Public Parties - Phase 2a Signage and Trade Contracts

Size: px
Start display at page:

Download "Public Parties - Phase 2a Signage and Trade Contracts"

Transcription

1 Monthly Progress Report for April 2011

2 Table of Contents Section 1: Executive Summary Section 2: Schedule Section 3: Development Manager s Report Section 4: Budget Section 5: Economic Inclusion Section 6: Construction Manager s Report Section 7: Cincinnati Riverfront Park Report Section 8: Communications Appendices o o o o o o A Project Scope & Description B Designer s Report C Budget Detail D Economic Inclusion Detail E Glossary of Acronyms F Distribution List Page 1

3 Monthly Progress Report for March 2011 Section 1: Executive Summary

4 Section 1: Executive Summary As the saying goes, April Showers Bring May Flowers, but to The Banks Project, April meant rain and rising Ohio River levels that challenged construction crews. Whether it was intermittent showers or thunderous cloudbursts, the downpours of the month did little to dampen the commitment nor stall the progress achieved by The Banks team. All the Public Parties Phase 1 work is completed (with Bid Package #10 signage remaining to be installed in the Phase 2a parking facility). Phase 2a construction work continued on schedule. Despite weather affecting certain work on Phase 2a work (Mehring Way relocation, Bid Package #9 and Block 2 Garage, Bid Package 11), contract completion is still expected to hit all target milestones for the parking counts required by the sports teams leases and the opening in October, weather permitting, of Freedom Way and the new garage segment west of the National Underground Railroad Freedom Center. Both construction phases of Public Parties work are within approved budgets and on target to meet SBE, DBE and safety goals. Federal Highway Administration and Ohio Department of Transportation inspection and audit took place in April. Inspection and audit included all construction work in place as well as the Project files. There were no negative comments on the construction. There was one minor comment on the Construction Manager s change order records for one contract; correction will not change totals, just improve documentation. Bid Package #12 for Street Grid and Pedestrian Network Improvements will now be bid in two parts. A draft of the first Local Public Agency Agreement is expected soon. Turn to Appendix A: Project Scope Description for a complete listing of the locations of the work under both parts of the scope. This Monthly Report cover photo (top left) captures a close-up of the April 1 concrete pour of the last section of Freedom Way. The top right photo shows the pour nearly completed. The main photo is a view of Lot 2 Garage construction, which continued on schedule despite one of the wettest months on record. Developer April welcomed the first residents into Current@TheBanks, as tenants moved into the north building. Installation of landscaping in the amenity terrace continued, as did work to complete building skin and finishes. On Block 16, the south building, work on the building skin was substantially complete, with Brasfield & Gorrie installing exterior components and building finishes at all levels. Block 16 is on schedule Page 1

5 for May 15, 2011 completion. Construction on the Police Welcome Center continued, and plans for Toby Keith and Johnny Rockets have been submitted for permit review. Parks Progress continued on The Cincinnati Riverfront Park project. Workers from Monarch Construction continued to construct form work and steel installation for the Grand Stair, and framing for the Bicycle Center storefront and doors. Megen Construction began creating planters and the large Schmidlapp Event Lawn on the roof of the south end of the Phase 1 Garage by waterproofing the roof, setting large granite capstones and seat walls, and then filling the large recesses in the garage roof with sand, gravel and soil in preparation for the landscape planting and sod installation planned for May. The Moerlein Lager House contractor, Schumacher-Dugan Construction, completed elevator shaft construction, continued structural block work, began utility installation, and prepared to begin exterior shell construction in May. Safety A total of 1,670 trade workers have attended safety orientations. The Project logged 356,939 hours without a lost-time accident. Economic Inclusion As of March 25, 2011, Small Business Enterprise (SBE) construction participation is 36.1% (goal 30%). Minority Business Enterprise (MBE) participation totaled 16.1% and Women Business Enterprise (WBE) is 2.8%. Combined minority and female workforce participation was 17.95%. Of the production workers active on the Project, 77.4% resided in the Cincinnati- Middletown MSA. Budget Construction expenditure projections are within approved target budgets for both Phase 1 and for Phase 2a. Combined approved and potential change orders for both phases equal 5.28% of total approved contract amounts. Schedule Phase 2a construction remains on schedule. All parties continue to coordinate project construction schedule successfully. See Section 3: Development Manager s Review for the Master Project Schedule. See Section 6: Construction Manager s Report for the Phase 2a Schedule. Page 2

6 Section 2: Schedule

7 Section 2: Schedule In the month of April, Phase 2a infrastructure work by the Public Parties proceeded on schedule. Opening of Freedom Way (East to West) is scheduled for October, with the East portion planned official opening slated for June. Opening of the Lot 2 Garage is still projected for late fall, despite heavy rains during the month. See Section 6: Construction Manager s Report for details and a schedule. Work on the overbuild by the Private Developer continues on schedule, with a ribboncutting mid-month to welcome first residents to their apartment in Current@The Banks. Work continues on designs, permitting and construction for dining and entertainment tenants. See Section 3: Development Manager s Report and Master Project Schedule for details. Cincinnati Riverfront Park construction made noticeable progress and remained on schedule, as the Walnut Street Fountain and Grand Stair as well as the Event Lawn became recognizable to the casual passer-by. See Section 7: Cincinnati Riverfront Park Report. Page 1

8 Section 3: Development Manager s Review

9 Section 3: Development Manager s Review Master Schedule: Included at the end of this Section. Progress Update on Public Parties work Phase 1 All Phase 1 work has been completed with the exception of the Bid Package #10 signage being installed in the Phase 2 parking facility. A final certificate of occupancy will replace the current temporary certificate of occpancy once the elevator installation at the Freedom Way East head house is completed. Messer is working with the trade contractor to schedule final inspections for the elevator and it is hoped that a final certificate of occupancy document will be in hand before the end of May. As documented in last month s report, the team is working toward resolution on several deficient work items. An agreement on the approach to rework the expansion joint blockout conditions has been reached with the Private Developer. Freedom Way West has recently exhibited more issues with silica fume pop-outs. The City is reviewing this issue with Baker and the concrete supplier to determine the appropriate next steps. Phase 2 The Phase 2 work of the Parking Facility continues to progress according to the schedule. Prus has completed the Mehring Way realignment and pedestrian accessibility for Lots D and F. They also completed the street paving scope for the Joe Nuxhall Way. With these efforts finalized, Prus work is now confined to the removal of Theodore M. Berry Way. Since the closure of Theodore M. Berry Way in January, Prus has removed the existing utilities and pavement at the roadway and has installed the piles to support the soil tieback wall where the existing roadway intersects Rosa Parks Street. Excavation activities have been underway for approximately two months. Prus began hauling material off-site in mid-march. The majority of the haul-off will be taken to the Parks site. Record-breaking rain in April has limited this work over the past month; however, the team is looking toward a drier month of May to increase the Page 1

10 progress of removal. In the interim, Messer worked with Prus to determine alternate access options, allowing for the excavation and haul-off to be expedited once production resumes. Originally the haul-off was anticipated to run through the end of May; the team is now targeting haul-off completion in June. The team was able to resolve the soil tieback wall issue at Theodore M. Berry Way and Rosa Parks Street associated with the tieback sizes. However, as work has started, the quality of the soil and existing obstructions have raised constructability issues as well as a new potential cost exposure. The design team is working to finalize direction on the modifications to the work. The trade contractor has submitted a claim in the last several days, and the team is working to determine validity of the request. Although Baker s work has slowed somewhat with the recent weather conditions, progress is still being made. Pile cap work is nearing completion, as are the first column lift pours. This in turn will allow the slab on grade work to be completed. Several elevated pours were made at the 500 level during the month, as were the podium pours along Second Street. The electrical and plumbing rough-ins are closely following the structure work on the facility, and the fire protection contractor mobilized in recent weeks. The mason will be beginning on site within the next two weeks. Waterproofing work on Freedom Way West will begin as the weather permits. Baker completed all of the work the Second Street sidewalk replacement west of Rosa Parks Street. They also completed the curb cut at the deck entrance on Block 26, as well as repairs to the sidewalk at the northeast corner of the block to accommodate an existing condition grade differential. All of this work proceeded with few to no issues. The Freedom Way head houses are substantially complete. Baker is working to finish all miscellaneous caulking and punchlist work. Installation of the elevator is nearly complete, with final adjustment work ongoing. The team anticipates being able to receive a final inspection on the elevator soon which in turn allows the head house to be fully operational. The stair head house has been open to the public for approximately three weeks. Safety continues to be a tremendous success. The Project continues to accrue manhours worked without a lost time accident beyond the 350,000-hour threshold. This continues to speak to the Project team s focus on safety. Weekly site inspections continue to be favorable, with only minor items being cited. The team continues to work with the City and County to ensure that the environment is safe for patrons and general public. Traffic circulation at the project site Page 2

