SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM
|
|
|
- Charles Neal
- 9 years ago
- Views:
Transcription
1 Page 1 of 9 SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Distribution Integrity Management Program ( DIMP ) activities are focused on obtaining and evaluating information related to the distribution system that is critical for a risk-based, proactive integrity management program that involves programmatically remediating risks. The DIMP rules were promulgated by the Pipeline and Hazardous Materials Safety Administration ( PHMSA ) in The DIMP rules address how gas utilities identify, prioritize and evaluate risks, repair threats, and validate the integrity of their gas distribution system. Distribution systems typically operate at lower pressures (<1 psi - <150 psi), but, due to their inherent location within population centers, are deemed to be within high consequence areas. Under the federal rules, pipeline operators were required to develop their DIMP plans on or before August 2, The Company published its DIMP plan in August 2011 and submitted it to the Colorado Public Utilities Commission on September 28, Although the foundational requirements underlying the DIMP rules are similar to the Transmission Integrity Management Program ( TIMP ) rules -- know your assets, identify the threats and risks to those assets, and proactively mitigate those threats -- the DIMP rules have less of a prescriptive nature than the TIMP rules. PHMSA determined that more general requirements were needed for distribution systems given the diversity of distribution systems and the unique threats to which they may be exposed. Activities included as part of the Company s 2014 DIMP include: Programmatic Risk-Based Pipe Replacement Program (exclusive of Accelerated Main Replacement Program ( AMRP ) and Cellulose Acetate Butyrate ( CAB ) Services Replacement Program; Distribution Valve Replacements; Pipeline Data Project ( PDP ) Distribution; Intermediate Pressure ( IP ) Assessments; Close Interval/Direct Current Voltage Gradient ( DCVG ) Surveys; Meter Barricades; Accelerated Leak Surveys; and Bridge Crossings/Exposed Pipes Asset Types Included: The Company s DIMP projects cover all distribution facilities, such as meters, mains, valves, regulators and services. The DIMP category of projects for purposes of the PSIA excludes distribution pipelines comprised of the following pipe types: cast iron, bare steel, polyvinyl chloride ( PVC ) and CAB, which are covered by the Company s AMRP and CAB Services Replacement programs. 1
2 Page 2 of 9 Vintage of Assets: All Key Changes Since the October 1, 2012 PSIA Filing: The Sewer Line Conflict project described in the Company s October 2012 PSIA filing is not in the current 2014 DIMP plan. This project focused on proactively inspecting portions of the gas distribution system where installation involved directional boring to ensure there were no instances of gas distribution pipelines intersecting sewer lines. The Sewer Line Conflict project was initiated in 2010 and performed through 2013 and did not identify any conflicts in the Public Service gas system based on the surveys performed. Based on known available information, the Company believes it has mitigated this risk, and considers this project complete. Meter barricades is a new project that has been added for Additional details on this project are provided in a subsequent section of this exhibit. The Programmatic Risk-Based Pipe Replacement Program is also included in DIMP in the 2014 PSIA. To add clarity, this program is a combination of four (4) existing projects already contained in the 2013 PSIA. In addition to Pre-1973 Aldyl-A mains and services, and Coupled- IP mains, it also includes both the coated steel replacement program, which was previously a stand-alone project under the DIMP, and the replacement of mill wrap main and services, which was previously a part of AMRP. The Company believes that consolidating these pipe types into one program under DIMP achieves two primary goals. First, it eliminates confusion associated with various types of coated steel and vintages. And, second, it creates closer alignment with the Proactive Stage of the Transition Model and the component of Data and Risk Driven Decision Making. Additional pipe types may be included in the future, based on assessments and identified risks DIMP Activities Status Update: The Company has continued to utilize robotic in-line-inspection tools to assess the condition of intermediate pressure pipelines. It is estimated that, by year end 2013, approximately three miles of IP pipe will have been assessed using this technology. The Company has also utilized Close Interval and DCVG surveys to assess the condition of over 20 miles of its gas distribution system. The distribution valve replacement program has successfully replaced a number of valves, isolating sections of the system in the event of an emergency or incident and minimizing customer impacts during these events. Generally, the areas of work related to the various DIMP initiatives are outside the regions that were impacted by Front Range flooding that occurred within the Company s service territory in September However, the availability of engineering and construction resources focused on flood related restoration work could have a potential impact on the fourth quarter 2013 work plans. 2
