AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate



Similar documents
Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel

WSSC Ad-Hoc Committee on Large Diameter Water Mains. August 2, 2013

Meeting the Challenge of Pipeline Emergency Repair

Force Main Condition Assessment: New Technologies & Case Studies

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Chesapeake Section AWWA Symposium

Prestressed Concrete Pipe Fitness for Service and Repair

Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

SECTION 3 SANITARY SEWER DESIGN

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

DEPARTMENT OF ENVIRONMENTAL QUALITY

Sanitary Sewer Master Plan

Pipeline Asset Management: From Assessment to Prioritized Projects List

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C.

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

WEKO-SEAL Internal Joint Sealing WEKO-SEAL. internal pipe-joint sealing

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT

Contracting Opportunities Vendor Day May 17, 2011

Funding the Vision: Investing in Safe, Reliable Service

Wastewater Capital Projects Management Standard Construction Specification

SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM

Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems.

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES

Rehabilitation or Replacement? That Is The Question

Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES

Township of Enniskillen. Asset Management Plan

RESPONSIBLE DEPARTMENT: ADDITIONAL DIRECTOR (S): ASSISTANT CITY MANAGER: JIM CALLAWAY

COLLECTION SYSTEM SETTLEMENT AGREEMENT

North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show. Orlando, Florida April 13-17, 2014

RESTRICTING GROUNDWATER WITHDRAWALS TO PROTECT WATER RESOURCES: ECONOMIC IMPACT ASSESSMENT

Bridges & Culverts Condition by Quantity

Section SEWER PIPE INSTALLATION AND TESTING

TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT

Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

Emerging Technologies in Wastewater Collection Systems

Using Risk-Based GIS Modeling Software to Optimize Sewer Renewal Planning

At the end of today s seminar you should be better. Recognize the causes of Sewer Lateral backup. Identify techniques to protect your home from

SANITARY SEWER SYSTEM ASSESSMENT

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida

CLEANING, INSPECTION, AND TESTING OF SEWERS

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

SEWER CLEANING, INSPECTION AND ASSESSMENT

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort

HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS

Water Main Lining A Sustainable Alternative to Open Cut Replacement

Design Criteria & Service Goals

Best Practices Manual for Prestressed Concrete Pipe Condition Assessment: What Works? What Doesn t? What s Next?

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

SOCALGAS APROACH TO PIPELINE INTEGRITY

49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards

City Code citations from various small, medium and large cities on ownership of sewer service connections:

Dry Weather Flow from Footing Drains and Service Connections

Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective

SECTION PRECAST CONCRETE UTILITY STRUCTURES

ASSET MANAGEMENT PLAN Published January 2009

MEMORANDUM. General: Foundation:

CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN

Houston Asset Management In The Fast Lane: Final Report

Let Us Give Utilities the Respect that they Deserve.

Bulletin. Gerard D. Perry, Director of Accounts. DATE: August Sewer Rate Relief Fund FY2015

INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By

The Original Carbon Fiber Reinforced Polymer System

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

Transcription:

AGENDA ITEM C9 DATE: February 2, 2015 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles Carden, Chief Operating Officer South Pasco Transmission Main Condition Assessment Services with Pure Technologies U.S. Inc. - Approve SUMMARY: A desktop analysis of the pipelines in Tampa Bay Water s Pre-stressed Concrete Cylinder (PCCP) system was completed to prioritize pipelines for inspection based on relative condition and consequence of failure. Staff has negotiated a scope of services for condition assessment of the South Pasco Transmission Main with Pure Technologies U.S. Inc. RECOMMENDATION: Approve condition assessment services for the South Pasco Transmission Main with Pure Technologies U.S. Inc. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate DISCUSSION: A desktop analysis of the pipelines in Tampa Bay Water s Pre-stressed Concrete Cylinder (PCCP) system was completed by AECOM to prioritize pipelines for inspection based on relative condition and consequence of failure. The South-Central Hillsborough Regional Wellfield Transmission Main had the highest priority, and was the first piping to be inspected as part of this program in April 2013. The Cypress Creek Wellfield Collection Main condition assessment was completed in July 2014. The South Pasco Transmission Main was constructed as multiple sections between 1971 and 2004 and has a medium risk of failure based on potential condition and risk of failure as determined by the desktop analysis. This pipeline is critical to Tampa Bay Water s system because it provides regional supply to Hillsborough County s Fawn Ridge and Lake Park delivery locations and to St. Petersburg s Cosme Water Treatment Plant and is the pipeline that conveys the South Pasco Wellfield supply through the regional system. Due to the length of this pipeline, staff intends to perform the assessment over two budget years. During FY 2015 5.8 miles of the Transmission Main will be assessed. There is currently only one vendor, Pure Technologies U.S. Inc. that provides condition assessment services for PCCP while keeping the line in service. Tampa Bay Water is using the terms, conditions and unit rates of the $5.8 million dollar Miami-Dade Contract BW9537-0/16 for pipeline condition assessment that was awarded February 15, 2012 and expires February 28, 2017. This is the same procedure used previously to assess the South- Central Hillsborough Regional and Cypress Creek Wellfield Collection mains. These attached scope of services will include a detailed plan for the assessment, insertion and extraction of the devices in the pipe, a detailed report of the damage and leaks found, a

