AMS Victorian Electricity Transmission Network

Similar documents
TABLE OF CONTENT

GroundRod AC Substation Earthing Tutorial

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

Substation Grounding Study Specification

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

TS 813 GROUNDING AND BONDING TTD TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD CONTROLLER CABINET GROUNDING

November Stray Voltage Test Procedure for Electrical Contractors

Electrical Grounding. Appendix C

CATHODIC PROTECTION SYSTEM DESIGN

Lightning Protection Introduction

Transmission Business Electrical Incident & Safety Performance Reporting Guide

SECTION 22 LIGHTNING PROTECTION SYSTEM

ALCOA OF AUSTRALIA LIMITED BUSHFIRE MITIGATION AND LINE CLEARANCE PLANS 2013/2014

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Work in Substations - General

Hyperlinks are Inactive

EARTHING SYSTEM CALCULATION

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION

Telemetry system for cathodic protection equipment of underground metal pipelines

AMS Victorian Electricity Transmission Network

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

TC Grounding and Bonding for Telecommunications Systems

Specifications for Lightning Protection. ASAE Engineering Practice

Asset Management Strategy

The Electrical Safety Regulation (pre and post 1 January 2014)

environment briefing02

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE:

Strength and Durability for Life CORROSION CONTROL. The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers

Earthing Guidance Notes

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS

Grounding and Bonding Against Static Electricity. Jon Koppari, CSP, MS Occupational Safety and Health Instructor OSHA Training Institute

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

ADM1TE 5/30A DIN rail single phase two wire energy meter

Lightning Arresters P KVA P KVA. Description & Installation

DRM75A 230V 20/100A DIN rail single phase two wire energy meter

Chapter 9. Bonding and Grounding

SES Training & Certification Programs Welcome to the SES Grounding, EMI and Lightning Academy

Victorian Purchasing Guide for UEG11 Gas Industry Training Package Version No 2

Grounding Practice at Data and Communications Centers. David Brender, P.E., CPQ National Program Manager Copper Development Association Inc.

Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria

Living with Electricity Easements

AORC Technical meeting 2014

1. Franklin Rod Performance 2. LEC/DAS Performance

Application Bulletin NEC Reference Guide for SolarBridge-Enabled AC Module Installers

How Much Voltage Drop Is Acceptable?

NEW ZEALAND ELECTRICAL CODE OF PRACTICE. for ELECTRICAL SAFE DISTANCES

V.A PJM Design and Application of Overhead Transmission Lines 69kV and Above

EDS CUSTOMER LV INSTALLATION EARTHING DESIGN

EMC Engineering Guidelines For Automation Systems PS 4 PS /97 AWB GB

Code of Practice Electricity transmission and distribution asset management. February 2009

Security Cameras, CATV, GPS & Satellite Protection. White Paper

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

STREETLIGHT SYSTEM GROUNDING AND BONDING

WIRELESS REMOTE MONITORING OF CATHODIC PROTECTION SYSTEMS. John Hawkyard MICorr Deputy General Manager Rawabi Corrosion Technology Co Ltd Al-Khobar

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time

Copper Applications A Case Study

Video Camera Installation Guide

SAES-P January, 2004 Grounding. Electrical Systems Designs & Automation Standards Committee Members

CODE OF PRACTICE FOR EARTHING AND BONDING SYSTEM FOR SIGNALLING EQUIPMENTS SPECIFICATION NO. RDSO/SPN/197/2008 SIGNAL DIRECTORATE

reduction ore = metal oxides metal oxidation

Checklist Testing and inspection without interconnection

INTERNATIONAL STANDARD

SANS : 2008 CODE OF PRACTICE THE WIRING OF PREMISES Part 1 : Low Voltage Installation

ELECTRICAL SAFETY Information Bulletin

Cathodic Protection. Remote Monitoring of Cathodic Protection on a Gas Distribution Network

Steel Pole & Tower Assessment & Remediation Turnkey Solutions for Aging Steel Infrastructure

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

Grounding & Bonding Why it is done And How to Install Properly

By Mark Coles. This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.