11 now circumvents the closed portion of Theodore M. Berry Way, with direction being provided through site signage, including a variable message board. Second Street sidewalks have now been opened back up, with the completion of both Baker s and the Private Developer s work in this area. The sidewalks at Walnut Street and Joe Nuxhall Way that were previously closed are now opened back up to the public, as is the north sidewalk on Freedom Way East. The balance of Freedom Way East is targeted to open on June 1, Quality is also a ongoing focus of the team. Through the services of four independent testing firms and various City and County inspections, review of ongoing and completed work is evaluated. As deficient items are raised, they are tracked on a deficiency log. A request for information (RFI) is issued to the design team for their input on the deficiency. All parties are working to ensure that each field issue is properly addressed and closed out. The most recent log reflects that all deficient items have been closed out, and no new deficient items have been cited in over five months. The design team is sufficiently supporting the trade contractor s efforts. As submittal and request for information (RFI) documents are issued, they are being addressed. To date, the design team has been responsive and their turnaround times have supported the work flow of the project. Budget Review The were no changes made during the month to the budget projection for Phase 1. On Phase 2, there was a minor increase in the hard costs projection. Previously this projection was showing an amount of $29.830M for Bid Packages #9 and #11. Currently these packages combined total $29.893M. The change is a result of several additive and deductive change orders. This projected amount is approximately $10.3M below the Construction Manager Published Estimate of $40.3M. Bid Package #9 was awarded at an amount of $7.1M. Change orders totaling $133,693 have been executed. This change order total is approximately $91,000 higher than what was reported last month, due to a handful of miscellaneous small changes. An allowance of $800,000 was included within the contract. Approximately $190,000 of this allowance remains, the majority of which is the specific allowance for historical archeological excavation. The original contract amount for Bid Package #11 is $22.3M. Two change orders have been executed to date totalling $337,136. The change order amount decrease in this past month was due to a credit related to the reconciliation of Allowance #3 within Baker s contract. A contract allowance of Page 3

12 $975,000 was included in the contract. Approximately $250,000 of this allowance is projected as remaining at this point in the Project. The County and City are working to finalize the soft costs budget. In the past month, a draft of the overall budget was prepared and is being reviewed and approved by the Project Team. Currently, the soft costs are tracking within budget. Inclusion Review See Section 5: Economic Inclusion report. Parks and Overbuild Update Parks See Section 7: Cincinnati Riverfront Park report. Developer The first residents moved into The Banks during the past month! A temporary certificate of occupancy was received on April 13, Punchlist activities are underway on all floors of the building, as well as at the building exterior. Installation of landscaping at the amenity terrace is underway, with weather being the primary hurdle to final completion. Final installation of exterior applied components such as metal panels and handrails is wrapping up. On Block 16, work on the building skin and envelope is substantially complete. Brasfield & Gorrie is working to install the applied exterior building components such as railings, metal panels, and zinc shingles. Installation of the building finishes is ongoing at all levels of the building. Punchlist work has begun on the second floor, and will proceed up the building in the coming weeks. Amenity terrace work is underway and will follow completion of the terrace at Block 26. Block 16 is tracking on schedule for a May 15, 2011 completion. Construction on the Police Welcome Center continued throughout the month. Plans for Toby Keith and Johnny Rockets have been circulated to the Private Developer for review and comment, and have also been submitted to the City for permit review. Construction will begin upon receipt of permits. The Doyle Group is working to finalize their plans in the coming weeks for landlord review, and then submit for permit. Prepared by Patti Neal, Carter. Page 4

13 Page 5

14 ID Task Task Name 2009 Duration Start Finish Mode Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 IDMA Phase days?mon 3/15/10 Fri 10/28/11 2 Bid Package 9: Mehring Way, Main St, Ted Berry Way 370 days?mon 3/15/10 Fri 8/12/11 3 Mehring Way 235 days Mon 3/15/10 Fri 2/4/11 4 Mehring Way - West of Roebling, Lot D Work 108 days Mon 3/15/10 Wed 8/11/10 5 Mehring Way - East of Roebling 180 days Mon 3/15/10 Fri 11/19/10 6 Phase 1 of Addendum #1 Sewer Main Install 10 days Fri 5/21/10 Thu 6/3/10 7 Interim Completion Date - Lot D 0 days Wed 8/11/10 Wed 8/11/10 8 Mehring Way - Open to Traffic 0 days Mon 11/1/10 Mon 11/1/10 9 Northern Lane and Sidewalk under Roebling 45 days Mon 12/6/10 Fri 2/4/11 10 Lot F Extension Work 15 days Mon 11/1/10 Fri 11/19/10 11 Main Street 104 days Mon 11/8/10 Thu 3/31/11 12 Pavement Replacement - East 30 days Mon 11/8/10 Fri 12/17/10 13 Pavement Replacement - West 19 days Tue 2/1/11 Fri 2/25/11 14 Pavers, Sidewalk 45 days Mon 1/10/11 Fri 3/11/11 15 Main Street Interim Completion Date 0 days Thu 3/31/11 Thu 3/31/11 16 Ted Berry Way 350 days Mon 4/12/10 Fri 8/12/11 17 Approach Work - West and East of Roebling 102 days Mon 4/12/10 Tue 8/31/10 18 Sewer Installation (By Others) 15 days Mon 4/12/10 Fri 4/30/10 19 Interim Completion Date - Between Vine and Walnut 0 days Tue 8/31/10 Tue 8/31/10 20 Removal Between Elm and Rosa Parks 119 days Mon 1/17/11 Thu 6/30/11 21 Phase 3 of Addendum #1 Sewer Main Install 40 days Fri 5/6/11 Thu 6/30/11 22 Ted Berry Way Contract Completion Date 0 days Fri 8/12/11 Fri 8/12/11 23 Freedom Way Central, Race Street 24 Phase 2 of Addendum #3 Sewer Main Install 7 days Mon 8/23/10 Tue 8/31/10 25 Bid Package 11: Lot Two Garage, Freedom Way Central, Race 370 days Mon 5/31/10 Fri 10/28/11 26 Start 0 days Mon 5/31/10 Mon 5/31/10 27 Demolition, Mass Excavation, Site Utilities 40 days Mon 5/31/10 Fri 7/23/10 28 Augercast Piles 0 days Fri 10/29/10 Fri 10/29/10 29 Storm and Sanitary Mains 14 days Mon 7/19/10 Thu 8/5/10 30 Pile Caps 150 days Mon 8/23/10 Fri 3/18/11 31 Columns, Walls 150 days Mon 8/30/10 Fri 3/25/11 32 Underslab Utilities 150 days Mon 9/6/10 Fri 4/1/11 33 Slab on Grade 178 days Fri 9/17/10 Tue 5/24/ Level 178 days Mon 10/11/10 Wed 6/15/ Level 160 days Mon 11/22/10 Fri 7/1/11 36 MEP 85 days Thu 5/19/11 Wed 9/14/11 37 Finishes 85 days Thu 5/19/11 Wed 9/14/11 38 Second Street Work 44 days Mon 1/31/11 Thu 3/31/11 39 Street Grid Work, Wp'ing, topping slabs, lights 85 days Thu 5/19/11 Wed 9/14/11 40 Punchlist 10 days Thu 9/29/11 Wed 10/12/11 41 Temporary Certificate of Occupancy 0 days Fri 9/30/11 Fri 9/30/11 42 Project Completion 0 days Fri 10/28/11 Fri 10/28/11 43 Phase IA Residential and Retail 378 days Wed 12/2/09 Fri 5/13/11 44 Block days Wed 12/2/09 Thu 4/14/11 The Banks - Master Project Schedule Page 1 5/31 8/11 8/31 11/1 10/29 3/31 8/12 9/30 10/28

