Water and Sewer Utilities
|
|
|
- Gwen Hunter
- 9 years ago
- Views:
Transcription
1 Water and Sewer Utilities Capital Improvement Program
2 Utilities Water and Sewer Requested - $98,295,000 - $97,792,600 Funded - $32,951,600 Sewer 53.3% Sewer 54% Water 27% Water Water 46% 46.7% Sewer 73% Funding Sources Reserve 13% Utility Connection Charges % Current Revenue 87% Utility Rates % Utility Funding - $32,951,600 Average Annual Current Revenues Utility Rates - $3,922,333 Connection Charges - $865,000 Total Average Annual Revenue - $4,787,333 53
3 City of Kirkland Capital Improvement Program WATER/SEWER UTILITY PROJECTS Funded Projects: 54 Project Number Prior Year(s) Funding Source Project Title Current External Reserve Debt Revenue Source WA th Ave NE Watermain Replacement 525, , , ,000 WA Water System Telemetry Upgrade 200, , ,000 WA th Ave S / 8th St S Watermain Replacement 553, , ,000 WA th Street Watermain Replacement 372, , , ,000 WA th Avenue S Watermain Replacement 325,000 53,000 53,000 53,000 WA th Street Watermain Replacement 467, , ,000 27,000 WA rd Street Watermain Improvement 440, , , ,000 WA th Street Watermain Replacement Phase 2 290, , , ,000 WA th Avenue NE Watermain Improvement 437, , , ,000 WA nd Avenue NE Watermain Improvement 505, , , ,000 WA th Avenue W Watermain Improvement 421, , , ,000 WA 0158 NE 112th Street Watermain Improvement 365, , ,000 WA 0159 NE 113th Place Watermain Improvement 373, , ,000 WA th Avenue NE Watermain Improvement 990, , ,000 WA 0161 Kirkland Way Watermain Replacement 90, , , ,000 90,000 WA 0162 LWB Watermain Replacement at Cochran Springs 260, , ,000 WA nd Street South Watermain Replacement 290, , ,000 WA 8888 Annual Watermain Replacement Program 359, , ,400 WA 9999 Annual Water Pump Station/System Upgrade Pgm 359, , ,400 SS th Street S Sewermain Replacement 884, , ,000 SS th Avenue NE Sewermain Replacement 865,800 2,861,800 1,624,400 5,352,000 4,652, ,200 SS NE 108th Street Sewermain Replacement 766,000 3,677,200 1,966,800 6,410,000 5,708, ,600 SS st Street Sewermain Replacement 958,900 2,861,100 3,820,000 2,420,000 1,400,000 SS th Street Sewermain Replacement 419, ,500 1,284,000 1,284,000 SS th Street Sewermain Replacement 287, , ,000 SS Kirkland Avenue Sewermain Replacement 850, , ,000 SS 0073 Rose Point Sewer Lift Station Replacement 1,450,000 1,110,000 2,560,000 2,560,000 SS th Avenue S Sewermain Replacement 188,900 38,000 38,000 38,000 SS rd Avenue S & 2nd Street S Sewermain Replacement 865, ,600 1,227,000 1,227,000 SS rd & Central Way Sanitary Sewer Crossing 300, , ,000 SS 8888 Annual Sanitary Pipeline Replacement Program 549, , ,800 20,600 SS 9999 Annual Sanitary Pump Station/System Upgrade Pgm 549, , ,800 20,600 Total Funded Water/Sewer Utility Projects 886,400 5,679,000 4,477,000 6,025,000 4,886,000 6,479,800 5,404,800 32,951,600 28,723,800 4,227, Total Notes Italics = Modification in timing and/or cost (see Project Modification/Deletion Schedule for more detail) Bold = New projects + = Moved from unfunded status to funded status " = Moved from funded status to unfunded status