Undergrounding high voltage electricity transmission. The technical issues

Introduction to Data Centre Design

ICM Project Underground Infrastructure and Cable

About our Chairman cum- Managing Director

Coaxial Cable Entry Panels, Coax and Grounding Connectors. Technical Note

Technical Guidance Note 287. Third-party guidance for working near National Grid Electricity Transmission equipment

Static Electricity. A Health and Safety Guideline for Your Workplace. What Are Some Sources of Static Electricity? What is Static Electricity?

Earth Ground Resistance

How To Monitor Water Penetration In A Cable Screen

NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT SECTION GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS

LUXEON LEDs. Circuit Design and Layout Practices to Minimize Electrical Stress. Introduction. Scope LED PORTFOLIO

Canopy Surge. User Manual

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

Consultants Handbook

SAFETY AND HEALTH STANDARD KUC ELECTRICAL STANDARD Effective Date: 04/4/12 Standard: 15.1 Document Number: KUCSH0065 Rev: 06

David Brender Copper Development Association Inc. Miramar, March 8, 2013

Structured Cabling, Earthing & Equipotential Bonding

Title: Grounding and Bonding Rev-01

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Heading FACT SHEET. Overview.

2012 Canadian Electrical Code, Part I (CEC) Top Fifteen changes

Multiple Meter Installation Amperes Per Position -Single Phase, Self-contained

Please check with your local inspection authority for any additional requirements before installation.

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

How To Wire Wire Wire For A Decoder System

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

Transcription:

AMS Victorian Electricity Transmission Network Document number AMS 10-60 Issue number 9 Status Approver Approved J. Dyer Date of approval 17/09/2015

ISSUE/AMENDMENT STATUS Issue Number Date Description Author Approved by 5 22/11/06 Editorial review. G Lukies D Postlethwaite 7 17/03/07 Editorial review. G Lukies D Postlethwaite 8 12/11/12 Revised Structure and General update. P Seneviratne P Yeung C Rabbitte 9 17/09/15 Editorial Review D Platt B Li T Gowland S Sridhar A Shah A Bugheanu G Towns G Towns D Postlethwaite J Dyer Disclaimer This document belongs to AusNet Services and may or may not contain all available information on the subject matter this document purports to address. The information contained in this document is subject to review and AusNet Services may amend this document at any time. Amendments will be indicated in the Amendment Table, but AusNet Services does not undertake to keep this document up to date. To the maximum extent permitted by law, AusNet Services makes no representation or warranty (express or implied) as to the accuracy, reliability, or completeness of the information contained in this document, or its suitability for any intended purpose. AusNet Services (which, for the purposes of this disclaimer, includes all of its related bodies corporate, its officers, employees, contractors, agents and consultants, and those of its related bodies corporate) shall have no liability for any loss or damage (be it direct or indirect, including liability by reason of negligence or negligent misstatement) for any statements, opinions, information or matter (expressed or implied) arising out of, contained in, or derived from, or for any omissions from, the information in this document. Contact This document is the responsibility of the Asset Management division of AusNet Services. Please contact the indicated owner of the document with any inquiries. John Dyer AusNet Services Level 31, 2 Southbank Boulevard Melbourne Victoria 3006 Ph: (03) 9695 6000 ISSUE 9 17/09/2015 2 / 12

Table of Contents 1 Executive Summary... 4 2 Introduction... 5 2.1 Purpose... 5 2.2 Scope... 5 2.3 References... 5 3 Asset Summary... 6 3.1 Installed Assets... 6 3.2 Age Profile... 7 3.3 Condition... 8 3.4 Principal Aspects... 9 3.5 Inspection and Monitoring... 11 3.6 Investment Drivers... 11 4 Strategies... 12 ISSUE 9 17/09/2015 3 / 12

