The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
|
|
|
- Cody Horton
- 10 years ago
- Views:
Transcription
1 Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section 2. CHECKLIST The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Date Plans Received: Project Status (Circle One) Low Pressure Sewer Initial Review Yes No Date on Plans: Revised Submittal (Submittal No. ) Pump Station Yes No I. Minimum Requirements to Initiate Plan Review A. General YES NO N/A 1. Sewer plans and road plans have been combined and submitted to VDOT and the Authority simultaneously. 2. One complete set of plans was submitted for review, or four complete sets of plans for final approval, stamped, dated, and signed by a registered professional engineer or qualified registered land surveyor. 3. Design calculations were submitted and are stamped, dated, and signed by a registered professional engineer. 4. Original professional engineer seal and signature with date are on the cover sheet/title page of the plans and calculations. 5. Facsimile / reproduction of P.E. seal and signature with date are on subsequent plan sheets. 6. Plans are of adequate size (22" x 34" or 24" x 36"), scale and detail. 7. Prints and copies are legible. 8. The project name and date with latest revisions are clearly noted on the cover of the plans and calculations.
2 Page 2 of 6 9. Name and address of the engineering/surveying firm that prepared the documents are clearly shown on the cover sheet of the plans and calculations. 10. Developer Agreement package has been mailed to owner. 11. Developer Agreement has been signed and returned. 12. Review and inspection fees have been paid. 13. Sewer lines have been sized to correspond to the Authority s Master Plan. 14. For revised submittals, each item from review comments is specifically addressed and acknowledged in a cover letter. B. Plans YES NO N/A 1. Vicinity map on title sheet clearly shows the location of the project. 2. Site plan of the project with topography is provided, or topography is provided on the plan / profile sheets. 3. Plan and profile views are provided for all sections of sewer line. 4. Vertical and horizontal scales are identified. 5. Manhole stationing and sewer slopes are shown. II. Plan Review A. General YES NO N/A 1. Note on plans states that the project shall be constructed in accordance with the Authority s Master Specifications. 2. Only special details (those not covered in Master Specifications) are shown on plans. 3. Profile elevations reference an established elevation datum (USGS State Plane). 4. North arrow is shown in each plan view. 5. Street names or route numbers are noted correctly on plans. 6. All distances, angles, offsets, and elevations are correct and drawn correctly to scale. 7. Descriptions, stations, and appurtenance locations match between the plan and profile views. 8. Direction of stub-outs is shown (i.e., angle right from downstream line, bearing, or angle offset from upstream line). 9. Utility crossings, sewer lines, manholes, manhole tops, etc. are drawn at their correct elevations and stations in the profile.
3 Page 3 of Existing waterlines, valve boxes, fire hydrants, sewer lines, manholes, clean-outs, and other physical appurtenances for water/sewer systems are identified. 11. Concrete encasement is shown in the plan and profile views. 12. Length of concrete encasement is noted. 13. Underground and overhead utilities that may influence construction are identified in the plan and profile views and are drawn at their correct elevations in the profile. 14. Boundaries of marshes, bogs, and wetlands are identified. 15. Flood plain elevations are shown where appropriate. B. Property, Right-of-Ways, Easements, and Survey Control YES NO N/A 1. Adequate easements are provided with the greater of a minimum 20 width, or two times the depth of the pipe, with the pipe centered within the easement. 2. Property, easement, and right-of-way lines are adequately defined throughout the project. 3. Property ownership information is noted. 4. Rods, other right-of-way markers, and any easement information such as fences, telephone/power lines, and utilities have been identified. 5. Benchmarks are set outside of construction area. 6. Property lines match those shown on subdivision plat. 7. Sufficient number of benchmarks are located and described on the plans to provide adequate vertical control during construction (approximately one per plan / profile sheet). C. Manholes YES NO N/A 1. Manhole stations are shown in profile. 2. Match lines are only shown at manholes in profile. 3. Invert elevations and manhole top elevations are shown. 4. Manholes are drawn schematically in profile. 5. Basic manhole information such as angle, station, stub-outs, type of top, and appropriate notes are identified. 6. Manholes are no more than 400 feet apart. 7. The fall across the manholes is at least 0.2 feet and 0.5 feet for a change of flow direction equaling approximately 90 or less. 8. Manholes are set high enough for slopes to be accommodated.