15 The Banks - Master Project Schedule ID Task Task Name 2009 Duration Start Finish Mode Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 45 Structure 185 days Wed 12/2/09 Tue 8/17/10 46 Skin 139 days Wed 8/18/10 Mon 2/28/11 47 Roof 16 days Wed 8/18/10 Wed 9/8/10 48 Interiors 172 days Wed 8/18/10 Thu 4/14/11 49 Hardscape 126 days Thu 10/21/10 Thu 4/14/11 50 Certificate of Occupancy 0 days Thu 4/14/11 Thu 4/14/11 4/14 51 Block days Mon 4/12/10 Fri 5/13/11 52 Structure 130 days Mon 4/12/10 Fri 10/8/10 53 Skin 124 days Mon 10/11/10 Thu 3/31/11 54 Roof 65 days Mon 10/11/10 Fri 1/7/11 55 Interiors 150 days Mon 10/18/10 Fri 5/13/11 56 Hardscape 100 days Mon 12/27/10 Fri 5/13/11 57 Certificate of Occupancy 0 days Fri 5/13/11 Fri 5/13/11 5/13 58 Parks 104 days Thu 4/28/11 Wed 9/21/11 59 Walnut Street Event Lawn 0 days Thu 4/28/11 Thu 4/28/11 4/28 60 Walnut Street Fountain and Grand Stair 0 days Wed 9/21/11 Wed 9/21/11 9/21 Page 2

16 Section 4: Budget

17 Section 4: Budget Phase 1 construction budget expended as of April 30, 2011 was 95.64%. A total of 41.42% of the Phase 2a construction budget was expended as of the end of April. Phase 2a construction expenditures and projections remain within the approved budget. Construction budget detail appears on the following pages. Representatives of the City, County, OKI and ODOT continued discussions in April to finalize the scope, budget and schedule for Bid Package #12. Construction activities to complete street grid and pedestrian improvements in this Bid Package will be divided into two parts. Draft of the Local Public Agency Agreement is in development. Page 1

18 Construction Construction Budget as of Budget as of Approved Contract Potential Remaining Grant Expenditures Balance to Complete BP# Description 2/10/09 4/29/09 May, 2010 Amount Amount Changes (F+G+H) Allocation to Date (I-K) (I-E) 1 Site Demolition $ 698,900 $ 698,900 $ 698,900 $ 698,900 $ (25,123) $ - $ 673,777 $ 673,777 $ - $ (25,123) THE BANKS PHASE 1 PUBLIC PARTIES CONSTRUCTION BUDGET AS OF APRIL 30, 2011 Revised Construction Budget as of Approved Change Order Forecasted Total Construction Amount Forecast to Budget Variance 2 Partial Pile Package 505, , , ,000 (54,912) - 450, ,088 - (54,912) 3 Piles & Soil Retention 4,200,000 4,200,000 4,200,000 3,510,188 (58,773) - 3,451,415 3,451,415 (0) (748,585) 4 Foundations, Underground Utilities & FW 5,681,210 5,681,210 5,681,210 5,681, ,217-6,061,427 6,032,904 28, ,217 5 Block 26 Concrete Structure, Slab on Grade through & including Podium 3,794,500 3,794,500 3,794,500 3,871,260 (98,266) - 3,772,994 3,772,994 (0) (21,506) 6 Block 16 & 20 Concrete Structure, Slab on Grade thru & including Podium + Plumbing & Fire Protection 15,649,009 11,487,414 11,487,414 8,539, ,730-8,666, ,480 8,559, ,392 (2,821,380) 7 FW East & West Streetgrid 6,102,417 4,341,168 4,341,168 4,992, ,258-5,674, ,348 5,524, ,264 1,333,120 8 Block 26, 16 & 20 Architectural & Mech & Elec 2,477,288 5,768,025 5,768,025 5,783, ,865-6,031,865 5,969,055 62, ,840 9 Mehring Way Relocation - Elm to Main including utilties 11,482,236 6,991,000 N/A Signage 368,900 38, , ,344 96, , Freedom Way Central - 7,400,000 N/A Plumbing 498,514 (31,163) 467, , ,351 Subtotal - Construction $ 50,590,560 $ 50,867,217 $ 36,476,217 $ 34,448,306 $ 1,208,291 $ - $ 35,656,597 $ 1,056,828 $ 35,212,594 $ 444,003 $ (819,620) Parking Grant 3,200,000 3,200,000 3,200, ,800, ,000 - Soft costs 11,367,117 11,367,117 9,374,258 9,374,258 3,006,642 12,380,900 12,380,900-3,006,642 Economic Development Assistance Grant 12,000,000 12,000,000 12,000, ,000,000 3,000,000 - Parks 10,750,000 10,750,000 10,750, ,750, Owner's Contingency 2,874,513 2,597,856 3,788, ,056,828 2,187, ,920 (2,187,022) Project Totals $ 90,782,190 $ 90,782,190 $ 75,589,245 $ 43,822,564 $ 4,214,933 $ - $ 48,037,497 $ 1,056,828 $ 72,330,516 $ 4,388,923 $ -

19 THE BANKS PHASE IIA PUBLIC PARTIES CONSTRUCTION BUDGET AS Of APRIL 30,2011 A B D E F G H I J K Construction Approved Approved Change Forecasted Total Construction Remaining Balance to Forecast to Budget BP# Description Budget as of March 2010 Contract Amount Order Amount Potential Changes Amount (E+F+G) Grant Allocation Expenditures to Date Complete (H-I) Variance (H-D) 9 Mehring Way Relocation and Site Demolition $ 7,119,555 $ 7,119,555 $ 133,693 $ 83,124 $ 7,336,372 $ 4,798,190 $ 2,538,182 $ 216, Intermodal Garage and Freedom Way West 30,466,924 22,303, ,136-22,640,569 4,788,568 12,290,161 10,350,408 (7,826,355) 12 Street Grid & Pedestrian Network 2,860, Subtotal - Construction $ 40,446,479 $ 29,422,988 $ 470,829 $ 83,124 $ 29,976,941 $ 4,788,568 $ 17,088,352 $ 12,888,589 $ (7,609,538) Soft costs 9,302,691 9,302, ,302,691 1,000,000 4,861,616 4,441,075 - Owner's Contingency 2,487, ,788,568 (7,609,538) 4,308,429 7,609,538 Project Totals $ 52,236,629 $ 38,725,679 $ 470,829 $ 83,124 $ 39,279,632 $ 5,788,568 $ 14,340,430 $ 21,638,093 $ -

20 Section 5: Economic Inclusion

21 Section 5: Economic Inclusion As we near the end of the initial phase of The Banks Project, Ellington Management Services, Inc., (EMS) is assessing the outcome of the inclusion commitments made by prime contractors since project inception. Seventeen of the 18 prime contracts subject to the Small Business Enterprise (SBE) Program are closed, and most of the contractors meet or exceeded their inclusion commitments. We are continuing to monitor the one open contract; the work of its SBE subcontractors is yet to be completed. To date, the overall project outcomes exceed the Public Partnership s SBE contractor inclusion goal by 6.1% at 36.1% compared to the 30% goal. As of March 25, 2011 SBE participation is 36.1%, Minority Business Enterprise (MBE) participation is 16.1% and Women Business Enterprise (WBE) participation remains at 2.8% (see Appendix D, Attachment A). There are five bid packages supported by state and/or federal funding and are subject to the goals for Disadvantaged Business Enterprise (DBE) participation established by the Ohio Department of Transportation (ODOT). Three of these contracts are closed out and are highlighted in the table below. Bid Package No. ODOT DBE Goal Contractor Commitment Actual DBE Participation DBE Dollars 5 8.0% 10.8% 12.0% $746, % 10.7% 11.7% $676, % 5.0% 5.5% $615,285 The DBE goal for Bid Package #9 is 4%. The commitment is 4.9%. The actual DBE participation is 2.8%, and 2.5% actual WBE participation. The goal for Bid Package #11 is 8%. The commitment is 8.2%. Actual participation to date is 6.5% (see Appendix D, Attachment B). The goal is 10% SBE participation for professional services. The current level of participation is 8.9%. Results are moving closer to the goal, but remain 1.1% below the goal. The total dollar value of these contracts has increased with no corresponding increase to sub-consultants. The MBE participation is 7.6% and WBE participation is 2.0% (see Appendix D, Attachment C). The Public Partnership set a combined minority and women workforce participation goal of 22%, which is measured in work hours. Minority workforce participation is 16.46%, which includes minority female hours. The total female participation is 2.26% for a combined participation of 17.95% (minority females are not counted Page 1

