1 Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary School 22 Hazel Wolf K-8 at Pinehurst 33 Olympic Hills Elementary School 44 Seattle New World School at TT Minor 53 New Thornton Creek Building 64 October 30, 2015
2 Arbor Heights Elementary School Elementary School Site: SW 104 th Street is being prepped for concrete curbs, gutters and sidewalk; installation of temporary gravel access around South Building in progress. South Building: Exterior sheathing on-going floor 1. Light-gauge metal framing continues at the exterior and interior walls at floor 2. Hollow metal door frame installation ongoing on floor 2. Mechanical, electrical, and plumbing (MEP) rough-in ongoing at floors 1 and 2. Metal roof decking is being placed and welded. North Building: Installation of capillary break ongoing, concrete slab-ondeck poured at 3rd floor, structural steel erection ongoing, roof joists up to cafeteria have been welded.
3 Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015
4 Arbor Heights Elementary School Aerial View from the South September 30, 2015
5 Arbor Heights Elementary School South Building First Floor Exterior Sheathing Commenced October 26, 2015
6 Arbor Heights Elementary School South Building - Second Floor Interior Wall Installation October 26, 2015
7 Arbor Heights Elementary School South Building Second Floor Window Opening Blocking October 26, 2015
8 Arbor Heights Elementary School South Building - Metal Roof Deck Welding Ongoing October 26, 2015
9 Arbor Heights Elementary School South Building - Roof Welding October 26, 2015
10 Arbor Heights Elementary School North Building Capillary Break Ongoing October 26, 2015
11 Arbor Heights Elementary School North Building - Looking West towards Multi-Purpose and Gymnasium October 26, 2015
12 Arbor Heights Elementary School North Building - Third Floor Slab-on-Deck October 26, 2015
13 Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan
14 Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo
15 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Footings, Looking North West October 21, 2015
16 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Parking Lot Preparation, Looking South East October 21, 2015
17 Cascadia Elementary School & Robert Eagle Staff Middle School Forming Concrete Curbs at Elementary School Parking Lot October 21, 2015
18 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Concrete Retaining Wall, Looking South October 21, 2015
19 Cascadia Elementary School & Robert Eagle Staff Middle School Concrete Block Retaining Wall, East of Pilling s Pond October 21, 2015
20 Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Concrete Footings, Looking North October 21, 2015
21 Cascadia Elementary School & Robert Eagle Staff Middle School Woodlawn Avenue North Street Restoration Work for SPU October 21, 2015
22 Genesee Hill Elementary School Site: Excavation and installation of the sanitary sewer conveyance system ongoing; importing crushed rock to winterize site around the building. Area 1: Installation of windows ongoing; CMU veneer installation is complete; installation of spray foam insulation is complete; installation of GWB at level 1 is complete; installation of GWB at level 2 ongoing. Miscellaneous electrical rough-in ongoing. Area 2: Exterior and interior framing ongoing at floors 1 and 2; exterior sheathing installation ongoing; HVAC ductwork installation at mechanical mezzanine ongoing; MEP is ongoing. Area 3: Foam insulation installation at exterior walls ongoing; interior wall framing ongoing; MEP ongoing. Area 4: Exterior framing and sheathing complete; MEP is ongoing.
23 Genesee Hill Elementary School Site Plan 4
24 Genesee Hill Elementary School Aerial View October 15, 2015
25 Genesee Hill Elementary School Installation of Deepest Manhole for Sanitary Sewer Conveyance System
26 Genesee Hill Elementary School Area 1 - North Elevation Envelop System Installation
27 Genesee Hill Elementary School Area 1 - Floor 3 Gypsum Wallboard Installation Ongoing
28 Genesee Hill Elementary School Area 2 - Level 1 Main Entry Stairs
29 Genesee Hill Elementary School Area 2 - Interior Wall Framing at Library
30 Genesee Hill Elementary School Area 2 - Mechanical Mezzanine Installation of HVAC Ductwork
31 Genesee Hill Elementary School Area 2 - Installation of Metal Panels at Roof Fascia
32 Genesee Hill Elementary School Area 4 - Gym and Commons
33 Hazel Wolf K-8 at Pinehurst Site: Side sewer installation ongoing, backfilling around concrete foundations, general site clean up. Building A: A1 concrete slab completed. Area A2 metal stud framing ongoing on first and second floors and penthouse, MEP installation ongoing. A3 final concrete footings formed and poured, concrete stem wall pours ongoing, waterproofing started and installation of utilities under slab ongoing. Building B: Structural steel for the outside play area completed. Roof decking started. Building C: Metal roof decking installation completed. Skylight frames installed welded and completed. Slab on deck for 2 nd floor (child care) area concrete pour completed.