4 Page 4 of 6 9. Drop manholes are used for invert differences equal to or greater than 2.00 feet. 10. Watertight frame and covers are used in areas subject to flooding or surface flow. 11. Stub-outs are shown at manholes suitable for future connections. 12. Manhole tops are buried when located in VDOT right-ofway. 13. Elevations of manhole tops are shown to the nearest 0.1 of a foot. 14. Ventilation requirements are met for line when watertight covers are used. 15. Sewer lines or manholes are not within 10 horizontal feet of existing waterlines, or the pipe materials and manhole types conform to VDH Sewer Regulations for cases with less than 10 feet of separation. D. Sanitary Sewer Line YES NO N/A 1. Pipe materials meet Authority requirements. 2. Gravity sewer is sized no smaller than 8 inches, with the exception of 6 inch sewer with terminal cleanout. 3. Ductile iron pipe and concrete encasement is used when cover does not meet VDH and Authority minimum depth requirement of 36 inches. 4. Ductile iron pipe or AWWA specified material (i.e., SDR 18 PVC) is used when crossing water line. 5. Ductile iron pipe is specified with Protecto 401 or other approved epoxy lining. 6. Ductile iron pipe and concrete encasement are used when crossing under streams. 7. If special circumstances exist that require change in pipe material between manholes, a Harco coupling or equal is used when PVC pipe is connected to D.I. Pipe. Location of couplings is identified in the profile view. 8. Ductile iron pipe and vertical anchors are used if slope of pipe is greater than 20%. 9. Erosion protection is supplied in the sewer line if velocity exceeds maximum limit according to VDH Sewer Regulations. 10. Adequate clearance between the sanitary sewer line and any water or storm sewers is provided (18 inches minimum separation).
5 Page 5 of Existing and proposed utilities that cross sewer line are shown in the plan and profile. 12. Minimum cover requirements for sewer line installation are met and indicated in the profile view. 13. Minimum cover requirements are met when sewer line crosses existing utilities, streams, drainage ditches, etc. 14. Steel casing and SDR 26, C900, or ductile iron pipe with Protecto 401 lining is specified under roadways and restrained. 15. Minimum cover is indicated in the profile view when crossing utilities, streams, drainage ditches, roads, etc. 16. Pipe material is consistent between manholes. 17. All grades are correct. 18. Minimum grade requirements are met for all lines. 19. Sewer lines are at a constant slope between manholes. 20. Minimum slope of 0.4% is met for gravity sewer sizes 8 inches or larger. 21. Minimum slope of 0.5% is met for gravity sewer cleanout lines. 22. Stationing of the utility line is labeled every 500 feet at a minimum in the plan view with short lines drawn perpendicular to the centerline every 100 feet. 23. Stations are set at each structure and angle point in line. 24. Stations run from the lower end toward the upper end of the line. E. Laterals YES NO N/A 1. Existing and proposed lot lines are identified for proper lateral placement. 2. Existing houses, septic tanks, and septic fields needed to determine proper lateral placement have been identified. 3. Size of laterals indicated on plans. 4. Minimum pipe diameter of 4 inches is used for single house service connections, and a minimum pipe diameter of 6 inches is used for double house service connections. 5. Sewer line is deep enough to serve adjacent properties. 6. If sewer line is near a stream, the line is deep enough to serve properties on the other side of stream. 7. Laterals are connected to manholes if possible.
