1 Waste Management Infrastructure Rehabilitation in the U.S. Virgin Islands The United States Virgin Islands is a group of islands in the Caribbean that are an insular area of the United States. The islands are geographically part of the Virgin Islands archipelago and are located in the Leeward Islands of the Lesser Antilles. The U.S. Virgin Islands consist of the main islands of Saint Croix, Saint John and Saint Thomas, along with the much smaller but historically distinct Water Island and many other surrounding minor islands. The total land area of the territory is square miles (346.4 km 2 ). As of the 2000 census, the population was 108,612. Prior to the 1970 s, wastewater was collected in the major cities of Christiansted and Frederiksted on St. Croix and Charlotte Amalie on St. Thomas and discharged to the ocean with little or no treatment. During the 1970 s, a comprehensive program was completed under the Clean Water Act to implement primary treatment with treated effluent discharge through ocean outfalls to the Caribbean Sea for the major population centers of the two main islands of St. Croix and St. Thomas. I became involved in the project as the Resident Project Representative and oversaw construction of the first phase of the project from October 1970 to August 1973 which included the treatment plant and pumping station, sewer interceptors, and force main from Frederiksted. The Christiansted sewer interceptors and force main from Christiansted were constructed in the following three years. As part of the project, large 18-, 24- and 30-inch diameter sewers were constructed long distances to transport sewage from the population centers to the new primary wastewater treatment facilities. On St. Thomas, wastewater from the capital Charlotte Amalie was transferred several miles through the downtown area along St. Thomas Harbor and around Crown and Lindbergh Bays to the new primary treatment plant at the St. Thomas airport. On St. Croix, wastewater from Christiansted was transported over 51,000 feet and from Frederiksted over 46,000 feet by interceptor, large centrifugal pumping stations and 12-inch force mains to the new primary plant also located adjacent to the St. Croix airport. On St. Croix large portions of the interceptor followed along natural drainage ways called guts often through the bushes and vegetative overgrowth. From hydraulic and land taking viewpoints, these guts were a natural location to site gravity sewer lines. In later years, this played a major role in the difficultly of maintenance and the ability to locate and repair leaks. During large rain events, the guts often overflow, undermine and even change course also attributing to the failure of adjacent pipelines. As PVC pipe was not yet a popular option for large diameter sewers, the original designs called for reinforced concrete pipe. Due to the cost of either fabricating the pipe on the island or shipping from the United States, the contractor who ultimately was low bidder on the most of the interceptors submitted for approval a new pipeline product by Johns Manville, a well known and respected manufacturer of the time who later had problems with asbestos pipe and other asbestos
2 products. The new pipe, Flextron, was a reinforced plastic mortar gravity sewer pipe which consisted of a catalyzed isophthalic polyester resin binder, a siliceous sand aggregate filler, and glass fiber reinforcement. Numerous tests were run before and during construction on tensile strength, flexibility, load bearing capacity, corrosivity, etc. One great advantage was that most of the gravity sewer pipe was designed as 18, 24, and 30 inch and due to the thinness of the pipe, the three sizes could be nested one inside the other to take up 2/3 less room on the shipping barges than the same size concrete pipe. Any damaged pipe was easily repaired and spherical fittings could be made up in the field with a two part epoxy resin. One factor that was overlooked both for the pipe and the concrete materials was the extreme wastewater strength including very high levels of hydrogen sulfide that developed in the lines. These high strength wastewater levels have been attributed to several factors. Due to the scarcity of water for flushing toilets much of which was either rain water or brackish water which contained sulfides, flushing was done more infrequently where plumbing was connected directly to the waste pipe. A second factor was the distance the sewer was transported from the point of origin to the treatment plant which allowed the sewer to become septic and give off large quantities of very corrosive and odorous hydrogen sulfide gas. By the 