34 Hazel Wolf K-8 at Pinehurst Site Plan
35 Hazel Wolf K-8 at Pinehurst Aerial View looking North West
36 Hazel Wolf K-8 at Pinehurst Area A2 Looking North West October 20, 2015
37 Hazel Wolf K-8 at Pinehurst Area A2 First Floor Interior Framing October 21, 2015
38 Hazel Wolf K-8 at Pinehurst Area A2 First Floor Floor Grinding October 21, 2015
39 Hazel Wolf K-8 at Pinehurst Area A2 Penthouse October 22, 2015
40 Hazel Wolf K-8 at Pinehurst Area A2 Penthouse Roofing October 21, 2015
41 Hazel Wolf K-8 at Pinehurst Area A3 Admin Concrete Stem Wall October 20, 2015
42 Hazel Wolf K-8 at Pinehurst Area B Structural Steel October 21, 2015
43 Hazel Wolf K-8 at Pinehurst Area C Gym Metal Deck and Skylights October 20, 2015
44 Olympic Hills Elementary School Site Plan
45 Olympic Hills Elementary School Aerial Photo October 15, 2015
46 Olympic Hills Elementary School Removing Soil Stockpile, Looking South October 21, 2015
47 Olympic Hills Elementary School Underground Detention Vault Backfilled and Covered, Looking North October 21, 2015
48 Olympic Hills Elementary School Manhole at Detention Vault October 21, 2015
49 Olympic Hills Elementary School Underground Utilities, Looking West October 21, 2015
50 Olympic Hills Elementary School Geothermal Well Drilling, Looking East October 21, 2015
51 Olympic Hills Elementary School Geothermal Well Drilling, Looking South October 21, 2015
52 Olympic Hills Elementary School Site View, Looking South October 21, 2015
53 Seattle World School at T.T. Minor Area A Administration Office, Student Services, Health Clinic and Library: Administration office addition concrete footings poured, underground utilities ongoing, temporary shoring installed. Health Clinic underground utilities ongoing, concrete grade beam complete. Library demolition complete. Area B Multipurpose, Kitchen, Boiler Room: Concrete stem wall pour complete, concrete slab preparation ongoing. Boiler Room hazardous material abatement complete, demolition ongoing. Area C Classrooms: CMU wall layout ongoing, CMU rebar installation ongoing, underground utilities complete, CMU grade beams complete, 2 nd floor demolition ongoing.