3 Page 3 of 9 Planned 2014 DIMP Activities: Overall DIMP 13 Month Average Plant In Service Revenue Requirement Total DIMP $37.8 M $6.0 M $23.8 M $9.3 M DIMP Project Financial Details Programmatic Risk-Based Pipe $32.68 M $2.12 M Replacement Distribution Valve Replacements $3.60 M $0 Pipeline Data Project Distribution $1.50 M $0 IP Assessments $0 $1.70 M Close Interval/DCVG Surveys $0 $1.30 M Meter Barricades $0 $0.34 M Accelerated Leak Surveys $0 $0.20 M Bridge Crossings/Exposed Pipe $0 $0.25 M DIMP Labor, Employee Expense $0 $0.13 M Total DIMP $37.78 M $6.04 M Specific DIMP Projects Activities: The Company s DIMP under the PSIA includes a variety of projects focused on advancing the primary elements of the program: know your assets, understand the risks and threats to your assets, and proactively mitigate risks. A brief description of each project is provided below. Programmatic Risk-Based Pipe Replacement Program Program Overview: This program identifies and programmatically replaces distribution mains not covered by the AMRP or CAB programs that have a higher relative risk to public safety than other segments within the gas distribution system. The program is currently focused on three general pipe types: Older, vintage (pre-1950) steel pipe, that has been previously referred to as the Coated Steel Main Replacement Program, which also includes the specific type of coated steel referred to as mill wrap; Aldyl-A mains and services; and Coupled Intermediate Pressure (IP) mains. The pipe segments and/or areas targeted for replacement are risk-ranked and identified based on history of leakage, pipes with problems in the coating or cathodic protection as identified through direct assessment, and engineering judgment provided by subject matter experts 3
4 Page 4 of 9 ( SME ). As discussed below, the PDP-Distribution project is designed to address data gaps associated with these pipe types and, as such, new information will be integrated into the programmatic risk-based replacement strategy. The scope of this project does not include pipe types that are part of other main or service replacement programs, such as cast iron, bare steel, PVC, and CAB. Programmatic Risk-Based Pipe Replacement Program (Total) $32.68 M $2.12 M Vintage Steel Current plans include targeted replacement of nearly 40 miles of distribution main. This is comprised of older vintage (pre-1950) steel pipe that is located in various portions of the Denver Metro region, as well as in Boulder and Pueblo. This project is unrelated to the Pre-1950s Vintage Transmission Main Replacement Program, which covers only transmission pipelines. This project began in 2013 and was originally called the Coated Steel Main Renewal project in the Company s October 2012 filing. In accordance with the accelerated timetable proposed in the Company s pending rate case in Proceeding No. 12AL-1268G, the Company plans to replace the known high risk vintage steel pipe over the next ten years. Coupled Intermediate Pressure (IP) Pipe Replacement This project is focused on the replacement of vintage IP pipelines in the Denver Metro area that are known to contain a high number of compression couplings (also known as mechanical couplings). These types of couplings have been involved in incidents at other utilities, and are considered obsolete and pose a higher than normal risk to the public and employees who must work on these lines. In addition, there has been a PHMSA advisory bulletin related to the risks of mechanical couplings (see PHMSA Advisory Bulletin ADB-08-02). The planned work for 2014 includes replacement of two vintage IP lines in the Denver Metro area that are known to contain a high number of compression couplings. The first targeted line is 3,400 feet of 1947-vintage mill wrap pipe installed under Highway I-25 near West 13 th Avenue in Denver. The second project is a 10-inch line near where Highways I-25 and I-70 intersect, installed under I-25 and running parallel to I-70. The line is 6100 feet in length and was constructed in the 1940 s of mill wrapped steel. There are currently 75 miles of coupled IP estimated for replacement, as described in the Company s gas rate case in Proceeding No. 12AL-1268G, at page 31, lines 3-13, of Ms. Campbell s Direct Testimony. Initial plans are to remove these pipe types over a 10-year time period. 4