1980s, some signs of deterioration were already occurring especially in a section of the Fredriksted interceptor that accepted waste from the rum factory. In 1984, the U.S. Environmental Protection Agency (EPA), working with the USVI Department of Planning and Natural Resources, signed a federal court-ordered Consent Decree with the USVI government that required that the upgrade of primary treatment plant to secondary treatment and a maintenance program for the gravity sewers, pumping station and force mains. By the 1990s, the 25-year old sewer system was developing aging and growing pains. The St. Thomas plant had been replaced by a temporary lagoon during the expansion of the International Airport and the St. Croix facility had deteriorated to the point that failure was eminent. After many years of slow progress and several amended decrees, the waste water system continued to fail frequently and discharged untreated waste water through outfalls and bypasses. Under threat of criminal enforcement action for waste water violations and mounting EPA Administrative Orders on Consent for landfill and solid waste regulatory compliance issues, the Government of the Virgin Islands established the Virgin Islands Waste Management Authority (VIWMA) in 2004 to focus more attention and funding to address longstanding problems with waste water and solid waste management in the territory. With funding from Corrective Action Trust Funds and general and special operating funds, the operations staff was hired to improve the operations and maintenance of the waste water system and solid waste facilities. Additionally, with federal grants and bond proceeds, the engineering staff and consulting companies were hired to plan, design, and manage capital projects and major maintenance and facility upgrades. Several initiatives were immediately undertaken and significant milestones have been met. Emergency Task Order Contracts were established to reduce emergency response and repair time for sewer system failures and bypasses. Numerous manhole rehabilitation projects were
3 completed in this emergency response mode. One major force main replacement project is currently underway and another will be advertised for bids this fiscal year. New upgraded pumps were installed at all of the major pump stations on St. Croix. Upgrade work on the major pump station on St. Thomas and the replacement of the Cruz Bay, St. John main pump station are also scheduled to begin this fiscal year. A Request for Proposals was developed for the design, construction, and operation of the two new secondary wastewater treatment plants. In 2006 and 2007, Veolia Water North America (VWNA) completed the construction of the two new secondary wastewater treatment facilities in St. Croix and St. Thomas, respectively. The Authority utilized state-of-the-art zoom camera technology and global positioning system (GPS) equipment to map and assess the condition of the gravity sewers and manholes on St. Croix. Prior to this evaluation, the sewer pipes had to be cleaned and flushed; therefore, vacuum and flushing vehicles and equipment were procured and engineering and waste water operations staff were trained to use this equipment during the systematic cleaning of the sewer lines. Pipe Assessment and Condition Program (PACP) training was also provided to the WMA staff. This two-day program included identifying and rating defects found in both pipelines and manholes in four main categories: Structural Defects; Operational (O&M) Defects; Construction Features; and, Miscellaneous Features. Cataloguing these defects and identifying their severity has led to an easily understood process for prioritizing the Authority s Capital Improvement Program and Operation and Maintenance Program. During the field assessments, at several locations along the guts, storm water erosion and flooding had exposed the pipe and manhole causing sewage to bypass and storm or surface water to inflow. In one notable case, a large shark was found in the bar screen and several small parrot fish were found in the clarifier at the treatment plant resulted from an inlet crossing adjacent to the ocean where a large vortex and subsequent pipe failure was found and repaired. In some cases, due to the extreme levels of the very corrosive hydrogen sulfide, portions of manholes and pipe were nonexistent. Point repairs commenced immediately using both no dig and dig replacement methods. Technologies used included cured-in-place liners, spiral-wounded PVC, slip linings, epoxy coatings, pipe bursting, sealing grouting and others. To fully evaluate these repair options and build local capacity in these new