22 twice) as reported by hours for September 1, 2008 March 25, 2011 (see Appendix D, Attachment D). From February 26, 2011 to March 25, 2011, employees on The Banks Project living within the 15-County Cincinnati-Middletown Metropolitan Statistical Area (MSA) represented 83.5% of the workforce (see Appendix D, Attachment E). Workforce inclusion reporting forms and certified payroll records were used to analyze the residency composition of The Banks Project workforce from December 2008 through July 25, The most recent data covering July 26, 2010 through January 25, 2011, includes a review of the inclusion reporting forms but does not include a review of certified payroll records. Only information for production workers active on site during the covered period was analyzed. Analysis of data for 1,241 workers active on the Project during the covered period revealed the following: Geographic Area Residency Percentage Tri-State 97.7% Cincinnati-Middletown 77.4% MSA Hamilton County 25.9% City of Cincinnati 9.12% There were no local residency participation goals established for this Project. Prepared by Ellington Management Services; Bernice Walker, Hamilton County; and Rochelle Thompson, City of Cincinnati. Page 2

23 Section 6: Construction Manager s Report

24 Section 6: Construction Manager s Report A newly poured slab on grade in the Lot 2 Garage (looking north). Progress Update The term "April Showers" took on a whole new meaning this month as crews battled record rainfall to keep the Project moving forward. Contrary to what you may recall, there were a handful of days where it didn't rain and crews took full advantage by often pouring multiple concrete slabs in a single day. Although the rain certainly hindered progress in regard to hauling the Theodore M. Berry Way dirt, crews did begin installing the tiebacks that will support the new retaining wall at the intersection of Theodore M. Berry Way and Rosa Parks Street. Page 1

25 Current Highlights Bid Package #11 trade contractor continued pouring structural slabs at the 500' level and street level (see photos #1 and #2). Bid Package #11 trade contractor continued pouring slabs on grade at the 489 level (see photo #3). Bid Package #11 trade contractor continued excavating and pouring pile caps. The team anticipates the last of the caps will be poured in mid-may (see photo #4). Bid Package #11 trade contractor poured all the podium slabs at Second Street (see photo #5). Bid Package #11 trade contractor began forming the stairs in the Garage (see photo #6). Bid Package #9 trade contractor began installing the tiebacks to support the retaining wall at Theodore M. Berry Way and Rosa Parks Street (see photo #7). Photo #1 Bid Package #11: Trade contractor continued pouring the structural decks. Page 2

26 Photo #2 Bid Package #11: Trade contractor pours the parking deck at the bottom of the Race Street ramp. Photo #3 Bid Package #11: Trade contractor prepped and poured the slab under Freedom Way. Page 3

27 Photo #4 Bid Package #11: Trade contractor continued excavating and pouring pile caps. Photo #5 Bid Package #11: Trade contractor poured all podium slabs at Second Street. Page 4

28 Photo #6 Bid Package #11: Trade contractor began forming the stairs in the garage. Photo #7 Bid Package #9: Trade contractor began installing tiebacks at Rosa Parks Street and Theodore M. Berry Way. Page 5

29 Community Environment Impact and Project Safety Bid Package #9 and Bid Package #11 Trade Contractors have continued to make public safety a priority. They have been mindful of the public within the Lots B and C, on Second Street, at Theodore M. Berry Way and along Joe Nuxhall Way and have utilized construction fencing to isolate their activities. Pro-active communication with the City and County has also kept the public informed of the ongoing Riverfront changes associated with the construction work. Between Phases 1 and 2, a total of 1,670 trade workers have attended the site safety orientation. The Project currently stands at 356,939 hours without a lost time accident. Formal site safety walk-thrus are conducted three times a week. Workers continue to maintain a very good attitude about working safely. In fact, the score for the site walk-thru has been a 100% multiple times in April meaning not one hazard was observed. The scorecard below categorizes observations from our safety walk-thrus by hazard, severity and resolution rate for the past 30 days. Page 6

30 The impact to Riverfront Operations around the Phase 2 work has been as follows: Traffic Race Street between Second Street and Theodore M. Berry Way will remain closed until the fourth quarter of Theodore M. Berry Way is now permanently closed between Elm Street and Rosa Parks Street and remains closed at the dogleg at Walnut Street. Operation of Adjacent Facilities No impact to GABP, the Reds HOF, PBS, the Arena or the Transit Center. Pedestrian Routes Theodore M. Berry Way is now permanently closed between Elm Street and Rosa Parks Street and continues to be closed at the dogleg at Walnut Street. The West Pete Rose Way entrance to the Central Riverfront Garage remains closed for Bid Package #11 work. Pedestrians within the Garage are being routed up to street level from the Central Riverfront Garage. The sidewalk replacement at Second Street was completed in March. Parking The West Pete Rose Way entrance to the Lot 3 Garage remains closed for Bid Package #11 work. This will require Lot 3 Garage patrons to utilize the new entrances to the Garage on Mehring Way and Main Street. Signage and Fencing Site fencing and gates are checked on a daily basis to insure they are secure. Construction Schedule The schedule included in this month's report includes activities associated with the two active Phase 2 contracts: Bid Packages #9 and #11. Bid Package #9 The Bid Package #9 trade contractor has completed the work associated with Mehring Way, the reconfiguration of Lots D and F, and Joe Nuxhall Way and is 90% complete with the pavement and sidewalk rework on Theodore M. Berry Way between Walnut and Rosa Parks Streets. The last lane of pavement and sidewalk at Rosa Parks Street and Theodore M. Berry Way will be completed in late summer. The removal of Theodore M. Berry Way between Elm Street and Rosa Parks Street is ongoing. This work, including the parking lot to be paved within the old Theodore M. Berry Way footprint, is on schedule for completion in August. Page 7

31 Bid Package #11 The Bid Package #11 trade contractor is 90% complete with the slabs on grade, 80% complete with the structural slabs at the intermediate level and is 70% complete with the structural slabs at the street level. The electrical, plumbing and fire protection contractors have already started their rough-in. The sidewalk work on the south side of Second Street is complete. The head houses and elevator on Freedom Way East will be completed in May. The Lot 2 Garage, Freedom Way and Race Street are all on schedule for completion in October. Cost Recap The Cost Recap Report includes the following Trade Contractors: TC-24 (Bid Package #9 General Trades) construction work is now in progress. To date, Prus Construction has billed $4,953,469 of their $7,253,249 contract (68%). TC-25 (Bid Package #11 General Trades) construction work is now in progress. To date, Baker Concrete has billed $13,612,046 of their $22,640,568 contract (60%). Change Management Updated Approved and Pending Change Order Logs for Bid Package #9 (TC-24) and Bid Package #11 (TC-25) are included in Appendix C. Also included in Appendix C are updated allowance tracking logs describing the changes being billed against the allowances for each Bid Package. RFIs and Bulletins The RFI Log identifies request for information issued to date and the status of each RFI. To date, there have been 201 RFIs created, 193 of which are closed. To date, there have been six bulletins issued for the Bid Package #11 work. Quality Management and Assurance Plan The QM/QA currently incorporates professional firms to do special inspections and testing associated with the construction of Bid Packages #9 and #11. Thelen Associates Inc. and HC Nutting are the professional firms providing support to execute the Project QM/QA Plan for Bid Package #9. HC Nutting and ATC Associates are the Page 8

32 professional firms providing support for Bid Package #11. The City and the County provide personnel for inspections and material verification per ODOT requirements. Prus Construction and Baker Construction will also have their own testing agencies to provide services per their contracts. In addition to the inspections above, local utility providers such as Greater Cincinnati Water Works, Cincinnati Bell, Duke Energy and the Metropolitan Sewer District are on site regularly to inspect the installations associated with their systems. Installations are also subject to the approval of the building department, as well as local electrical and plumbing inspectors. The QM/QA plan will cover areas such as inspection and testing of shallow foundations, controlled structural fill, mix design, material certification, reinforcement and installation, formwork geometry, concrete placement, evaluation of concrete strength, grouting operations and evaluation of masonry strength. The Quality Management and Assurance Plan continue will be used for Bid Packages #9 and #11. All Non-Conforming Work gets addressed with the Trade Contractor in a timely manner. Prepared by Brian Borcherding, Messer Construction. Page 9

