ROCKHAMPTON TO YEPPOON PIPELINE - PROJECT MANAGEMENT ASPECTS. Chris Hegarty & Neville L Oste Brown



Similar documents
Design Criteria & Service Goals

Policy 11: Land Development Guidelines

SECTION IX SLIP LINING PIPELINES

SHOALHAVEN RIVER CROSSING (NOWRA NSW) SEWER MAIN REPAIR. Steve Glennan. Shoalhaven Water, Shoalhaven City Council

Water Supply Code of Australia WSA

Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Engineering Policy 146. Severe Weather Management Plans

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

2.1 Development of Risk-Based Asset Management Framework

WATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods

1.1 At its meeting on 11 December 2014, Council resolved to (9.3): 1.3 This report also seeks the Council s approval to:

Appendix A: Acceptable pipe and fitting materials

On Your Lot Building How To Get Started

City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #37-15 REQUEST FOR PROPOSAL

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline

Exploration for natural gas

LNG A Different Approach The Teesside GasPort Project

The Pipelines Regulations, 2000

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

NEVADA IRRIGATION DISTRICT DEVELOPER REQUIREMENTS FOR TREATED WATER SYSTEM EXTENSIONS GENERAL

Water Supply. Simulation of Water Distribution Networks. Mohammad N. Almasri. Optimal Design of Water Distribution Networks Mohammad N.

Standard terms and conditions

PALMERSTON REGIONAL HOSPITAL PROJECT Status Report to the Commonwealth for the period: June November 2015

DESIGN IS GOOD BUSINESS

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Frequently asked questions July 2014

LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM

2014 STAMP Conference MIT Partnership for a Systems Approach to Safety Using STAMP Principles in Risk Management of Large Scale Pipeline Projects

ENGINEERING COMPETENCY CLAIMS

Water Management in Helsinki. Water supply. Mikael Sillfors

For business. Wiring your business for broadband. What happens when copper is required?

MAKING WATER WORK EVERY DAY

Repaired 24 Mainline Leaks

Application for the Alteration of a Gas Supply

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS -

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

Frequently Asked Questions About PennEast Pipeline Project

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

MOKOLO AND CROCODILE RIVER (WEST) WATER AUGMENTATION PROJECT TRAFFIC MANAGEMENT

Water and Sewer Utilities

PREFERRED REQUIREMENTS: WATER SUPPLIES AND ACCESS FOR SUBDIVISIONS IN RURAL ZONES

Inquiring Minds Want to Know: Questions Landowners Should Ask in Negotiations with Companies Seeking Easements

Emerging Technologies in Wastewater Collection Systems

ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE

EXPRESSION OF INTEREST DESIGN, DOCUMENTATION AND PROJECT MANAGEMENT UNIT COMPLEX - LOT 8955 PALMERSTON

PROJECT COST ESTIMATES & FEASIBILITIES

Gas to the West INFORMATION LEAFLET. gastothewest.com. www

WUJAL WUJAL ABORIGINAL SHIRE COUNCIL DEMAND MANAGEMENT PROJECT. Peter Kirchmann. Wujal Wujal Aboriginal Community

Contractor of the Year

PART 4: SITE INFORMATION

Township of Enniskillen. Asset Management Plan

SECTION 5 DRAFTING STANDARDS

CONSERVING OUR RURAL ENVIRONMENT

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES

NON-TRADITIONAL UTILITY COORDINATION on KYTC Projects. KYTC Partnering Conference September 9, 2014

Definition of Tower from the Bradley County Zoning Resolution

ENGINEERING REPORT FOR PAIES WATER SUPPLY SYSTEM KlTTl MUNICIPALITY, SECTION I, POHNPEI FEDERATED STATES OF MICRONESIA

Water Mains Rehabilitation Framework (NI) Northern Ireland Water

Historic Flood Impact on the Nashville Drinking Water System. Scott Potter, Director Metro Water Services, Nashville, TN

Sample Micro Hydro Initial Report

BONATTI: COMPANY OVERVIEW

A Break Even Analysis and Potential Profitability of a Proposed Residential Development within the City of La Crosse, Wisconsin USA

Buildings Construction Procurement Strategy

Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar

WHAT DO YOU KNOW? HOW TO GET THE BEST INFORMATION OUT OF YOUR SYSTEM AND THE FOLKS THAT RUN IT.