technologies for manhole and pipe repairs, several specialty manufacturers of these repair products and technologies from the mainland were invited to participate in a two-day seminar on St. Croix to explain and demonstrate the benefits and applications of their products and establish licensing agreements with the local contractors who would using these repair products and technologies. Presently, the Authority continues to prepare bid specification packages for the manholes and sewer lines that were rated as imminent failure condition by prioritizing locations, recommending types of repairs, and developing a maintenance program. This sewer system evaluation and pipe condition rating will be duplicated on the St. Thomas and St. John islands in upcoming years. A value-added asset management system for these underground assets is also being reviewed to achieve the long-term goals for Capacity Management and Operation and
4 Maintenance standards. This asset management system will assist in the implementation of a systematic maintenance programs, the execution of sewer system rehabilitation and replacement projects, and the planning of future infrastructure upgrades and improvements. Problem Evaluation Sewer Manhole Corroded by Hydrogen Sulfide Gas, St. Croix Hoyle, Tanner s Dick Perez Investigates Sinkhole by Sewer Manhole, St. Croix Manhole Concrete Deteriorated by Hydrogen Sulfide Gas, St. Thomas Smoke Testing to Locate Deteriorating Sewer Line, St. Thomas
5 Solutions Epoxy-Lining Manhole Repair, St. Thomas Pipe Bursting Repair, St. Croix Slip Lining Repair, St. Croix
6 Nelson Thibault, P.E. Hoyle, Tanner and Associates Nisky Center, East Wing, Suite 740 St. Thomas, USVI Richard Perez Nisky Center, East Wing, Suite 740 St. Thomas, USVI May Adams Cornwall, P.E. U.S. Virgin Islands Waste Management Authority P.O. Box 5089 Christiansted, VI
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
Rehabilitation or Replacement? That Is The Question
Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections
Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology
2007 Pumper & Cleaner Environmental Expo International Wednesday February 7, 2007 Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology What is Cured-In-Place Pipe (CIPP)
Monterey Regional Water Pollution Control Agency. Sewer System Management Plan
Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance
REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC
REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC What is really out there? DO YOU DIG IT? INDUSTRY CONCERNS UNEXPECTED DEVELOPMENTS
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
DEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
Kansas City s Overflow Control Program
Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses
Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to
Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District
Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Paul F. Wilson 1 and Robert J. Warren 2 1 1525 Faraday Ave, Suite 290, Carlsbad, California, USA 92008; e-mail: [email protected].
At the end of today s seminar you should be better. Recognize the causes of Sewer Lateral backup. Identify techniques to protect your home from
Preventing Sewer Backups Presented by IAPMO Today s Objectives At the end of today s seminar you should be better able to: Recognize the causes of Sewer Lateral backup Identify techniques to protect tyour
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water
United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows
LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD
www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.
MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect
Emerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
FY15 Gravity Sewer and Manhole Rehabilitation
Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington
M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to
M E M O R A N D U M DATE: August 7, 2015 TO: FROM: SUBJECT: Metropolitan Wastewater Management Commission (MWMC) Matt Stouder, MWMC General Manager Capacity Management, Operations, and Maintenance (CMOM)
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
Rehabilitation Alternatives. MWEA Collection System Seminar October 1, 2009
Rehabilitation Alternatives MWEA Collection System Seminar October 1, 2009 Overview Types of Rehabilitation Trenchless Categories On-Line Replacement In-Situ Options Selecting the Best Solution Types of
See Appendix A for additional information, or contact ASTM directly.
DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion
DRAFT Public Outreach Document for What s an SSMP?
DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials
Bridges & Culverts Condition by Quantity
3.4.3 What condition is it in? Approximately 93% of the municipality s bridge structures are in good to excellent condition, with the remaining 7% in fair condition. As a result, the municipality received
Proposed General Plan Update Goals, Policies, and Implementation Actions
Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance
SANITARY SEWER BACKUP. Causes & Prevention
SANITARY SEWER BACKUP Causes & Prevention A. PURPOSE The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups. 2. It provides
Contracting Opportunities Vendor Day May 17, 2011
Customer Care Team Contracting Opportunities Vendor Day May 17, 2011 Customer Care Team: What We Do Team Office customer advocacy and contracting Customer Relations Group call centers, claims, special
UVDB empowered by Achilles
UVDB empowered by Achilles DISAB Centurion: High Performance Wet/Dry Materials Handling Unit DISAB Centurion: High performance vacuum tanker that will vacuum dry or wet material The DISAB can vacuum material
City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007
City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 1/12/2007 1 Briefing Purpose Provide update on Wastewater Collection Activities
REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE
REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE Submit Proposals to: Town of Woodside Public Works Department 2955 Woodside
CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall
CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection
SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND
SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND Wastewater Utility Overview In the late 1950 s, the Village of Old Forge began to realize the impacts of dumping sewage in the Moose River.
Unauthorized Discharges and Sanitary Sewer Overflows
TCEQ REGULATORY GUIDANCE Field Operations Support Division RG-395 Revised April 2011 Unauthorized Discharges and Sanitary Sewer Overflows What does this document cover? The Texas Commission on Environmental
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,
Sanitary Sewer Master Plan
, Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper C-4-04 CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES Brad Jenson
City of Bakersfield Public Works Department Sewer System Management Plan December 2014
City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals
Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014
Relining of Water Mains with Flexible High Pressure Pipelines Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014 Aging water main infrastructure The American Society of Civil Engineers
REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION
REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION ABSTRACT Chris L. Windley PE, McKim & Creed, Inc. Ben R. Latino, Jr., PE, McKim & Creed, Inc. Greg Anderson, PE, McKim & Creed, Inc. When designing to
Installation of Large Diameter Buried Pipes
Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants
Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets
*Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; [email protected] Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana
A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015
A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015 Infiltration/Inflow (I/I) I & I Reduction: Three-Prong Attack
NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES Brad Jenson
Foul Drainage, systems and responsibility. Environmental Protection
Foul Drainage, systems and responsibility Environmental Protection The Building Act 1984 The Building Act 1984 can be used to deal with unsatisfactory provision for drainage and appliances which are harmful
SAWS SSO Reduction Program
SAWS SSO Reduction Program Jeff Haby, P.E. Director Sewer System Improvements February 20, 2014 TMDL Implementation Plan Technical Committee Overview Sanitary Sewer Overflows Consent Decree Overview Major
Clean Water State Revolving Fund (CWSRF) Requirements and Guidance for a Fiscal Sustainability Plan (FSP)
Clean Water State Revolving Fund (CWSRF) Requirements and Guidance for a Fiscal Sustainability Plan (FSP) Maine CWSRF Fiscal Sustainability Plan Requirements Starting October 1, 2014, a Fiscal Sustainability
Module 3 : Sewer Material. Lecture 3 : Sewer Material
1 P age Module 3 : Sewer Material Lecture 3 : Sewer Material 2 P age 3.1 Important Factors Considered for Selecting Material for Sewer Following factors should be considered before selecting material for
SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE
SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final
GIS Applications for Regulatory Compliance
4 GIS Applications for Regulatory Compliance Uzair (Sam) M. Shamsi Many cities in the world especially in the United States and Canada are dealing with regulatory enforcement actions for sewer overflows,
SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.
SEPTIC SYSTEMS Who Has A Septic System? Approximately 30 percent of Connecticut s population is served by on-site subsurface sewage disposal systems (a.k.a. septic systems). This means a large percentage
EPA Region 4 Introduction to Conducting Evaluations of Municipal Wastewater Collection System Management, Operation, and Maintenance Programs
EPA Region 4 Introduction to Conducting Evaluations of Municipal Wastewater Collection System Management, Operation, and Maintenance Programs Version 1.0 PURPOSE & DISCLAIMER This document is the work
Sewer System Management Plan University of California Kearney Agricultural Research & Extension Center 9240 S. Riverbend Ave.