4 WATER/SEWER UTILITY PROJECTS Unfunded Projects: 55 Project Number Project Title Total WA th Avenue NE Watermain Replacement 1,584,000 WA th Avenue NE Watermain Replacement 2,731,000 WA 0067 North Reservoir Pump Replacement 611,000 WA 0096 NE 83rd Street Watermain Replacement 450,000 WA 0097 NE 80th Street Watermain Replacement (Phase III) 1,386,000 WA th Ave NE/NE 83rd & 84th St/128th Ave NE Watermain Replacement 1,197,000 WA 0103 NE 113th Place/106th Ave NE Watermain Replacement 841,000 WA th Ave NE/NE 62nd St-NE 64th St Watermain Replacement 1,493,000 WA th Ave NE/NE 58th St Watermain Replacement 504,000 WA th Ave NE Watermain Replacement 1,179,000 WA 0111 NE 45th St And 110th/111th Ave NE Watermain Replacement 1,303,000 WA th Ave NE/NE 70th-NE 80th St Watermain Replacement 2,222,100 WA th -114th Avenue NE/NE 67th-68th Street Watermain Replacement 3,360,100 WA th Ave NE/111th Way NE Watermain Replacement 2,304,000 WA th Avenue Watermain Replacement 182,000 WA th Avenue NE/NE 100th Street Watermain Replacement 1,506,000 WA 0123 NE 91st Street Watermain Replacement 453,000 WA 0124 NE 97th Street Watermain Replacement 685,000 WA 0126 North Reservoir Outlet Meter Addition 72,300 WA Booster Pump Station 1,603,000 WA th Ave NE-110th Ave NE/NE 116th St-NE 120th St Watermain Replacement 2,305,000 WA 0129 South Reservoir Recoating 981,000 WA th Place Watermain Replacement 339,000 WA 0131 Supply Station #1 Improvements 61,500 WA th Avenue/Central Avenue Watermain Replacement 907,000 WA 0133 Kirkland Avenue Watermain Replacement 446,000 WA 0135 NE 75th Street Watermain Replacement 711,000 WA 0136 NE 74th Street Watermain Replacement 193,000 WA 0137 NE 73rd Street Watermain Replacement 660,000 WA 0138 NE 72nd St/130th Ave NE Watermain Replacement 1,476,000 WA th Street S Watermain Replacement 785,000 WA 0145" 6th Street South Watermain Replacement 585,100 WA th Street/Kirkland Way Watermain Replacement 693,000 WA th Avenue NE Watermain Replacement 661,500 WA 0149 Lake Washington Blvd Watermain Replacement 655,000 SS th Avenue NE Sewermain Replacement 1,315,000 SS 0077 West Of Market Sewermain Replacement 21,681,000 SS 0080" 20th Avenue Sewermain Replacement" 812,000 SS th Avenue NE Sewer Main Rehabilitation 725,000 SS 0084 Reclaimed Water (Purple Pipe) Opportunity Fund 5,000,000 Subtotal Unfunded Water/Sewer Utility Projects Funding Available from Annual Programs for Candidate Projects Net Unfunded Water/Sewer Utility Projects 66,658,600 1,817,600 64,841,000 Notes Italics = Modification in timing and/or cost Bold = New projects + = Moved from unfunded status to funded status " = Moved from funded status to unfunded status
5 WATER AND SEWER UTILITIES - Water CITY OF KIRKLAND CAPITAL IMPROVEMENT PROGRAM PROJECT SUMMARY WA South Juanita 104TH AVE NE WATERMAIN REPLACEMENT Replacement of approximately 1,600 feet of 4-inch asbestos concrete line with new 8-inch ductile iron pipe on 104th Avenue NE between NE 110th Street and NE 113th Street. Cost includes half-street overlay $0 $686,000 $0 $686,000 WA City-wide WA Everest WATER SYSTEM TELEMETRY UPGRADE The final phase for replacement of the remaining Rugid (brand name) telemetry system elements -- a system that currently operates over a phone line. The new system will be a frame relay Supervisory Control and Data Acquisition (SCADA) system. The new frame relay systems have been proven to be more reliable than phone line systems, providing better service. $0 $200,000 $0 $200,000 5TH AVENUE S/8TH STREET S WATERMAIN REPLACEMENT Replacement of approximately 2,170 feet of 6-inch asbestos concrete with new 16-inch ductile iron pipe along 5th Avenue S, between 6th Street S and 8th Street S and on 8th Street S, between 5th Avenue S and Kirkland Avenue $0 $553,000 $0 $553,000 WA WA TH STREET WATERMAIN REPLACEMENT Replacement of approximately 1,210 feet of undersized 8-inch diameter asbestos cement and cast iron water main originally installed in the 1960's with 8 and 12-inch ductile iron water main. The proposed improvements include: 12- inch water main in 6th Street between