5 Page 5 of 9 Aldyl-A Mains & Services This project proactively replaces pre-1973 Aldyl-A plastic distribution main and services consistent with multiple Advisory Bulletins issued by PHMSA (Advisory Bulletins ADB and ADB-02-07) and based on data that this particular material can become brittle over time and is subject to failure. Approximately four miles of pipe, primarily in the Boulder and North Metro operating areas, have initially been identified for replacement in Modifications to these projects may be made based on future discovery of poor performing pipe locations, leakage data and/or SME input. There are currently a total of 26 miles of this pipe type identified for replacement, as described in the Company s gas rate case in Proceeding No. 12AL-1268G. The Company currently plans to remove this pipe type over the next 10 years. Distribution Valve Replacements The placement, accessibility and functionality of valves in the distribution system are critical components of gas operations, providing the ability to isolate sections of the system in the event of an emergency or incident and minimizing customer impacts during these events. The Company has identified a need to add, replace or otherwise rehabilitate existing valves. The current plan estimates nearly 20 valves for replacement and these range in size from 6-inch to 20-inch valves. Distribution Valve Replacements $3.60 M $0 This project became part of the PSIA in Ongoing inspection of current valves as well as evaluation of the system will likely identify additional valves or areas for valve installation. Pipeline Data Project Distribution The Pipeline Data Project Distribution is a multifaceted project to improve distribution asset records. This project aligns with the gathering data for system knowledge stage within the Transition Model contained in the Overview of PSIA Programs and Projects section of this filing. 5
6 Page 6 of 9 In 2014, specific attention will be given to the development of more complete asset records for both Aldyl-A pipe and coupled IP pipe to support the on-going risk-based evaluation and prioritization of future replacements. The project will also focus on valves, including mapping of valves and inclusion of asset data in the geographical information system ( GIS ), as well as the work management system. Additionally, vintage and material information were not populated historically for a number of mains and services in the GIS system. This project will review legacy records and fill in those data gaps. Pipeline Data Project Distribution $1.50 M $0 The 2014 project described above may experience carryover into the first quarter of 2015, dependent on the extent of missing records identified and the time necessary to process this information. After these initial data gaps on vintage and material type are identified, the Company will confirm the inconsistencies within GIS and take steps to mitigate the conflicting data. Intermediate Pressure (IP) Assessments The purpose of this project is to perform In-Line Inspections ( ILI ) using a robotic smart tool on vintage IP pipelines to better understand internal and external conditions of these pipelines. Based on an understanding of the type of data that can be obtained through use of similar ILI technology, the Company concluded that it would be prudent to have select, critical IP pipelines assessed by this method of ILI. Five lines will be tested in 2014 and a minimum of five miles will be evaluated. Preference will be given to performing multiple tests on each line to further extend the amount of data on these pipelines. Estimates are based on 2013 actual costs and carry the assumption that multiple tests can be performed on each line and that there will be no capital assets installed. IP Line Assessments $0 $1.70 M Distribution system ILI technology is still being developed and the Company will continue to assess the feasibility and benefits of new technology for these assets. The Company is still 6
7 Page 7 of 9 evaluating the extent of assessment needs on the distribution pipelines, but current plans include assessments over the next several years. Close Interval/Direct Current Voltage Gradient (DCVG) Surveys The Company continues to look for effective ways to apply technology and approaches to its distribution system that have been successful under its TIMP. Indirect surveys will be performed on distribution pipelines with risk factors associated with external corrosion and third party damage. The close interval technique provides information on the level of cathodic protection on coated steel pipelines. A complementary survey, DCVG, provides information on the condition of the coating on the pipeline and identifies defects that may require additional action. The scope is limited to Intermediate Pressure and High Pressure distribution lines. Survey plans include 16 pipeline segments, totaling nearly 60 miles. The Company intends to perform this type of survey on pipelines with higher risk, as determined based on