Sewer System Management Plan University of California Kearney Agricultural Research & Extension Center 9240 S. Riverbend Ave. Parlier, CA 93648 Wastewater ID # 5SSO11453 1 Goals 1.1 Regulatory Requirements
Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards
Potential Safety Hazards Required items Potential PPE None Additional References - Collection System Related Work Practices & Forms Jet Truck Cleaning Work Practice (Do not drive on peoples driveway) CDL
OVER-HEAD SEWER ASSISTANCE GRANT
OVER-HEAD SEWER ASSISTANCE GRANT The Village of North Aurora has a vested interest in the proper operation of the North Aurora sanitary system. Understanding that some residential users of the sanitary
Village of St. Louis Sewer Back-up Policy
Village of St. Louis Sewer Back-up Policy The Village of St. Louis is responsible for maintaining sewer mains and manholes, which are located in public rights-of-way (Village and Provincial maintained
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
CLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
Storm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
Florida Department of Environmental Protection
Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,
Pine Creek Culvert Upgrade $ 560,000. Located at exiting hump dike, just south of Fire Training Center
To: BOS From: Joseph Michelangelo, P.E. Director of Public Works Re: CDBG-DR Pine Creek Culvert Upgrade Date: April 20, 2015 On June 19, 2014, the Town of Fairfield was awarded the above referenced project
Does Part of My Basement Floor Have to Be Removed to Install. Where Does the Water from the Sump Pump Go?...Page 5
PROTECTIVE PLUMBING - WHAT IS IT? TABLE OF CONTENTS Protective Plumbing What is it?...page 1 What is Foundation Drainage?...Page 2 What is a Sump Pumping System?...Page 4 Does Part of My Basement Floor
Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation
Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation Dan Broderick Director of Pipeline Rehabilitation ACHEN-GARDNER ENGINEERING,
Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective
Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Building the Foundation for an Effective Asset Management Program Scott D. Kelly, P.E. Assistant City Administrator
Introduction to Pressure Pipe Rehabilitation with CIPP
Introduction to Pressure Pipe Rehabilitation with CIPP Founded in early 1990 s RS Technik is a global leader in the rehabilitation of underground pipes RS Technik uses Cured-in- Place (CIPP) technology
CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is
~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions
CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R
CCTV PIPE INSPECTION AND EVALUATION For RUNWAY 17L-35R At ST. PETERSBURG CLEARWATER INTERNATIONAL AIRPORT February 2011 CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R ST. PETERSBURG CLEARWATER INTERNATIONAL
Sewer systems: Failures and rehabilitation
Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting
ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems
ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems Please see the DEFINITIONS of terms at the end of this section. If you have any questions about these definitions, do not understand a question,
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water
Addressing SSOs in Austin, Texas: Initial Call to Final Fix
Addressing SSOs in Austin, Texas: Initial Call to Final Fix Gopal K. Guthikonda, P.E., Barbara L. Wilde, Steven W. Schrader, P.E., and Rajendra P. Bhattarai, P.E. Austin Water Utility City of Austin 2600
Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010
Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010 A. Purpose The purpose of this policy is to explain how and why sewer or stormwater backups occur, what to do in the event a homeowner
by Leonard Friesenhahn, P.E.
by Leonard Friesenhahn, P.E. of sight, out of mind is an adage your top administrators may apply to your campus Out wastewater collection system but as a facilities professional, you know how serious a
CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center
CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center Thomas A. Fishbaugh Ohio RCAP What is CMOM? CMOM: Capacity,
Platte River Interceptor Slipline Rehabilitation
Platte River Interceptor Slipline Rehabilitation Owner: Metro Wastewater Reclamation District Contractor: American West, Denver CO Slipline Pipe Manufacturer : Hobas Pipe USA Presented by: Tom Furie, Area
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University
Aquatera 2015/16 Business Plan Highlights
Who We Are Aquatera 2015/16 Business Plan Highlights Aquatera is a full-service utility corporation the provider of choice for governments, businesses, and communities. Our business is to provide high-quality