Matt Jordan February 2, 2015 Page 2 prediction of the rate of future damage and failure, and a recommendation for the repair priority of any damaged or leaking pipe sections. The results of the condition assessment may lead to repair of the areas of poor condition. Recommended repairs will be included in a future renewal and replacement project for portions of the South Pasco Transmission Main. BACKGROUND: Buried pipelines comprise approximately 80% of Tampa Bay water s total agency assets. These pipes vary in age and material. Tampa Bay Water and many other Municipalities have had failures of Pre-stressed Concrete Cylinder Pipe (PCCP). PCCP is constructed with a steel cylinder wrapped with pre-stressed wires, which is coated and lined with cement. Failure of PCCP can occur due to corrosion of the pre-stressed wires, caused by low-grade materials of construction, or damage during original transport and installation. For example, the 20 mile long Cypress Creek Transmission Main was replaced in its entirety due to multiple pipeline failures and its critical position in the system. It would be extremely costly to replace all of the remaining 62 miles of PCCP in our system. Advanced condition assessment technologies have been developed over the years to help utilities identify where pipe future failures are more likely to occur. This will allow staff to target pipe section for repair or replacement rather than a more expensive replacement of the entire pipeline. Attachment

Suzannah Folsom, P.E. January 29, 2015 Tampa Bay Water 2575 Enterprise Road Clearwater, FL 33763 Dear Ms. Folsom: Pure Technologies U.S. Inc. (Pure) is pleased to offer our services to Tampa Bay Water (TBW) for pipeline assessment. We understand that TBW would like to assess the condition of the South Pasco Transmission Main (pipeline). The pipeline is constructed of prestressed concrete cylinder pipe (PCCP) and was installed in stages between 1961 and 1975. According to the plans provided by TBW, the pipeline to be assessed consists of the following diameters and lengths: South Pasco o 42-inch 30,500 linear feet or 5.78 linear miles (Note: 1.18 miles of this section is a Steel pipeline and only SmartBall will be analyzed). The total distances listed above are according to a preliminary review of the pipeline asbuilt plans. Accessibility to the pipelines will be confirmed following a field visit and the total distance of assessment will be confirmed after the analysis of the collected data. The pipeline will be inspected in one mobilization and are tentatively scheduled to occur after March 1, 2015. A detailed project plan will be provided to TBW upon acceptance of this scope of work. In the interim, the preliminary plan for South Pasco will be to insert the equipment through the access manhole at Station 98+65 on the 42-inch main (C-42 drawings). Extraction is suggested at an access manhole located at 36-inch main at approximately Station 219+69 (C-35 drawings). Details for the insertion and extraction shall be coordinated with TBW but if feasible, should include a temporary shut down and depressurization by TBW. 1 P a g e

This project will deliver to TBW the following: 1. The number of broken prestressing wire wraps in each inspected pipe section as well as any leaks found. 2. A performance curve for each pipe design class/soil depth combination for each pipe design with broken pre-stressing wires calculated using a 3-D non-linear finite element analysis 3. A structural engineering analysis detailing the repair priority for each pipe section with broken prestressing wire wraps. This report will provide TBW: A. Categorization of the structural damage found, allowing TBW to prioritize its rehabilitation program and allocate funds accordingly in an emergency and/or an annual basis. B. Information needed to extend the useful life of their pipelines using the information as a starting point for a root cause analysis if the pipeline is deteriorating. 2 P a g e

Cost Estimate Pure will deliver the electromagnetic inspection on the PipeDiver platform; leak detection will be performed on the SmartBall platform. TBW will be contracting Pure through an agreement Pure currently has with the Miami-Dade Water and Sewer Department (WASD). The terms and conditions associated with the assessment for TBW are based on the contract approved for WASD by the Miami-Dade County Department of Procurement Management (Master Agreement BW9537-0-16). The cost for this project is referenced in Appendix B of this Master Agreement and is detailed in the table below. Service Quantity Unit Cost Total Cost PipeDiver/Smartball Mobilization & Planning 1 $85,000.00 $85,000.00 Inspection/Analysis/Reporting: 4.60 miles $69,984.00 $321,926.40 South Pasco SmartBall only 6,230 linear $4.00 $24,921.00 feet Total $431,847.40 TBW and Pure s responsibilities are detailed in the Master Agreement, Appendix A. We look forward to providing these specialized services. If you have any questions or concerns, please do not hesitate to contact me. Regards, Mike Garaci 416-574-4446 mike.garaci@puretechltd.com 3 P a g e