PJM Generator Interconnection Request Queue #V3-009 Desoto-Tanners Creek 345 kv Facilities Study

Similar documents
Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

TRANSMISSION AND SUBSTATION PROJECTS

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Minimizing Impact of Electric Utility Outages with Backup Generation

Transmission Related Station Power Use at Substations

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

OVR Three-Phase Recloser and PCD Control Style Guide 1VAL SG October 13, 2009 Revision F

N O W A V A I L A B L E

Technical Specification Of Substation Protection & Control System with IEC BHEL s Perspective

Generation and Transmission Interconnection Process

6. The estimated costs here do not include any applicable ITCC tax

TRANSMISSION Field Services (January 30, 2014)

SPECIFICATION COG-2007

Smart energy, clean energy, today s energy. The. Mariah. wind power project

Electric Power 2005 in Chicago. Dr. Aiham Alsammarae Minister Of Electricity Iraq

Addendum #2 Contract UK-11-13

Morris S. Stover, P.E. Sponsor, Transmission Area

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

DTE Energy: an Enterprise PI approach

Introduction to The Trans Bay Cable Project

ABB PSPS Erich Steinmann; Generator control-2013

16 West Coast Regional Plan

PJM LMP Market Overview

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis

SCADA Systems Automate Electrical Distribution

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

Seattle City Light s Asset Management Program

Offshore Wind. IEEE Boston PES - November 16, 2010

T5 CHARLOTTE REGION WEST DATA CENTER PARK

Il Progetto INTEGRIS. Risultati e nuove prospettive per lo sviluppo delle Smart Grid October 2nd 2013 Brescia

Chapter 7 - Appendix A

Basics in Energy Information (& Communication) Systems Substation Automation

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Tehachapi Wind Energy Storage Project (TSP)

Industrial IT for Substation Automation & Protection

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR)

About Southern California Edison

TERMS AND CONDITIONS

Chapter 1. Network Structures

Power products and systems. Intelligent solutions for power distribution Zone concept

IEEE Smart Grid Series of Standards IEEE 2030 TM (Interoperability) and IEEE 1547 TM (Interconnection) Status. #GridInterop

Get Into Energy Math Quiz 12 Answer Key Fractions and Decimals

Q140 Cluster Addendum

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Grid connection of near shore wind farms

Capital Project Prioritization Process (CPPP)

Transmission Planning in the ERCOT Interconnection

University of Maryland College Park District Energy System. IDEA Campus Energy Conference February 9, 2012

IESO Supply Deliverability Guidelines

FIXED CHARGE: This is a cost that goes towards making the service available, including

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

January 23, Minimum Design Standards Task Force

Design Criteria Additions Related To PJM IPP R02 project

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

ABB Power Systems. Substations References

THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM. Lawrence P. Hayes FirstEnergy Corp.

Fiber Winds Renewable Energy Project. Over $87 Million in U.S. Government Subsidies

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

Contestability on the Distribution System ESB Networks Key Principles and Processes Paper

Modular Systems wind portfolio overview Power Collection and Grid Connection products

Passion for Offshore. Wind Power & Renewables Division Market Unit Offshore

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

Basics in Energy Information (& Communication) Systems Summary Substation Automation

A. 5MWp SPV Plant at Khimsar, Rajasthan. B. 5MWp SPV Plant Installed Technologies. D. 5MWp SPV Plant Challenges. E. 5MWp SPV Plant - Performance

Electric and Natural Gas Distribution Systems. Presented by Brian Beam New Jersey Board of Public Utilities Division of Reliability & Security

Grid Solutions. PROJECT MANAGEMENT SOLUTIONS for infrastructure projects from Border States. Border States

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER. tgood.com. Energy. Fast.

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014

Emergency Response Solution- Keyspan

Operation and Control Microgrid and Distributed Generation. Mohammad Shahidehpour Illinois Institute of Technology

From: Jean Hicks [ ] Sent: May 4, :55 AM To: SiteC Review / Examen SiteC [CEAA] Subject: Public Submission

Draft Electric Resource Plan Technical Workshop. Technology Screening Analysis

Oncor s Pioneering Transmission Dynamic Line Rating (DLR) Demonstration Lays Foundation for Follow-On Deployments

Who is National Grid?

