Testing of 400 kv GIS. ROBERT LE ROUX, DERMOT DORGAN, BRIAN PERRY ESB International Ireland

Similar documents
ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

Transformer Bushings for GIS

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

MiCAFIL. 1 RIP Technology. Bushings. Z. Zic 09/2003

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

High-Voltage Compact Switchgear 3AP1 DTC for 145 kv and 245 kv

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

Unified requirements for systems with voltages above 1 kv up to 15 kv

Condition Monitoring of equipment to improve quality of supply to customers by averting failures

Preliminary Results from Present Cigre Survey

SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

High-Voltage GIS yesterday - today - tomorrow

FAQs-Main switchboard design criteria

Modular Systems, PPMV, 2014 UniPack-G Glass Fiber Reinforced Polyester Compact Secondary Substation

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

High Voltage Electrical Equipment Failure Diagnosis. Presented by: Spencer Tang & Terence Ng T&T Inspection & Engineering Sdn Bhd

EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK

HV Submarine Cable Systems Design, Testing and Installation

J W Spencer School of Electrical Engineering, Electronics and Computer Science

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Siemens AG Power Transmission and Distribution Medium Voltage Division Mozartstr. 31c Erlangen Germany.

Modular Systems wind portfolio overview Power Collection and Grid Connection products

F05D Meeting on Damped AC Voltage Testing

How To Test For Safety On A Power Cable

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & Instructions For Installation, Operation & Maintenance

Residual life aspects on GIS with the focus on SF 6

Engineering innovation

INTERNATIONAL STANDARD

TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets. 17th April 2012

The Intelligent AX1 Switchgear for Medium Voltage

High-Voltage Circuit-Breakers 3AP1/ kv up to 550 kv. Power Transmission and Distribution

PD Monitor GIS. 24/7 Partial Discharge (PD) monitoring system for Gas Insulated Switchgear. Benefits NEW PRODUCT

e 2 ALPHA Medium Voltage Switchgear Data Sheet K EN

White Paper. Safety Considerations When Using Optocouplers and Alternative Isolators for Providing Protection Against Electrical Hazards.

2. INDUCTIVE VOLTAGE TRANSFORMERS Oil-paper insulation Gas insulation

5.0 Reference: Application, Volume I, Chapter 5, Heritage Contract

IEC/CIGRE UHV Symposium Beijing KVDC: EXTERNAL INSULATION, INSULATION COORDINATION, TEST LEVELS

METAL-CLAD AND METAL-ENCLOSED SWITCHGEAR 3.6KV~40.5KV. tgood.com. Energy. Fast.

Respecting the environment

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms

produces and delivers products worldwide can provide the optimal are dedicated to supplying you with superior advice and global support.

How To Choose A Transformer

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

Effective Condition Assessment of Medium Voltage Switchgear

High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy.

Network Consulting for Power Grid Optimization

CONTENTS.

Fault location on power cables. Fault location on power cables

SURGE PROTECTIVE DEVICES

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV a. Section INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

SIEMENS Transmission and Distribution

PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions

The standards mentioned in this document

Presentation to CIGRE Next Generation Network. Visit of Seine substation

Our brand POWER DYNAMIC PASSION COMMITMENT CREATIVITY. A strong brand for strong products: 8PU Premium. MV Energy

UGVCL/SP/591/11KV HT AB CABLE

Testing of Power Transformers. Routine tests, Type tests and Special tests

Medium voltage products UniSec for Smart Grid Air-insulated medium-voltage secondary distribution switchgear

IEEE802.3poep Study Group Revision of isolation requirements in IEEE802.3 clause 33.

Automated test systems for distribution transformers Part II. Detailed analysis of the test system features EVENTS ABSTRACT KEYWORDS

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

On-line monitoring of substation condition a Romanian experience. V. ZAHARESCU, Vl. ROSCA Nova Industrial SA. CN Transelectrica SA Romania

Enhance Power Equipment Reliability with Predictive Maintenance Technologies

Power transformers. Special transformers Railway

A Practical Guide to Dielectric Testing

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

The Impact of Transmission Cable System Construction and Design on Commissioning Test Options & Results

CLAMPS CONNECTORS & EQUIPOTENTIAL RING

HIGH VOLTAGE SHORE CONNECTION

IEC & 2 standard. The reference for safe and reliable LV switchboards

Electrical Predictive and Preventative Maintenance

ABB s Disconnecting Circuit Breakers Higher substation availability and lower environmental impact

Advantages of Fixed Circuit Breaker Switchgear

AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A

Guide to the electrical parameter classifications of IEC and IEC safety standards

SECTION DRY-TYPE TRANSFORMERS

MNS is Switchgear System Technical Overview

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

David O Brien, CMP Products (David.OBrien@cmp-products.com)

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution

NATUS NES / NES-H Draw-out Type Medium Voltage Switchgear Systems. Safe energy distribution that meets the highest industrial requirements

An Overview of Lapp Insulator High Voltage Bushing Design

Insulation resistance

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Hyperlinks are Inactive

Engineering Specification

Ralf Christian, CEO Low and Medium Voltage. Making Things Right with Totally Integrated Power (TIP)