33 Act ID BP#9 - Mehring Way, Ted Berry Way, Main St BP9 Pre-Construction and Bidding Description Dur Start Finish 1350 BP9 - PSE review and approval 0 19OCT09 A 25JAN10 A 1360 BP9 - Public Bidding Advertisement 15d 28JAN10 A 22FEB10 A 1370 BP9 - Pre-bid Meeting 1d 04FEB10 A 04FEB10 A 1380 BP9 - Bids Due 0 22FEB10 A 1390 BP9 - Prosecutor Review and Approval 3d 24FEB10 A 26FEB10 A 1400 BP9 - County Commissioners Approval 4d 01MAR10 A 04MAR10 A Mehring Way 1000A Demo, grade and storm work - west of Roebling 30d 15MAR10 A 22APR10 A 1040A Mehring Way west of Roebling, Lot D restorations 108d 15MAR10 A 11AUG10 A 1050A Mehring Way work east of Roebling 175d 15MAR10 A 19NOV10 A 1120A BP9 estimated construction start 0 15MAR10 A 1230A Phase 1 laydown requirement east of d 15MAR10 A 21MAY10 A 1010A Duke Energy - 8" and 4" gas main 30d 23APR10 A 09JUL10 A 1200A Phase 1 of addendum #1 water main installation 20d 21MAY10 A 03JUN10 A 1160A Interim Completion Date for Restoration of Lot D 0 11AUG10 A 1070A Bengals '10 Season 107d 12AUG10 A 31DEC10 A 1060A Lot F extension work 15d 01NOV10 A 19NOV10 A 1200A10Mehring Way - open to traffic 0 01NOV10 A 1200A20Northern lane and sidewalk under the Roebling 40d 06DEC10 A 04FEB11 A Total Float FEB 1140A Start of Bengals '11 Season 0 25AUG11 * 72d Main St 1100A Joe Nuxhall Way Pavement Replacement - East 20d 08NOV10 A 17DEC10 A 1180A20Joe Nuxhall Way Pavers, Sidewalk 20d 10JAN11 A 11MAR11 A 1180A10Joe Nuxhall Way Pavement Replacement - West 20d 01FEB11 A 25FEB11 A 1180A Joe Nuxhall Way Interim Completion Date 0 31MAR11 A Ted Berry Way 1020A Roebling closed for painting project 145d5h 12APR10 A 01NOV10 A 1090A Ted Berry Way Approach - north, west of Roebling 102d 12APR10 A 31AUG10 A 1220A Sewer main installation (by others) 15d 12APR10 A 30APR10 A 1110A Ted Berry Way Approach - East of Roebling 82d 10MAY10 A 31AUG10 A 1150A Interim Completion Date - TBW between Vine/Walnu 0 31AUG10 A 1130A Ted Berry Way Removal between Elm and Rosa 119d 17JAN11 A 11AUG11 81d 1190A Phase 3 of addendum #1 water main installation 20d 15JUL11 11AUG11 81d 1170A Contract Completion Date 0 12AUG11 * 80d Lot 2, Freedom Way Central, Race St 1210A Phase 2 of addendum #1 water main installation 20d 23AUG10 A 31AUG10 A BP#11 - Lot 2 Garage, Freedom Way Central, Race BP11 Pre-Construction and Bidding MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOVDEC BP9 - PSE review and approval BP9 - Public Bidding Advertisement BP9 - Pre-bid Meeting BP9 - Bids Due BP9 - Prosecutor Review and Approval BP9 - County Commissioners Approval Demo, grade and storm work - west of Roebling BP9 estimated construction start Mehring Way west of Roebling, Lot D restorations Phase 1 laydown requirement east of Duke Energy - 8" and 4" gas main Mehring Way work east of Roebling Phase 1 of addendum #1 water main installation Interim Completion Date for Restoration of Lot D Sewer main installation (by others) Bengals '10 Season Lot F extension work Mehring Way - open to traffic Northern lane and sidewalk under the Roebling Joe Nuxhall Way Pavement Replacement - East Roebling closed for painting project Joe Nuxhall Way Pavers, Sidewalk Ted Berry Way Approach - north, west of Roebling Ted Berry Way Approach - East of Roebling Start of Bengals '11 Seaso Joe Nuxhall Way Pavement Replacement - West Interim Completion Date - TBW between Vine/Walnu Phase 2 of addendum #1 water main installation Joe Nuxhall Way Interim Completion Date Ted Berry Way Removal betw Phase 3 of addendum #1 wat Contract Completion Date Start date 19OCT09 Finish date 28OCT11 Data date 05MAY11 Run date 06MAY11 Page number 1A Primavera Systems, Inc. Messer/MBJ The Banks Phase 2 Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

34 Act ID Description Dur Start Finish 1410 BP11 PSE Submission and Approval 1d 13NOV09 A 22APR10 A 1420 BP11 - Public Bidding Advertisement 1d 22MAR10 A 11MAY10 A 1430 BP11 - Bids Due 0 11MAY10 A 1440 BP11 - Prosecutor Review and Approval 3d 13MAY10 A 17MAY10 A 1450 BP11 - County Commissioner Approval 4d 18MAY10 A 21MAY10 A Lot 2, Freedom Way Central, Race St 1000 Construction Start 0 31MAY10 A 1140 Demo, Mass Exc, Site Utilities 30d 31MAY10 A 23JUL10 A 1040 Pete Rose Way and Ramp Demo allowed to begin 0 07JUN10 A 1260 Demo, mass exc at ramp and PRW 20d 07JUN10 A 23JUL10 A 1060 Race St closed for construction 0 21JUN10 A 1130 Augercast Piles 90d 12JUL10 A 29OCT10 A 1340 Storm and Sanitary Mains 30d 19JUL10 A 05AUG10 A 1330 Bengals season 122d 12AUG10 A 28JAN11 A 1150 Pile Caps 95d 23AUG10 A 18MAR11 A 1160 Columns, Walls 90d 30AUG10 A 25MAR11 A 1170 Underslab Utilities 80d 06SEP10 A 01APR11 A Total Float FEB 1180 Slab on Grade 120d 17SEP10 A 24MAY11 45d 1190 Supported Slab (500' level) 153d 11OCT10 A 15JUN11 45d 1070 Interim milestone - piles complete 0 28OCT10 A 1200 Supported Slab (515' level) 125d 22NOV10 A 01JUL11 45d 1310 Replace 2nd St south sidewalk 40d 31JAN11 A 31MAR11 A 1210 Street grid - H2Oproofing, topping slabs, lights 94d 05MAY11 14SEP11 57d 1220 MEPS 94d 05MAY11 14SEP11 57d 1230 Finishes 94d 05MAY11 14SEP11 37d 1320 Approach slabs and sidewalk - 2nd St north 60d 23MAY11 * 15AUG11 79d 1280 Interim milestone - slab on grade complete 0 24MAY11 137d 1290 Interim milestone - supported slabs complete 0 01JUL11 109d 1300 Interim milestone - permanent power energized 0 01JUL11 109d 1270 Project Punchlist and Closeout 20d 15SEP11 12OCT11 37d 1240 Milestone - Temporary C of O 0 30SEP11 * 45d 1120 Milestone - Project Completion 0 28OCT11 * 25d MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOVDEC BP11 PSE Submission and Approval BP11 - Public Bidding Advertisement BP11 - Bids Due BP11 - Prosecutor Review and Approval BP11 - County Commissioner Approval Construction Start Demo, Mass Exc, Site Utilities Pete Rose Way and Ramp Demo allowed to begin Demo, mass exc at ramp and PRW Race St closed for construction Augercast Piles Storm and Sanitary Mains Bengals season Pile Caps Columns, Walls Underslab Utilities Slab on Grade Supported Slab (500' level) Interim milestone - piles complete Supported Slab (515' level) Replace 2nd St south sidewalk Street grid - H2Oproofin MEPS Finishes Approach slabs and sidewalk Interim milestone - slab on grade complet Interim milestone - supported slabs Interim milestone - permanent powe Project Punchlist an Milestone - Tempora Milestone - Proje Start date 19OCT09 Finish date 28OCT11 Data date 05MAY11 Run date 06MAY11 Page number 2A Primavera Systems, Inc. Messer/MBJ The Banks Phase 2 Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

