Rehabilitation or Replacement? That Is The Question
|
|
|
- Cornelius Bell
- 10 years ago
- Views:
Transcription
1 Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014
2 Overview Project Background Existing Sewer Condition Flow Projections and Impact Replacement/Rehabilitation Alternatives Evaluation of Rehabilitation Technologies Summary/Conclusions
3 Project Background Existing Lower Walnut Creek Interceptor Approximately 16,000 LF of 48-inch and 54-inch gravity sewer Reinforced concrete pipe installed around 1975 Located in existing 100 wide utility easement Thirty-two (32) manholes primarily brick construction Discharges to concrete octagon shaped junction box Siphon across Walnut Creek to COR Walnut Creek Pump Station
4 Project Background
5 Existing Sewer Condition 2012 CCTV and limited manhole inspections indicated significant corrosion in the majority of the pipe sections. Corrosion pipe defect scoring ranged from 3 to 5
6 Existing Sewer Condition Limited inspections on 4 manholes Moderate hydrogen sulfide corrosion in the concrete manholes Missing mortar in the brick manholes
7 Existing Sewer Condition Limited structural analysis for greenway trail construction: Indicated pipe sections could fail under certain loading conditions The results of this analysis highlighted the need for a rehabilitation technology that provides structural integrity independent of the existing host pipe
8 Flow Projections and Future Pipe Sizing 2040 planning horizon Average daily flow of 16.4 mgd Peak flow of 69.6 mgd Anticipated single replacement in 66-to 72-inch range. If rehabilitation was selected, parallel pipe in 54-inch to 60-inch range
9 Replacement/Rehabilitation Alternatives CORPUD initiated an evaluation of multiple rehabilitation technologies and replacement methods for largediameter gravity sewer. The evaluation included four alternatives: 1. A single replacement interceptor 2. A single parallel interceptor replacement 3. Rehabilitation of the existing 48-inch and 54-inch interceptor and construction of a parallel interceptor 4. A combination of Alternative 2 and Alternative 3
10 Rehabilitation Technology Evaluation Rehabilitation technology for the LWC should provide the following: Applicable to the LWC pipe sizes and materials Corrosion resistance inherent to the rehabilitation technology materials without additives or field-applied coatings or sealants Stand-alone structural characteristics Reduced requirements for manned entry during installation
11 Rehabilitation Technology Evaluation 12 technologies reviewed 3 selected for further investigation: Segmented sliplining Geopolymer spray-in-place pipe Cured-in-place pipe (CIPP) 7 criteria to assess the pipe renewal methods: Flow capacity and diameter range Structural integrity Corrosion resistance Expected useful life Construction factors Social costs Previous experience with the City
12 Rehabilitation Technology Evaluation The Environmental Protection Agency (EPA) characterizes renewal of gravity sewer mainlines as repair, replacement, or rehabilitation Repair techniques are generally referred to spot or point repairs and not applicable to this project Replacement techniques make no use of the existing pipe structure and a new stand-alone pipe is provided, such as sliplining Rehabilitation techniques are defined as those that utilize the existing pipe structure, such as CIPP or sprayin-place pipe
13 Replacement - Segmented Sliplining One of the earliest forms of pipeline rehabilitation recorded, with installations dating back to the 1940s The process involves installing a smaller diameter carrier pipe within the existing host pipe by pushing or pulling the carrier pipe into place and filling the annular space between the two pipes with grout The final product provides a new pipe with adequate structural stability and a projected life expectancy of between years
14 Replacement - Segmented Sliplining There are many different types of piping materials that have been successfully used for sliplining applications The three generally utilized pipe materials for segmented sliplining are: Glass-reinforced plastic (GRP)/fiberglass reinforced plastic (FRP) Polypropylene (PP) PVC (closed profile) Will require a reduction in the capacity of the pipe
15 Replacement - Segmented Sliplining Pipe pushing force and push lengths for each type of sliplining pipe material are project dependent Grouting is required to seal the annular space between the new, slipline pipe and host pipe. A benefit of a segmented installation approach involves the potential to install the carrier pipe without having to bypass the flow during the sliplining installation