age, leak history, cathodic protection history, pressure and/or proximity to highly populated areas. It is anticipated that remedial action could be required on a portion of the lines being surveyed. Close Interval/DCVG Surveys $0 $1.30 M These assessments will continue to be a part of the Company s integrity strategy for several years, as it is recognized as a viable proactive assessment method used to gather information about metallic pipes and develop mitigation strategies. Meter Barricades This project is a continuation of work that commenced in 2013 to install protection around gas metering and related facilities that are subject to the threat of outside force damage, primarily due to vehicular traffic. This project is a proactive initiative to protect at-risk facilities based on the development of regulations addressing these risks in other states. Sites are prioritized to mitigate facilities that pose the highest risk based on consequence. Typically, the order would be regulator stations, commercial and industrial meter sets, followed by residential and trailer park meter sets. It is anticipated that approximately 800 unique sites will be protected via installation of a single or dual bollard and/or cross bars. It is anticipated 7
8 Page 8 of 9 that this project will end in 2015, at which time installation of protection will become part of routine work as sites are identified through surveys. Meter Barricades $0 $0.34 M The Company is still investigating the extent of this work needed on the system. The Company will evaluate the full extent of the need for this program in Accelerated Leak Surveys This project performs annual leak surveys on an accelerated frequency for the worst performing pipe types as measured by leak per mile ( leak ratios ). This is considered an Additional/Accelerated ( A/A ) leak survey under the Company s DIMP plan and is done on pipe types such as cast iron, bare steel, PVC and CAB. The intent is to understand and mitigate the risk of these pipe types while renewal programs are underway. The accelerated leak survey is estimated to cover over 500 miles of main and nearly 20,000 services. The total miles and number of services surveyed will decrease each year as these poor performing mains and services are replaced as part of the AMRP and CAB programs. Only the incremental costs of surveys over and above the minimum survey intervals previously required for these pipe segments are included in this project. Accelerated Leak Surveys $0 $0.20 M Accelerated leak surveys will continue until all of the pipe types covered under this program are removed from the system in the next ten years. Since these pipe types are part of replacement programs currently in progress, the scope of this project is reduced by a corresponding amount each year. Bridge Crossings/Exposed Pipes In 2012, the Company began a phased approach to inspecting the condition of its distribution pipes that are installed on bridges, or otherwise exposed to the elements that cause atmospheric 8
9 Page 9 of 9 corrosion. The purpose of this project is to identify and repair pipes that pose the highest risk in the event of a failure, as measured by indications of damage, corrosion, insufficient support, and/or placement on defective bridge crossings. The estimated project costs include assessments, evaluation, and potential bridge repairs. It is estimated that there will be as many as 15 assessments performed, along with additional costs associated with required repairs. Bridge Crossings/Exposed Pipe $0 $0.25 M This project to assess and repair pipelines will continue through
Program Design and Engineering Key to Infrastructure Replacement and Cost Containment
Program Design and Engineering Key to Infrastructure Replacement and Cost Containment By: Tom Ziegenfuss, COO Les Goodman VP/Distribution Dave Klimas, VP/Distribution Glen Armstrong, Senior Codes Specialist
SOCALGAS APROACH TO PIPELINE INTEGRITY
SUMMER 2011 SOCALGAS APROACH TO PIPELINE INTEGRITY Southern California Gas Company (SoCalGas ) is committed to providing clean, safe and reliable natural gas to its customers and takes important steps
APPENDIX J GAS DISTRIBUTION
APPENDIX J GAS DISTRIBUTION Ji Jii APPENDIX J GAS DISTRIBUTION NEIL G. THOMPSON, PH.D. 1 SUMMARY The natural gas distribution system includes 2,785,000 km (1,730,000 mi) of relatively small-diameter, low-pressure
Pipeline Engineering. Natural Gas Distribution
R Pipeline Engineering Natural Gas Distribution Gas Distribution Engineering Services Our team of professionals at EN Engineering has been designing, upgrading and maintaining distribution system assets
April 15, 2011 VIA ELECTRONIC TRANSMISSION
Enbridge Pipelines (Lakehead) L.L.C. Shaun G. Kavajecz, Manager 119 N 25 th Street E Pipeline Compliance Superior, WI 54880 Tel 715 394 1445 www.enbridgepartners.com Fax 713 821 9428 [email protected]