ICM Project Station Infrastructure and Equipment

HVL 5 38 kv Load Interrupter Switchgear. The Standard for Performance, Protection and Dependability

ELEKTROTEHNI KO PODJETJE Leskoπkova cesta 12, 1000 Ljubljana, SLOVENIA

Electrical Shore Connections / Cold Ironing

New mitigation methods for transient overvoltages in gas insulated substations

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time

Transcription:

2016 CIGRE-IEC Colloquium 21, rue d Artois, F-75008 PARIS May 9-11, 2016 http : //www.cigre.org Montréal, QC, Canada Testing of 400 kv GIS ROBERT LE ROUX, DERMOT DORGAN, BRIAN PERRY ESB International Ireland SUMMARY The 400 kv transmission grid backbone in Ireland is designed to cater for critical periods of low loading. The original design parameters were set on the basis of low projections of energy usage in the late 1970 s as a result of high oil prices and economic recession at the time. Due to this critical under dampening, the lightning impulse (BIL) and switching impulse (SIL) levels for the transmission system were selected for the equivalent to that of a 550 kv transmission system. While energy demand and bulk transmission grew in the intervening years, the later effect of renewable generation, primarily connected to the lower voltage distribution systems, has led to frequent periods of low demand. During night valley periods up to 50 % of demand is often meet from renewable sources at embedded distribution level. The 400 kv system is relied on for frequency support and spinning reserve in the case of sudden loss of renewable generation, but lightly loaded for significant periods. The associated primary Gas Insulated Switchgear substations, when lightly loaded, may be more critically at risk of dielectric failure due to high Transient Recovery Voltages incurred during switching events. Dielectric failures of GIS invariably lead to forced outages of a greater amount of HV plant due to the protection schemes employed and compactness of the switchgear itself. As a result of recent experiences in new GIS installations in Ireland, ESB International has developed more stringent criteria for type, factory routine and in particular site tests after installation.in the specifications prepared for its parent company ESB, the transmission asset owner in Ireland. Specific tests and procedures, in addition to IEC standard tests according to 62271-203, have been carried out in multiple installations to date. These specific test requirements have been performed on a range of GIS installations from different manufacturers at various rated voltage levels. Some notable issues that the tests are designed robert.leroux@esbi.ie

to provide reassurance against include internally leaking insulators, intermittent partial discharge sources, particle generation from switching operation and latent manufacturing defects that may pass normal routine factory testing. KEYWORDS Gas Insulated Switchgear Lightning Impulse Withstand voltage Switching Impulse Withstand Transient Recovery Voltage (GIS) (BIL) (SIL) (TRV) Site Testing Factory Testing Flashover Partial Discharge

Introduction Ireland has a weak 400 kv transmission system, two lines connecting a generating station on the west coast to the main load centre on the east coast and due to this, the specified TRV and BIL levels for the 400 kv system are those normally used on a 550 kv transmission system. The consequence of dielectric failure presents a greater risk for GIS switchgear at this voltage level leading to more stringent requirements for the design specification, testing and site quality assurance. Specification Specifying exactly what is required with respect to quality and expected performance of manufacturers equipment is not a straight-forward task. As part of ESB International s technical and quality management process a dedicated team monitor, log and track all high voltage plant issues, regardless of age or asset type, in a database. This Primary Plant Log trends all equipment failures, common quality issues and defects. It provides a historical record of all issues whose mitigation or elimination is an objective in every revision of the equipment specification. The detailed specifications include key manufacturing quality checkpoints or tests to ensure that previously known manufacturing defects on previous equipment are detected in any new order. The specific number of mechanical operations for switching devices,, corrosion protection tests and other specific checks are specified according to equipment type and the relevant defect history. VT Supplier / Selection Following an open tender for 400 kv GIS switchgear, submissions from several major suppliers were technically and commercially evaluated. Several manufacturers opted to offer 400 kv rated voltage switchgear but type tested to 550 kv insulation withstand levels. The order was given to a manufacturer offering a compact 400 kv design which provided the lowest total cost of ownership for the customer due to its size. During initial tests of the prototype GIS voltage transformer, two flashovers occurred. Both were due to dust or particles on the inner surface of the insulator. Investigation with the manufacturer and root cause analysis found the barrier insulator to be the main cause of any test failures during production of all VT types. These barrier insulators are commonly freeissued by the GIS manufacturer to the manufacturer of the VT. The insulator design used can influence the risk and rate of routine test failures. Conical barriers with raised surface profiles are deemed a lesser risk as particles are not retained as easily on the insulator surface. The VT to be used on the GIS was based on the design for a 420 kv rated voltage unit. The housing used was identical to that used to meet 420 kv insulation levels. The VT manufacturer redesigned the active part only i.e. the primary winding insulation design and the shape of the high voltage electrode (grading ring) to achieve the 550 kv insulation levels required. The width of the insulation foil used on the primary winding was increased to enlarge the insulation distance between the conductor, core and inner surface of the