Central Way and Kirkland Way; and 8-inch water main in 6th Street between Kirkland Way and Kirkland Ave $372,500 $148,000 $0 $520,500 7TH AVENUE SOUTH WATERMAIN REPLACEMENT Replace 900 feet of 10-inch asbestos concrete watermain with 12-inch ductile iron main $325,000 $53,000 $0 $378,000 WA TH STREET WATERMAIN REPLACEMENT Replace 890 feet of existing 6-inch diameter asbestos-cement water main with 8-inch diameter ductile iron pipe, on 4th Street between the limits of 15th Avenue and 18th Avenue. Replace water hydrants, valves, and other related appurtenances within the alignment. The existing main, constructed in 1949, has exceeded its design service life and has experienced multiple failures in recent years. The existing pipe is also undersized as identified by the 2014 Water System Comprehensive Plan. $0 $467,000 $0 $467,000 56
6 WA RD STREET WATERMAIN IMPROVEMENT Replace approximately 875 feet of 8-inch asbestos concrete watermain with 8-inch ductile iron watermain, and approximately 1,150 feet of 6-inch asbestos concrete watermain with 12-inch ductile iron watermain. $0 $757,000 $0 $757,000 WA TH STREET WATERMAIN REPLACEMENT PHASE 2 Replace approximately 1,300 feet of 4 and 6-inch asbestos concrete watermain with new 8-inch ductile iron watermain. $0 $464,000 $0 $464,000 WA TH AVENUE NE WATERMAIN IMPROVEMENT South Rose Hill Replace approximately 600 feet of 8-inch ductile iron watermain and 750 feet of 6-inch asbestos concrete watermain with 1,350 feet of 20-inch ductile Iron watermain; also replace 200 feet of galvanized pipe with 200 feet of 16-inch ductile iron watermain $0 $710,000 $0 $710,000 WA ND AVENUE NE WATERMAIN IMPROVEMENT South Rose Hill Replace approximately 600 feet of 8-inch ductile iron pipe with 16-inch ductile iron watermain; also replace 1,100 feet of 6-inch asbestos concrete pipe with 12-inch ductile iron watermain $0 $696,000 $0 $696,000 WA Market 8TH AVENUE WEST WATERMAIN IMPROVEMENT Replace approximately 1,900 feet of 4-inch cast Iron pipe with 8-inch ductile iron watermain $0 $710,000 $0 $710,000 WA South Juanita NE 112TH STREET WATERMAIN IMPROVEMENT Replace approximately 820 feet of 6-inch asbestos concrete pipe with 820 feet of 8-inch ductile iron watermain $0 $365,000 $0 $365,000 WA South Juanita NE 113TH PLACE WATERMAIN IMPROVEMENT Replace approximately 900 feet of 4-inch asbestos concrete pipe, with 900 feet of 8-inch ductile iron watermain $0 $373,000 $0 $373,000 WA TH AVENUE NE WATERMAIN IMPROVEMENT South Rose Hill Replace approximately 2,600 feet of 8-inch asbestos concrete pipe with 2,600 feet of 8-inch ductile iron watermain $0 $990,000 $0 $990,000 57
7 WA KIRKLAND WAY WATERMAIN REPLACEMENT Replacement of approximately 800 feet of 8-inch and 10-inch asbestos concrete pipe with new 12-inch ductile iron pipe. $0 $400,000 $0 $400,000 WA Lakeview WA LWB WATERMAIN REPLACEMENT AT COCHRAN SPRINGS Two city water mains: an 8-inch water main and 12-inch water main will be relocated (much deeper) prior to the installation of a new concrete box culvert to convey Cochran Springs Creek across Lake Washington Boulevard (surface water project CSD 0048). $0 $260,000 $0 $260,000 2ND STREET SOUTH WATERMAIN REPLACEMENT Replacement of approximately 400 feet of 8-inch asbestos concrete pipe with new 8-inch ductile iron pipe. $0 $290,000 $0 $290,000 WA City-wide WA City-wide ANNUAL WATERMAIN REPLACEMENT PROGRAM Replacement of existing watermain and water system appurtenances as required to complete the prioritized watermain projects list contained within the Water Comprehensive Plan Update. Candidate