SDG&E DIRECT TESTIMONY OF MARIA T. MARTINEZ (PIPELINE INTEGRITY FOR TRANSMISSION AND DISTRIBUTION) November 2014
Company: San Diego Gas & Electric Company (U0M) Proceeding: 01 General Rate Case Application: A.1--XXX Exhibit: SDG&E-0 SDG&E DIRECT TESTIMONY OF MARIA T. MARTINEZ (PIPELINE INTEGRITY FOR TRANSMISSION
California Public Utilities Commission Risk Assessment Unit Hazard Database Project Report on Status and Initial Recommendations
California Public Utilities Commission Risk Assessment Unit Hazard Database Project Report on Status and Initial Recommendations March 14, 2012 I. Introduction The California Public Utilities Commission
ICM Project Underground Infrastructure and Cable
EB 0 00 Tab Schedule B ( pages) ICM Project Underground Infrastructure and Cable Handwell Replacement Segment (THESL) EB 0 00 Tab Schedule B I EXECUTIVE SUMMARY. Project Description 0 The handwell replacement
FEDERAL GOVERNMENT OVERSIGHT OF PIPELINE SAFETY
Operational Safety INTRODUCTION The Millennium Pipeline Company (Millennium) is proud of the key role it plays in New York s energy infrastructure. The Millennium Pipeline is a vital link in a system that
THE STATE OF THE NATIONAL PIPELINE INFRASTRUCTURE
US DEPARTMENT OF TRANSPORTATION Introduction THE STATE OF THE NATIONAL PIPELINE INFRASTRUCTURE Over the past 70 plus years, a nationwide system of pipelines has been constructed to transport almost 100
Operations and Maintenance Procedures for Natural Gas Systems
Operations and Maintenance Procedures for Natural Gas Systems Contact Information John West Transportation Specialist U.S. Department of Transportation PHMSA Office of Training and Qualifications Office
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
Railroad Commission of Texas Page 1 of 48 16 TAC Chapter 8-Pipeline Safety Regulations
Railroad Commission of Texas Page of 0 0 The Railroad Commission of Texas (Commission) adopts new.0-.0, relating to Risk- Based Leak Survey Program, Leak Grading and Repair, and Mandatory Removal and Replacement
Jeffrey D. Wiese Associate Administrator for Pipeline Safety
U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration NOV 1 Z 2015 1200 New Jersey Ave, 5.E. Washington, D.C. 20590 VIA CERTIFIED MAIL AND FAX TO: 713-646-4378 Mr. Troy
Funding the Vision: Investing in Safe, Reliable Service
Funding the Vision: Investing in Safe, Reliable Service KUB Financial Plan Executive Summary Fiscal Year 2015 Table of Contents Funding The Vision: Investing in Safe, Reliable Service 1 KUB Proposed Fiscal
Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions
Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions Seth Anderson, GISP Management Consultant Celine Hyer, P.E. Associate Vice President Presentation Topics The Infrastructure
Water Loss and Leak Detection. Gary Armentrout, Project Associate Environmental Finance Center Wichita State University
Water Loss and Leak Detection Gary Armentrout, Project Associate Environmental Finance Center Wichita State University Water Meters The Atlanta Journal-Constitution: Thousands of city of Atlanta water
ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES
ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES Jose L. Villalobos, P.E. 1 and Carl Perry 2 Abstract: This paper presents strategies for the control of external corrosion on municipal
Portable Natural Gas Supply Solutions
Portable Natural Gas Supply Solutions Presented by Dimitri Karastamatis, P.E. September 22, 2015 Overview CenterPoint Energy Mobile Energy Solutions Pipeline Integrity Portable Gas Supply (CNG & LNG) Other
NW Natural & Pipeline Safety
NW Natural & Pipeline Safety We Grew Up Here NW Natural is an Oregon-based utility company founded in 1859. The company purchases natural gas for its core market in western Oregon and southwestern Washington,
WSSC Ad-Hoc Committee on Large Diameter Water Mains. August 2, 2013
WSSC Ad-Hoc Committee on Large Diameter Water Mains August 2, 2013 Purpose: To Gain an Understanding of WSSC s Current Approach to PCCP Inspections, Monitoring and Repair/Replacement 2 PCCP Management
Technical Losses in Natural Gas Transportation, Distribution, and Storage. Paul Metro Pennsylvania Public Utility Commission
Technical Losses in Natural Gas Transportation, Distribution, and Storage Paul Metro Pennsylvania Public Utility Commission 1 Unaccounted for Gas (UFG or Technical Losses) Unaccounted for gas is the difference
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines Jeff Schell General Manager United Pipeline Middle East, Inc. Introduction HDPE Liners A cost effective and environmentally beneficial
TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT
TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT I / 7 Natural Gas Transport. General principle The most efficient and effective method of natural gas distribution from the place of production to the
Frequently Asked Transmission Pipeline Questions
Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).
DEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Gas Company (U 904 G) and San Diego Gas & Electric Company (U 902 G) to Proceed with Phase 2 of their
Trenching and Excavation Safety
1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking
Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
Urban Pipeline. Replacement Project. Calgary, Alberta. Safety First. Always.
Urban Pipeline Replacement Project A Natural Gas Pipeline Initiative Calgary, Alberta Safety First. Always. The Consequences of NOT Proceeding with the UPR Project If the Urban Pipeline Replacement (UPR)
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
Chapter 7 Plumbing Connections
Chapter 7 Plumbing Connections 7-1 General All plumbing equipment and installations must be designed, constructed, and installed in accordance with this code and where not specific, to the applicable provisions
The city of Odessa, Texas,
http://dx.doi.org/10.5991/opf.2012.38.0027 John D Antoni is a principal with Alan Plummer Associates (www.apaienv.com), Houston. Roy Staggs, assistant director of utilities, and Ajay Shakyaver, city engineer,
Compliance Inspections of Natural Gas Systems
Compliance Inspections of Natural Gas Systems Safety Regulations Applicable to Natural Gas Systems Who are these people and why are they calling me? Where do they get their authority? USC Section 60117
AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate
AGENDA ITEM C9 DATE: February 2, 2015 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles Carden, Chief Operating Officer South Pasco Transmission Main Condition Assessment Services with Pure Technologies
Cathodic Protection Use On Tank Bottoms & Underground Piping In Power Generation Plants
Cathodic Protection Use On Tank Bottoms & Underground Piping In Power Generation Plants PG&E Office San Francisco January 18, 2007 Craig K. Meier Corrosion Control Incorporated Corrosion process for tanks
49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards
49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards THIS DOCUMENT CONTAINS ONLY THE SECTIONS NEEDED FOR THE API 1169 ICP EXAMS Subpart G General Construction
Force Main Condition Assessment: New Technologies & Case Studies
Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the
SMALL DIAMETER, MULTIPLE DATASET INSPECTION IN LOW FLOW AND LOW PRESSURE ENVIRONMENTS
WHITE PAPER 15-01 SMALL DIAMETER, MULTIPLE DATASET INSPECTION IN LOW FLOW AND LOW PRESSURE ENVIRONMENTS Chuck Harris T.D. WILLIAMSON HOUSTON, TEXAS [email protected] Mark Graves WILLIAMS OKLAHOMA
Regulation of Natural Gas Pipelines. June 23, 2008
Regulation of Natural Gas Pipelines June 23, 2008 Federal and State Regulations Federal: 49 United States Code 60101. et. seq. Title 49 Code of Federal Regulations The Office of Pipeline Safety (OPS),
Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets
*Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; [email protected] Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes
Cathodic Protection. Remote Monitoring of Cathodic Protection on a Gas Distribution Network
Cathodic Protection Remote Monitoring of Cathodic Protection on a Gas Distribution Network Author: Martin Alderson Northern Gas Networks Issued for UKOPA members CP measurements are very labour intensive
Guidance 1 for Strengthening Pipeline Safety Through Rigorous Program Evaluation and Meaningful Metrics
Guidance 1 for Strengthening Pipeline Safety Through Rigorous Program Evaluation and Meaningful Metrics 1 This document is to provide guidance describing methods to evaluate and measure IM program effectiveness.