Terms of Reference. Aqaba Water and Wastewater Utility Asset Valuation

APPENDIX 7 : PHYSICAL CULTURAL RESOURCES MANAGEMENT PLAN

APT Petroleum Pipelines Limited. Queensland Floods

Redland City Council. 1. Recommendation. 2. Local government metrics. The Commission recommends:

Request for Proposal #

Request for Proposals PROFESSIONAL SERVICES FOR DRINKING WATER, WASTEWATER AND STORMWATER PROJECTS OPEN-END CONTRACTS

SECTION 8 WATER SUPPLY SYSTEMS

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

OSU Extension FACT SHEET

fëëìé=m~ééê aê~ñí=`çêéçê~íé=mä~å=omms=ó=omnm= 1. Issue Name 2. Contributors

Background and Goals for the Project

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG

Bridges & Culverts Condition by Quantity

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

JUNIOR ENGINEER (11 Positions)

Black Mountain Reservoir Land Rezoning

TOWN OF SAUGEEN SHORES WATER AND SANITARY SEWER SERVICING MASTER PLAN 2014 REPORT

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Swalley Fees, Fines, & Assessment Policy 2016

THE RIGHT-OF-WAY ACQUISITION SECTION

APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY

Teesside GasPort. World s first dockside high pressure gas offloading facility for Energy Bridge Regasification Vessels (EBRV)

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

San Diego County Water Authority Contracting Opportunities - July 4, 2016, 1:52 a.m.

ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION

How To Install An Overhead Sewer

Design Deliverables Checklist

May This document is not a public record. Amador Water Agency

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

Comanche Trail Pipeline Project. September 2015

Aspects of Energy Efficiency in Water Supply systems

Transcription:

ROCKHAMPTON TO YEPPOON PIPELINE - PROJECT MANAGEMENT ASPECTS Paper Presented by: Chris Hegarty & Neville L Oste Brown Authors: Chris Hegarty, Senior Water Engineer, Cardno Mike Truscott, Manager Major Projects, Fitzroy River Water 35th Annual Qld Water Industry Operations Workshop Community Sports Centre, CQ University, Rockhampton 22 to 24 June, 2010 35 th Annual Qld Water Industry Operations Workshop Page No. 123

ROCKHAMPTON TO YEPPOON PIPELINE - PROJECT MANAGEMENT ASPECTS Chris Hegarty, Senior Water Engineer, Cardno Mike Truscott, Manager Major Projects, Fitzroy River Water ABSTRACT This $49.4 million project provides a link between the Rockhampton and Capricorn Coast water supply networks. The project has received State and Federal Government funding and will supplement the existing Waterpark Creek source for the Capricorn Coast. It involves approximately 42km of 600mm and 750mm diameter Ductile Iron Cement Lined pipeline as well a pump station and a 10ML reservoir. Project Delivery will be explored in terms of the number and type of contracts employed, risk and the management of the many contract interfaces. Special design aspects are discussed including above ground valve facilities, rural fire hydrants and service connection points. 1.0 PROJECT BACKGROUND The Rockhampton to Yeppoon Pipeline (known hereafter as the pipeline ) will deliver treated water to the Capricorn Coast water supply system. Raw water will be drawn from the Fitzroy River and treated at the existing Glenmore Water Treatment Plant before being pumped through the pipeline to the Capricorn Coast. The pipeline is comprised of mainly 750mm and 600mm diameter PN35 DICL pipe and is capable of delivering up to 37ML/day to the Capricorn Coast System with 2 pumps operating at Ibis Ave No 2 Pump Station. This water will supplement the existing Waterpark Creek source which is nearing the extraction limit of 17 ML/day (4,400 ML per annum). The Capricorn Coast Water Supply Sources Study (Cardno Jan. 2005) concluded that the least cost method of supplementing the Capricorn Coast s water supply beyond the development of Waterpark Creek and Sandy Creek was by the construction of a pipeline from the Fitzroy River Barrage, provided substantial financial support could be secured from the other tiers of Government. The capital cost of the infrastructure required to meet the year 2056 water demands of the Capricorn Coast was $49.4 million and the funding secured for the project is outlined in Table 1. Table 1: Funding Sources Rockhampton to Yeppoon Pipeline Project Federal Government $16,467,000 33.3% Queensland Government $20,000,000 40.5% Livingstone Shire / Fitzroy $12,933,000 26.2% River Water Total $49,400,000 Five alternative routes for a pipeline to the Capricorn Coast were examined in the Capricorn Coast Water Supply Sources Study (Cardno Jan. 2005). 35 th Annual Qld Water Industry Operations Workshop Page No. 124