projects under this Annual Program include: WA NE 113th Place/106th Ave NE Watermain Replacement, WA th Avenue NE 114th Avenue NE Watermain Replacement, WA th Avenue Watermain Replacement, WA NE 97th Street Watermain Replacement, WA th Place Watermain Replacement, WA NE 74th Street Watermain Replacement and WA NE 73rd Street Watermain Replacement, WA th Street/Kirkland Way Watermain Replacement, WA th Avenue NE Watermain Replacement. Ongoing Ongoing $0 $359,400 $0 $359,400 ANNUAL WATER PUMP STATION/SYSTEM UPGRADE PROGRAM The replacement of existing water system appurtenances as required to complete the prioritized system upgrades list contained within the Water Comprehensive Plan Update. Candidate projects under this Annual Program include: WA North Reservoir Pump Station Replacement, WA North Reservoir Outlet Meter Addition, WA Booster Pump Station and WA Supply Station #1 Improvements. $0 $359,400 $0 $359,400 58
8 WATER AND SEWER UTILITIES - Sewer 2020 CITY OF KIRKLAND CAPITAL IMPROVEMENT PROGRAM PROJECT SUMMARY SS TH STREET SOUTH SEWERMAIN REPLACEMENT Everest Preliminary design will examine feasibility of slip lining the existing sewer line or the need to replace the existing 10- inch concrete sewer line from NE 68th Street to approximately 8th Avenue South, with approximately 950 feet of 12- inch to 15-inch polyvinyl chloride (PVC) pipe. Capacity issues with this sewer line that were identified in the 1992 Sewer Comprehensive Plan were alleviated with the installation of a new sewer main in NE 68th Street between 6th Street S/108th Avenue NE and Cross Kirkland Corridor in $0 $884,000 $429,100 $1,313,100 SS TH AVENUE NE SEWERMAIN REPLACEMENT Central Hought Replace and/or rehabilitate approximately 4,000 feet of 8-inch concrete pipe with 8 to 12-inch PVC pipe. Perform video inspection to determine extent and priority of section improvements; preliminary design will examine the feasibility of installing replacement sewer line at a shallower depth than currently exists along this line (specifically between NE 59th Street to NE 53rd Street). This trunk line requires high maintenance due to significant structural deficiencies. $0 $5,352,000 $0 $5,352,000 SS South Juanita SS NE 108TH STREET NE SEWERMAIN REPLACEMENT Replace and/or rehabilitate the existing trunk line with approximately 3,000 feet of 12-inch to 18-inch diameter PVC pipe. Perform video inspection to determine the extent of the improvements. The existing trunk line, a likely source of inflow and infiltration (I/I), experiences minor storm event surcharging and does not have adequate capacity for full development within the basin $0 $6,410,000 $0 $6,410,000 1ST STREET SEWER MAIN REPLACEMENT Replace existing 8-inch concrete sewerline with approximately 4,170 feet of 8-inch polyvinyl chloride (PVC) sewerline. The existing line was first built in 1950 and is deteriorating, having exceeded its design life. $0 $3,820,000 $0 $3,820,000 SS TH STREET SEWER MAIN REPLACEMENT Replace existing 8-inch concrete sewerline with approximately 1,430 feet of 8-inch polyvinyl chloride (PVC) sewerline. The existing line was first built in 1950 and is deteriorating, having exceeded its design life. $0 $1,284,000 $0 $1,284,000 SS TH STREET SEWER MAIN REPLACEMENT Replace existing 6-inch concrete sewerline with approximately 325 feet of 8-inch polyvinyl chloride (PVC) sewerline. The existing trunk line does not have adequate capacity to accommodate projected flows. $0 $287,000 $0 $287,000 59
