PRE-CHLORINATED PIPE BURSTING PROJECT: LARGEST EVER IN NORTH AMERICA

Similar documents
LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM

Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City Wide Program

Pipe bursting provides viable alternative for rehab work By Greg Key, U.S. Pipe

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

A Revolution for Telecom, Electric, Gas, & Water"

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

FY08 SEWER POINT REPAIRS BID TABULATION

WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW

Pneumatic Pipe Bursting

Trenchless Methods for Service and Mainline Pipe Rehab and New Install

Pipe Bursting Water Lines with Confidence

MUNI OWNER S CHRONICLE OF REPLACING 35 MILES OF ASBESTOS CEMENT WATER MAIN UTILIZING PRE-CHLORINATED WATER MAIN BURSTING

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy

Sewer Rehabilitation Design Requirements

Water Main Lining A Sustainable Alternative to Open Cut Replacement

City of Mill Valley Sewer Capital Improvement Plan

Water CIPP What to Do When You re Between a Fence and a Hard Place

Water Transmission & Sewer Force Main Renewal 16 through 60

Dewatering - Time and Cost Relief by way of Trenchless Construction

Sustainable trenchless rehabilitation of supply pipelines applying static pipe bursting or close-fit lining

Sewer Line Rehabilitation

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

City of Hilshire Village Pine Creek Ln Reconstruction

UNDERGROUND INFRASTRUCTURE SPECIALISTS TABLE OF CONTENTS

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS

City of Balch Springs, Texas. Request for Proposal (RFP ) Pipe Bursting Sewer Line Replacement

INTERNATIONAL PIPE BURSTING ASSOCIATION. Guideline for Pipe Bursting

Emerging Technologies in Wastewater Collection Systems

PORTLAND BES ADVANCES IN SEWER MAINTENANCE AND REPAIRS BY OPERATING MULTIPLE CIPP CREWS.

Guaranteed Solutions for Solving Sewer Backups

King County/Skyway Water & Sewer District Infiltration and Inflow Reduction Project

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY

North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show. Sacramento, California March 3-7, 2013

Morgan County Quality Water District Water Main Flood Damage Repair Project

Analyzing The Bread & Butter Benefits of Sewer Main Pipebursting. Matt Werth General Manager PM Construction

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Dry Weather Flow from Footing Drains and Service Connections

RENEW. A Water Main Cleaning and Lining Program Designed to Improve Water Quality and Service

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Design Criteria & Service Goals

Special Specification 7021 Water Main and Sewer Line Replacements

BROOKS BRIDGE WATERLINE REHABILITATION

Pipe Bursting. Chapter 16

THE BIG FIX: Public works administration would be easy if infrastructure. San Diego s Sewer Renewal Program. By Steve Gibbs


CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES

DEPARTMENT OF ENVIRONMENTAL QUALITY

Close-Out Documents... 9

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting

CONSTRUCTION COST OF UNDERGROUND INFRASTRUCTURE RENEWAL: A COMPARISON OF TRADITIONAL OPEN-CUT AND PIPE BURSTING TECHNOLOGY SEYED BEHNAM HASHEMI

WATER MAIN REPLACEMENT

San Antonio, TX July 28, 2011

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

What is water main cleaning & lining

Western Europe. Pipe rehabilitation. Auger boring. CIPP works during the cold snap. Take-off by the Boeing plant. Expanding the market share

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair

INTERNATIONAL PIPE BURSTING ASSOCIATION. Guideline for Sewer Lateral Pipe Bursting

LS 2540 SEWER LATERALS AND INSPECTION TEES

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

RECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE TRANSACTION INSPECTIONS

Reference Guide for Obtaining Permits and Utility Services For New Construction

SECTION 15 AIR RELEASE VALVE ASSEMBLIES General

Sewer systems: Failures and rehabilitation

Section Installation of pipe and casing for sanitary sewer by methods of augering.

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Waste Collection Systems

by Leonard Friesenhahn, P.E.

Guidelines For Pipe Bursting of Potable Water Mains

POTENTIAL FOR THE APPLICATION OF TRENCHLESS REHABILITATION TECHNOLOGIES IN KENYA: A FOCUS ON PIPE BURSTING.