54 Seattle World School at T.T. Minor Site Plan
55 Seattle World School at T.T. Minor Area A - Administration Addition Concrete Footings Poured October 27, 2015
56 Seattle World School at T.T. Minor Area A Original Building Seismic Footing Retrofit Concrete Pour October 27, 2015
57 Seattle World School at T.T. Minor Area A Administration Area Temporary Shoring October 27, 2015
58 Seattle World School at T.T. Minor Area A Library Hazardous Material Abatement and Demolition Complete October 27, 2015
59 Seattle World School at T.T. Minor Area A Health Clinic Underground Utilities Ongoing October 27, 2015
60 Seattle World School at T.T. Minor Area B New Kitchen and Commons Addition Slab Preparation October 27, 2015
61 Seattle World School at T.T. Minor Area B Boiler Room Abatement Complete Demolition Ongoing October 27, 2015
62 Seattle World School at T.T. Minor Area C Science Classrooms Underground Utilities Complete October 27, 2015
63 Seattle World School at T.T. Minor Area C 2 nd Floor Demolition Ongoing October 27, 2015
64 New Thornton Creek Building Site: Continued installing footing drainage piping and downspouts. Continued remove excess soil stockpile. Began Phase 2 geothermal well drilling in playfield north of the parking lot. Building A: Continued with interior backfill around footings. Began installing below grade masonry around footing. Set subgrade for remaining concrete slab-on-grade. Building B: Continued erecting structural steel in both library and two story academic wing. Began placing steel joist and decking in both library and first story of two story wing. Place edge form for slab-on-deck. Building C: Continued interior framing on classrooms. Continued installing interior hollow metal window frames in hallway for classrooms. Began installing roof. Continued installing HVAC ductwork and above ceiling plumbing and electrical. Continued with MEP rough-in in classroom walls.
65 New Thornton Creek Building Key Plan
66 New Thornton Creek Building Aerial Photo October 15, 2015
67 New Thornton Creek Building Inserting Piping into Geothermal Well
68 New Thornton Creek Building Building A Preparing to Place Below Grade Masonry
69 New Thornton Creek Building Building C Installing Backing to Interior Framing
70 New Thornton Creek Building Building C Installing Hollow Metal Frames for Interior Windows
71 New Thornton Creek Building Building C Electrical Rough-in
72 New Thornton Creek Building Building C Installing Exterior Sheathing to Parapet
73 New Thornton Creek Building Building C Roofing
74 New Thornton Creek Building Building C Hot Mopping Asphalt on Roof
Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components
Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development
More informationSAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT
SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer
More informationName of course: Residential Construction Site Management (RCSM) Level 1
Name of course: Residential Construction Site Management (RCSM) Level 1 Core (required courses) or Optional (elective course): Required Delivery Method: This is an online course only with no classroom
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5
Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012 Geo-Thermal
More informationREQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update
REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management
More informationSlavic Village Building Condition Review
Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities
More informationEstimating Database Checklist
Estimating Database Checklist If you are creating a new estimating database for projects, the following list offers a thorough listing of Main and Sub Categories. You can also use it as a checklist to
More informationEAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
More informationMTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
More informationMarch 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
More informationNAHB 1-00-0000 PRODUCT DEFINITION
NAHB Standard Homebuilder Cost Codes Cost Code Description 1-00-0000 PRODUCT DEFINITION 1-01-0000 PREAQUISITION COSTS 1-01-0110 Feasibility Study 1-01-0120 Environmental Impact Study 1-01-0130 Option Fees
More informationAdditions and Alterations
Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal
More informationThe Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE
The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE BUILDING SERVICES DEPARTMENT 789 Broadway Street, Box 3000 Wyoming, ON N0N 1T0 Telephone: 519 845-0801 Toll-free: 1-866-324-6912 Fax: 519
More informationOPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY
Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic
More informationConstruction Technologies Career Field Pathways and Course Structure
Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry
More informationKIEWIT CM/GC Enabling/Utilities
South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 john.todd@kiewit.com General
More informationDRAPER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationSCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationCOMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS
COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications
More informationElevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
More informationSECTION 3 ONM & J STRUCTURAL ANALYSIS
Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION
More informationThe minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
More informationCITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST
CITY OF BERKELEY DETAILED CHECKLIST This checklist will assist you in preparing plans for submittal with a building permit application. Alterations, additions and remodeling projects may not require all
More informationC-2 Construction, Inc. - NAICS Codes
C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining
