SECTION IX SLIP LINING PIPELINES

Size: px
Start display at page:

Download "SECTION IX SLIP LINING PIPELINES"

Transcription

1 AN SECTION IX SLIP LINING PIPELINES February, 2008

2 TABLE OF CONTENTS SECTION IX - SLIP LINING PIPELINES GENERAL SCOPE MATERIAL CONSTRUCTION REQUIREMENTS EXISTING SERVICES ENTRY AND EXIT PITS PIPE JOINTING... 3 PVC PIPES... 3 POLYETHYLENE PIPES BYPASS PUMPING PIPE LINING CONNECTIONS SERVICE CONNECTIONS CONNECTIONS TO EXISTING NETWORK GROUTING TESTING MEASUREMENT FOR PAYMENT...4 Section IX - Sliplining Pipelines.doc February,

3 SECTION 9 - SLIP LINING PIPELINES GENERAL Slip lining is a technique used to renovate an existing pipeline by inserting a new pipe usually of a smaller diameter, by pushing or pulling it into the existing pipe and grouting the annulus between them SCOPE Specified in this section are requirements of slip lining of existing pipelines generally, including but is not limited to the following: flow diversion and temporary works traffic management excavating entry and exit pits pipe lining fabrication, storage and placement service connections, connecting to access chambers and make water tight Grouting other specific structural works testing reinstatement MATERIAL Suitable pipe lining materials are HDPE, MDPE and UPVC. Contractor may specify other material for consideration by the Superintendent. Use clause 2.04 joints, of general specifications pipe works. Grout to comply with AS3600. Use cement and water at a water cement ratio of 0.5. If blockage with pumps is a problem Contractor may use additives such as Methocell. Obtain prior approval before using any additives CONSTRUCTION REQUIREMENTS Provide all necessary plant, equipment, material and labour for carrying out the slip lining activities EXISTING SERVICES Locate existing service connections using closed circuit television (CCTV) method or using sonde and mark them on site. Carry out the necessary excavation to verify their locations ENTRY AND EXIT PITS The approximate locations of the entry and exit pits are shown on the drawing. Review the pit locations and submit details of the pit dimensions and any change of locations to the Superintendent for approval. Avoid locating these pits closer to buildings if possible. Carry out excavation as specified in Section I, Earthworks. Section IX - Sliplining Pipelines.doc February,

4 PIPE JOINTING PVC PIPES Solvent welded pipe joints are permitted. Ensure pipe pushing or pulling apparatus does not cause shattering or compression of the new pipeline. POLYETHYLENE PIPES Butt fusion weld all pipe joints to Australian Standard AS Remove both the internal and the external beading around the pipe joint caused by the welding BYPASS PUMPING Maintain the flow in the system during lining by bypass pumping or flow diversion. Submit details of bypass pumping or flow diversion to the Superintendent for approval. Stopping of the live flow and storing in the pipeline may be permitted only if there is sufficient storage in the upstream pipeline that will prevent overflows, flooding or blockage of the system. In such cases, provide detail of the length of time proposed for stopping flows. In any case stopping of live flow is permitted for a maximum of 8 continuous hours and thereafter the drainage system must be put back into operation. Give one week notice to the Superintendent, so that the affected public can be notified PIPE LINING Submit details of the pipelining plan to the Superintendent for approval. Include in the details at least the following: Type of mechanical head to be use, Application pressure, Length of pipe to be install per day, Impact of any vibration on adjacent buildings, Storage requirements Environmental issues such as noise, vibration and how they will be minimised, Calibration details of measuring devices, Safety aspects, and Any temporary works proposed Carry out the pipelining operations as approved by the Superintendent and in accordance with the drawings. Stop pipe-cracking operations immediately and take direction from the Superintendent if any of the following occurs: surrounding structures show signs of cracking or vibration pipe lining tool goes off-line incomplete insertion of new pipe flooding of the system due to blockage Arrange for storage of materials and plant with the property owners, if the work is located within the property boundary. Provide adequate traffic management in accordance with Special Conditions of Contract Clause S9.0, if the work is located on roadways. Minimise the impact of disturbances to buildings and property owners. Reinstate the site to its existing conditions and obtain satisfactory written clearance from property owners and the Superintendent ( Use form 596). Section IX - Sliplining Pipelines.doc February,