6 Page 6 of 6 8. Drop connections are used when depth of sewer lateral is greater than 8 feet. 9. Service line crossings are minimized and consolidated where possible. F. Calculations YES NO N/A 1. Sufficient data is provided to support pipe sizing for the proposed development and future flows. Calculations conform to VDH Sewer Regulations for peak design flows and minimum line sizes. 2. Calculations indicate a velocity of flow in the sewer lines acceptable according to the VDH Regulations. 3. Upstream needs and future connections are considered in the calculations. 4. Calculations indicate that the existing downstream facilities have adequate capacity to handle the additional flows (peak flows) from the proposed sewer system. Section 1. REVISIONS A. This policy was approved and adopted by the Authority s Executive Director on June 27, 2013, effective July 1, 2013.
SEWER LINE EXTENSION DESIGN CHECKLIST
SEWER LINE EXTENSION DESIGN CHECKLIST SWLE# Utilities Staff Date DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling design plans for
SECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
CITY OF FARMERSVILLE, TEXAS
CITY OF FARMERSVILLE, TEXAS MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES Subdivision Ordinance #2007-08 Exhibit B February 13, 2007 TABLE OF CONTENTS Description Page No. General... 1 Water
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued
SECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS
CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS 6.00 Objective Page 1 6.01 Additional Referenced Standards Page 2 6.02 Special Design Problems Page 2 6.03
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
Chapter 9 Sanitary Sewers
Chapter 9 Sanitary Sewers S:/Engineering/Design Standards/Chapter 9 12/29/2014 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow
CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST
CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST NOTE: The following list shall only be used as a guide and shall not be used in lieu of the specifications found in the CITY OF ANN ARBOR PUBLIC
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African
TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African Regional Office 01 CHAPTER ONE Checklist Page 2 of 8
3A-1---------------------------------General Information A. Concepts... 1 B. Conditions... 1
Statewide Urban Design and Specifications Table of Contents Design Manual Chapter 3 Sanitary Sewers Table of Contents TOC Chapter 3 Sanitary Sewers 3A General Information 3A-1---------------------------------General
SITE IMPROVEMENT PLANS CHECKLIST
REVIEW SERVICES TEAM SITE IMPROVEMENT PLANS CHECKLIST (Also for SITE DEVELOPMENT PERMIT applications) GENERAL REQUIREMENTS This checklist applies to commercial building site work involving engineering,
City of Lubbock Public Works Engineering Design Standards and Specifications
City of Lubbock Public Works Engineering Design Standards and Specifications Department of Public Works Engineering City of Lubbock, Texas January 1, 2012 These Standards and Specifications are general
PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
Guidelines for Fiber Optic Cable Permits
Guidelines for Fiber Optic Cable Permits NOVA District (Fairfax/Arlington) Permits www.virginiadot.org/business/fairfax-permits-main.asp Email: [email protected] 14685 Avion Parkway
SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN
S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain
Standards for Water, Sewer, and Sewage Lift Station Design
Standards for Water, Sewer, and Sewage Lift Station Design February 2015 Edition I. Plan Format Requirements General Requirements Water Line Requirements Sewer Line Requirements II. III. IV. Water Design
CITY OF TUCSON, WATER DEPARTMENT DESIGN STANDARD NO. 8-07 WATER PLAN DRAFTING STANDARDS TABLE OF CONTENTS
