WSSC Ad-Hoc Committee on Large Diameter Water Mains. August 2, 2013
|
|
|
- Alison Boyd
- 10 years ago
- Views:
Transcription
1 WSSC Ad-Hoc Committee on Large Diameter Water Mains August 2, 2013
2 Purpose: To Gain an Understanding of WSSC s Current Approach to PCCP Inspections, Monitoring and Repair/Replacement 2
3 PCCP Management Program PCCP Management Program: An Asset Management Strategy for 36-inch and Larger PCCP Water Transmissions. Program First Established in Early 1980 s. In 2007, WSSC Initiated the Current Program Strategy using a 5-Year Inspection Plan. Program Objectives: PCCP Pipeline Condition Assessment and Monitoring for Maintenance Repairs and Long Term Capital Planning. Ensures Timely Routine Inspection and Repairs. Ensures the Pipelines Reach Their Useful Life. Provides Safer, More Reliable Water Supply. 3
4 Focus of PCCP Management Program PCCP Management Program Focus WSSC has 357 Miles of Pre-Stressed Concrete Cylinder Pipe (PCCP) Water Mains. Program Focuses on 145 Miles of 36-inch and Larger Which Includes: 77 miles 48 and Greater 68 miles 36 and 42 Inspection Goals and Intervals Annual Inspection Mileage Goal is Currently 18 miles. By the end of 2013, all Pipelines 48- inch and Larger will have been Inspected, Repaired and Equipped with AFO monitoring. Majority of PCCP Water Mains 54-Inch and Greater have been Inspected Between 1 to 3 times and a few of the more Problematic Mains have been Inspected 4 to 5 times. Mains 48-inch and Larger are on a 5 to 7 Year Inspection Cycle Depending on AFO Wire Break (WB) Data. Inspection of Mains 36 and 42-inch Began in 2013 and are on an 8 to 10 Year Inspection Cycle also Depending on AFO WB data. They will also be Equipped with AFO Monitoring Following Inspection. 4
5 Program Logistics Timing: Internal Inspections are Typically Performed During Periods of Lesser Water Demand Between October through May. Inspections: Mains 48-inch and Larger are Manned and Require Complete Pipeline Dewatering. Mains 36 and 42-inch are Robotic and can be Done Fully Pressurized or Partially Dewatered. Testing Methods: Mains 48-inch and Larger Includes Visual and Sounding, Sonic/Ultrasonic, Electromagnetic, and Acoustical Leak Testing. Mains 36 and 42-inch Includes Visual if Not Pressurized, Electromagnetic and Acoustical Leak Testing. Repairs/Replacements: Damaged Pipe Sections are Either Repaired or Replaced Prior to Placing Main Back in Service. Acoustical Fiber Optic Monitoring (AFO): Permanent AFO Monitoring Installed to Detect Wire Break Activity in Mains 36-inch and Larger. 5
6 Visual and Sounding 48-Inch and Larger Visual and Sounding: (48-inch and Larger) Pipe Numbering for Documentation and AFO Monitoring, Lay Schedule. Visual Inspection for Defects. Sounding Inspection for Hollows. 6
7 Manned Electromagnetic 48-Inch and Larger Manned Electromagnetic Testing: (48-inch and Larger) Locate/Estimate the Number of Broken PCCP Wires Establish Baseline for AFO Monitoring 7
8 Robotic (Crawler) Electromagnetic 36 and 42-inch PCCP Robotic Crawler Electromagnetic Testing: (36 and 42-inch) Locate/Estimate the Number of Broken PCCP Wires. Establish Baseline for AFO Monitoring. Includes Visual Camera Inspection. Partially Dewatered Main. 8
9 Robotic (Free-Floating) Electromagnetic 36 and 42-inch PCCP Robotic (Free-Floating) Electromagnetic Testing: (36 and 42-inch) Locate/Estimate the Number of Broken PCCP Wires. Establish Baseline for AFO Monitoring. Does Not Include Camera Inspection. Fully Pressurized Main. 9
10 Sonic/Ultrasonic Testing 48-Inch and Larger Sonic/Ultrasonic: (48-inch and Larger) Locate Delamination, Poor Pipe Composite, Concrete Defects. Run in Parallel to Electromagnetic. Follow-up Detailed Testing. 10