1 Executive Summary This document defines the asset management strategies for earthing systems of AusNet Services terminal stations and transmission line towers. Earthing systems are installed to: ensure safety of personnel and the public; form low impedance discharge path for earth fault currents and transient surges to protect HV and LV electrical installations; ensure correct operation of electrical protection, control and communication systems; ensure appropriate electrical insulation coordination; and maintain network reliability. Earthing systems consist of buried main earth grid electrodes and earthing conductors that are connected to equipment or other infrastructure from main earth grid electrodes within terminal stations. The majority of main earth grid electrodes were installed when the terminal stations were originally established. Since then, they have been enhanced and/or expanded as part of installation of new plant or extension of existing electrical installations. The condition of the earth grid electrodes is generally good. The condition of some station overhead earth wires is showing a level of deterioration due to surface corrosion, and is monitored during inspection. For transmission lines, overhead earth wires were also installed at the same time that the transmission lines were constructed. Some original overhead earth wires have been replaced by optical fibre ground wire as part of augmentation of protection and communication system. Overhead earth wires for transmission lines are covered in AMS 10-79 Transmission Line Conductors. Key asset management strategies are summarised as follows: Complete the earthing system condition monitoring program for station earth grids. Undertake analysis of historical results to establish an understanding of the capability of each earth grid. Ensure earth grid step and touch voltage hazard limits for operational and maintenance requirements are consistent with international limits 1, national limits 2 and are specified in the AusNet Services Station Design Manual. Continue monitoring program for terminal stations main earth grid electrodes and earthing conductors, continue the ongoing monitoring programs. For terminal station overhead earth wires, continue to carry out visual inspections at a maximum interval of 2 years and replace deteriorated earth wires and connectors when appropriate. Continue the practice of visual inspection and earth continuity tests on representative critical earthing joints/connectors and sample main earth grid conductors during major terminal station projects. Continue to test earthing performance, and to analyse results to determine if augmentation and/or enhancement works are required based on risk assessment. 1 International limits include IEC 61936-1, IEC 60479.1 and IEEE 80. 2 National limits include AS 2067, AS 7000 and AS60479. ISSUE 9 17/09/2015 4 / 12

2 Introduction 2.1 Purpose The purpose of this document is to define the asset management strategies for earthing systems of AusNet Services terminal stations earth grids and transmission line towers. This document is intended to assist personnel involved in managing the assets, meeting regulatory obligations and informing other stakeholders by: Presenting an overview of the station earth grids and transmission line tower earthing; Managing business and network risks presented by station earth grids and transmission line tower earth electrodes efficiently and ensuring that these risks are kept within the limits of safety; Achieving supply reliability targets taking into account risk, costs and customer expectations; and Ensuring the effective and consistent asset management activities relating to station earth grids and transmission line tower earthing throughout their life-cycle. 2.2 Scope This asset management strategy applies to all terminal station earth grids and transmission line tower earthing systems that are associated with the Victorian electricity transmission network. The strategies in this document are limited to maintaining installed capability in terms of asset performance and rating. Improvements in quality or capacity are not included in the scope of this document. 2.3 References This asset management strategy forms part of a suite of documentation that supports the management of AusNet Services assets, which include the following: AMS 01-01 AMS 10-01 AMS 10-19 AMS 10-143 Asset Management System Overview Asset Management Strategy Transmission Network Plant and Equipment Maintenance Terminal Station Earth Grid Management Review ISSUE 9 17/09/2015 5 / 12

3 Asset Summary Terminal station earth grids and transmission line tower earth electrodes are designed and constructed to: ensure safety of personnel and the public; provide a low impedance path for fault currents and transient surges to protect electrical installations; and ensure correct operation of the electrical protection, control and communication schemes. 3.1 Installed Assets 3.1.1 Terminal Stations and Communications Sites Station earth grids consist of main earth Bare Copper Conductors (BCCs) buried at 0.3 to 0.5m depths in the ground, copper bonded earth rods, copper flat bars, earth mats and associated connections. Connections are either bolting, CAD welding, brazing or swaging type. Figure 1 and Figure 2 demonstrate typical earth conductors. Figure 1 Main earth grid BCC Figure 2 Copper flat earthing conductors To further mitigate potential step and touch voltage hazards, a crushed rock surface material is used. This is placed over switchyards and can be found on some sites. Ground wires, which are connected to the station earth grid via termination hardware and structure steelwork, are strung above switchyard plant in most terminal stations to provide protection from direct lightning strikes. These ground wires are slack strung compared with transmission line ground wires. 3.1.2 Transmission Lines Transmission line towers (including those inside terminal station boundary fences) do not normally have a dedicated earth grid. However, the tower footing resistance is measured during construction to ensure that access near the tower is safe. In a small number of cases, where footing resistance is not adequate, the tower foundations have counterpoise (earth conductors) installed. Ground wires are strung between the tops of towers, above the line conductors primarily for lightning protection but they also provide additional paths for fault currents which reduce step and touch potentials at individual towers. This ground wire is connected (via the termination hardware) to the steelwork of each tower. It is also connected to the rack structure steelwork at the line termination point in terminal stations. ISSUE 9 17/09/2015 6 / 12

