heaters

Guidelines for Earthquake Bracing Residential Water Heaters Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the

More information

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels Estimation of Adjacent Building During Drilling of Urban Tunnels Shahram Pourakbar 1, Mohammad Azadi 2, Bujang B. K. Huat 1, Afshin Asadi 1 1 Department of Civil Engineering, University Putra Malaysia

More information

Guidelines for Earthquake Bracing of Residential Water Heaters

Guidelines for Earthquake Bracing of Residential Water Heaters Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)

More information

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2 Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2 W.F. Bawden, Chair Lassonde Mineral Engineering Program, U. of Toronto, Canada J.D. Tod, Senior Engineer, Mine Design

More information

Design Considerations for Water-Bottle Rockets. The next few pages are provided to help in the design of your water-bottle rocket.

Design Considerations for Water-Bottle Rockets. The next few pages are provided to help in the design of your water-bottle rocket. Acceleration= Force OVER Mass Design Considerations for Water-Bottle Rockets The next few pages are provided to help in the design of your water-bottle rocket. Newton s First Law: Objects at rest will

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Pneumatic Pipe Bursting

Pneumatic Pipe Bursting A Guide to Pneumatic Pipe Bursting with the GRUNDOCRACK SYSTEM Table of Contents 1) Foreword...4 2) Company Background...5 3) Pipe Bursting History...6 4) GRUNDOCRACK Concept...7 5) Project Considerations...

More information

PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.

PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method. PERMEABILITY TEST A. CONSTANT HEAD OBJECTIVE To determine the coefficient of permeability of a soil using constant head method. need and Scope The knowledge of this property is much useful in solving problems

More information

Rotary Vertical Drilling System (RVDS)

Rotary Vertical Drilling System (RVDS) 1 Rotary Vertical Drilling System (RVDS) 2 www.micon-drilling.de phone +49.5144.4936.0 Contents Company Profile... 03 MICON Rotary Vertical Drilling System (RVDS)... 04/05 RVDS 7.3/4...06/07 RVDS 10...08/09

More information

COMPARISON OF DRILLING TECHNOLOGIES BETWEEN TOP DRIVE AND ROTARY TABLE IN GEOTHERMAL FIELDS: A CASE STUDY OF OLKARIA GEOTHERMAL FIELDS.

COMPARISON OF DRILLING TECHNOLOGIES BETWEEN TOP DRIVE AND ROTARY TABLE IN GEOTHERMAL FIELDS: A CASE STUDY OF OLKARIA GEOTHERMAL FIELDS. Proceedings 5 th African Rift geothermal Conference Arusha, Tanzania, 29-31 October 2014 COMPARISON OF DRILLING TECHNOLOGIES BETWEEN TOP DRIVE AND ROTARY TABLE IN GEOTHERMAL FIELDS: A CASE STUDY OF OLKARIA

More information

DITCH WITCH MT12 MICROTRENCHER. ditchwitch.com

DITCH WITCH MT12 MICROTRENCHER. ditchwitch.com DITCH WITCH MT12 MICROTRENCHER ditchwitch.com Rule With An Iron Fist. ditchwitch.com DITCH WITCH MT12 MicroTrencher Throughout the world, demand is increasing for faster broadband communications, necessitating

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Identification of Practices, Design, Construction, and Repair Using Trenchless Technology Final Report October 2010

Identification of Practices, Design, Construction, and Repair Using Trenchless Technology Final Report October 2010 Identification of Practices, Design, Construction, and Repair Using Trenchless Technology Final Report October 2010 Sponsored by Iowa Highway Research Board (IHRB Project TR-570) Iowa Department of Transportation

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation Design Manual Chapter 14 - Trenchless Construction Table of Contents TOC Table of Contents Chapter 14 - Trenchless Construction 14A General Information 14A-1---------------------------------General Information

More information

Properly maintaining your septic system will help reduce the. It s Your Septic System. Homeowner s Guide. Here s How to Take Care of It

Properly maintaining your septic system will help reduce the. It s Your Septic System. Homeowner s Guide. Here s How to Take Care of It Homeowner s Guide for Maintenance and Care of On-Site Sewage Systems It s Your Septic System Here s How to Take Care of It Properly maintaining your septic system will help reduce the possibility of health

More information

Certificate Programs in. Program Requirements

Certificate Programs in. Program Requirements IHRDC Online Certificate Programs in OIL AND GAS MANAGEMENT Program Requirements IHRDC 535 Boylston Street Boston, MA 02116 Tel: 1-617-536-0202 Email: certificate@ihrdc.com Copyright International Human

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2 Introduction Canadian Oilwell Systems Company and it s subsidiaries are suppliers of oil well Electric Submersible Pumping systems (ESPs). Such pumps are used to lift oil from oil wells so that the oil

More information

Control ball valves for severe services. Author: Michele Ferrante, PARCOL S.p.A., Italy

Control ball valves for severe services. Author: Michele Ferrante, PARCOL S.p.A., Italy Control ball valves for severe services Author: Michele Ferrante, PARCOL S.p.A., Italy Control valves are primarily classified according to the type of their obturator motion which can be linear or rotary.