11 SmartBall - Acoustical Leak Testing Acoustical Leak Testing: (36-inch and Larger) Deployed/Retrieved in Pressurized Main Free Floating. Requires all Branch Valves to be Closed. Pinpoints Acoustical Leaks. Leaks Repaired Following Main Dewatering. 11
12 Actions Following Inspection Internal Inspection Data Analysis FEA* Curve for Each Pipe Class High to Moderate Level Damage Low Damage No Damage Repair or Replace by Planned Emergency Acoustic Monitoring * Finite Element Analysis
13 Repairs or Replacements Following Inspection The Pipe Sections Found with a High to Moderate Level of Damage as Determined by the Finite Element Analysis Curve are Repaired or Replaced. Repair versus Replacement is Based Primarily on Location of Pipe for Excavation. Replacements: Ductile Iron or PCCP Repair Kit used for Pipe Sizes 54-inch and Below. PCCP Repair Kit used for Greater than 54-inch (Non-DIP Sizes). Repairs: Primarily Internal with Full Stand Alone Carbon Fiber Composite. All Repairs and Replacements are Permanent for the Life of Pipeline. 13
14 Internal Repair with Carbon Fiber Composite 14
15 PCCP Replacement with PCCP Repair Kit PCCP Repair Kits are Not Pre-Stressed Pipe Made of Steel Pipe with Concrete Encasement 15
16 PCCP Replacement with Ductile Iron Pipe 16
17 Acoustical Fiber Optic Monitoring AFO Monitoring Installed Following Pipe Repairs/Replacements. Requires Electric Power and Communication Line for Data Reporting. Data Acquisition and Communications Cabinet in a WSSC Water Pumping Station d Fiber Optic Cable Installed Inside Pipe 17
18 Acoustical Fiber Optic Monitoring Data Acquisition and Communications Wire/Power Connections Back of Data Acquisition Unit 18
19 Electronic Wire Break Alert The SoundPrint Data Processing Center has classified a Wire Break event for the monitoring station at WSSC-PAFO48. Event Data Site: WSSC-PAFO48 Date / Time: Jul 17, :56:47 Eastern Standard Time Event Classification: Wire Break Location: PFO48 (13) Station # 4+87 Pipe Data Pipe Diameter: 48 " Pipe Class: PCCP Repaired: No Replaced: No Inspected (Electromagnetic): Dec 10, 2010 Charts and Maps Project Overview Map: Zoomed Location Map: Pipe Location Maps Are Not Shown 19
20 AFO Wire Break Data Analysis Data Analysis Process: Acoustical Wire Breaks Go Directly to Pure Technologies Calgary Office for Analysis. Baseline Wire Break Count added to AFO Wire Breaks. Compared to FEA Curve for that Pipeline. No Concern: No Action Concern: WSSC is advised by Pure Technologies of Recommended Action. 20
21 Acoustical Fiber Optic Monitoring What Does it Do? Monitors Acoustical Pre-Stressed Wire Break Activity. Coupled with Baseline Determines Rate of Deterioration. Used to Prioritize/Adjust PCCP Inspection Schedule. Provides Advance Notice of Pending Pipe Failure to Initiate Proactive Response. What Does it Not Do? Prevent Deterioration. Monitor for Pipe Leaks. Guarantee a Pipe Will Not Fail. 21
22 How do the Pipes Fail? What are the Causes of Failures? PCCP Pipe Fails Catastrophically Typically as Result of Long Term Deterioration or a Compromise of the Composite Pipe Structure. Common Causes of PCCP Failure: Most Common Failure Mechanism: Pre-Stressed Wire Corrosion Leading to Progressive Wire Failures then Cracked Concrete which leads to Corrosion and Failure of Steel Cylinder, Miscellaneous Manufacturing Defects. Pre-Stressed Wire Corrosion: Electrochemical Corrosion: Common Corrosion due to Exposure to Ground Water or Potable Water. Occurs when the PCCP Concrete Mortar Coating is Damaged or Compromised. Hydrogen Embrittlement: Brittle Tensional Failure of Wire due to Exposure to Hydrogen Unintentionally Introduced during Forming Operations and Increases Cracking in the Material. Some PCCP Wires were Subject to this During Pipe Manufacturing. Common Types of Mortar Coating Damage: Third Party Damage, Handling, Improper Pipe Bedding or Trench Backfill Material, Etc. 22