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
2015 ANNUAL OPERATING AND FINANCIAL PLAN
2015 ANNUAL OPERATING AND FINANCIAL PLAN TABLE OF CONTENTS 2015 ANNUAL OPERATING AND FINANCIAL PLAN Executive Summary... 3 Summary... 7 Revenue and Expenditure Overview... 15 2015 Enterprise Financial
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
General Utility Work Obligations
General Utility Work Obligations This Section addresses the Utility Company (or Utility Owner) requirements. It does not apply to existing stormwater facilities, irrigation ditches, Intelligent Transportation
CHAPTER IV SPECIAL REGULATIONS - GAS UTILITIES ONLY. Records. Each gas utility shall maintain and keep the following records:
CHAPTER IV SPECIAL REGULATIONS - GAS UTILITIES ONLY Section 401. Records. Each gas utility shall maintain and keep the following records: (a) Monthly record of the heating value of gas produced or purchased
Pipeline Basics & Specifics About Natural Gas Pipelines
Last updated: September 2015 Pipeline Basics & Specifics About Natural Gas Pipelines Introduction to Pipelines There are over 2.6 million miles of fuel pipelines in the United States. Who regulates pipelines
WATER SUPPLY SYSTEMS FOR 150/5220-4B AAS-100 AIRCRAFT FIRE AND RESCUE PROTECTION
WATER SUPPLY SYSTEMS FOR 150/5220-4B AAS-100 AIRCRAFT FIRE AND RESCUE PROTECTION 1. PURPOSE. This Advisory Circular (AC) provides guidance for the selection of a water source and standards for the design
Managing the integrity of pipeline assets
ROSEN Integrity Solutions Managing the integrity of pipeline assets Pipeline Integrity Services ROSEN: Leading the way in integrity management The safe and efficient operation of major transmission pipe
Recently Completed Projects - Consulting Service Projects
Nicor Gas Corrosion Control, Cathodic Protection & Integrity Management Illinois USA Multi-year contract providing corrosion control, cathodic protection and integrity management services since 2001. Primary
PUTTING IT ALL TOGETHER: INTEGRATING MASTER PLANNING WITH ASSET MANAGEMENT
PUTTING IT ALL TOGETHER: INTEGRATING MASTER PLANNING WITH ASSET MANAGEMENT Jeffrey B. Stillman, P.E., Practice Leader (Main Author/Presenter) Kevin T. Laptos, P.E., Regional Planning Leader Kent A. Lackey,
Pipeline Asset Management: From Assessment to Prioritized Projects List
PROGRAM MANAGEMENT INEERING Pipeline Asset Management: From Assessment to Prioritized Projects List TAWWA / WEAT Summer Seminar July 28, 2011 PLANN NING ENG Andrew Hunt, PE Asset Management Project Manager
M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to
M E M O R A N D U M DATE: August 7, 2015 TO: FROM: SUBJECT: Metropolitan Wastewater Management Commission (MWMC) Matt Stouder, MWMC General Manager Capacity Management, Operations, and Maintenance (CMOM)
PIPELINE FUNDAMENTALS. texaspipelines.com
PIPELINE FUNDAMENTALS texaspipelines.com Texas Oil & Gas: Generating $2.6 Billion for State Revenues texaspipelines.com Texas Oil & Gas Texas produces 20% of US Domestic Oil Production 1.1 Million Barrels
City of Mill Valley Sewer Capital Improvement Plan 2012 2016
City of Mill Valley Sewer Capital Improvement Plan 2012 2016 I. BACKGROUND Between December 2004 and February 2008, the ed States Environmental Protection Agency (EPA) conducted inspections of the SASM
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF
Introduction to Asset Management. Presented by: John J. Jackman, P.E. Associate - Asset Management Specialist
Introduction to Asset Management Presented by: John J. Jackman, P.E. Associate - Asset Management Specialist Agenda Infrastructure Management Inventory Condition Assessment Maintenance Life Cycle Costs
Acoustic Leak Detection. Gander Newfoundland 2006
Acoustic Leak Detection Gander Newfoundland 2006 Overview Background on Leakage and leak Detection Water Loss Management Fundamentals of Correlation Leakage The unintentional escape or loss of water from
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes the repair, demolition, and disposal of asbestos
Recent outbreaks of pinhole leaks nationally are a significant issue. Figure 1.1 shows the
CHAPTER 1 - INTRODUCTION 1. 1 Motivation Recent outbreaks of pinhole leaks nationally are a significant issue. Figure 1.1 shows the national distribution of pinhole leaks based on the data gathered by
COMPARISON OF INTEGRITY
COMPARISON OF INTEGRITY MANAGEMENT ASSESSMENT TECHNIQUES FOR NATURAL GAS TRANSMISSION PIPELINES Prepared for The INGAA Foundation, Inc. by: Process Performance Improvement Consultants, LLC (P-PIC) 201