9 SS Everest KIRKLAND AVENUE SEWER MAIN REPLACEMENT Replace existing 8-inch concrete sewerline with approximately 1,550 feet of 12-inch polyvinyl chloride (PVC) sewerline. The existing trunk line does not have adequate capacity to accommodate projected flows $0 $850,000 $1,309,000 $2,159,000 SS Market SS Everest SS SS SS City-wide SS City-wide ROSE POINT SEWER LIFT STATION REPLACEMENT Relocation/reconstruction of the existing lift station due to age and insufficient pumping capacity at peak flows during major storm events. The station improvements include a new wetwell/drywell layout compatible with the surrounding area, new system control, new 8-inch overflow line from the new station to adjacent top-of-the Waverly Basin manhole (if feasible), an emergency generator set (if new overflow line is not feasible) and 1,800 feet of 8-inch ductile iron or polyvinyl chloride (PVC) forcemain $0 $2,560,000 $0 $2,560,000 5TH AVENUE S SEWERMAIN REPLACEMENT Replace existing 6-inch concrete sewer line with approximately 200 feet of 8-inch diameter polyvinyl chloride (PVC) sewer pipe. Work extends east from the manhole at the intersection of 5th Avenue S to the terminus manhole about 120 feet west of 8th Street S. This right-of-way is unopened to vehicles but contains a pedestrian path. $188,900 $38,000 $0 $226,900 3RD AVENUE S / 2ND STREET S SEWERMAIN REPLACEMENT Replace existing 6-inch concrete sewer line with approximately 780 feet of 8-inch diameter polyvinyl chloride (PVC) sewer pipe. Work extends from 234 3rd Avenue S west to 2nd Street S and north to approximately 106 2nd Street S. This project may be a candidate for trenchless technology (pipe lining, pipe bursting, etc.). $0 $1,227,000 $0 $1,227,000 3RD & CENTRAL WAY SANITARY SEWER CROSSING Replace 90 feet of 24-inch diameter sanitary sewer and two 48-inch diameter manholes with 48-inch diameter polyvinyl chloride (PVC) sanitary sewer and two 60-inch diameter manholes. Shallow crossing utilities may require a manifold system with concrete box vaults, gas main relocation and/or sleeving of sanitary sewer over watermain. Ongoing $0 $300,000 $0 $300,000 ANNUAL SANITARY PIPELINE REPLACEMENT PROGRAM Installation of sewermain replacements to improve overall system reliability and to reduce maintenance and I & I (Infiltration and Inflow) costs. Candidate projects under this Annual Program include: SS th Avenue NE Sewermain Replacement; SS th Avenue Sewermain Replacement $0 $549,400 $0 $549,400 ANNUAL SANITARY PUMP STATION/SYSTEM UPGRADE PROGRAM Installation of sewer pump station upgrades to improve overall system reliability and to reduce maintenance costs. Ongoing $0 $549,400 $0 $549,400 60
10 ACTIVE PROJECTS-WATER/SEWER City of Kirkland Capital Improvement Program Prior Activity - Projects Active as of 12/31/2014: Project Proj. Budget Expenses Proj Balance Number Project Title through 2014* through /31/2014 SS th Avenue South Sewermain Replacement 897, , ,510 SS 0067 NE 80th Street Sewermain Replacement (Phase II) 2,436, ,018 2,289,982 SS 0074 Sewer System Telemetry Upgrades 150, ,157 8,843 SS 0075 Inflow & Infiltration Reduction Program 200,000 85, ,736 SS th Avenue S Sewermain Replacement 188,900 33, ,302 SS th / 8th Avenue West Alley Sewermain Replacement 354, , ,870 SS Emergency Sewer Construction 130,000 99,210 30,790 WA 0063 Supply Station #3 Replacement 141, ,000 WA 0093 Vulnerability Analysis 367,900 61, ,632 WA 0094 North Reservoir Painting 3,399,000 3,031, ,698 WA 0115 Telemetry Upgrades 150, ,277 17,723 WA 0116 NE 80th Street Watermain Replacement (Phase II) 2,836, ,182 2,698,218 WA 0140 NE 85th Street Watermain Replacement 3,992,200 2,224,118 1,768,082 WA 0148 Park Lane Watermain Replacement 297,000 58, ,842 WA th Street Watermain Replacement 372,500 70, ,802 WA th Avenue S Watermain Replacement 325, , ,475 WA Emergency Sewer Replacement - Water 50, ,553 Total 16,287,700 6,947,643 9,340,057 *Includes prior years' project balance plus funding 61