16 Replacement - Segmented Sliplining Evaluation Criteria Sliplining - Segmented Flow Capacity/Diameter Range Reduction of pipe capacity of approximately 20-25% based on LWC slope. Diameter reduction of approximately 10% depending on pipe material selected. Structural Integrity Corrosion Resistance Expected Useful Life Construction Factors Social Costs Previous Experience with City Excellent. Structural strength of the slipline pipe is independent of the host pipe. High years May not require bypass pumping. Requires excavation of installation pits depending on material/length of push. Residents could be impacted by noise and limited access due to staging of equipment. Yes
17 Rehabilitation - Geopolymer Centrifugally Sprayed-In-Place Pipe The most utilized material for rehabilitating large-diameter concrete pipes and concrete structures is a Portland cement-based cementitious mortar Recent advancements in the development of geopolymer-based materials with anti-microbial systems now provide a renewal system applicable for large-diameter piping systems and structures that are subjected to corrosive environments
18 Rehabilitation - Geopolymer Centrifugally Sprayed-In-Place Pipe Evaluation of the geopolymer technology indicated that, to accurately identify the associated cost for completing rehabilitation of the 48-inch and 54-inch gravity sewers, several key items would need to be evaluated, including: Bypassing of wastewater flows if necessary, based on the size of the parallel line Equipment setup for centrifugal casting Application thickness
19 Rehabilitation - Geopolymer Centrifugally Sprayed-In-Place Pipe Evaluation Criteria Flow Capacity/Diameter Range Structural Integrity Corrosion Resistance Expected Useful Life Construction Factors Social Costs Previous Experience with City Geopolymer Coating Negligible. Geopolymer application will only be ½-inch thicker than original deteriorated thickness of concrete pipe Excellent High, but limited age on existing applications in sanitary sewer years May require bypass pumping of a minimum of two sections of interceptor at a time if parallel line is not available to convey flow. Receiving surface must be cleaned and all loose material removed Does not require excavation pits on both sides. Residents could be impacted by noise and limited access due to staging of equipment. None
20 Rehabilitation - Cured-In-Place Pipe (CIPP) CIPP was the initial product utilized for rehabilitating deteriorating utility piping, with the first known installation dating back to It is estimated that approximately 40,000 miles of CIPP liners have been installed worldwide to date. Basic CIPP concept involves resin impregnation of a felt/ fiberglass tube by use of a pinch roller type assembly, with needle felt tubing being saturated at a controlled volume per length of proposed installation. Following resin impregnation, the tubing is inserted within a host pipe using water or air pressure and cured by the introduction of heat, UV light or ambient temperature
21 Rehabilitation - Cured-In-Place Pipe (CIPP) Currently there are many variations in method of installation, tube construction, resin systems and curing methods. Structural enhancements in CIPP lining are more related to resin and tube material changes than installation and cure methods. Improvements/changes in installation method generally dictate the cure method and are generally driven by a cost saving advantage.
22 Rehabilitation - Cured-In-Place Pipe (CIPP) Evaluation Criteria Flow Capacity/Diameter Range Structural Integrity Corrosion Resistance Expected Useful Life Construction Factors Social Costs Previous Experience with City Cured-In-Place Pipe Negligible. CIPP liner will generally replace original deteriorated thickness of concrete pipe and flow characteristics of the pipe will be enhanced with reduced roughness and elimination of joints Excellent High years Required onsite resin impregnation will significantly affect the cost of installation. May require bypass pumping if parallel line is not available to convey flow. Does not require excavation pits, however due to the size of the CIPP liner tops of manholes will need to be removed. Yes (smaller diameter applications)
23 Discussion The analysis revealed that each of the three types of products/installation processes evaluated could be successfully employed on the LWC project. All of the products provide corrosion resistance When evaluating the soft costs associated with each option, the commonality that exists is the need for accessing the piping to install any of the products. Sliplining approach requires the most excavation Both the geopolymer and CIPP liner installation processes also require limited excavation.