To provide increased safety for the public, activities such as the building of structures, swimming pools, fences and other conducting items on line easements are restricted. Insulating panels are often installed in metallic fences, located in the vicinity of towers. The aim of these measures is to limit voltage transfer to remote sites and to limit public exposure to conducting mediums in the event of an earth fault. Refer to the AMS 10-65 - Line Easements for further information. 3.2 Age Profile The main earth grids electrodes were installed when the terminal station switchyards and communication sites were originally established. They have been progressively enhanced and extended as additional plant or facilities were installed. Figure 3 and Figure 4 illustrates the terminal station and structure age profiles respectively. Figure 3 Terminal Station Age Profile Figure 4 Transmission Line Tower Age Profile Ground wires that run above transmission lines were installed during construction of the lines. ISSUE 9 17/09/2015 7 / 12

3.3 Condition The physical conditions of the below ground earth grids are generally good. This is due to: Copper is not adversely affected by the majority of soils; Stations generally have effective surface drainage systems; Comparatively non-aggressive soils and backfill materials are used in stations; and Long life materials with high-reliability joints are used. However, the following concerns are raised and are to be addressed in ongoing inspection program. Potential mechanical damage due to traffic impact; and Stray AC current resulting in acceleration of corrosion. Figure 5 and Figure 6 demonstrate examples of minor damage which can be identified during routine inspection. Figure 5 Damaged earthing conductor Figure 6 Early stage of corrosion Current injection tests are carried out as part of initial earth grids installations. Earth grid current injection tests are also performed every fifteen (15) years to check the integrity of the existing terminal station grids. The majority of terminal station earth grids have been checked within the last 10 years. There is a plan in place to test the remaining terminal station earth grids within their scheduled timeframe. These tests include the measurement of soil resistivity, step and touch potentials at key locations, earth grid impedance and potential rise. In addition, excavations that allow checking the condition of the copper joints in earth grids are typically carried out when a station is rebuilt. As part of the ongoing maintenance programs, sample below ground earth grid joints and inspection of the switchyard surface conditions are now included. The condition of some of the station ground wires is showing a level of deterioration due to surface corrosion, and is monitored during inspection. The condition of transmission line ground wires is included in AMS 10-79 Transmission Lines Conductors. ISSUE 9 17/09/2015 8 / 12

3.4 Principal Aspects 3.4.1 Safety in earthing systems The main safety hazard to personnel or the public associated with terminal station earthing system is a portion of earth fault current flowing through the heart and resulting in ventricular fibrillation. The risks, safety conditions, methodology and assessment criteria are defined in AS2067 3. This standard also forms part of electricity safety regulation requirements. To comply with safety regulations, AusNet Services ESMS requires the integrity of electricity transmission earthing systems to be continuously assessed and managed. AS2067 defines a methodology to further address risks based on a probabilistic approach, in particular, for areas outside of stations that maybe subjected to earth fault. To comply with these safety regulatory requirements, in particular, to eliminate and/or mitigate touch voltage, step voltage and transfer potential risk so far as is practicable. AusNet Services intends to review the adequacy of terminal station earthing systems to assess risks to align with new standards requirements, and aims to eliminate/mitigate safety risks. 3.4.2 Switchyard Surface Material The switchyard surface, and its material composition, is an integral part of the earthing system which can be designed to obtain higher allowable touch and step voltage limits. As such, surfaces with high resistivity must be maintained to provide an acceptable level of surface stability when subjected to pedestrian, vehicle and mobile plant traffic. This issue is outlined in AMS 10-55 Civil Infrastructure. Further investigation needs to be carried out to ascertain the best switchyard surface material that is to be used to satisfy both electrical safety and traffic stability issues. 3.4.3 Tower Footing Corrosion Corrosion problems have been identified in the footings of towers with grillage type foundations and those that are located close to terminal stations (both inside and outside the station). Electrical currents circulating via the line ground-wire and the station earth grid cause this corrosion. This problem can be reduced by installing insulators to separate the line ground-wire from the tower and station rack structure steelwork in order to prevent these circulating currents. To further protect against the adverse effects of circulating currents, cathodic protection (CP) and impressed current cathodic protection (ICCP) systems have been installed on 36 structures situated close to terminal stations. CP and ICCP systems minimise the impact of circulating currents by redirecting electrical charge, which promotes corrosion, to a sacrificial anode thereby protecting the structure footings. 3.4.4 Portable Earthing Devices AusNet Services employs portable earthing devices for the purpose of earthing plant items to the station earth grid or tower steel work. This action ensures safe access for personnel during installation, operational, maintenance or demolition activities. These devices usually comprise of a flexible copper conductor with plug or clamp fittings and are applied to electrically isolated plant using (in most cases) insulated switch-sticks 4. The plugs or clamps are attached to a dedicated attachment point such as an earthing cone to provide a suitable contact to earth for the isolated plant item. Due to manual handling issues and increasing fault levels, AusNet Services has a policy of using only fixed earth switches to provide safe access earthing at voltages of 220 kv and above in terminal stations. 3 Substations and high voltage installations exceeding 1kV a.c. 4 Transmission Field Work Procedures FWP 06-02 & SDM Volume 2, Section 6. ISSUE 9 17/09/2015 9 / 12

ISSUE 9 17/09/2015 10 / 12

3.5 Inspection and Monitoring Performance of the earthing systems within the stations should be monitored to ensure that the systems operate effectively. In addition to above ground visual inspections, there are two levels of ongoing monitoring programs for terminal stations main earth grid electrodes and earthing conductors. Level 1 monitoring tests include earth continuity test on earthing connections of the following assets and are performed every three years 5 : Power transformer and neutral points; Neutral earthing reactors/resistors; Operation earth mat on manually operated earth switches; CTs and VTs; Lighting masts; and Surge arresters. Level 2 monitoring tests are performed every 15 years involving: Current injection test on grid impedance; Step and touch voltages on critical items; Earth potential rise contours; and Transferred potentials. 3.6 Investment Drivers The main investment driver is the requirement to ensure the adequacy and integrity of existing earth grids from the viewpoint of electrical safety and plant operation limit. This is expected to be achieved by continuously assessing and managing residual earthing risks, ongoing earth grid condition monitoring program, and inspection of the condition of foundations for atrisk transmission line towers that are located close to terminal stations. 5 Dependant on severity of corrosion and duty. ISSUE 9 17/09/2015 11 / 12

4 Strategies High level strategies to be adopted for prudent and efficient management of the earthing systems of terminal stations and transmission line towers are: Complete the earthing system condition monitoring program for station earth grids. Undertake analysis of historical results to establish an understanding of the capability of each earth grid. Ensure earth grid step and touch voltage hazard limits for operational and maintenance requirements are consistent with international limits 6, national limits 7 and are specified in the AusNet Services Station Design Manual. Continue monitoring program for terminal stations main earth grid electrodes and earthing conductors, continue the ongoing monitoring program which include the following: o Carry out Level 1 monitoring tests on station earth grids at maximum interval of 3 years if subjected to severity of corrosion and duty on conductors. o Carry out Level 2 monitoring tests on station earth grids at maximum interval of 15 years depending on risk assessment. o Carry out above ground visual inspections with maximum interval of 2 years. For terminal station overhead earth wires, continue to carry out visual inspections at a maximum interval of 2 years and replace deteriorated earth wires and connectors when appropriate. Continue the practice of visual inspection and earth continuity tests on representative critical earthing joints/connectors and sample main earth grid conductors during major terminal station projects. Continue to test earthing performance, and to analyse results to determine if augmentation and/or enhancement works are required based on risk assessment. 6 International limits include IEC 61936-1, IEC 60479.1 and IEEE 80. 7 National limits include AS 2067, AS 7000 and AS60479. ISSUE 9 17/09/2015 12 / 12