While there was little difference in an economic comparison of the alternative routes, construction along the Rockhampton Yeppoon Road alignment was considered the less expensive option. The pipeline route and the overall strategic design of the project was further refined through the Fitzroy River Pipeline Preliminary Alignment and Investigation (Cardno Sept. 2006). The existing and future demands used in design consider population increases on the Capricorn Coast between 2.5% and 3% per annum. The estimated water requirement by the year 2056 to meet the needs of the Capricorn Coast is predicted to be about 13,000ML/a (refer Figure 1). Figure 1: Predicted growth in Capricorn Coast water demand Figure 2 shows a basic layout of the system as it will commence operation in 2010. Waterpark Creek Woodbury Water Treatment Plant Feed to Parkhurst area via link to 600 above ground main Glenmore Water Treatment Plant Yaamba Rd Boundary 10ML Temp Feed to Pineapple Patch Yeppoon West Valve Facility St Faiths To Yeppoon and Northern Areas Fitzroy River Barrage Ibis Ave No 2 Pump Station To Rockhampton Yeppoon West (Future) New Pipeline and reservoir Existing Pipeline and reservoir Taranganba To Emu Park and Southern Areas Figure 2: Rockhampton to Yeppoon Pipeline Infrastructure Layout 35 th Annual Qld Water Industry Operations Workshop Page No. 125

2.0 PROJECT DELIVERY The following Table 2 outlines the approximate forecast cost break-up for the project. These costs include preliminary expenses but do not represent contract totals. Project Management includes easement acquisition/compensation, legal expenses and other expenses not attributed to specific infrastructure items. Table 2: Forecast break up of expenses Rockhampton to Yeppoon Pipeline Project Work Parcel Contractor Contract Form Percentage of project cost Pipe and Fittings Tyco Supply Contract 39.1% Ibis Ave Pump Station Yeppoon West Valve Facility and Taranganba Connection Yeppoon West (discontinued) Boundary 10ML Underbores Pipeline Construction JCQ Project Builders JCQ Project Builders Bailey Civil Contractors Hornick Constructions UEA Bailey Civil Contractors Design and Construct Contract It was intended to use the minimum amount of contracts possible in order to minimize any interface issues between contracts. There are potential issues in any situation where a contractor is relying on the actions of others. Two examples encountered on this project are given below and some further issues are raised under risk: 35 th Annual Qld Water Industry Operations Workshop Page No. 126 5.2% 4.7% 0.4% 6.0% 1.7% 23.9% Pipeline Construction Fitzroy River Water In House 8.7% Design / Project Management Fitzroy River Water / Cardno In House / Professional Services Agreement 10.3% construction contracts were lump sum contracts using a Modified AS2124. The contracts included specific requirements required by the federal funding including compliance with the National Code of Practice and the Equal Opportunity for the Women in the Workplace Act 1999. All documentation was issued electronically and this worked well except for some minor issues regarding the pdf of drawings. The use of a Design and Construct contract for Boundary was seen as an opportunity to allow a contractor to competitively bid on what is a reasonably standard product. It is considered that a quality product and value for money was achieved. Project management was carried out by officers of the former Livingstone Shire Council and Fitzroy River Water with support from Cardno when necessary. 3.0 INTERFACES BETWEEN CONTRACTS