24 Discussion The geopolymer and CIPP liner approaches offer the best solution from a hydraulic standpoint Geopolymer products have limited long-term data available on corrosion resistance in sanitary sewer environments The City has limited experience with geopolymer products and there are limited applications of the relatively new product in North Carolina.
25 Conclusions Based on presentation of the results and discussions with CORPUD, the client selected CIPP and segmental sliplining with fiber reinforced plastic/glass reinforced plastic (FRP/GRP) pipe to be further evaluated for applicability and cost in this particular situation
26 Conclusions Alternative Description Opinion of Probable Construction Cost 1 A single, replacement interceptor located in the same alignment as the existing interceptor and sized to carry the entire future flow. $29,704,000 2 A single, parallel interceptor replacement sized to carry the entire future flow and abandonment of the existing 48- inch and 54- inch interceptor. $27,053,000 3 Rehabilitation of the existing 48- inch and 54- inch interceptor and construction of a parallel interceptor sized to carry the remainder of the future flow. ~$31,000,000 to $33,000,000 depending on rehabilitation method 4 A combination of Alternative 2 (single, larger parallel interceptor) and Alternative 3 (rehabilitation/smaller parallel interceptor) to address areas with potential constructability issues. ~$28,250,000 to $28,550,000 depending on rehabilitation method
27 Conclusions Alternative 2 a single parallel interceptor replacement sized to carry the entire future flow and abandonment of the existing 48-inch and 54-inch interceptor offers the most viable and economical solution for the CORPUD. the parallel line sizes required for rehabilitation of the existing interceptors were only one to two typical pipe diameters smaller than the single replacement line the capital and social cost incurred to install the parallel lines in addition to rehabbing the existing lines outweighed the cost of a single replacement line. The Lower Walnut Creek Interceptor replacement is currently under design.
28 Contact Information: Chris Windley, PE Greg Anderson, PE
REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION
REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION ABSTRACT Chris L. Windley PE, McKim & Creed, Inc. Ben R. Latino, Jr., PE, McKim & Creed, Inc. Greg Anderson, PE, McKim & Creed, Inc. When designing to
Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology
2007 Pumper & Cleaner Environmental Expo International Wednesday February 7, 2007 Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology What is Cured-In-Place Pipe (CIPP)
San Antonio, TX July 28, 2011
Rehabilitation of a Deteriorated 60 RCP Wastewater Interceptor Using Competing Trenchless Technologies Bruce Cole, PE Corey Anderson, EIT TAWWA/WEAT Summer Seminar San Antonio, TX July 28, 2011 Wendy Martinez,
REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC
REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC What is really out there? DO YOU DIG IT? INDUSTRY CONCERNS UNEXPECTED DEVELOPMENTS
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort
Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort June 25, 2012 Thomas Gossiaux, PE (AECOM) Matt Raysin, PE (GCDC-WWS) Dave Barnas, PE (AECOM) Ed Tharp, PE (AECOM) Summary
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
Storm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
Rehabilitation Alternatives. MWEA Collection System Seminar October 1, 2009
Rehabilitation Alternatives MWEA Collection System Seminar October 1, 2009 Overview Types of Rehabilitation Trenchless Categories On-Line Replacement In-Situ Options Selecting the Best Solution Types of
CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper C-4-04 CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES Brad Jenson
Introduction to Pressure Pipe Rehabilitation with CIPP
Introduction to Pressure Pipe Rehabilitation with CIPP Founded in early 1990 s RS Technik is a global leader in the rehabilitation of underground pipes RS Technik uses Cured-in- Place (CIPP) technology
SPR PE Steel Reinforced Liner
ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
FY15 Gravity Sewer and Manhole Rehabilitation
Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE
Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014
Relining of Water Mains with Flexible High Pressure Pipelines Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014 Aging water main infrastructure The American Society of Civil Engineers
Structural Lining for Water Mains. Presenters: Stephen Marcino, PE and Micah Blate, EIT (JMT)