23 Pipe/Wire Corrosion Hydrogen Embrittlement Wire Failures: Wire Split Fractures Wire Tensile Fracture 23
24 Pipe/Wire Corrosion Wire Failures Due to Electrochemical Corrosion: Wire Corrosion Wire Corrosion 24
25 Are PCCP Technologies 100% Guaranteed? WSSC Uses State of the Art PCCP Technologies. What They Cannot Guarantee: Electromagnetic Testing: Cannot Detect Broken Pre-Stressing Wire Within Approximately one foot of the edge of Steel End Rings and Steel Saddle Plates used for Factory Fabricated Outlets. Acoustical Leak Testing: Cannot Detect Very Small Leaks. Acoustical Fiber Optic Monitoring: Cannot Detect Wire Breaks on Pipe that is not Properly Pre-Stressed: Example: Chevy Chase Failure. AFO Monitoring is susceptible to power and communication outages. Other Challenges; Shutdowns for Emergencies are Typically Manual and Take Time and Often Require Multiple Valve Closures. Conflicts with Other Operational Constraints may Complicate Emergency Shutdowns or Create Large Water Outages. 25
26 26
Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel
OAWWA 73 rd Annual Conference Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel By Jason DeLaet, P.E. Supervising Engineer Greater Cincinnati Water Works & Michael J. Livermore
Measuring the Condition of Prestressed Concrete Cylinder Pipe
Measuring the Condition of Prestressed Concrete Cylinder Pipe John Marshall, P.E.I, I J.W. Marshall and Associates, and Paul S. Fisk, President NDT Corporation Introduction Prestressed Concrete Cylinder
Meeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
Force Main Condition Assessment: New Technologies & Case Studies
Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick
AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate
AGENDA ITEM C9 DATE: February 2, 2015 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles Carden, Chief Operating Officer South Pasco Transmission Main Condition Assessment Services with Pure Technologies
Prestressed Concrete Pipe Fitness for Service and Repair
Prestressed Concrete Pipe Fitness for Service and Repair Rasko Ojdrovic [email protected] 781-907-9231 IAEA - EPRI 15 October 2014 www.sgh.com SGH Pipeline Experience More than 25 years of research, analysis,
Pipeline Asset Management: From Assessment to Prioritized Projects List
PROGRAM MANAGEMENT INEERING Pipeline Asset Management: From Assessment to Prioritized Projects List TAWWA / WEAT Summer Seminar July 28, 2011 PLANN NING ENG Andrew Hunt, PE Asset Management Project Manager
Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System
Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Luis Aguiar Miami-Dade Water & Sewer Department Anna Pridmore, PhD Structural Technologies PROJECT BACKGROUND Miami-Dade Water & Sewer Department
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University
Best Practices Manual for Prestressed Concrete Pipe Condition Assessment: What Works? What Doesn t? What s Next?
Best Practices Manual for Prestressed Concrete Pipe Condition Assessment: What Works? What Doesn t? What s Next? Subject Area: Infrastructure Best Practices Manual for Prestressed Concrete Pipe Condition
Chesapeake Section AWWA Symposium
PRESTRESSED CONCRETE CYLINDER PIPE (PCCP) Chesapeake Section AWWA Symposium HANSON PRESSURE PIPE Steve Smith January 16,2014 Interpace Projects with Problems INTERPACE 45 MILLION FEET 11,500 PROJECTS Slide
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes the repair, demolition, and disposal of asbestos
CONDITION ASSESSMENT AND RISK MANAGEMENT OF WATER MAINS SAVES TENS OF MILLIONS OF EUROS?