TABLE OF CONTENTS 8-07.0.0... 3 8-07.1.0 GENERAL... 3 1.1 Purpose... 3 1.2 Definitions... 3 1.3 Applicability... 3 8-07.2.0 CONTENT REQUIREMENTS, WATER PLAN SHEETS... 3 2.1 Content Requirements, All Plan
STAFFORD COUNTY DEPARTMENT OF UTILITIES WATER AND SEWER
STAFFORD COUNTY DEPARTMENT OF UTILITIES WATER AND SEWER DESIGN AND CONSTRUCTION STANDARDS March 2006 DEPARTMENT OF UTILITIES WATER AND SEWER DESIGN AND CONSTRUCTION STANDARDS ISSUE DATE: March 10, 2006
MANUAL FOR THE DESIGN OF WATER AND SEWER LINES
SECTION I: GENERAL PROVISIONS 1.01 This manual is intended to aid and assist engineers in the layout and design of sanitary sewers and water lines to definite standards and to obtain uniformity in the
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
SECTION 221413 FACILITY STORM DRAINAGE PIPING
SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
CHAPTER 11 STORM DRAINAGE
CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,
ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS
ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
Close-Out Documents... 9
Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
SERVICES THAT MAY ONLY BE PERFORMED BY A NEW JERSEY PROFESSIONAL LAND SURVEYOR
SERVICES THAT MAY ONLY BE PERFORMED BY A NEW JERSEY PROFESSIONAL LAND SURVEYOR 1. ANY MAP OR PLAN THAT SHOWS: Property Lines. NJSA 45:8-28(e), NJAC 13:40-1.3, 13:40-5.1 Locations of Existing Buildings
Minimum Design Criteria for the permitting of Gravity Sewers
Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document
Exhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
Emerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM
CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM SECTION 3.1 INTRODUCTION... 1 (a) Objectives...1 (b) Applicability...1 (c) Drafting
CHAPTER 5. Storm Sewer
CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
CITY OF COLTON PUBLIC WORKS/ENGINEERING DEPARTMENT STORM DRAIN PLAN REVIEW CHECKLIST (PROVIDE SEPARATE ON-SITE & OFF-SITE STORM DRAIN PLAN SETS)
CITY OF COLTON PUBLIC WORKS/ENGINEERING DEPARTMENT STORM DRAIN PLAN REVIEW LIST (PROVIDE SEPARATE ON-SITE & OFF-SITE STORM DRAIN PLAN SETS) PROJECT NAME: TRACT, PARCEL MAP OR PROJECT ID NO. PLAN ED BY:
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
Specifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
SECTION 3 SANITARY SEWER DESIGN AND CONSTRUCTION REQUIREMENTS
SECTION 3 SANITARY SEWER DESIGN AND CONSTRUCTION REQUIREMENTS Page 3-1 INTRODUCTION 3-3 3-2 GRAVITY SEWER 3-2.01 Location 3-4 3-2.02 Easements 3-4 3-2.03 Capacity 3-5 3-2.04 Slope 3-6 3-2.05 Design Flows
SECTION 7- STORM SEWER
SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...
City of La Quinta Public Works Department - Storm Drain Plan Review Checklist
Tract or Parcel Project Name PCN Checked By Date City of La Quinta Public Works Department - Storm Drain Plan Review Checklist SUBMITTAL REQUIREMENTS Approved Tentative Tract Map Conditions of Approval
CHAPTER 11 STORM DRAINAGE
CHAPTER STORM DRAINAGE SECTION PC 0 GENERAL 0. Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. Storm water discharge shall be
September 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM
1.0 General Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM a) It is the intent of this specification to ensure that all gravity sewer system infrastructure constructed within the service
CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
Requirements for Building Application Submission
THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: [email protected] To: Architects, Designers
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER. GENERAL SURVEY INSTRUCTIONS EASEMENTS Authority 11 AAC 53
STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER GENERAL SURVEY INSTRUCTIONS EASEMENTS Authority 11 AAC 53 These instructions define the survey and platting criteria unique
Let Us Give Utilities the Respect that they Deserve.
Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous
DESIGN STANDARDS MANUAL
DEPARTMENT OF PUBLIC UTILITIES CITY OF VIRGINIA BEACH, VA DESIGN STANDARDS MANUAL Revised Table of Contents Table of Contents 1 Introduction... 1-1 1.1 Authority... 1-1 1.2 Revisions... 1-1 1.3 Organization
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
OAR52 A-1 (September, 1981)
APPENDIX A SEWER PIPELINES (1) MINIMUM REQUIREMENTS FOR SEWER - PIPELINES (a) Capacity: Sewers shall be of such diameter as to pass without overflow, bypass, or back flow onto damageable property of a
Sewage Compliance Form Instructions
CITY OF JOHNSTOWN DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT 401 MAIN STREET ROOM 200 JOHNSTOWN, PA 15901 814-533-2017 FAX 814-539-5816 RENEE K. DALY DIRECTOR Sewage Compliance Form Instructions 1)
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE
1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872
City of Edmonton Page 1 of 5 Foundation Drain Discharge Collection System Guideline November, 2005
City of Edmonton Page 1 of 5 This guideline will apply to all new developments involving singledetached, semi-detached or duplex houses in the City of Edmonton effective January 1, 2006. Preamble: This
CLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
DESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
City of Houston Department of Public Works and Engineering INFRASTRUCTURE DESIGN MANUAL JULY 2009 TABLE OF CONTENTS
City of Houston Department of Public Works and Engineering INFRASTRUCTURE JULY 2009 TABLE OF CONTENTS Chapter No. of Pages 1 General Requirements...8 2 Survey Requirements...8 3 Graphic Requirements...13
STORM DRAINS CHAPTER 7
CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
Sanitary Sewer Overflow (SSO) Incident Report Form
Submit completed form to EHS. Date of SSO spill: Sanitary Sewer Overflow (SSO) Incident Report Form Identify the SSO category (check one): Category 1 SSO Spills of any volume that reach surface water Category
Washington City Subdivision Development Application Checklist 435-656-6325
Application Checklist 1 Washington City Subdivision Development Application Checklist 435-656-6325 1) Wednesday Staff and Developer Meeting. *Call to schedule an appointment. A. Statement of project intent
CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
Elev. A = 200.05, Elev. B = 325.25, horizontal distance = 1625 feet a. 7.7 b..077 c. 12.98 d. 1.28
1. If the percent grade is 7.25 % and the horizontal length of grade is 1625 feet, what is the change in elevation? a. 117.81 feet b. 1178.13 feet c. 11.78 feet d. 1.17 feet 2. In surveying, the distance
Special Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
SECTION 8 WATER SUPPLY SYSTEMS
SECTION 8 WATER SUPPLY SYSTEMS Contents Page 8-1 INTRODUCTION... 1 8-2 INTENT OF WATER SYSTEM IMPROVEMENT STANDARDS... 1 8-3 DEFINITIONS... 1 8-4 APPLICABLE STANDARDS... 1 8-5 IMPROVEMENT AND LANDSCAPE
SECTION 7 UNDERDRAIN SERVICE
SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations
Engineering Specifications February, 2004 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18
Schedule H to Bylaw 7452, Subdivision Bylaw Page 18 3.4 Sanitary Sewers 3.4.1 Materials 3.4.1.1 The class and type of pipe and fittings, together with required class of bedding and trench widths, shall
SECTION 15410 GROUND WATER STORAGE TANKS
SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design
Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way)
Flood Control District of Maricopa County (District) 2801 W. Durango Street Phoenix, AZ 85009 Telephone: 602-506-4583 or 602-506-5476 Fax: 602-506-1663 Right-of-Way Permit Application Process (Plans that
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY
MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
505.3.6 For a building with a crawl space, see Figure 10. 505-1
505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the
Standard Specifications For Private Sewer Laterals
BUILDING SERVICES DEPARTMENT 250 Frank H. Ogawa Plaza, 2nd Floor, Oakland, CA 94612 Inspection Services: 510.238.3443 FAX: 510.238.2263 Standard Specifications For Private Sewer Laterals APPROVED MATERIALS
Town of Beaumont. Lot Grading Guidelines
Town of Beaumont Lot Grading Guidelines LOT GRADING APPROVAL PROCESS Lot Grading Guidelines... 3 Introduction... 3 Purpose... 3 Definitions... 3 Lot Grading... 3 Lot Grading Plan... 3 Lot Grading Certificate...