Structural Lining for Water Mains Presenters: Stephen Marcino, PE and Micah Blate, EIT (JMT) 2015 PA-AWWA Annual Conference Thursday, April 23 rd, 2015 Agenda 1. Introduction 2. Purpose of Lining 3. Lining
Trenchless Technology for Drainage Structures
Trenchless Technology for Drainage Structures Richard S. Williammee, Jr., MSCE, P.E. District Materials Engineer Fort Worth District TxDOT 2011 Transportation Short Course October 11, 2011 There are textbooks
CURED-IN-PLACE PIPE MINIMIZING RISK BY DEFECT CODING
North American Society for Trenchless Technology 2007 No-Dig Conference & Exhibition San Diego, California April 16-19, 2007 CURED-IN-PLACE PIPE MINIMIZING RISK BY DEFECT CODING Robert K. Lee, P.E. 1 1
REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND
North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper A-5-04 REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY
LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD
www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The
Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands
Waste Management Infrastructure Rehabilitation in the U.S. Virgin Islands The United States Virgin Islands is a group of islands in the Caribbean that are an insular area of the United States. The islands
NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES Brad Jenson
Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation
Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation Dan Broderick Director of Pipeline Rehabilitation ACHEN-GARDNER ENGINEERING,
REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542
1.0 INTENT REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES 1.01 It is the intent of this specification to provide for the reconstruction of pipelines and conduits by the installation of a resin-impregnated
Demonstration of an Innovative Large-Diameter Sewer Rehabilitation Technology in Houston, Texas
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper TA-T3-03 Demonstration of an Innovative Large-Diameter Sewer Rehabilitation Technology
Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District
Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Paul F. Wilson 1 and Robert J. Warren 2 1 1525 Faraday Ave, Suite 290, Carlsbad, California, USA 92008; e-mail: [email protected].
APPLICATION OF GLASS-REINFORCED PLASTIC TO SEWER REHABILITATION
North American Society for Trenchless Technology (NASTT) NO-DIG 2005 Orlando, Florida April 24-27, 2005 APPLICATION OF GLASS-REINFORCED PLASTIC TO SEWER REHABILITATION Lynn Osborn 1 1 ArmourGRiP Product
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets
*Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; [email protected] Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes
Installation of Large Diameter Buried Pipes
Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants
Trouble Shooting for Trenchless Liner Installation During Sewer Line Rehabilitation
Trouble Shooting for Trenchless Liner Installation During Sewer Line Rehabilitation Salam Khan*, P.E. and Christoph Dobson, P.E. Sacramento County Sanitation District 1 (CSD-1) 10545 Armstrong Avenue,
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
Water Main Lining A Sustainable Alternative to Open Cut Replacement
Water Main Lining A Sustainable Alternative to Open Cut Replacement Sean O Dell, PE Baxter & Woodman, Inc. B&W Client Seminar, Crystal Lake May 1, 2014 Agenda Why, What, When, Where, Who, How Reduction
THE ECOLOGICAL IMPLICATIONS OF TRENCHLESS PIPE REHABILITATION
THE ECOLOGICAL IMPLICATIONS OF TRENCHLESS PIPE REHABILITATION Bridget Donaldson Research Scientist Virginia Transportation Research Council Transportation Infrastructure Deterioration of pipes is a growing
Trenchless Construction Technology and Issues
Trenchless Construction Technology and Issues Dr. Mohammad Najafi, P.E., F. ASCE Director, Center for Underground Infrastructure Research & Education (CUIRE) Professor and Director of Construction Engineering
PIPE REHABILITATION. Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes
PIPE REHABILITATION Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes About Us An HDPE after mechanical insertion into an egg-shaped brick work sewer sized 1400 x 2100 mm (or 56
Culvert Rehabilitation Practices
Culvert Rehabilitation Practices TABLE OF CONTENTS Report Objective...1 Introduction...1 General Culvert Rehabilitation...3 Culvert Cleaning...3 Grouting...4 REHABILITATION METHODS Slip Lining...5 Sprial
Flowtite Jacking Pipe
U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe
PRODUCT CATALOGUE. for. SMARTPHONE / WEBSITE / DIGITAL EDITION / BOOK / ipad / GPS
PRODUCT CATALOGUE for This product catalogue has been downloaded from COSSD.com. Listed products/services and their descriptions are shown as supplied by the title company COSSD does not guarantee the
by Leonard Friesenhahn, P.E.