More informationSchedule B to By-law 33-2009
Amended by By-law 8-2016 Note: This consolidation is prepared for convenience only. For accurate reference the original by-laws should be reviewed. Floor Area Calculation Floor area shall: Schedule B to
More informationCherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016
Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Year Opened 2003 Current Square Footage 391,000 Site Acreage 86.22 cherokeetrail.cherrycreekschools.org $279,200 Asphalt and concrete
More informationLindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1
School Facilities Evaluation Project Page 1 Executive Summary In November 1999, Alberta Infrastructure, School Facilities Branch engaged Stephens Kozak Carr and Brown Architects to conduct evaluations
More information1. Maintenance. Mechanical, Electrical & Plumbing Improve ligh>ng control an sensoring $230,239
1. Maintenance Building Component Detail Est. Cost. Alkali Building Envelope Replace windows $40,425 Replace worn and rippling carpet $81,335 Improve ligh>ng control an sensoring $230,239 Repair and replace
More informationPage & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
More informationSaint Cloud Business Center
Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with
More informationHIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL
HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone
More informationWOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME
WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME 1 THE BUILDING PROCESS The focus of Woodland Homes building department is Quality, Service and Predictability. Through
More informationSODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
More informationSECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request
SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table
More informationOPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003
OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationWhen is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:
When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory
More informationBasement Moisture Problems
Foundations Foundation Purpose The purpose of a foundation is to distribute the weight of a structure securely into the ground. Engineering data regarding soil, rock and water conditions are used to design
More informationVeterans Memorial Coliseum Options Study Appendix A - Deconstruction Scope of Work and Cost Estimate August 31, 2015
Stage 1 DA.01 Fencing and cameras deployed Baseline - 3-5 years for Stage 1 for purposes of this study costs are described for a 3 year period $45,000 $0 Stage 1 DA.02 Secure all building doors and access
More informationEngineered Wood Foundations
Engineered Wood Foundations Emeraldfoundations.com 1 EWF Planning and Installation manual This manual will serve as a guide to planning and installing an Emerald Foundation system. This system is comprised
More informationSingle Family Residential Building Permit Questions & Answers
Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday
More informationEstimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
More informationMURCH ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationD Sample Notices to Property Owners, Sample Affidavits, and Other Material
D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully
More informationExecutive Summary. June 2005 Auke Bay Elementary School Condition Survey Report Page 4 of 228
Building History 1. The original building was built in 1968. It is essentially a 2 story building built into a hillside. A portion of the second floor steps up the hill a half level above the second floor
More informationDAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN
DISTRICT "SHELL" SUBMISSION DATE: 11/13/12 questions 11/26/12 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 11/19/12 revised 11/26/12 (delete following Hearing) KBE APPROVAL DATE: FEBRUARY
More informationSECTION 00335 EXISTING HAZARDOUS MATERIALS CONDITIONS
PART 1 GENERAL 1.01 SUMMARY SECTION 00335 EXISTING HAZARDOUS MATERIALS CONDITIONS A. This section provides a list of known and assumed hazardous materials that may be impacted during renovation, demolition,
More informationEFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection
EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED
More informationVision Home Inspection
Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the
More information17,280 square feet Overview:
CENTRAL OFFICE Located at 167 Boston Post Road, East Lyme, Connecticut, the Central Office was built in 1916 as the original Flanders Elementary School and remains connected to the current school. The
More informationPoint Auditorium Design Narrative PROJECT NAME: Point Auditorium DATE: 06/25/15 TO: Lance Francis FROM: Leslie Ellsworth
INTRODUCTION: Kronberg Wall Architects is pleased to present the Design Narrative for the Point University Auditorium conversion from the existing warehouse space. General Project Description: This project
More informationBuilding, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements
Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule
More informationStructural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
More informationRehab Inspection Report Page 1
Rehab Inspection Report Page 1 Home Address: Construction Style: Number of bedrooms Square footage: Value of offer: Estimated rehab cost: Value of resale: Orientation of house: N S E W Note: orientation
More informationSample Drawing Package for One and Two Family Dwelling Applications
Sample Drawing Package for One and Two Family Dwelling Applications For a full list of submission requirements, refer to the relevant checklist for your application found on our website: http://vancouver.ca/home-property-development/application-forms-and-checklists.aspx
More informationCLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.