4.0 RISK The underbore contractor was required to install and test the enveloper pipe and the service pipe. However, in order to test the service pipe, a concrete thrust block was necessary to hold the 2,100kPa test pressure. This thrust block would have been sizeable due to the large entry and exit pits the underborer used and would then need to be removed by the main contractor to allow the pipe connection to be made. The matter was resolved by the underbore contractor testing to 500kPa test pressure (thrust was held by connection to the enveloper pipe) and the main contractor completing a test to the required 2,100kPa pressure at a later time; and A situation arose where one contractor was given possession of site over an area held by another contractor. Whilst the possession of site issue could be easily resolved the fact that AS2124 provides that the Principal Contractor remains so until the final certificate is issued presented a problem. AS2124 provides that 21 days notice is required to remove a Principal Contractor. The following Table 3 briefly outlines some of the risks for the project, their controls and comments on the effectiveness of the controls / approaches Table 3: Project Risks Rockhampton to Yeppoon Pipeline Project Risk Control Comments Delay in the supply of pipe due to high demand for pipe at the time had the potential to delay the project A separate contract was let for pipe supply before detailed design was completed. Fittings supply contracts were let immediately design was completed. Mismanagement of environmental issues could result in fines and embarrassment Delays in taking easements had potential to delay the project. Delays in obtaining State Agency approvals had potential to delay the project. The original federal government funding required that the project be completed by November 2009. A detailed Construction and Environmental Management Plan was prepared for the project which the contractor was required to adopt. The Acquisition of Land Act was utilized to take easements rather than negotiation with landowners over compensation. The compensation is determined after the easement is taken. The environmental approval was sought in 2 stages. Stage 1 related to the majority straightforward aspects of the project. Stage 2 related to a more contentious marine crossing at Ross Creek, Yeppoon. Local Government amalgamation and the consequent redesign of some aspects of the project resulted in a new completion date of June 2010. Would have been good to avoid a separate contract for this if possible. No issues of significance arose. Some design changes resulted in new easements being required. Work in these areas was postponed until approvals were in place. The Stage 2 application still caused some minor project delay. All major works are expected to be complete by 30 June 2010. 35 th Annual Qld Water Industry Operations Workshop Page No. 127

Risk Control Comments Compliance with Cultural Heritage obligations could result in fines and embarrassment Addressed early through investigations and contracts with the local aboriginal people. Potential delay due to contract interface issues. The provision of underbores is specialist high risk work and would potentially affect project timeframes. The volume of rock encountered had potential for significant additional cost and would potentially affect project timeframes. Provision of service connections to the pipeline may affect pipeline integrity The most significant issue was due to principal supplied pipe and fittings. This was managed through detailed stockpile site inventory and direct communication between the contractor and the supplier. A separate underbore contract was let prior to the major construction contract in an attempt to complete this work early. Rock was to be paid at an agreed rate per cubic metre (that is the Principal took the risk). Rock was defined as production rates less than 15m 3 per hour for a 30 Tonne excavator. Tees rather than direct tapped service connections were used. No issues of significance arose. There was some delay in material supply, delivery to incorrect stockpile sites and related matters. Issues with the underbore contract and rain delay meant that the desired early completion of work did not result. The volume of rock encountered was slightly less than the 9,750m 3 budgeted for pipeline excavation. 5.0 SPECIAL DESIGN FEATURES Three rural fire hydrants, involving a hydrant, concrete slab and formed access were provided at strategic road intersections to service nearby communities along the route. The Yeppoon West Valve Facility is an above ground facility including 9 major valves and 2 flowmeters. It is intended to provide ease of maintenance and operation rather than the installation of traditional pits which have issues of confined space access and cramped working conditions. The provision of the above ground facility is considered to be cost neutral when compared to the alternative which involved three large concrete pits. The provision of service connection points to a major pipeline for the conveyance of bulk water is unusual. However, the local political landscape demanded that connections be provided. As a result 40 tees were installed at strategic locations to service the maximum amount of properties. Many of the service connections were co-located with scours and air valves to reduce cost. Pressure reducing valves will be required on some connections and individual small diameter PRV s for each service are to be installed at the time of connection. 35 th Annual Qld Water Industry Operations Workshop Page No. 128

6.0 CONCLUSIONS What did we learn and what advice can we provide? Do not underestimate the time required for taking easements and obtaining State Agency approvals; Carefully analyze the risk and focus effort in the right area; and Utilize the minimum number of contracts as possible. Pay careful attention to contract interfaces as these will present potential risk. 7.0 ACKNOWLEDGEMENTS Special thanks to Dan Toon and Nev Brown of the former Livingstone Shire Council who were influential in getting the project off the ground. Special thanks to the many Fitzroy River Water officers involved in the project for their efforts in delivering a successful project. Many photographs and other information from Fitzroy River Water has been included in this presentation. 35 th Annual Qld Water Industry Operations Workshop Page No. 129