by Leonard Friesenhahn, P.E. of sight, out of mind is an adage your top administrators may apply to your campus Out wastewater collection system but as a facilities professional, you know how serious a
MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.
MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade
Presented by: Scott E. Belz Project Manager- URS Corporation Robert P. Kelly, P.E. Director of Engineering-City of Westlake James J. Smolik, P.E.
Presented by: Scott E. Belz Project Manager- URS Corporation Robert P. Kelly, P.E. Director of Engineering-City of Westlake James J. Smolik, P.E. Engineer-City of Westlake City of Westlake Facts Founded
Sewer systems: Failures and rehabilitation
Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting
02780 LINER FOR SEWER REHABILITATION
Section 02780 Liner for Sewer Rehabilitation Page 02780-1 (Revised 11/06/09) 02780 LINER FOR SEWER REHABILITATION SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Part 1 GENERAL Part 2 PRODUCTS Part
APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR
APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM Stadium Reconstruction EIR Appendices \ AECOM Technical Services, Inc 401 West A Street Suite 1200 San Diego, CA 92101 www.aecom.com 619-610-7600 tel 619-610-7601
Repair or Replacement - Band-Aids vs. Surgery
Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing
PORTLAND BES ADVANCES IN SEWER MAINTENANCE AND REPAIRS BY OPERATING MULTIPLE CIPP CREWS.
North American Society for Trenchless Technology 2007 No-Dig Conference & Exhibition San Diego, California April 15-20, 2007 Paper # PORTLAND BES ADVANCES IN SEWER MAINTENANCE AND REPAIRS BY OPERATING
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598
Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**
Collection Systems Technology Fact Sheet Sewers, Conventional Gravity
United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment
Force Main Condition Assessment: New Technologies & Case Studies
Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
ENGINEERING DESIGN GUIDE FOR REHABILITATION WITH CURED-IN-PLACE PIPE Second Edition
ENGINEERING DESIGN GUIDE FOR REHABILITATION WITH CURED-IN-PLACE PIPE Second Edition Lanzo Company History Lanzo has been a leading competitor in the construction industry for over 45 years. Lanzo was founded
CHALLENGES IN LINING A 100 YR OLD BRICK SEWER
North American Society for Trenchless Technology 2007 No-Dig Conference & Exhibition San Diego, California April 15-20, 2007 CHALLENGES IN LINING A 100 YR OLD BRICK SEWER Brad Jenson 1, Keith Hanks 2,
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.
Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. 1 Pipe Bursting A Mature and Diverse Trenchless Technology December 10, 2014 1:00 3:00 pm Eastern How to Participate Today
SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER
Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating
The Environmental Implications of Road Culvert Repair Technologies. Bridget Donaldson Senior Research Scientist
The Environmental Implications of Road Culvert Repair Technologies Bridget Donaldson Senior Research Scientist Presentation Overview Culvert repair technologies Past and ongoing research by VCTIR Cured-in-Place
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
INSTALLATION OF INSITUFORM LINER
PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation
DEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
GENERAL SPECIFICATIONS AND GUIDELINES FOR INSTALLATION MASTERLINER CURED-IN-PLACE PIPE SYSTEMS
GENERAL SPECIFICATIONS AND GUIDELINES FOR INSTALLATION OF MASTERLINER CURED-IN-PLACE PIPE SYSTEMS 34 TABLE OF CONTENTS 1.00 INTRODUCTION 2.00 SITE WORK PREPARATIONS 3.00 THE PRODUCT AND COMPONENT MATERIALS
Let Us Give Utilities the Respect that they Deserve.
Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous
City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS
City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS Page No. 1.0 INTRODUCTION...2 2.0 PIPE MATERIAL CONSIDERATIONS...3 2.1 RCP...
Meeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
THAT FIT SOLUTIONS. profile COVER STORY INLAND WATERS POLLUTION CONTROL, INC., DETROIT, MICH.
COVER STORY SOLUTIONS THAT FIT profile W When aging sewer lines in Detroit and the surrounding area begin INLAND WATERS POLLUTION CONTROL, INC., DETROIT, MICH. SERVICE AREA: CIPP lining (water, sewer and
Appendix A: Acceptable pipe and fitting materials
Watercare Services Limited Water and Code of Practice Content from the NZS 4404:2010 Land development and subdivision infrastructure has been reproduced for use in the Infrastructure Design s Manual for
Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems.
Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems. Aging pipeline infrastructure and industry s inability to evaluate and inspect has left many engineers and plant managers
HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS
HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS Shiwei William Guan, Ph.D. Vice President, R&D and International Business Madison Chemical Industries Inc. 490
REHABILITATION METHOD FOR INCREASING FLOW VELOCITY AND REDUCING SEDIMENTATION
.asu/ North American Society for Trenchless Technology (NASTT) NO-DIG 2005 Orlando, Florida April 24-27, 2005 REHABILITATION METHOD FOR INCREASING FLOW VELOCITY AND REDUCING SEDIMENTATION Hwan-Kook Hwang
IS THAT LINER THICK ENOUGH?
IS THAT LINER THICK ENOUGH? Philip McFarlane, Opus International Consultants Ltd ABSTRACT The amount of pipeline rehabilitation being undertaken in New Zealand is increasing each year. Larger diameter
Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009
State Revolving Fund Project Plan Overview Public Meeting June 10, 2009 What is the OMI? The OMI is the Oakland Macomb Interceptor Sewer. The OMI transports much of the sanitary sewage from Oakland and
The leader in trenchless rehabilitation
The leader in trenchless rehabilitation The trenchless rehabilitation of underground water and sewer pipes is a solution that s more ecological, more cost efficient, faster and less invasive for taxpayers
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University
Platte River Interceptor Slipline Rehabilitation
Platte River Interceptor Slipline Rehabilitation Owner: Metro Wastewater Reclamation District Contractor: American West, Denver CO Slipline Pipe Manufacturer : Hobas Pipe USA Presented by: Tom Furie, Area
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect
Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts
Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts Outline Update on Soapstone Emergency Response Provide project background Provide project purpose & need Present proposed
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines Jeff Schell General Manager United Pipeline Middle East, Inc. Introduction HDPE Liners A cost effective and environmentally beneficial
Pipeline Asset Management: From Assessment to Prioritized Projects List
PROGRAM MANAGEMENT INEERING Pipeline Asset Management: From Assessment to Prioritized Projects List TAWWA / WEAT Summer Seminar July 28, 2011 PLANN NING ENG Andrew Hunt, PE Asset Management Project Manager
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Interactive Decision Tree Automates Sewer Rehabilitation Planning
Interactive Decision Tree Automates Sewer Rehabilitation Planning IWPCA Annual Conference June 5, 2008 Rodney Moeller, P.E., John Schroeder, P.E. BCEE, C. Timothy Fallara, P.E. & Mel Meng, P.E. Agenda
SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES
1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other
Waste Collection Systems
Waste Collection Systems System Maintenance and Repair Maintenance and Repair Training Objectives To gain an understanding of: System Maintenance and Repair vocabulary System Maintenance and Repair techniques