CONDITION ASSESSMENT AND RISK MANAGEMENT OF WATER MAINS SAVES TENS OF MILLIONS OF EUROS? International Public Works Conference 2011 Canberra 21-25 August 2011 Geert Jan van Heck 24-8-2011 Overview of the
External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902
External Wrapping of Steel Riser Pipe Case Study HJ3 CS200902 Introduction Refineries process a wide variety of petroleum products. As part of the process, they rely on cooling towers, which recycle water
Stay Cable Replacement of the Luling Bridge
Stay Cable Replacement of the Luling Bridge Armin Mehrabi, Bridge Engineering Solutions, PC 2009 Louisiana Transportation Engineering Conference February 8-11, 2009, Baton Rouge, LA Lower Anchorage Upper
Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses
Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
The Original Carbon Fiber Reinforced Polymer System
Infrastructure The Original Carbon Fiber Reinforced Polymer System Phone: 52.292.39 Toll Free: 866.38.269 Fax: 52.48.5274 282 E. Fort Lowell Rd. Tucson, AZ 8576 www.dowaksausa.com Test results are supported
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show. Orlando, Florida April 13-17, 2014
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Miami Thrice; Lanzo, HJ3, and Carbon Fiber combine to preempt Catastrophic Line Breaks
SECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE
SECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified The work specified shall include all labor, materials, tools, equipment, services, and incidentals necessary
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
Appendix A: Acceptable pipe and fitting materials
Watercare Services Limited Water and Code of Practice Content from the NZS 4404:2010 Land development and subdivision infrastructure has been reproduced for use in the Infrastructure Design s Manual for
SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM
Page 1 of 9 SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Distribution Integrity Management Program ( DIMP ) activities are focused on obtaining and evaluating information
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines Jeff Schell General Manager United Pipeline Middle East, Inc. Introduction HDPE Liners A cost effective and environmentally beneficial
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR
LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR ABSTRACT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 Virginia
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains
Structural Rehabilitation of the Kenilworth PCCP Transmission Main with Steel Slipliner
705 Structural Rehabilitation of the Kenilworth PCCP Transmission Main with Steel Slipliner Jeff Peluso, P.E. 1, Ron Brown 2 1 Engineer, Baltimore County Department of Public Works, 111 West Chesapeake
Corrosion Control & Cathodic Protection for Water & Wastewater Systems
Corrosion Control & Cathodic Protection for Water & Wastewater Systems Presented By: James T Lary Corrpro Companies, Inc 1090 Enterprise Dr. Medina, OH 44256 Tel. 330-723 723-5082 (x1215) email: [email protected]
FEDERAL GOVERNMENT OVERSIGHT OF PIPELINE SAFETY
Operational Safety INTRODUCTION The Millennium Pipeline Company (Millennium) is proud of the key role it plays in New York s energy infrastructure. The Millennium Pipeline is a vital link in a system that
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
APPENDIX J GAS DISTRIBUTION
APPENDIX J GAS DISTRIBUTION Ji Jii APPENDIX J GAS DISTRIBUTION NEIL G. THOMPSON, PH.D. 1 SUMMARY The natural gas distribution system includes 2,785,000 km (1,730,000 mi) of relatively small-diameter, low-pressure
NEW CONNECTION INDUSTRIAL PRODUCTS NC.10V NC.20V NC.30V. NC. SD.10 NC. SD.20 NC. F.Clamp
Repair and Construction. Complete stainless steel pipe repair clamps to repair cracks, fractures, pin holes, torn sockets or welded tees, broken asbest-cement pipe coupling and more. Available for all
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Installation of Large Diameter Buried Pipes
Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
Steel Pole & Tower Assessment & Remediation Turnkey Solutions for Aging Steel Infrastructure
Steel Pole & Tower Assessment & Remediation Turnkey Solutions for Aging Steel Infrastructure Understanding and Addressing the Risks of Aging Steel T&D Assets Once thought to be permanent structures free
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
Leakage Management & Control
Leakage Management & Control (An overview) Saroj Sharma April 2008 Delft, The Netherlands Contents Introduction Causes of leaks and benefits of leakage control Leakage management strategy Economic level
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
Introduction to Pressure Pipe Rehabilitation with CIPP
Introduction to Pressure Pipe Rehabilitation with CIPP Founded in early 1990 s RS Technik is a global leader in the rehabilitation of underground pipes RS Technik uses Cured-in- Place (CIPP) technology
CHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper D-4-02 LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE
Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014
Relining of Water Mains with Flexible High Pressure Pipelines Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014 Aging water main infrastructure The American Society of Civil Engineers
Design Criteria & Service Goals
4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on
Town House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
POTENTIAL FOR HYDROGEN GENERATION AND EMBRITTLEMENT OF PRESTRESSING STEEL IN GALVANIZED PIPE VOIDED PILE
FDOT Research Report No. FL/DOT/SMO 04-477 POTENTIAL FOR HYDROGEN GENERATION AND EMBRITTLEMENT OF PRESTRESSING STEEL IN GALVANIZED PIPE VOIDED PILE submitted to Florida Department of Transportation State
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013
VIDEO INSPECTION AND LASER PROFILING IN FLORIDA AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013 PIPE INSPECTION Over the last 5 years, the Department has spent approximately 175 million dollars
ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES
ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES Jose L. Villalobos, P.E. 1 and Carl Perry 2 Abstract: This paper presents strategies for the control of external corrosion on municipal
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced
HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS
HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS Shiwei William Guan, Ph.D. Vice President, R&D and International Business Madison Chemical Industries Inc. 490
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
INDEX. Sec. No. Items Page Nos.
INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............
Contracting Opportunities Vendor Day May 17, 2011
Customer Care Team Contracting Opportunities Vendor Day May 17, 2011 Customer Care Team: What We Do Team Office customer advocacy and contracting Customer Relations Group call centers, claims, special
ASSET MANAGEMENT PLAN Published January 2009
San Diego County Water Authority 2 0 1 1 ASSET MANAGEMENT PLAN Published January 2009 4677 Overland Avenue San Diego, CA 92123 858-522-6600 www.sdcwa.org This page intentionally left blank. Table of Contents
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?
Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting
Health Care for Pipelines From Cradle to Grave
Health Care for Pipelines From Cradle to Grave By Jim Costain, GE Inspection Technologies Assuring the mechanical integrity of piping systems, whether they be in exploration, transmission, or process plants
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
Chapter 7 Plumbing Connections
Chapter 7 Plumbing Connections 7-1 General All plumbing equipment and installations must be designed, constructed, and installed in accordance with this code and where not specific, to the applicable provisions
Let Us Give Utilities the Respect that they Deserve.
Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous
Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE
1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint
Module 3: Sewer Material Lecture 3: Sewer Material
Module 3: Sewer Material Lecture 3: Sewer Material [NPTEL, IIT Kharagpur, Prof. M.M.Ghangrekar, Department of Civil Engineering Page 1 3.0 SEWER MATERIAL 3.1 Important Factors Considered for Selecting
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
1-800-327-8276 www.jfcson.com
Trenchless Cost Effective Internal Pipe Rehabilitation 101 East Broadway, Hackensack, N.J. 07601 Folsom, NJ Linden, NJ Beltsville, MD Sylmar, CA 1-800-327-8276 www.jfcson.com In-Weg Internal Joint Sealing
Special Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
WATER & SEWER CORROSIVE RESISTANT PRODUCTS
WATER & SEWER CORROSIVE RESISTANT PRODUCTS The Standard of Excellence in the Industry CASING SPACERS COUPLINGS & FLANGE COUPLING ADAPTERS REPAIR CLAMPS DUCTILE IRON SADDLES STAINLESS STEEL SADDLES TAPPING
City of Dallas Water Utilities Department Advanced Leak Detection
City of Dallas Water Utilities Department Advanced Leak Detection Presented to Transportation and Environment Committee January 12, 2009 1 History of Program Dallas Water Utilities implemented Leak Detection
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
beams columns blast walls slabs pipes protective coatings polymer concrete Solutions Looking for Problems...
beams columns blast walls slabs pipes protective coatings polymer concrete Solutions Looking for Problems... CarbonWrap Solutions Services Turnkey Innovative Solutions and Products CarbonWrap Solutions,
Rehabilitation or Replacement? That Is The Question
Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections
WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION
WATER MAIN CONSTRUCTION TECHNIQUES Overview Water Main - Materials Specifications Installation Future? Water Main Materials Material Types There are various material types used for water mains, these include:
High Capacity Helical Piles Limited Access Projects
High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices
Rental Services Temporary Cooling - Flexible Water Hose
Engineering Bulletin Rental Services Temporary Cooling - Flexible Water Hose September 2006 CHS-PRB007-EN Warnings and Cautions Warnings and Cautions. Notice that warnings and cautions appear at appropriate
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
NW Natural & Pipeline Safety
NW Natural & Pipeline Safety We Grew Up Here NW Natural is an Oregon-based utility company founded in 1859. The company purchases natural gas for its core market in western Oregon and southwestern Washington,
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer The user may choose to adopt part or all of this Model Specification; however, the user should ensure that all parts