11 MARKET ST 120TH AVE NE 122ND AVE NE 90TH AVE NE SIMONDS NE 145TH ST RD N E NE 144TH ST HOLMES POINT DR NE HOLMES POINT DR NE 76TH NE 141ST ST NE 122ND PL PL NE 84TH AVE NE WA NE JUANITA DR NE 120TH PL 98TH 104TH AVE NE 108TH AVE NE NE 120TH ST NE 132ND ST NE 124TH ST TOTEM LAKE BLVD NE 116TH ST WA NE 128TH ST 124TH AVE NE NE 124TH ST 132ND AVE NE 132ND AVE NE NE 124TH ST AVE NE NE 112TH ST WA SS FORBES CREEK DR Project Locations SS TH ST SOUTH SEWERMAIN REPLACEMENT SS TH AVE NE SEWERMAIN REPLACEMENT SS NE 108TH ST SEWERMAIN REPLACEMENT SS ST ST SEWERMAIN REPLACEMENT SS TH ST SEWERMAIN REPLACEMENT SS TH ST SEWERMAIN REPLACEMENT SS KIRKLAND AVE SEWERMAIN REPLACEMENT SS ROSE POINT SEWER LIFT STATION REPLACEMENT SS TH AVE S SEWERMAIN REPLACEMENT SS RD AVE S/2ND ST S SEWERMAIN REPLACEMENT SS RD & CENTRAL WAY SANITARY SEWER CROSSING WA TH AVE NE WATERMAIN REPLACEMENT WA TH AVE SOUTH/8TH ST SOUTH WATERMAIN REPLACEMENT WA TH ST WATERMAIN REPLACEMENT WA TH AVE SOUTH WATERMAIN REPLACEMENT WA TH ST WATERMAIN REPLACEMENT WA RD ST WATERMAIN REPLACEMENT IMPROVEMENT WA TH ST WATERMAIN REPLACEMENT PHASE 2 WA TH AVE NE WATERMAIN IMPROVEMENT WA ND AVE NE WATERMAIN IMPROVEMENT WA TH AVE WEST WATERMAIN IMPROVEMENT WA NE 112TH ST WATERMAIN IMPROVEMENT WA NE 113TH PL WATERMAIN REPLACEMENT WA TH AVE NE WATERMAIN IMPROVEMENT WA KIRKLAND AVE WATERMAIN REPLACEMENT WA LAKE WASH BLVD WATERMAIN REPLACEMENT AT COCHRAN SPRINGS WA ND ST S WATERMAIN REPLACEMENT Projects With Various Locations SS ANNUAL SANITARY PIPELINE REPLACEMENT PROGRAM SS ANNUAL SANITARY PUMP STATION/SYSTEM UPGRADE PROGRAM WA WATER SYSTEM TELEMETRY UPGRADE WA ANNUAL WATERMAIN REPLACEMENT PROGRAM WA ANNUAL WATER PUMP STATION/SYSTEM UPGRADE PROGRAM SS SS WA WA SS SS WA Legend CIP Projects Sewer Water WA City Limits Parks School 18TH AVE 15TH AVE WA LAKE ST S SS RD ST 7TH AVE NE 52ND ST 5TH PL NE 38TH PL 12TH AVE 7TH AVE WA NE 85TH ST Funded Sewer and Water CIP LAKE ST S 8TH ST S 116TH AVE NE SS SS SS TH AVE NE 116TH AVE NE 116TH AVE NE WA SLATER AVE NE WA NE 100TH ST NE 95TH ST NE 90TH ST NE 85TH ST 126TH AVE NE NE 60TH ST NE 104TH ST NE 80TH ST NE 60TH ST SS WA WA WA WA WA SS ,000 4,000 6,000 Feet Produced by the City of Kirkland. the City of Kirkland, all rights reserved. No warranties of any sort, including but not limited to accuracy, fitness or merchantability, accompany this product. 62
Kansas City s Overflow Control Program
Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater
Bridges & Culverts Condition by Quantity
3.4.3 What condition is it in? Approximately 93% of the municipality s bridge structures are in good to excellent condition, with the remaining 7% in fair condition. As a result, the municipality received
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.
MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade
Sanitary Sewer Master Plan
, Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
S-16 Sewer Pump Station Improvements
S-16 Pump Station Improvements Status: Ongoing Location: Pump stations throughout the Utility s service area Budget 20,600,491 12,181,491 512,000 1,340,000 2,310,000 1,075,000 1,097,000 1,090,000 995,000
The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section
McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C.
McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C. 111 Wheatfield Drive, Suite 1 Milford, Pennsylvania 18337 (570) 296-2765 fax: (570) 296-2767 e-mail: [email protected] RICHARD D. McGOEY, P.E. (NY &
City of Largo Environmental Services Department Environmental Control Program 5100 150 th Avenue North Clearwater, FL 33760 Phone: (727) 518-3076
POCTS # (To be assigned by City of Largo Environmental Control.) City of Largo Environmental Services Department Environmental Control Program 5100 150 th Avenue rth Clearwater, FL 33760 Phone: (727) 518-3076
PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
DEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements
Moving Ruston Forward City of Ruston Infrastructure Maintenance and Improvements MLK Extension Project will be done in conjunction with proposed water and sewer improvements Connect Martin Luther King
Close-Out Documents... 9
Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter
Using GIS to Track and Prioritize Your Assets
Using GIS to Track and Prioritize Your Assets What is GIS?? Geographic Information System Geographic Location of an asset Information Characteristics of an asset System Software that allows connection
Emerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
TOWN OF GRIMSBY ASSET MANAGEMENT PLAN
TOWN OF GRIMSBY ASSET MANAGEMENT PLAN August 20, 2014 DFA Infrastructure International Inc. Executive Summary ES1 Background The Town of Grimsby (Town) with a population of approximately 25,325 is located
Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective
Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Building the Foundation for an Effective Asset Management Program Scott D. Kelly, P.E. Assistant City Administrator
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
CITY OF FARMERSVILLE, TEXAS
CITY OF FARMERSVILLE, TEXAS MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES Subdivision Ordinance #2007-08 Exhibit B February 13, 2007 TABLE OF CONTENTS Description Page No. General... 1 Water
Standards for Water, Sewer, and Sewage Lift Station Design
Standards for Water, Sewer, and Sewage Lift Station Design February 2015 Edition I. Plan Format Requirements General Requirements Water Line Requirements Sewer Line Requirements II. III. IV. Water Design
Town of Essex NE Lagoon. Service Area. Essex Plant. Service Area. Pumping Station No. 4. Wastewater Pumped To NE Lagoons (Treatment Plant No.
Town of Essex Basement Flooding Study Town of Essex NE Lagoon Service Area Pumping Station No. 4 Essex Plant Service Area Wastewater Pumped To NE Lagoons (Treatment Plant No. 2) Essex Treatment Plant (Treatment
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans
Special Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
Asset Management Plan
Corporation of the Town of Innisfil Asset Management Plan Prepared by: AECOM 55 Cedar Pointe Drive, Suite 620 705 721 9222 tel Barrie, ON, Canada L4N 5R7 705 734 0764 fax www.aecom.com Project Number:
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)
REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE
REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE Submit Proposals to: Town of Woodside Public Works Department 2955 Woodside
Contracting Opportunities Vendor Day May 17, 2011
Customer Care Team Contracting Opportunities Vendor Day May 17, 2011 Customer Care Team: What We Do Team Office customer advocacy and contracting Customer Relations Group call centers, claims, special
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
City of Cape Coral, Florida FY 2015-2017 Proposed Operating Budgets
FUNDED CAPITAL IMPROVEMENT PROGRAM FY 2015-2020 SUMMARY OF REQUIRED REVENUES FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 TOTAL All Hazards $ 100,000 $ - $ - $ - $ - $ - $ 100,000 Capital Facility Expansion
SECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
SECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana
See Appendix A for additional information, or contact ASTM directly.
DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN
S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
City of Mill Valley Sewer Capital Improvement Plan 2012 2016
City of Mill Valley Sewer Capital Improvement Plan 2012 2016 I. BACKGROUND Between December 2004 and February 2008, the ed States Environmental Protection Agency (EPA) conducted inspections of the SASM
CHAPTER 8 CIVIL DESIGN
CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical
Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective
Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective An Owner Operator s Approach for Asset Management on a Budget Lane Longley, City of St. Petersburg Presented by the April
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000
Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared
Monterey Regional Water Pollution Control Agency. Sewer System Management Plan
Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance
Storm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
Engineering Specifications February, 2004 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18
Schedule H to Bylaw 7452, Subdivision Bylaw Page 18 3.4 Sanitary Sewers 3.4.1 Materials 3.4.1.1 The class and type of pipe and fittings, together with required class of bedding and trench widths, shall
A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015
A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015 Infiltration/Inflow (I/I) I & I Reduction: Three-Prong Attack
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN. Presentation to Insurance Companies 19 January 2012
JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN Presentation to Insurance Companies 19 January 2012 Topics of Discussion Investigation Levels of Service Cause of Flooding Analysis Undertaken
ENVIRONMENTAL ASSESSMENT (EA) VILLAGE OF EAU CLAIRE - BERRIEN COUNTY INFILTRATION/INFLOW REMOVAL PROJECT APRIL 2015
ENVIRONMENTAL ASSESSMENT (EA) VILLAGE OF EAU CLAIRE - BERRIEN COUNTY INFILTRATION/INFLOW REMOVAL PROJECT APRIL 2015 I. PROJECT IDENTIFICATION Applicant: Authorized Representative: Village of Eau Claire
WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598
Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**
PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
Chapter 9 Sanitary Sewers
Chapter 9 Sanitary Sewers S:/Engineering/Design Standards/Chapter 9 12/29/2014 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems
ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems Please see the DEFINITIONS of terms at the end of this section. If you have any questions about these definitions, do not understand a question,
Pipe bursting provides viable alternative for rehab work By Greg Key, U.S. Pipe
Pipe bursting provides viable alternative for rehab work By Greg Key, U.S. Pipe As the Environmental Protection Agency tightens groundwater quality regulations, old leaking sewers lines made of pipe clay,
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
SECTION 15410 GROUND WATER STORAGE TANKS
SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
Design Criteria & Service Goals
4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on
Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS
CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS 6.00 Objective Page 1 6.01 Additional Referenced Standards Page 2 6.02 Special Design Problems Page 2 6.03
CD i -STREETS- Detail #
-STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction
RESPONSIBLE DEPARTMENT: ADDITIONAL DIRECTOR (S): ASSISTANT CITY MANAGER: JIM CALLAWAY
CITY COUNCIL AGENDA REQUEST AGENDA OF: 07-01-14 AGENDA REQUEST NO: IV-D INITIATED BY: GREG NICHOLS PROJECT MANAGER RESPONSIBLE DEPARTMENT: ENGINEERING PRESENTED BY: TIMOTHY JAHN, P.E. SENIOR ENGINEER DIRECTOR:
CLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
89 Avenue Road GP Ltd. Functional Servicing and Stormwater Management Report for 89 Avenue Road Re-Development City of Toronto
89 Avenue Road GP Ltd. Functional Servicing and Stormwater Management Report for 89 Avenue Road Re-Development City of Toronto Prepared By: R.J. Burnside & Associates Limited 6990 Creditview Road, Unit
FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES
FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES 1 FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN Wastewater Treatment Facilities The Wastewater Treatment System (System)
INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By
INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By ABSTRACT Migdalia Hernandez, City of Sanford P.O. Box
12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.
Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. 1 Pipe Bursting A Mature and Diverse Trenchless Technology December 10, 2014 1:00 3:00 pm Eastern How to Participate Today
08003-1 WATER SERVICE 2
08003_Mar08_2011.pdf Page 1 of 7 INDEX Page 08003-1 WATER SERVICE 2 1.1 Pipe 2 1.1.1 Copper 2 1.1.2 Polyethylene 2 1.2 Valves and Fittings 2 1.2.1 Main Stops 3 1.2.2 Curb Stops 3 1.2.3 Curb Box 3 1.2.4
KANSAS CITY WATER SERVICES FISCAL YEAR 2016 CAPITAL IMPROVEMENT PROGRAM
KANSAS CITY WATER SERVICES FISCAL YEAR 2016 CAPITAL IMPROVEMENT PROGRAM TABLE OF CONTENTS Water...Page 2 Design Professional Services... Page 3 Construction... Page 8 Wastewater...Page 12 Design Professional
SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER
Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating
WATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods
WATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods NEIGHBORHOOD MEETING Wednesday, February 10, 2016 6:00 7:00 p.m. Childsplay, 900 S. Mitchell Drive, Tempe, AZ Neighborhood Meeting Welcome,