35 Section 7: Cincinnati Riverfront Park

36 Section 7: Cincinnati Riverfront Park Despite record rainfall of nearly 14 inches, the rising Ohio River, and severe weather outbreaks throughout April, The Cincinnati Riverfront Park project forged ahead. The contractor for the Walnut Street Fountain and Grand Stairway, Monarch Construction, continued concrete placements and began new structural wall form work and steel on the north side along Theodore M. Berry Way. Form work and steel installation continued on the grand stairway, and framing for the bike center storefront and doors began in April. Plumbing continued and Monarch began electrical and fixture installation for the fountain lighting. Elevator equipment arrived on site and preparations for the elevator and head house installation began. Elevated deck forming for May concrete placements was underway. Granite seat walls for the grand stairway and bike center glass storefront installation will take place in May. During April, the contractor for the Schmidlapp Event Lawn and Stage, Megen Construction, began filling the Event Lawn with sand, gravel and soil in preparation for landscape planting and sod installation in early May. Plumbing and electrical installation continued throughout the lawn area and within the garage electric room. The Duke Energy transformer arrived on site and will be energized in mid-may. Waterproofing flood tests continued as the waterproofing contractor neared completion and installation of expansion joint systems began. Solar panel design by Third Sun Solar was completed and approved by the Cincinnati Park Board; installation of the PV panels will begin in late May. Granite paver installation began and will continue throughout May. Megen Construction is progressing toward a late May substantial completion date. Tilsley and Associates, architect for the Moerlein Lager House, progressed toward final interior design and continued coordination with adjacent projects. In April, The Lager House contractor, Schumacher-Dugan Construction, completed elevator shaft construction, continued structural block work, began utility installation work in the MLH service level and began preparations to start exterior shell construction in May. Prepared by Dave Prather, Cincinnati Park Board and Kimberlee Curtis, Parsons Brinckerhoff. Page 1

37 Granite delivery for Walnut Street Fountain and Grand Stairway. Construction progress on Walnut Street Fountain and Grand Stairway. Page 2

38 Monthly Progress Report for April 2011 Event Lawn Stage takes shape. Progress continues on the Moerlein Lager House. Page 3

39 Section 8: Communications

40 Section 8: Communications This section details highlights of April media coverage of The Banks Riverfront Development. These items were published on newspaper websites, magazine websites, television websites and blogs. The media mentions are listed in chronological order. The actual headlines of the articles are highlighted in the bold text. Links to each article are provided, as well as the publication date of each item. For more information on The Banks Public Partnership, please visit: How to Access the Original Articles For those of you who have an electronic copy of the report, simply click on the link provided and you will be taken to the article in its original form (Some programs may require you to hold down the control key while simultaneously clicking the link). For those of you with a hard copy version, type the URL into your web browser or search the exact title of the article through an online search engine. Banks Project Moves Forward Overnight April 1, 2011 WLWT.com Concrete Pour Starts Next Step in Banks Project WLWT.com Youtube Video The Banks Project gets more concrete April 1, 2011 WCPO.com Structural deck concrete poured at the Banks April 1, 2011 WXIX.com Page 1

41 Riverfront Fusion April 13, 2011 CincinnatiUSA.com Holy Grail (Review) Seen in print edition as Banking on Big Business April 13, 2011 City Beat Years after the concept arose, first people moving to The Banks April 18, 2011 FOX19.com First residents to move into The Banks Tuesday April 18, 2011 Cincinnati.com Developing Now Blog Soapdish: Blooming on the Banks April 19, 2011 Soapbox Media First tenants move into apartments at The Banks April 19, 2011 WCPO.com First apartment residents move into The Banks April 19, 2011 Cincy Biz Blog (Cincinnati Business Courier) First Residents Move Into Banks Apartments More Than Half Of Units Already Rented April 19, 2011 WLWT.com Page 2

42 First residents move in at The Banks April 19, 2011 Cincinnati.com -residents-move-banks?odyssey=nav head Developers, city leaders welcome first residents to $80M first phase of The Banks April 19, 2011 Urbancincy.com Mayor welcomes first residents to The Banks April 19, 2011 Thecincinnatiherald.com 23/News/Mayor_welcomes_first_residents_to_The_Banks.html Page 3

43 Mallory s full State of the City speech April 19, 2011 Cincinnati.com City managers and investors praise downtown redevelopment April 21, 2011 Fox19.com Holy Grail Tavern (on the Banks) April 25, 2011 cincinnatireadventure.com Page 4

44 Appendices

45 Appendix A: Project Scope Description The Central Riverfront Intermodal Transit Facility, and the completion of Central Riverfront Street Grid and pedestrian network, utility infrastructure and traffic control (i.e., the Project ) is the design and construction of multiple structured public parking facilities and related public infrastructure improvements including, but not limited to, site development, streets and sidewalks, public utility distribution, structural elements, mechanical, electrical and plumbing systems, interior and exterior building and parking systems and fixtures, fire and security systems, interior and exterior pedestrian and vehicular traffic control and access systems, landscaping and related improvements. The overall Project will be planned, designed and constructed in multiple phases or parts over a period of several years. This Project is executed through the efforts of Hamilton County, the City of Cincinnati, and the Development Manager, Carter Dawson. Hamilton County has retained THP Limited, Inc. for Central Riverfront Intermodal facility design services. The City of Cincinnati has retained Burgess & Niple for Freedom Way structural bridge deck, utility infrastructure and traffic control design services. In addition, Hamilton County has retained Messer Construction for construction management services. Phase 1 of the Project includes the Central Riverfront Intermodal facility between Second Street (to the North), Mehring Way (to the South), Walnut Street (to the West) and Main Street (to the East). Central Riverfront Intermodal Transit Facility Phase 1 Page 1

Opening Day crowds lined streets at The Banks before, during and after the game.

Opening Day crowds lined streets at The Banks before, during and after the game. Opening Day crowds lined streets at The Banks before, during and after the game. THE BANKS PROJECT MONTHLY REPORT: APRIL 2015 The Banks Monthly Report: April 2015 In April, Opening Day crowds filled Freedom

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012 Geo-Thermal

More information

TABLE OF CONTENTS. Article II. DEVELOPMENT MANAGEMENT SERVICES...9

TABLE OF CONTENTS. Article II. DEVELOPMENT MANAGEMENT SERVICES...9 TABLE OF CONTENTS Article I. DEFINITIONS...3 Article II. DEVELOPMENT MANAGEMENT SERVICES...9 2.1 GENERAL...9 2.2 THE PROJECT TEAM...10 2.3 PRE-DESIGN AND DESIGN PHASE...10 2.3.1 Consultation During Project

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management

More information

NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008

NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008 NORWALK LA MIRADA UNIFIED SCHOOL DISTRICT Measure S Program Construction Management Progress Report For Citizens Oversight Committee Fall Quarter 2008 PROGRAM AND CONSTRUCTION MANAGER SEPTEMBER 30, 2008

More information

NAHB 1-00-0000 PRODUCT DEFINITION

NAHB 1-00-0000 PRODUCT DEFINITION NAHB Standard Homebuilder Cost Codes Cost Code Description 1-00-0000 PRODUCT DEFINITION 1-01-0000 PREAQUISITION COSTS 1-01-0110 Feasibility Study 1-01-0120 Environmental Impact Study 1-01-0130 Option Fees

More information

Every Student I Every Day I Every Possibility

Every Student I Every Day I Every Possibility For the Facilities Master Plan March 4, 2015 1 Introduction This has been prepared to describe a proposed process to be implemented in order to develop comprehensive Facility Master Plans for all schools

More information

KIEWIT CM/GC Enabling/Utilities

KIEWIT CM/GC Enabling/Utilities South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 john.todd@kiewit.com General

More information

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

The work has continued on final Phase 4 and is nearing completion.