5 On completion of the pipelining and the installation of the new pipe, inspect all access chambers. Make the connections of the new pipe and the access chambers watertight by using approved sealant. If mortar is used, it should comply with AS3600, Clause Maximum shrinkage allowable is 1% by volume CONNECTIONS SERVICE CONNECTIONS Reconnect all service lines to the new pipeline as identified by the CCTV survey and in accordance with Standard Drawing 7600 series. Property connections or adjoining mains are not to be out of service for more than 8 hours. If this is not possible, temporary connections are to be made at convenient locations, as approved by the Superintendent CONNECTIONS TO EXISTING NETWORK Reconnect all new works to the existing network in accordance with Section Drainage GROUTING Carry out grouting of the annulus between the old and the new pipes using grout specified in Clause Submit to Superintendent details of grouting technique and verification methods to be used for approval prior to commencement of grouting TESTING Provide CCTV equipment and inspect pipeline after all connections have been reconnected. Submit the CCTV surveys to the Superintendent for approval. Field test the pipelines as directed by the Superintendent and in accordance with Section General Specifications, Drainage MEASUREMENT FOR PAYMENT Payment shall be based on the Schedule of Rates as tendered for the contract. The following units of measurement shall be used in the preparation of the Schedule of Rates if lump sum prices are not required. a) Pipe material is measured in linear metres. Include all items in accordance with Section Pipe Works. b) Slip lining is measured in linear metres. Include in the rate the supply of all plant, equipment and labour including all CCTV, temporary works, bypass pumping, jointing and positioning the pipeline in its final alignment and testing. c) Entry pits and exit pits are measured by cubic metres. Include in the rate the cost of excavation, backfilling and support if required. Excavation in rock if encountered shall be measured for payment in cubic metres separately. d) Service and access chambers connections are measured by numbers. Include in the rate locating them above ground, CCTV, any temporary works, all fittings, connecting to pipeline and making water tight using mortar. e) Relaying of service connections is measured in linear metre. Include in the rate the supply of materials, equipment, labour, excavation, backfilling and reinstatement. Section IX - Sliplining Pipelines.doc February,

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

Sewer Line Rehabilitation

Sewer Line Rehabilitation 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines: Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

SPR PE Steel Reinforced Liner

SPR PE Steel Reinforced Liner ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

Working together to improve beach water quality. Fixing our. public and private. sewers

Working together to improve beach water quality. Fixing our. public and private. sewers Working together to improve beach water quality Fixing our public and private sewers May 2004 FIND FIX DECIDE Narrow Neck Beach on a summer day As part of Project CARE, our long-term project to improve

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

Policy Guidance Notes and Requirements

Policy Guidance Notes and Requirements Policy Guidance Notes and Requirements Building over/close to Public Sewers Domestic Extensions and Garages 1.0 Introduction Householders and developers planning to build close to or over a public sewer

More information

INSTALLATION OF INSITUFORM LINER

INSTALLATION OF INSITUFORM LINER PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation

More information

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued) BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset

More information

725-R-599 PIPE LINING. (Revised 05-01-12) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

725-R-599 PIPE LINING. (Revised 05-01-12) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE PIPE LINING (Revised 05-01-12) The Standard Specifications are revised as follows: SECTION 725, DELETE LINES 1 THRU 317. SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density

More information

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE 1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint

More information

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11 Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;

More information

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals. SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in

More information

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

PART 5 : WASTEWATER DRAINAGE

PART 5 : WASTEWATER DRAINAGE Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction

More information

Pipeline Replacement using Relining

Pipeline Replacement using Relining Pipeline Replacement using Relining Mark Heathcote, March 2006 Relining of old pipeline systems is becoming an increasingly attractive option to asset owners and operators as an effective alternative to

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542 1.0 INTENT REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES 1.01 It is the intent of this specification to provide for the reconstruction of pipelines and conduits by the installation of a resin-impregnated

More information

Platte River Interceptor Slipline Rehabilitation

Platte River Interceptor Slipline Rehabilitation Platte River Interceptor Slipline Rehabilitation Owner: Metro Wastewater Reclamation District Contractor: American West, Denver CO Slipline Pipe Manufacturer : Hobas Pipe USA Presented by: Tom Furie, Area

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Trenching and Excavation Safety

Trenching and Excavation Safety 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking

More information

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING 1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of testing wastewater and/or storm mains to ensure construction conforms to the proper line, grade, cross section and performance. 2.1 The

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

Sewer Rehabilitation Design Requirements

Sewer Rehabilitation Design Requirements Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared

More information

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology 2007 Pumper & Cleaner Environmental Expo International Wednesday February 7, 2007 Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology What is Cured-In-Place Pipe (CIPP)

More information

LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM

LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper D-4-02 LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE

More information

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials

More information

Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice

Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice M. R. Zare 1, S. Wilkinson 2, R. Potangaroa 3 1. PhD candidate, University of Auckland, Auckland, New

More information

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing CCTV INSPECTION OF SEWER LINES PART 1 GENERAL 1.1 SECTION INCLUDES A. CCTV Inspections 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02731 Sanitary Gravity Sewer Line Testing

More information

Let Us Give Utilities the Respect that they Deserve.