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

Lab 8: Ballistic Pendulum

Lab 8: Ballistic Pendulum Lab 8: Ballistic Pendulum Equipment: Ballistic pendulum apparatus, 2 meter ruler, 30 cm ruler, blank paper, carbon paper, masking tape, scale. Caution In this experiment a steel ball is projected horizontally

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

Drill String Design. The following topics will be discussed

Drill String Design. The following topics will be discussed Drill String Design The following topics will be discussed Kelly Drill pipe Drill collars Accessories; heavy wall drill pipe, jars, stabilizers, reamers, shock sub and bit sub Drill bits 1 Kelly Used to

More information

EXCAVATOR SAFETY TRAINING

EXCAVATOR SAFETY TRAINING EXCAVATOR SAFETY TRAINING INSPECTION CHECKLIST INSPECTION AREA INSPECTION RESULTS Sat. Unsat. N/A Comments Carrier & Car Body Rotation system Tracks Rollers Frame, welds, bolts Drive system Upper Structure

More information

Pipe Bursting. Chapter 16

Pipe Bursting. Chapter 16 535 Introduction Underground service utilities in many American cities have been in place for over 100 years. While existing systems have functioned well beyond reasonably anticipated service life, underground

More information

2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET

2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET 2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET D. Wright StoneAge, Inc. Durango, Colorado, U.S.A. ABSTRACT The removal of refractory

More information

Ductile-Iron Pipe and Fittings

Ductile-Iron Pipe and Fittings Ductile-Iron Pipe and Fittings AWWA MANUAL M41 Third Edition Manual of Water Supply Practices M41, Third Edition Ductile-Iron Pipe and Fittings Copyright 1996, 2003, 2009, American Water Works Association

More information

AKRON EDUCTORS TROUBLESHOOTING GUIDE OPERATION & THEORY OF EDUCTORS GENERAL OPERATING AND MAINTENANCE INSTRUCTIONS

AKRON EDUCTORS TROUBLESHOOTING GUIDE OPERATION & THEORY OF EDUCTORS GENERAL OPERATING AND MAINTENANCE INSTRUCTIONS AKRON EDUCTORS TROUBLESHOOTING GUIDE OPERATION & THEORY OF EDUCTORS GENERAL OPERATING AND MAINTENANCE INSTRUCTIONS Products Include: 60 gpm eductors Style 3060, 3061, 3062 & 3070 95 gpm eductors Style

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

SETTLEMENT INSTRUMENTATION & MONITORING

SETTLEMENT INSTRUMENTATION & MONITORING SECTION 02445 SETTLEMENT INSTRUMENTATION & MONITORING PART 1 - GENERAL 1.01 SUMMARY A. The Work specified in this Section includes furnishing, installing, and monitoring settlement instrumentation to monitor

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Owen Equipment and Keg Technologies. Welcome you to Nozzle Technology

Owen Equipment and Keg Technologies. Welcome you to Nozzle Technology Owen Equipment and Keg Technologies Welcome you to Nozzle Technology Sewer Cleaning 101 Water Systems, and Nozzle Selection Presented by Ken Billingham International Product Specialist KEG GMBH Basics

More information

Standard Test Method for Mechanical Cone Penetration Tests of Soil 1

Standard Test Method for Mechanical Cone Penetration Tests of Soil 1 Designation: D 3441 98 AMERICAN SOCIETY FOR TESTING AND MATERIALS 100 Barr Harbor Dr., West Conshohocken, PA 19428 Reprinted from the Annual Book of ASTM Standards. Copyright ASTM Standard Test Method

More information

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the

More information

Letty Arvide-Gomar, PE

Letty Arvide-Gomar, PE Letty Arvide-Gomar, PE Outline DIP History and Applications Corrosion Issues Internal Cleaning Technologies Rehabilitation Options DIP History and Applications Corrosion Issues Internal Cleaning Technologies

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

Technical Data. 7. Bearing Fits. 7.1 Interference. 7.2 Calculation of interference F B LLLLLLLLL( A-54

Technical Data. 7. Bearing Fits. 7.1 Interference. 7.2 Calculation of interference F B LLLLLLLLL( A-54 Technical Data 7. Bearing Fits 7.1 Interference For rolling s the rings are fixed on the or in the housing so that slip or movement does not occur between the mated surface during operation or under. This

More information

vulcanhammer.net This document downloaded from

vulcanhammer.net This document downloaded from This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works

More information