The work has continued on final Phase 4 and is nearing completion. Updates-January 22, 2013 29369-Rehab Plaza Deck/Drainage Budget: $18,000,000, constr. Start 8/2009 The work has continued on final Phase 4 and is nearing completion. The main plaza area of phase 4 is now

More information

UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY

UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY The term capitalized fixed assets includes land, improvements to land, easements, buildings, building improvements, vehicles, machinery, furniture,

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or 9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org Construction Permitting Guidelines for Businesses Moving into Existing Buildings in Culver City If your business is moving into an existing

More information

Pre-Existing Structures at the Site Project Duration Type of Structure Under Construction Any Other Entities with Interests in the Property

Pre-Existing Structures at the Site Project Duration Type of Structure Under Construction Any Other Entities with Interests in the Property Speakers: Vice President, Global Risk Management & Insurance Starwood Hotels & Resorts Worldwide Senior Vice President - National Director National Property Claims - Strategic Outcomes Practice Willis

More information

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Design Development Quality Management Phase Checklist Project Phase Checklist Series Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA

More information

Technical Assignment 2

Technical Assignment 2 Architectural Engineering 2012 Senior Thesis -+ + Technical Assignment 2 Reston Station Phase 1 Garage Reston, VA Jonathan A Fisher Oct. 12, 2012 A d v i s o r : D r. R o b e r t L e i c h t Executive

More information

Application for Tax Abatement for Rehabilitation of Property in a Local Historic District

Application for Tax Abatement for Rehabilitation of Property in a Local Historic District Application for Tax Abatement for Rehabilitation of Property in a Local Historic District Historic Preservation Office Austin, Texas 512-974-2727 Adopted December 2012 To encourage preservation and maintenance

More information

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015 I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES All searches and notifications on Bid4Michigan are based on National Institute of Government Purchasing (NIGP) codes. It

More information

CONSTRUCTION MANAGEMENT REPORT NO. 1

CONSTRUCTION MANAGEMENT REPORT NO. 1 CONSTRUCTION MANAGEMENT REPORT NO. 1 Expansion and Renovation Prepared for: HOLLAND PUBLIC SCHOOL BOARD Date September 20, 2011 HOLLAND PUBLIC SCHOOLS HIGH SCHOOL EXPANSION AND RENOVATION TABLE OF CONTENTS

More information

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are: When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory

More information

July 29, 2014. Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following:

July 29, 2014. Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following: ADDENDUM NO. 2 TO REQUEST FOR QUALIFICATIONS FOR NEW DEVELOPMENT OF OAKLAND UNIFIED SCHOOL DISTRICT PROPERTIES, INCLUDING THE PARCELS HOUSING THE PAUL ROBESON ADMINISTRATION BUILDING AND DEWEY HIGH SCHOOL

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

CONSTRUCTION MANAGEMENT REPORT NO. 2

CONSTRUCTION MANAGEMENT REPORT NO. 2 CONSTRUCTION MANAGEMENT REPORT NO. 2 Expansion and Renovation Prepared for: HOLLAND PUBLIC SCHOOLS BOARD OF EDUCATION Date: October 31, 2011 HOLLAND PUBLIC SCHOOLS HIGH SCHOOL EXPANSION AND RENOVATION

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions Evanston Main Street Station TOD Plan and Study Appendix A.1: Station Area Existing Conditions EvanstonMainStreetStation TODPlanandStudy A 1 AppendixA.1: ExistingConditions Table of Contents Station Locations

More information

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals

More information

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION RESIDENTIAL: REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION 2 COMPLETE SETS OF PRINTS WITH ENGINEERS STAMP ON FOUNDATION PLAN INCLUDING ELECTRICAL, PLUMBING, ETC. SITE PLAN SHOWING HOUSE LOCATION

More information

PROPERTY EVALUATION AND RESERVE FUND STUDY

PROPERTY EVALUATION AND RESERVE FUND STUDY PROPERTY EVALUATION AND RESERVE FUND STUDY COMPLEX NORTH & WEST AVENUES LAS VEGAS, NV Prepared for: HOMEOWNER S ASSOCIATION Prepared by: CRITERIUM ENGINEERS 22 Monument Square Portland, ME 04101 CONTENTS

More information

Lincoln Downtown Master Plan Update

Lincoln Downtown Master Plan Update Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating

More information

Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas 77089. August 30, 2012. Prepared for:

Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas 77089. August 30, 2012. Prepared for: A Full Service Real Estate Inspection & Engineering Firm for Houston, Texas 77089 August 30, 2012 Prepared for: CLIENT S NAME MAILING ADDRESS Houston, Texas 77089 Prepared by: Charles J. Jenkins, P.E.

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS Village of Airmont BUILDING AND ZONING DEPARTMENT 251 CHERRY LANE, AIRMONT, NEW YORK Mailing Address: P.O. BOX 578, TALLMAN, NEW YORK 10982 Telephone: 845-369-8813 Fax: 845-357-8307 Website: www.airmont.org

More information

Milestones Primary. Early Start. Orig Dur. Early Finish. Act ID. Description NOTICE TO PROCEED START CONSTRUCTION

Milestones Primary. Early Start. Orig Dur. Early Finish. Act ID. Description NOTICE TO PROCEED START CONSTRUCTION Milestones Primary M1500 NOTICE TO PROCEED 0 11/01/ * M1510 START CONSTRUCTION 0 01/02/ * M1550 SUBSTANTIAL COMPLETION [ALL WORK IN PLACE] 0 04/15/ M1600 CERT OF OCCUP 0 04/15/ M1650 FINAL COMPLETION /

More information

Estimating Database Checklist

Estimating Database Checklist Estimating Database Checklist If you are creating a new estimating database for projects, the following list offers a thorough listing of Main and Sub Categories. You can also use it as a checklist to

More information

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer

More information

CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST

CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST CITY OF BERKELEY DETAILED CHECKLIST This checklist will assist you in preparing plans for submittal with a building permit application. Alterations, additions and remodeling projects may not require all

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

Bond Release Process for New Subdivision Developments in Fairfax County

Bond Release Process for New Subdivision Developments in Fairfax County Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document

More information

Greater Los Angeles County Region

Greater Los Angeles County Region Attachment 5 Greater Los Angeles County Region IRWM Implementation Grant Proposal Attachment 5: of the Greater Los Angeles County IRWM 2015 Solicitation Implementation Grant Proposal (Proposal) is divided

More information

Residential Building Permits Information

Residential Building Permits Information City of Bonham Building Department 514 Chestnut St. Bonham, Texas 75418 OFFICE: (903) 583-7555 FAX: (903)583-5761 Residential Building Permits Information Application for Permits: To apply for a permit,

More information

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

Sample Drawing Package for One and Two Family Dwelling Applications

Sample Drawing Package for One and Two Family Dwelling Applications Sample Drawing Package for One and Two Family Dwelling Applications For a full list of submission requirements, refer to the relevant checklist for your application found on our website: http://vancouver.ca/home-property-development/application-forms-and-checklists.aspx

More information

OHLONE COMMUNITY COLLEGE BOND MEASURE G

OHLONE COMMUNITY COLLEGE BOND MEASURE G Monthly Report OHLONE COMMUNITY COLLEGE BOND MEASURE G Fremont, California June 2014 TABLE OF CONTENTS 1. Executive Summary 2. Safety Status 3. Schedule Status 4. Design Progress 5. Construction Progress

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic

More information

BLOCK 400 PLANNED COMMUNITY DISTRICT

BLOCK 400 PLANNED COMMUNITY DISTRICT BLOCK 400 PLANNED COMMUNITY DISTRICT Newport Center December 1983 Newport Beach, California Ordinance 88-119 Adopted December 12, 1988 Amendment No. 672 Resolution No. 95-115 Adopted October 9, 1995 Amendment

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

CHARLOTTE COUNTY Community Development Department

CHARLOTTE COUNTY Community Development Department CHARLOTTE COUNTY Community Development Department Building Construction Services Division 18400 Murdock Circle, Port Charlotte FL 33948 Phone: 941.743.1201 Fax: 941.764.4907 www.charlottecountyfl.gov 50

More information

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul July 2010 Chair Peter Bell of the Metropolitan Council speaks about the Met Council s contribution of $1 million to a $1.5 million small business loan fund during a July 20 news conference with Mayor R.T.

More information

VILLAS OF TRADITIONS AT GREY OAKS

VILLAS OF TRADITIONS AT GREY OAKS Report of Turnover Survey VILLAS OF TRADITIONS AT GREY OAKS Grey Oaks Development Naples, Collier County, Florida Forge Engineering Project Number 2907-001.01 March 2015 Richard P..Lundberg, P.E cn=richard

More information

Building Code Inspections and Fees

Building Code Inspections and Fees St. Mary s County Department of Land Use & Growth Management Customer Assistance Guide 22 Building Code Inspections and Fees May 10, 2014 This guide is intended to assist in the proper construction sequence

More information

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME 1 THE BUILDING PROCESS The focus of Woodland Homes building department is Quality, Service and Predictability. Through

More information

New York State Office and Historic Homeownership Rehabilitation Tax Credit

New York State Office and Historic Homeownership Rehabilitation Tax Credit NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 DISCLAIMER : The New York State Office of Parks, Recreation and

More information

Braselton Bros. Store Redevelopment 5134 HWY 53 BRASELTON, GA 30548 LEVEL 0 - DEMO & NEW PLAN. Room. Room. Room. Room. Room. Room. Room. Room.