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE

Achieving Operational Efficiencies through On-Line Substation Monitoring. Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION FEASIBILITY STUDY FOR PROPOSED XXXXXXXX GENERATION ON THE SIERRA BLANCA-FARMER 69 KV LINE

ITP Evaluation Process Plan Cross-Tie Transmission Line

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

Technical Requirements for Renewable Energy Systems Connected to the Low Voltage (LV) Network via Inverters

Transcription:

PJM Generator Interconnection Request Queue #V3-009 Desoto-Tanners Creek 345 kv Facilities Study March 2016

V3-009 Desoto Tanners Creek 345 kv Facilities Study Report A. Facilities Study Summary 1. Project Description EDP Renewables north America LLC (EDPR) proposes to install PJM Project #V3-009, a 200 MW generating facility comprised of 111 1.8 MW wind turbine generators connecting to the American Electric Power (AEP) Desoto Tanners Creek 345 kv circuit at the substation constructed for the U2-090 IPP (Losantville Station). 2. Amendments/Changes to the Impact Study Report The impact study was a combined report for V3-007, V3-008, and V3-009. The facilities studies have been requested as separate reports. Studies documented in the Impact Study Report pre-date implementation of a Light Load criteria in the RTEP process Studies have been re-tooled to reflect withdrawals or reductions of projects in earlier queues. 3. Interconnection Customer Schedule EDPR has proposed the following schedule for their collector station: Receive back feed from AEP: May 17, 2019 Commercial Operation Date: October 31, 2019 4. Scope of Customer s Work Complete generation collector station including step up transformers. 345 kv connection from generation station to switching station. Dual fiber optic tie between stations. Station communications lines. PJM Interconnection 2016. All rights reserved 2 CERA #7098989

5. Description of Transmission Owner Facilities Included in the Facilities Study Direct Connection Work Install one 345 kv breaker to Losantville station to accommodate the connection for V3-009. (Network Upgrade n4780) Install 345 kv metering to the new line exit for the V3-009 connection. (Network Upgrade n4781) Network Upgrade Work None required. 6. tal Cost of Transmission Owner Facilities Included in the Facilities Study: Direct Connection facilities $1,183,400 Network Upgrade facilities $0 tal Cost $1,183,400 7. Summary of Schedule Milestones for Completion of Transmission Owner Work Included in Facilities Study: May 17, 2019 Interconnection Station ready for service B. Transmission Owner Facilities Study Results 1. Transmission Lines New None. 2. Transmission Lines Upgrades None. 3. Substation Facilities New Losantville 345 kv Station Add one 345 kv breaker to create a new line connection for the V3-009 IPP project. Add 345 kv metering for the new line exit within the Losantville station footprint. 4. Substation Facilities Upgrades None PJM Interconnection 2016. All rights reserved 3 CERA #7098989

5. Metering & Communications Physical Requirements - Install (1) - Steel -3PH Metering steel structure per CT/PT/SA application. - Install (1) - Foundation -Metering steel structure foundation. - Install Control Cable- run thru new installed trench. Metering Equipment Use standards SS-497001, DM 51.01 to add PT and CT & primary and backup SEL734 - Install (3) - Free standing CTs and PTs between wavetrap and the bus. - Install (3) - 84kV MCOV Station Class Arrester. The metering requirements are published in: AEP Metering and Telemetering Requirements for AEP Transmission Customers (document SS-490011). Communication requirements are published in the AEP SCADA RTU Requirements at Transmission Interconnection Facilities (document SS-500000). 6. Environmental, Real Estate and Permitting Issues Since the interconnection location is proposed at an existing station, no additional permitting issues are expected. 7. Summary of Results of Study Cost Estimates for AEP Network Upgrade Engineering Material Construction Misc. tal Number Losantville n4779 $27,400 $414,900 $123,100 $276,300 $841,700 Metering n4780 $21,800 $135,300 $63,200 $121,400 $341,700 tal $49,200 $550,200 $186,300 $397,700 $1,183,400 Schedule January 9, 2018 March 6, 2018 August 7, 2018 April 9, 2019 May 17, 2019 Station design begins Material ordered Station construction begins Outage begins Outage ends PJM Interconnection 2016. All rights reserved 4 CERA #7098989

Assumptions System conditions allow scheduled outages to occur. ISA executed by March 1, 2016. 8. Information Required for Interconnection Service Agreement Direct Interconnection Cost Breakdown Direct Material - $550,200 Direct Labor - $235,500 Indirect Material - $45,500 Indirect Labor - $352,200 tal $1,183,400 Network Upgrade Cost Breakdown None. PJM Interconnection 2016. All rights reserved 5 CERA #7098989

Figure 1 PJM Interconnection 2016. All rights reserved 6 CERA #7098989

Losantville Station Desoto-Tanners Creek 345 kv Circuit #1 Circuit #1 Keystone Sorenson ~13.8 miles ~70.7 miles Fall Creek Circuit #2 ~13.8 miles ~70.7 miles Circuit #2 Transformer #3 Desoto 345 kv Transformer #1 Headwaters U2-090 G V3-008 G POI G G V3-009 V3-007 Tanners Creek 345 kv (not completely shown) ITO IC Legend Point of Interconnection (POI) be Constructed Interconnected Transmission Owner Interconnection Customer Figure 2 PJM Interconnection 2016. All rights reserved 7 CERA #7098989