CLIENT Inspection Report 271 Front St. Alert Bay, B.C. Island Building Inspections 2013 V ANCOUVER I SLAND B. C. Elevation Photos For the Property at 271 Front Street Alert Bay, BC ELEVATION PICTURES Front
More informationSchool Construction Authority Architecture & Engineering
SCOPING GUIDELINES 1.0 GENERAL GUIDELINES 2.0 BUILDING ENVELOPE SCOPING GUIDELINES 3.0 CATEGORIES AND COMPONENTS: The Flood Elimination/Below Grade Capital Category may include some or all of the following
More informationSchool Facilities Referendum Recommendations
Haddonfield Public School District LONG RANGE PLANNING COMMITTEE School Facilities Referendum Recommendations NOVEMBER 19, 2015 School Facilities Referendum Recommendations Tonight s goals Presentation
More informationOctober 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.
117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This
More informationHartsfield-Jackson Atlanta International Airport s
Hartsfield-Jackson Atlanta International Airport s 2008-09 Closed Projects (Posted 1/6/2009) FC-3007000038C: MISCELLANEOUS BUILT-UP ROOF AND SINGLE PLY ROOF REPAIRS AT H-JAIA Furnish all labor, equipment,
More informationAll substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.
2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other
More informationOSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION Table of Contents Executive Summary... 1 Introduction... 1 Installing
More informationHunter College school of Social Work Thesis Proposal
Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing
More informationProject Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT February 2015 Project Management Division BELOW: Collins Construction crews complete recent exterior work and await delivery of exterior siding. Collins
More informationCertification: Building Plans Examiner. Exam ID: B3
Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building
More informationBuilding Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
More informationNATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES
NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES All searches and notifications on Bid4Michigan are based on National Institute of Government Purchasing (NIGP) codes. It
More informationDavid C. Barrow Elementary School 100 Pinecrest Drive, Athens, GA 30605
David C. Barrow Elementary School 100 Pinecrest Drive, Athens, GA 30605 Winner of the 2014 Cold-Formed Steel Engineers Institute (CFSEI) Design Excellence Award May 2014 The David C. Barrow Elementary
More informationREVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
More informationFacility Assessment for. 11801 East Main Street, Huntley, IL
Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested
More informationSt. Louis County Department of Public Works Division of Code Enforcement. When is a Building Permit required for Residential Projects?
St. Louis County Department of Public Works Division of Code Enforcement When is a Building Permit required for Residential Projects? BUILDING CONSTRUCTION WORK A Building Permit is required to construct,
More informationSCHEDULE A BY-LAW B-6 CLASSES OF PERMITS AND FEES
1. CALCULATION OF PERMIT FEES SCHEDULE A BY-LAW B-6 CLASSES OF PERMITS AND FEES Permit fees shall be calculated based on the formula given below, unless otherwise specified in this schedule: Permit Fee
More informationHolz Choices & Specifications
March 21, 2011 0. SALES AND DESIGN 1. UTILITIES AND PERMITS Holz Choices & Specifications 2. EXCAVATION AND LOT PREPARATION Job Beginning date of Monday May 2 nd, 2011 ALTERNATE: Garage walls as drawn
More informationCity of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage
City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number
More informationPresentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals
Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals Les Butler Associate Commissioner for Business and Regional
More informationSchedule B to By-law 33-2009 Part A Fees Payable for Permits
Floor Area Calculation Floor area shall: Part A Fees Payable for Permits (Effective January 1, 2015) a) be calculated by measuring to the outer face of exterior walls and to the centre of party walls or
More information4. ANCHOR BOLTS AND STRAPS a. ½" anchor bolts shall be embedded 7" into concrete a maximum of 6' on center and 12" from corners and ends of plates.