Braselton Bros. Store Redevelopment 5134 HWY 53 BRASELTON, GA 30548 LEVEL 0 - DEMO & NEW PLAN. Room. Room. Room. Room. Room. Room. Room. Room. 1.d 2.d 3.d 4.d 1.d 2.d 3.d 4.d REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE STAIR & INFILL WALL C.1 REMOVE DOOR &

More information

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project March, 2015

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project March, 2015 Addendum 1: Changes to the Draft IS/MND Text and Figures Introduction This summary presents minor corrections and revisions made to the Draft IS/MND initiated by the public, staff and/or consultants based

More information

National Archives and Record Administration

National Archives and Record Administration National Archives and Record Administration Installation of Self-Closing Flood Barriers and Loading Dock Turntable Removal and Structural Slab Repairs ! 2010 Baltimore Washington Chapter Outstanding Repair

More information

Historic Tax Credits in Texas: Combining the New State Credit with the Federal Investment Tax Credit. Downtown Amarillo 17 December 2013

Historic Tax Credits in Texas: Combining the New State Credit with the Federal Investment Tax Credit. Downtown Amarillo 17 December 2013 Historic Tax Credits in Texas: Combining the New State Credit with the Federal Investment Tax Credit Downtown Amarillo 17 December 2013 Ben Dupuy Anna Mod Stonehenge is a nationally respected finance company

More information

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer Development Services Department City of San Antonio Development Process 101 Permits & Licenses Michael Dice Development Services Manager Kathy Rodriguez Deputy Historic Preservation Officer 1 Permit &

More information

BUILDING PERMIT SPECIFICATIONS

BUILDING PERMIT SPECIFICATIONS BUILDING PERMIT SPECIFICATIONS The below noted requirements are based upon La Plata County Building Code. These specifications are not intended as a complete set of requirements, but are intended to provide

More information

Slavic Village Building Condition Review

Slavic Village Building Condition Review Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities

More information

Building Foundation and Structure

Building Foundation and Structure Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original

More information

BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS

BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS BUILDING BROCHURE BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS To ALTER, ADD TO, MOVE or CONSTRUCT a NEW HOME, CARPORT, GARAGE, SUNDECK, or other Building or Structure within the Regional District

More information

Saint Cloud Business Center

Saint Cloud Business Center Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with

More information

City of Cincinnati Streetcar Project

City of Cincinnati Streetcar Project City of Cincinnati Streetcar Project Project Analysis December 18, 2013 kpmg.com Table of Contents Section Slides Scope of Work 2 Approach 3 Exclusions 4 Executive Summary 5 Budget Summary 6 Design Vendor:

More information

MONTHLY MONITORING REPORT. World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York

MONTHLY MONITORING REPORT. World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York MONTHLY MONITORING REPORT World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York January 2014 PMOC Contract Number: DTFT60-09-D-00008 Task

More information

Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR)

Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR) Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR) Version 1.2 9/30/2010 Table of Contents IVR Instructions...3 Initial Entry Instructions...3 Permit Access Instructions

More information

Proposal for Construction Management and Inspection Services for the Mountains Recreation and Conservation Authoriy

Proposal for Construction Management and Inspection Services for the Mountains Recreation and Conservation Authoriy Proposal for Construction Management and Inspection Services for the Mountains Recreation and Conservation Authoriy To: August 6, 2012 To: Laura Saltzman Mountains Recreation & Conservation Authority Los

More information

Lake Charles Ward 3 Recreation Improvements To University Park

Lake Charles Ward 3 Recreation Improvements To University Park DATE APRIL 2015 Drawing Index A0.0 Cover Survey A1.0 Site Plan & Details A2.0 Pool Area Site Plan & Demo Plan A2.1 Pool Area Building Improvements A2.2 Pool Area Elevations & Wall Section A3.0 Basketball

More information

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are

More information

Architectural Design Standards Example Guide DESIGN STANDARDS EXAMPLE GUIDE

Architectural Design Standards Example Guide DESIGN STANDARDS EXAMPLE GUIDE Architectural Design Standards Example Guide DESIGN STANDARDS EXAMPLE GUIDE Commercial, Professional Office, and Public Facility Developments Purpose This Guide offers examples to clarify and explain the

More information

Planned Procurement Opportunities Report. June 2015

Planned Procurement Opportunities Report. June 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report June 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted

More information

State of Louisiana Residential Rehabilitation Tax Credit RS 47:297.6. Program Guidance

State of Louisiana Residential Rehabilitation Tax Credit RS 47:297.6. Program Guidance State of Louisiana Residential Rehabilitation Tax Credit RS 47:297.6 Program Guidance Effective January 1, 2006, homeowners may qualify for a 25% tax credit against their individual State income taxes

More information

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons)

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) DATE: March 8, 2006 TO: FROM: SUBJECT: Plan Commission Larry D. Nelson, P.E., City Engineer 5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) The City Engineering

More information

School Construction Authority Architecture & Engineering

School Construction Authority Architecture & Engineering SCOPING GUIDELINES 1.0 GENERAL GUIDELINES 2.0 BUILDING ENVELOPE SCOPING GUIDELINES 3.0 CATEGORIES AND COMPONENTS: The Flood Elimination/Below Grade Capital Category may include some or all of the following

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

PPM 591 HOME MODIFICATION

PPM 591 HOME MODIFICATION CONTENTS: 591.01 Purpose of Home Modification (p.1) 591.02 Qualifying Individuals (p.2) NATURE AND SCOPE OF ASSISTANCE 591.03 General Nature and Scope of Service Provision (p.2) 591.04 Home Modification

More information

NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1

NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 DISCLAIMER : The New York State Office of Parks, Recreation and

More information

Public Building Commission of Chicago. Board Meeting August 20, 2013

Public Building Commission of Chicago. Board Meeting August 20, 2013 Public Building Commission of Chicago Board Meeting August 20, 2013 Board Meeting August 20, 2013 Recent Events Enrico Tonti Elementary School Kindergarten Modular Opening August 5, 2013 Board Meeting

More information

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

More information

PARKVILLE HIGH SCHOOL LIMITED RENOVATION

PARKVILLE HIGH SCHOOL LIMITED RENOVATION PARKVILLE HIGH SCHOOL LIMITED RENOVATION DESIGN BRIEFING For Dr. Joe A. Hairston BALTIMORE COUNTY PUBLIC SCHOOLS August 11, 2009 Smolen 3 Emr + Associates Architects 1355 Piccard Drive, Suite 200 Rockville,

More information

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below

More information

Information for Construction Contractors. Terry O Neill Taxpayer Service Specialist

Information for Construction Contractors. Terry O Neill Taxpayer Service Specialist Information for Construction Contractors Terry O Neill Taxpayer Service Specialist Today s Webinar Definitions and details 4 types of contractors Sales tax for each type of contractor Materials, Equipment,

More information

COMMUNITY REDEVELOPMENT AGENCY FAÇADE IMPROVEMENT PROGRAM GUIDELINES

COMMUNITY REDEVELOPMENT AGENCY FAÇADE IMPROVEMENT PROGRAM GUIDELINES COMMUNITY REDEVELOPMENT AGENCY FAÇADE IMPROVEMENT PROGRAM GUIDELINES SEPTEMBER 2007 PURPOSE Clearwater s tropical environment provides many opportunities for festive activities and amenities for the downtown

More information

Single Family Residential Building Permit Questions & Answers

Single Family Residential Building Permit Questions & Answers Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday

More information

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone:

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: Choctaw Date Recorded: Permit # RESIDENTIAL - BUILDING Permit APPLICATION Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: YES NO Sec., Township, Range/Subdivision: Acres/Block:

More information

Concept Design Synopsis

Concept Design Synopsis Washington Headquarters Services Facilities Services Directorate The Pentagon Electric Upgrade (Substation No. 2) Concept Design Synopsis September 4, 2014 Prepared for Consultations with VA SHPO, ACHP,

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule

More information

How To Install An Overhead Sewer

How To Install An Overhead Sewer Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information