Victorian Purchasing Guide for UEG11 Gas Industry Training Package Version No 2
Victorian Purchasing Guide for UEG11 Gas Industry Training Package Version No 2 July 2014 State of Victoria (Department of Education and Early Childhood Development) 2014. Copyright of this material is
The State of Natural Gas Pipelines in Fort Worth
TheStateofNaturalGas PipelinesinFortWorth ProducedBy AccufactsInc. ClearKnowledgeintheOverInformationAge RichardB.Kuprewicz President,AccufactsInc. (425)836 4041 [email protected] 1155N.StateSt.Suite609
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Rehabilitation or Replacement? That Is The Question
Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections
Dewatering - Time and Cost Relief by way of Trenchless Construction
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper D-4-02 LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE
Bridges & Culverts Condition by Quantity
3.4.3 What condition is it in? Approximately 93% of the municipality s bridge structures are in good to excellent condition, with the remaining 7% in fair condition. As a result, the municipality received
NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES 2013 DATA REPORT
NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES 2013 DATA REPORT October 2014 Amended July 2015 Permission to Reproduce Materials may be reproduced for personal, educational and/or non-profit activities,
CATHODIC PROTECTION SYSTEM DESIGN
CATHODIC PROTECTION SYSTEM DESIGN Presented By DENIS L ROSSI P.E. CORROSION ENGINEER New England C P Inc. Corrosion Fundamentals What is corrosion? It is defined as the degradation or deterioration of
Info What? Using InfoMaster to Develop a Rehabilitation and Replacement Plan
Info What? Using InfoMaster to Develop a Rehabilitation and Replacement Plan Amanda Lei - City of San Jose Alex Palmatier - HDR 2014 HDR, Inc., all rights reserved. Background Forecasting and Budget Data
Design Criteria & Service Goals
4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on
How To Stop A Gas Leak
Natural Gas / Propane Emergencies Probationary Firefighter Academy Properties of Natural Gas / Propane Natural Gas and Propane are gaseous fossil fuels Natural Gas is primarily Methane(CH 4 ) Propane is
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
Repair or Replacement - Band-Aids vs. Surgery
Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing
MAR 23 2012. Sincerely,
MAR 23 2012 Mr. Terry Gottberg President Merit Energy Company, LLC 1327 Noel Road, Suite 500 Dallas, TX 75240 Re: CPF No. 5-2011-6001 Dear Mr. Gottberg: Enclosed please find the Final Order issued in the
Burlington County Board of Chosen Freeholders County Engineer s Office. NJ Natural Gas Company Proposed Secondary High Pressure Pipeline
Board of Chosen Freeholders County NJ Natural Gas Company Proposed Secondary High Pressure Pipeline NJ Board of Public Utilities Hearing August 26, 2015 NJ Natural Gas Company Company s Preferred Pipeline
Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49
Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49 This page intentionally left blank. PAGE 50 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN RISK MANAGEMENT ANALYSIS
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)
THE MYTH OF DEEP PIPES: CRITICALITY AND PIPE REHABILITATION STRATEGIES
THE MYTH OF DEEP PIPES: CRITICALITY AND PIPE REHABILITATION STRATEGIES Ken Harlow, Director of Management Services, Brown and Caldwell [email protected] Introduction A fundamental principal of asset
CD i -STREETS- Detail #
-STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction
Standard Operating Guideline Maintenance Management System
Standard Operating Guideline (SOG) Title: MAINTENANCE MANAGEMENT SYSTEM District Name: Date Prepared: Date Revised: OBJECTIVE: A Maintenance Management System is an organized method of collecting documentation
The Cost of a Pipeline Failure. Presented by Penn West
The Cost of a Pipeline Failure Presented by Penn West The Cost of a Pipeline Failure Failure Statistics Cost of a Failure Failure Causes Integrity Management Plan Risk Assessment 2 Annual Cumulative Pipeline
Instruments for the oil & gas industry
Instruments for the oil & gas industry Instruments high-quality instruments make the difference The ROSEN Group supports industries, with a focus on integrity and maximizing asset lifespan. Our wide range