GENERAL CODE REQUIREMENTS (BASEMENTS) 1. FOOTINGS a. Footings shall be below frost line depth (42"). b. For an 8" foundation wall, footings shall be no less than 8" deep and 16" wide. c. Steel reinforcement
More informationOHLONE COMMUNITY COLLEGE BOND MEASURE G
Monthly Report OHLONE COMMUNITY COLLEGE BOND MEASURE G Fremont, California June 2014 TABLE OF CONTENTS 1. Executive Summary 2. Safety Status 3. Schedule Status 4. Design Progress 5. Construction Progress
More informationCAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT RIGHT: the proposed conceptual profile of the new Joe Redington Sr. JR/SR High School January 2014 Project Management Division New Knik Area Middle/High
More informationLITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -
The original section of this building was constructed in 1941. The exterior walls are built of good quality stone. In the early 1980 s a similar addition was added to the north elevation. The exterior
More informationwww.citiesinspection.com October 5, 2015 Dear Client,
www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.
More informationCommercial Building Valuation Report
INSURED University of Houston - Victoria Effective Date: Expiration Date: Cost as of: 09/2010 BUILDING 1 217 - University Center 77901 Location Adjustments Climatic Region: High Wind Region: Seismic Zone:
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationMequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule
Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal
More informationA Homeowner s Guide to Building Permits
A Homeowner s Guide to Building Permits Building Division City of London 300 Dufferin Ave. P.O. Box 5035 London, ON N6A 4L9 Table of Contents What is a Building?... 3 Planning Your Project... 3 When is
More informationEstimated Useful Life (EUL) Tables
3900 Wisconsin Avenue, NW Washington, DC 20016-2892 INSTRUCTIONS FOR PERFORMING A MULTIFAMILY PROPERTY CONDITION ASSESSMENT (Version 2.0) APPENDIX F ESTIMATED USEFUL LIFE TABLES These Estimated Useful
More information2009 IECC Update. Scope. Content. International Energy Conservation Code
2009 IECC Update International Energy Conservation Code Scope The code applies to both residential and commercial buildings. In the code, the United States is divided into eight climate zones which are
More informationPROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)
APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL FIRE RESTORATION PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of
More informationMULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3
TOWN OF SIDNEY Multi-Family, Commercial, Industrial and Institutional Building Permit Guide The information provided is intended as a guide only and does not replace current bylaws and regulations. Complete
More informationCOST OF WORK FORM. Abbreviations: ea = each, LF = linear feet, SF = square feet, HSF = square feet of living area (including garage conversion space)
COST OF WORK FORM All costs shown are estimates using base grade materials, taxes, and labor. For houses where a higher quality is indicated, the costs should be increased for work requiring upgraded materials.
More informationHOMEOWNER S PERMIT GUIDE
HOMEOWNER S PERMIT GUIDE WHEN IS A PERMIT REQUIRED? Department of Development and Permits 306 Cedar Road, City Hall 2 nd Floor P.O. Box 15225 Chesapeake, VA 23328 Phone: (757) 382-6018 Fax: (757) 382-8448
More informationArchitectural Inspection Site Structures
0141 Freestanding Shelters Open air shelters not attached to the building. Bike rack shelter with bike racks: This 8'x30' structure is located on the north east side of the building on the wooded landscape
More informationBuilding Condition Assessment Report
C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses
More informationThe better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
More informationTAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE
TAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE 1/22/2008 1 STORES & COMMERCIAL BUILDINGS 1. General Construction Class Descriptions 2. Types a. Class A - Fireproofed
More informationCommon Problems with Walls
Common Problems with Walls Common Problems with Walls There are problems and concerns that are shared by all walls and siding installations. In this article, we will learn about the following commonly
More informationPDmB, Inc. Definitions
Page 1 of 11 Definitions S Satisfactory Meets industry standards for proper material and installation NP Not Present Condition or item was not present at time of inspection NI Not Inspected Condition or
More informationFEASIBILITY STUDY COST PLAN. for. Fresno Library Feasibility Study Fresno, California
FEASIBILITY STUDY COST PLAN for Fresno Library Feasibility Study August 29, 2002 August 29, 2002 Cynthia Ripley Ripley Architects 1730 Franklin Street Suite 103 Oakland, California 94612 Fresno Library
More informationExhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza