DESIGN AND DEVELOPMENT OF AUTOMATIC MAINS FAILURE PANEL FOR DIESEL GENERATOR

Similar documents
SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original

AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A

Fundamentals of Power

The following table shows approximate percentage wise the

Unified requirements for systems with voltages above 1 kv up to 15 kv

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches

BT300 HVAC Drives Conventional Bypass (C-Bypass) Options

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...

Specification Requirements DBL 700MX and 1000MX Series UPS

Transfer Equipment Controls

GTEC transfer switch open transition

Thyristor-controlled power supplies and battery chargers

Eaton s E-Series protective relay family

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits

ATS - Automatic Changeover

Speed Control Relays SX2

Safety technique. Emergency stop module BO 5988 safemaster

Primary and Secondary Electrical Distribution Systems

Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000

Arc Terminator Active Arc-Resistant Switchgear

OVERCURRENT & EARTH FAULT RELAYS. To study the protection of equipment and system by relays in conjunction with switchgear.

Power Generation. Power Control PCL System Generator Set Control

Liebert GXT MT+ CX UPS, 1000VA VA Intelligent, Reliable UPS Protection. AC Power for Business-Critical Continuity

How To Operate A Gec Transfer Switch Open Transition Amp Power Supply

DORMA MODEL PS-406BB POWER SUPPLY INSTALLATION INSTRUCTIONS

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

BB800 Off-Grid Solar System

Proper Application of 415V Systems in North American Data Centers. A White Paper from the Experts in Business-Critical Continuity

Inverter / Charger Installation General Operations and AC and DC Connections

Generic PCSR Sub-chapter 15.4 : Electrical Equipment

Cahier technique no. 196

TA Kahraman Yumak ELK412 - Distribution of Electrical Energy Lab. Notes v Spring web.itu.edu.tr/yumakk. Distance Protection

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services

*.ppt 11/2/ :48 PM 1

UniGear ZS1. Medium voltage, arc proof, air insulated switchgear for primary distribution

Grounding of AC generators and switching the neutral in emergency and standby power systems

Figure 1 - Crydom 3RHP Three-phase Hybrid Solid State Contactor. Crydom Inc.

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

PLC Based Liquid Filling and Mixing

Instruction Bulletin. MCS025 Sync-Check Module Installation Sheet

Electronic overload relay EF65, EF96 and EF146

ABB Fuses Competitive Advantages

New standardized approach to arc flash protection

Your Advantages For safety application up to PL e / Cat. 4 e.g. SIL 3 Manual or automatic start * see variants. Applications.

Electrical Shore Connections / Cold Ironing

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Typical Data Requirements Data Required for Power System Evaluation

THE INPUT/OUTPUT SYSTEM. Key Points

Cam switches. Page. Overview 4-2. ON-OFF switches, main switches, maintenance switches 4-3. Changeover switches, reversing switches 4-5

GS Semiconductor Fuselinks. GE Power Controls. GS Semiconductor fuselinks

Earth Fault Detection Basics in Theory

Positive-guided relay outputs: 3 safety contacts (N/O), instantaneous. 1 auxiliary contact (N/C), instantaneous

32VFD Variable Frequency Drives for Centrifugal Chillers

Bulletin 150 SMC Flex Smart Motor Controller Specifications

Product Guide. Low voltage grounding system. Answers for industry.

SD Series. SD Series Rectifiers. EPC Energy & Power Conversion

TECHNICAL SPECIFICATIONS FOR 1.5 KVA ONLINE UPS

Design of electrical power system for a 1000MW nuclear power generating station

How To Choose A Transformer

Permissible ambient temperature Operation Storage, transport

Circuit Breakers. Next Generation of Protection Capabilities

Single and three phase modular Automatic Transfer Switch from 40 to 160 A

Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500

Power Quality. Voltage Sag Ride-through Mitigation in Sequence by Increasing Cost

MOBILE DC POWER SYSTEMS FOR SUBSTATION APPLICATIONS

INSTALLATION & SERVICE MANUAL. Display Panel

Type: DILM115(RAC240) Article No.: Sales text Contactor,55kW/400V,AC operated. Ordering information

Transformerless UPS systems and the 9900 By: John Steele, EIT Engineering Manager

White paper. ABB solutions for switching and protection of low speed wind turbines

C.I.8.2 Offsite Power System. C.I Description

Challenges of Protection and Control System Verification on DP3 vessels with Focus on Ride Through Fault and Blackout

RISH EM 3490 DS Dual Source Energy Meter RISH EM 3490 DS. Application : Product Features:

Switchgear Application Issues for Mission Critical Power Systems, Part One

PowerCommand Paralleling System Digital MasterControl

21 st Century Facilities

The HVAC SOLUTION DELIVERING POWER...SAVING ENERGY

VOLTAGE REGULATOR AND PARALLEL OPERATION

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw

LESTRONIC DV AUTOMATIC 12 OR 24 VOLT DUAL OUTPUT DUAL MODE BATTERY CHARGER MODEL TYPE 12/24EL40-10ET

Technical Manual Functional Description for S800-RSU-H / S800W-RSU 2CCC413022M Schaffhausen 1 / 10

The Application of Circuit Breakers to Reduce Downtime in Datacentres

SELECTION OF FINAL CIRCUIT PROTECTION

Disturbance Recoder SPCR 8C27. Product Guide

Safety automation solutions

Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

Residual Current Circuit Breaker

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

VARIABLE FREQUENCY DRIVES Revised 4/30/ Mechanical Systems

32:(5#5$7,1* 4833#USP283#+] 4;33#USP293#+] 3ULPH 113 kva, 90 kw 124 kva, 99 kw 6WDQGE\ 114 kva, 91 kw 125 kva, 100 kw

Chapter 5. Components, Symbols, and Circuitry of Air-Conditioning Wiring Diagrams

Electronic overload relay EF19 and EF45

E-STOP relays, safety gate monitors

TABLE OF CONTENTS 1.0 INTRODUCTION PURPOSE DEVIATION INTERTIE PROTECTION REQUIREMENTS... 4

TOSHIBA G /100/160/225 kva

Solid-State Relays (SSRs) vs Electromechanical Relays (EMRs)

AUTOMATIC TRANSFER SWITCH CONTROL UNIT OPERATOR S MANUAL

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

Transcription:

DESIGN AND DEVELOPMENT OF AUTOMATIC MAINS FAILURE PANEL FOR DIESEL GENERATOR Dashpute Ajit, Pathan Mohsin, More Prashant., Kamble Vijaykumar Savitribai Phule Pune University, India, Department of Electrical Engineering, AISSMS s Institute Of Information Technology, Pune, India. ajit.dashpute21@gmail.com, mohsinpathan58@gmail.com, prashantmore.more64@gmail.com Abstract --Electricity is an essential commodity in our day to day life, electricity forms the basics of any developing country or a developed country. Electricity is required in Domestic, industrial and commercial purposes. Thus, electricity is very important. Failure in electricity supply or interruption in the supply has many adverse effect on Electrical equipments and Control systems. The purpose of this project is to design and build a system that is called Automatic Main Failure (AMF) System which can automatically allow switching from Mains power supply to a battery as backup power supply. Depending upon the Control unit,[1] there are three main types of AMF units 1) by using Microcontroller in AFM unit itself, 2) by using PLC (Programmable Logic Control) programming for control action & 3) with the help of Relay Machanism.In this paper a Relay based system is discribed for control action. Elements which are used they are voltage sensor(pfd), Overload Relay and Air Circuit Breaker. The system is continously monitoring the voltage level from the mains. If the voltage is dropped below the allowed level, this system will switch the Load to Generator(Auxillaury supply) and switch back to the Mains when the voltage is back to nominal required normal level.an interlocking of both the ACB is done to avoid any mal operation of switching of ACB. Some delay is also introdused in the system to avoid the transient condition fault in witch the source will not have to shift.continouty of supply to load is achieved with the help of AMF unit. Keywords: Phase Failure Detector; Overload Relay; Air Circuit Breaker; Battery Charger; Delay Timer; MCB, Bus bar. I. INTRODUCTION Automatic Main Failure (AMF) System is a system which can automatically transfer the switch from Mains power supply to Auxiliary when anomaly such voltage drop, over-voltage and outage or blackout is occurred at the main power & any Power Quality problem regarding the supply will also cause the system to operate. [2]AMF continuously monitor the level of voltage and the output is given to the Control Circuit. Feedback from the Overload relay, Low voltage monitoring relay will generate the signal for both the ACB to be operates corresponding and switch the supply accordingly. A. Objectives. The objectives of this project is to: i) Design a system that allows switching from mains power to backup power when anomaly is detected. ii) Design an automatic system using Relay Operating Control system. 458 www.ijergs.org

TABLE 1. Main Components and their Specification used in the system. Component List Phase Failure Detector Overload Relay Air Circuit Breaker Battery charger Delay Timer(ON delay) Single Pole MCB Ratings 415-440 VAC 440V,6 Amp 415V,800 Amp 24 V DC 10 Amp 240VAC 230/400V, 16 Amp B. Problem Statement i. A device will not operate efficiently due to the voltage drop ii. A device may damage due to overvoltage iii. Time Consuming, to switch the source manually. II. FUNCTIONAL DETAIL A. Phase Failure Detector. It is an electro mechanical device used in power system engineering to protect a load from damage due to failure in any of the phases supplying power to the load. It automatically cuts off the load from supply if one of the individual phase becomes faulty. A phase failure detector is particularly important component in many assembly plants using the mains power supply. A significant reduction in value due to uneven load conditions will cause serious problems. Phase Failure Detector will operate in following conditions; i) Unbalanced Voltage ii) Single Phase or Phase loss iii) Overload Condition iv) Power Outage v) Phase Reversal It monitor both Generator as well as Mains side parameter. Any above mentioned condition will cause PFD to operate & give signal to ACB as well as control signal is generated B. Overload Relay A thermal Overload relay is used for monitoring the over load in the system. Which causes the over current flow from supply side to the load side. This overcurrent will responsible for many damage that will occur in the system. Equipment fail to operate, life time of electrical machine will get reduced, and mal operation of other connected unit etc. are the main impact of this overload or current to the system. 459 www.ijergs.org

Thermal Overload relay is a bimetallic strip having different thermal properties like the melting or binding temperature of one strip will be less than that of other. In case overload, this high inrush current flowing through the relay will cause the one strip to be milt & relay contacts will get closed this gives the signal to control unit As per given feedback signal from thermal overload relay ACB & other control signal generated. Fig. 1 : Overload Relay C. Air Circuit Breaker Air circuit breaker is a device used to provide Overcurrent and short circuit protection for circuits ranging from 800Amps to 10000 Amps. Air circuit breakers are usually used in low voltage applications below 450 volts. ACB prevents the re-establishment of arcing after current zero by creating a situation where in the contact gap will withstand the system recovery voltage.for interrupting arc it creates an arc voltage in excess of the supply voltage. [3]There are three main methods by which this arc voltage get reduced. i) By cooling the Arc plasma Medium between the contactors of ACB has high temperature during the Arc reformation due to which free electrons are radially developed by collision, to avoid this a cooling system is provided in-between. ii) iii) By lengthening the Arc path As the length of Arc is increased, it require more voltage to restrike Arc between the contactors. Metallic strip tangential to contactor are used to increase the length of Arc. By Splitting of Arc into n no. series A series of non-conducting fringes are present above the Arc area.this causes the Arc to split in no. of small Arc directed upward resulting to avoid the reformation of Arc 460 www.ijergs.org

Fig. 2 : Air Circuit Breaker An interlocking of both ACB is done to avoid the unconditional or fault occurs in the control signal generated.both the ACB will operate one after another. If any fault occurs in the one ACB then other ACB will not operate. D. Delay Timer It is a device which is used to add a delay in operation.there are two types of timer, ON delay timer & OFF delay timer. In ON delay timer, when time has expired the contacts close until voltage removed. In OFF delay timer, control input for opening of contacts cause timer to start &contacts will not be operates until the time out.on delay timer used to avoid transient fault operation. Fig. 3 : Delay time 461 www.ijergs.org

III. OVERALL SYSTEM DESIGN Fig. 4 : Line diagram Fig. 5 : Block diagram 462 www.ijergs.org

Above fig. 5 of block diagram represents the function of AMF panel. Each block represent the main part of panel. Power from mains supply is continuously monitored by PFD with the help of relay unit. It gives signal to the ACB for its operation / protection. When fault occurs in the mains supply PFD detects the fault and disconnect the mains supply form the load side by tripping the ACB. Generator will start automatically. When generator runs at rated RPM & frequency then the ACB (DG) will operate & supply is given to the load form the generator. A delay is introduced in the system to avoid the transient fault condition. panel. Power from mains supply is continuously monitored by PFD with the help of relay unit. It gives signal to the ACB for its operation / protection.when fault occurs in the mains supply PFD detects the fault and disconnect the mains supply form the load side by tripping the ACB. Generator will start automatically. when generator runs at rated RPM & frequency then the ACB(DG) will operate & supply is given to the load form the generator. A delay is introduced in the system to avoid the transient fault conditio IV. DESIGN CONSIDERATIONS In the designing of AMF panel for 250 KVA load, Active power & Maximum Rated current are calculated to determine rating of contactor to be used as well as cable size.(assume PF=0.8 & Balanced Load)[1] (Tolerance of 25%) (IEC 60439 2: 2000) Each control equipment are selected as per the above current rating of system. Connection Diagram of panel is made & final wiring of equipment are carried out after mounting of each 463 www.ijergs.org

V. CONCLUSION Auto mains failure panel with generator starting/shut down facility has been designed to help man reduce the stress and loss of time associated with the starting and shutting down of the alternative sources of supply (generator) It will automatically switch the source when the voltage is lower than required value. And supply of electricity is obtained. REFERENCES: [1] L.S. Ezema Design of Automatic Change over Switch With Generator Control Mechanism ISSN-L:22223-9553 Vol. 3, No.3,nov 2012 [2] Jonathan Gana Kolo Design and Construction of an Automatic Power Changeover Switch AU J.T. 11(2):(Oct. 2007) [3] S.M. Chaudhari Switchgear and Protection.Techmax publication. [4] Google.com [5] wikipidea [6] online search engines 464 www.ijergs.org