Item No. Description Estimated Unit Total Unit Total Unit Total Unit Total Quantity Price Amount Price Amount Price Amount Price Amount

NW Natural & Pipeline Safety

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Pipeline Asset Management: From Assessment to Prioritized Projects List

SECTION DISINFECTION OF PIPE AND WATER STORAGE FACILITIES

Michigan Department of Environmental Quality Drinking Water Asset Management. Wayne Pratt

Water Technology Fact Sheet Pipe Bursting

Guidelines for Pipe Bursting

SECTION SELECTIVE DEMOLITION

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Water and Sewer Utilities

OSU Extension FACT SHEET

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

DESCRIPTION OF WORK:

REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

Transcription:

North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper D-4-04 PRE-CHLORINATED PIPE BURSTING PROJECT: LARGEST EVER IN NORTH AMERICA Collins Orton 1, and Todd Grafenauer 2 1 Product Specialist, TT Technologies, Aurora, Ill. 2 Director of Business Development, Murphy Pipeline Contractors, Jacksonville, Fla. ABSTRACT: The versatility and capability of the static pipe bursting method continues to accelerate thanks in large part to contractors like Murphy Pipeline, Inc., Jacksonville, Fla., that continue to push the method to achieve better, more effective results. A recent project in Livonia, Mich. demonstrates this point. With a population just over 100,000, Livonia is the eighth largest city in Michigan. Its average daily water demand is approximately 16 million gallons for its 38,000 residential, commercial and industrial users. As typical with many communities in the Detroit area, Livonia s infrastructure was constructed in 1940s, 50s and 60s and is beginning to deteriorate. A majority of the system was composed of cast iron and ductile iron pipe. The city of Livonia needed to replace approximately 23,000 feet of its undersized and deteriorated 6- and 8-inch cast iron and ductile iron water mains and the installation of about 4,000 feet of new main. This aged and undersized system had a history of breaks, along 14 different streets. The engineering firm developed construction contract documents that allowed the trenchless and traditional approaches to bid against each other, thereby allowing the bidding process to determine the most cost-effective means of replacement. Static pipe bursting with pre-chlorinated pipe proved to be the low-cost alternative. During the method pressure and disinfection testing are completed above ground, eliminating the installation of a temporary water distribution system, as well as the significant excavation associated with the traditional open-cut approach. Murphy Pipelines, Inc. was awarded the project. The project in Livonia was the largest pre-chlorinated static pipe bursting project ever completed in North America. 1. INTRODUCTION The city of Livonia needed to replace approximately 23,000 feet of its undersized and deteriorated 6, 8 and 12-inch cast iron and ductile iron water mains and the installation of about 4,000 feet of new main to loop dead ends. This aged and undersized system had a history of breaks, along 14 different streets. Engineering firm Hubbell, Roth & Clark, Inc. (HRC), Detroit, developed the project to upgrade the system. Construction contract documents were developed so they would allow the trenchless and traditional approaches to Paper D-4-04 - 1

be bid against each other, thereby allowing the bidding process to determine the most cost-effective means of replacement. 14 total bids were received on the project. A trenchless technique called pre-chlorinated pipe bursting proved to be the low-cost alternative, saving the city $212,000 over the second low bid of open-cut. During the method pressure and disinfection testing are completed above ground, eliminating the installation of a temporary water distribution system, as well as the significant excavation associated with the traditional open-cut approach. To complete the pre-chlorination bursting project, Murphy Pipeline was contracted utilized a Grundoburst 800G static pipe bursting system from trenchless equipment manufacturer TT Technologies, Aurora, Ill. 2. CITY OF LIVONIA, MI The city of Livonia receives water and wastewater services from the Detroit Water and Sewerage Department (DWSD). According to its Web site, the DWSD is the third largest water and sewer utility in the United States. With its beginnings dating back to the early 1800s, the department s original water system included wooden logs, brick and stone. Today, the utility has a 1,079-square-mile water service area and provides water services for approximately one million people in Detroit and three million people in the surrounding areas of southeastern Michigan. Wastewater service is provided to a 946-square-mile area that includes almost 35 percent of the state s population. 3. PRE-CHLORINATION BACKGROUND Since the first approval for the pre-chlorinated pipe bursting method in 2000, Murphy Pipeline has worked diligently to obtain approval from other states around the country. So far, 37 states in the U.S. have approved the process of pre-chlorinated pipe bursting because of the efforts of Murphy Pipeline. The project in Livonia would prove to be the largest pre-chlorinated pipe bursting project in North America so far. Pre-chlorinated pipe bursting utilizes HDPE pipe and entails the pre-assembly and testing of approximately 300- to 500-foot lengths of pipe above grade at a nearby staging location. The staging area is located away from the burst locations to further minimize the impact of construction to the community. Figure 1. Once the pipe is proven to be sound by the pressure and disinfection testing, a series of small excavations are made and the new pipe is pulled into place by bursting the existing main. A post-chlorination and flushing of the main is then performed and the new line is connected into the distribution system. Ultimately, all services are connected into the new main and the surface area is backfilled to preconstruction grade. The entire process is completed within a single day, 7 to 10 hours, thereby minimizing the disruption to area residents. Paper D-4-04 - 2