compartment. By increasing the width of the insulation foil layers that contain channels to hold SF6 gas, the effective insulation distance has been increased and considered similar to the effect of adding sheds to AIS insulators. The shape of the HV electrode or grading ring was adjusted for the increased stress and coated with layers of dielectric paint to achieve an even and smooth surface to ensure a uniform electric field. The HV withstand test was carried out at 710 kv per IEC 62271-203 insulation level for 550 kv rated voltage. Negligible PD was observed at the 1.2 times rated voltage level (phase to ground) for single-phase enclosed equipment. A maximum allowable partial discharge level of 2 pc was applied to the new equipment. The IEC limit is currently 10 pc therefore an increased quality margin over the IEC requirement was obtained. GIS Type Testing During the initial design review the manufacturing facility was inspected. A 400 kv bay was demonstrated and tested at the higher BIL level. Internal flashovers resulted at several barrier insulators. This was found to be due to incorrectly placed or incorrectly sized corona shields installed for the increased dielectric withstand requirement. Several points were also subject to dielectric field overstress due to particles formed during incorrect cleaning or mechanical operations. The dielectric insulation design was revised with changes to the profile of the insulators and increased SF6 pressure.. Factory Acceptance Testing Three complete GIS bays were presented for the factory customer acceptance tests in accordance with the agreed protocol. The bays chosen composed the three main variants of feeder, transformer and busbar coupler bays required by the client. Routine tests performed on the three bays were conducted in accordance with IEC 62271-1, IEC 62271-100, IEC 62271-203 and the customer specification. The following routine tests were performed as agreed with the manufacturer prior to the Factory Acceptance Test (FAT); Mechanical tests of the circuit breaker and all disconnector and earth drives Contact resistance measurement of the circuit breaker and disconnectors Gas tightness tests High voltage withstand tests with partial discharge measurement Customer-specific functional test of the control and operation systems In accordance with the customer specification the HV withstand tests were performed at insulation levels corresponding to 550 kv rated voltage, i.e. 710 kv.

During FAT testing there were six failures. One was due to incorrect assembly a 400 kv endcap installed instead of 550 kv type. The other five flashovers and PD events were due to particles and/or voids in the insulators. Site Testing Due to flashovers and partial discharge issues picked up with GIS in other installations the customer specification required an extra 200 mechanical operations to be carried out on all units as a standard mechanical conditioning procedure before any dielectric test. This is to ensure that all possible particles are formed and removed before the final on-site HV test. Successful completion of the procedure also provides some confirmation that there are no switch or contact misalignments. After the 200 operations the manufacturer must open and clean a number of sample compartments to check whether excessive particle generation has occurred. All on site tests were done generally as per IEC requirements, but with longer conditioned time according to the below table and lower threshold acceptance criteria for partial discharge detections. Table indicating values for 420 kv and customer requested values at 550 kv During the site testing there were fourteen occurrences of flashover or partial discharge. The reason for almost all the occurrences were due to metallic particles inside the gas compartments or due to voids within the insulators. After replacement and cleaning of the affected sections / chambers, the tests were repeated and then passed the required IEC clause of the HV tests.

Conclusion The drive to reduce cost has encouraged many manufacturers to reduce the size of their equipment which implies that these designs have lower thresholds of dielectric insulation margin. As very limited room for error in the manufacturing process and procedures are allowed this means that the slightest anomaly or intolerance can cause dielectric failure.. ESB International has noted an increasing trend of dielectric breakdown in new compact GIS types during factory routine tests and on site HV withstand tests after installation. A sizable number of failures have all occurred at close to nominal system voltage therefore decreasing the confidence of the asset owner in enduring any system disturbances or expected switching overvoltages. IEC specifications should include a minimum design margin on the test levels for all GIS switchgear. ESB International specifically would like to see a higher number of mechanical tests to be performed on the equipment prior to factory and site testing to minimise the increased threat posed by particles. A larger number of switching operations should also be performed after installation to disturb or shake out particles and increase the effectiveness of the on-site dielectric tests. On-site HV withstand tests should be performed for longer durations at 1.1 or 1.2 Un following the PD test voltage in order to better simulate increases above nominal system voltage that may be expected during valley periods due to the impact of embedded renewable generation. Switching operations during the increased soak period to simulate network switching events are advised to disturb any possible particles and trapped charges. The effectiveness of the GIS earthing for Transient Enclosure Voltage rises can also be confirmed in this manner. Parameters for equipment to pass factory and site tests should be rigid and clear in order to ensure no errors in specification interpretation. An acceptability criteria for dielectric failures incurred during on site tests should be considered by the purchaser. Failures due to incorrect assembly, while undesired are not necessarily indicative of material defects. Unexplained dielectric breakdowns in critical areas such as circuit breakers and other compartments with switching devices should however trigger a re-examination of the dielectric design margins. BIBLIOGRAPHY [1] Review of 400 kv GIS Voltage Transformer Supplier Trench Bamberg October 2014 [2] IEC 62271-1 [3] IEC 62271-100 [4] IEC 62271-203 [5] ESB specification 18124.

Appendix A: Photos Right and below HV Resonance test set used for site testing. Right failure on insulator during site High Voltage test Below: Moneypoint finished installation

Top: HV test layout, below 3D model of 400 kv GIS