Let Us Give Utilities the Respect that they Deserve. Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous

More information

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21 September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,

More information

Rehabilitation or Replacement? That Is The Question

Rehabilitation or Replacement? That Is The Question Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION GENERAL Rehabilitation of culverts with pipe liners is one of several methods available for extending the life of an existing culvert. It is often cost

More information

REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND

REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper A-5-04 REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY

More information

TG 105 ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS TECHNICAL GUIDELINE. Manager Asset Management SOUTH AUSTRALIAN WATER CORPORATION

TG 105 ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS TECHNICAL GUIDELINE. Manager Asset Management SOUTH AUSTRALIAN WATER CORPORATION TG 105 SOUTH AUSTRALIAN WATER CORPORATION TECHNICAL GUIDELINE ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS Issued by: Manager Asset Management Issue Date: SA WATER 2007 This document is copyright

More information

Federation of Piling Specialists

Federation of Piling Specialists Federation of Piling Specialists COMPANY NAME CONTRACT NAME TENDER REF SCHEDULE OF ATTENDANCES AND FACILITIES TO BE PROVIDED BY THE CLIENT TO A STEEL SHEET PILING SPECIALIST For the purposes of this document

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

San Antonio, TX July 28, 2011

San Antonio, TX July 28, 2011 Rehabilitation of a Deteriorated 60 RCP Wastewater Interceptor Using Competing Trenchless Technologies Bruce Cole, PE Corey Anderson, EIT TAWWA/WEAT Summer Seminar San Antonio, TX July 28, 2011 Wendy Martinez,

More information

3. QUALITY ASSURANCE REQUIREMENTS

3. QUALITY ASSURANCE REQUIREMENTS 3. QUALITY ASSURANCE REQUIREMENTS 3.1 General This section covers the Kaipara District Council requirements for monitoring and testing of physical asset construction to ensure that the final asset delivered

More information

Request for Quotation

Request for Quotation City of Richmond Finance & Corporate Services Division Request for Quotation Bidders are requested to respond to this Quotation call as instructed subject to the provisions contained herein. Name of Bidder:

More information

LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION

LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION Le Val LUND 1 And P E M ASCE 2 SUMMARY A number of methods are discussed which can be used for lifeline pipeline rehabilitation and improving the seismic

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding.

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding. Background & Issues To provide guidelines and requirements for Developers, the Community and the Shire s Planning and Sustainability officers for connection to the Shire s Stormwater Drainage Disposal

More information

ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE

ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE CODE OF PRACTICE FOR CITY INFRASTRUCTURE & LAND DEVELOPMENT ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE Issue 4.6 Sept 2008 Section 5 Page 1 SECTION 5.0 WASTEWATER DRAINAGE Note: The adoption

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting

Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting Setting the Industry Standard for the Rehabilitation of Underground Utilities The International Pipe Bursting Association

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

C. Section 014510 TESTING LABORATORY SERVICE.

C. Section 014510 TESTING LABORATORY SERVICE. SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,

More information

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. 1 Pipe Bursting A Mature and Diverse Trenchless Technology December 10, 2014 1:00 3:00 pm Eastern How to Participate Today

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall

More information

SPECIAL CONDITIONS OF CONTRACT

SPECIAL CONDITIONS OF CONTRACT AN SPECIAL CONDITIONS OF CONTRACT May 2013 TABLE OF CONTENTS S1. GENERAL... 2 S1.1 FORM OF CONTRACT... 2 S1.2 CONTINGENCY SUMS... 2 S1.3 STATUTORY REQUIREMENTS... 2 S1.4 GOODS AND SERVICES TAX... 2 S2.

More information

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,

More information

Public Landscape Aids And Protection Of Assets

Public Landscape Aids And Protection Of Assets Territory and Municipal Services Reference Document 4 LANDSCAPE MANAGEMENT AND PROTECTION PLANS (LMPP) Requirements for the Protection of Public Landscape Assets Adjacent to Development Works Issue 2 Revision

More information

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District 1. SCOPE OF WORK This Specification applies to the laying of sewer pipes and all associated appurtenances

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

What is water main cleaning & lining

What is water main cleaning & lining What is water main cleaning & lining The Borough s water distribution system includes cast iron pipe. The program involves cleaning older section of cast iron pipe and lining it with cement mortar. Over

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

Standard terms and conditions

Standard terms and conditions Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled

More information

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair 1. Objective: 1.1. To repair the water connection in a timely and efficient manner, minimizing

More information

Rainwater is directed away from walls at surface. Any water infiltrating is captured in drains below foundation

Rainwater is directed away from walls at surface. Any water infiltrating is captured in drains below foundation Ground Surface Rainwater is directed away from walls at surface. Any water infiltrating is captured in drains below foundation Ground Surface Soil Ground Water Level Basement Wall Groundwater drains to

More information

SA Pipe Relining is dedicated to finding simple, non intrusive

SA Pipe Relining is dedicated to finding simple, non intrusive SA Pipe Relining is dedicated to finding simple, non intrusive solutions to complex problems using latest technologies and methodical work practises in an environmentally friendly and cost effective manner.

More information

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk ALL YOUR NEEDS Tel: 01384 482228 www.midlanddrainage.co.uk Welcome to Midland Drainage Services Midland Drainage Services is a family owned and operated Drainage Company, based in the West Midlands and

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information