Figure 1. Pre-chlorinated HDPE pipe staging. 4. STATIC PIPE BURSTING Static pipe bursting has come to the forefront of trenchless methods in North America. During the static bursting process specially designed bladed rollers are pulled through an existing line by a hydraulically powered bursting unit. As the bladed rollers are pulled through, they split the host pipe. An expander attached to the rollers forces the fragmented pipe into the surrounding soil while simultaneously pulling in the new pipe. Figure 2. Figure 2. The static pipe bursting process. Paper D-4-04 - 3

Patented Quicklock bursting rods are linked not screwed together like traditional drill stems or other static systems. This system speeds the installation process as well as the breakdown procedure. The rods can be quickly removed one at a time at the exit pit as bursting is in operation. While HDPE is commonly used, new techniques and technologies are allowing contractors a choice when it comes to product pipe. Over the last several years various techniques have been developed that allow for the use of a range of product pipes with the static bursting method, including ductile iron, PVC, specially designed clay and steel. HDPE is still used as well, pre-chlorinated HDPE 5. PROJECT STATS For the Livonia project, HRC identified and grouped 16 priority areas into five separate project areas. 12 of the project areas were located in residential neighborhoods with lot lines between 40 to 100 feet apart. These areas had mature landscaping and historic oak trees. The 4 remaining project areas were in main thorough ways of the city with heavy traffic flow and businesses. As part of the specifications Murphy Pipeline crews could not begin installing water main in a new project area until final restoration was under way in the previous area. This helped minimized the time residents were disrupted by construction. Figure 3. Figure 3. Minimal disruption through the trenchless replacement method. Launch and exit pits measured approximately 5 feet wide by 12 feet long. Figure 4. Crews positioned pits as close as possible to proposed valves or hydrants, to limit the amount of total excavation. Figure 5. Typical pit depths ranged between 5 and 6 feet. Temporary shoring and bracing was also used throughout the project and open areas were fully surrounded with construction fencing. Figure 6 to 7. Paper D-4-04 - 4

Figure 4. Basic pit construction. Figure 5. Pits were located near tie in areas to minimize excavation. Paper D-4-04 - 5

Figure 6 Exit and launch pits on the project were properly shored. Paper D-4-04 - 6

Figure 7. Any open excavations were blocked off with safety fencing. For a typical bursting run, once pits were identified and prepared, Murphy Pipeline crews positioned the Grundoburst in the exit pit and prepared to pull in the 300-foot to 500-foot segment of pre-chlorinated 8-inch HDPE. Figure 8. Residents connected to the main being replaced that day only experienced a 6- to 10-hour interruption in water service before being reconnected. Crews typically began preparations around 7 a.m. and by noon the new prechlorinated HDPE was in place. Usually between 3 p.m. and 5 p.m., residents were reconnected to the water system. Paper D-4-04 - 7

Figure 8. Placing of the bursting unit in the exit (pulling) pit. 6. CONCLUSION This process was approved for water mains in Michigan 2005, however this was the first successful pre-chlorinated pipe bursting project in the state. It took six months longer than anticipated to award the contract, however, the work was completed on schedule. Furthermore, the cost savings to the city by using this technique were significant, enabling them to replace more pipe than originally anticipated. Due to the savings of the process, in total the city was able to replace 29,450 feet of undersized and deteriorated water mains, over a mile more than originally planned. The project received the APWA Environmental Project of the Year Award. Paper D-4-04 - 8