February 4, 2016. Estimate



Similar documents
Delaney-Vogel School

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

KIEWIT CM/GC Enabling/Utilities

Insured: John Smith Home: (555) Property: 1234 Avenue D Wapakoneta, OH 45895

CERVANTES COMMUNITY CENTER RE-ROOFING NEW MEXICO STATE UNIVERSITY

Roof Repair Project Report. Fairbank Complex 40 Fairbank Road Sudbury, Massachusetts. February 14, RBA Project No

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

Exterior Repair Project. By: Kami Farahmandpour, PE, RRC, RWC, CCS, CCCA Alex Szatanek. Building Technology Consultants, PC BTC

Estimated Cost of Repair

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Smooth cap sheet SQ $ Smooth cap sheet SQ $ Smooth cap sheet SQ $ Smooth cap sheet SQ $ 36.

Clear Fork Valley Local School District. Roofing Repairs Spring/Summer 2015

HOW TO ESTIMATE THE COST OF A HIGH SCHOOL LABORATORY AT CONCEPTUAL LEVEL

Repair Project for April 7, 2009

A0 SHEET 1 OF LOCUST STREET FRANKFORT, KANSAS FRANKFORT, KANSAS ROOF REPAIR OF THE 400 LOCUST STREET

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

INDIAN HEAD ELEMENTARY SCHOOL

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Building Condition Assessment Report

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

Article 11. Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools

FY08 SEWER POINT REPAIRS BID TABULATION

ELIGIBLE REPAIR PROJECT PARAMETERS

SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D

October 5, 2015 Dear Client,

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

BUNKER HILL ELEMENTARY SCHOOL

Veterans Memorial Coliseum Options Study Appendix A - Deconstruction Scope of Work and Cost Estimate August 31, 2015

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

Outline. Owner Perspective CM Definition Working Relationships Why CM? Project Approach Pre-construction Construction. Iowa League of Cities // 2011

PROPERTY INSPECTION OR ASSESSMENT OF DAMAGES

Asbestos Procedures. Asbestos Products

Hartsfield-Jackson Atlanta International Airport s

Vision Home Inspection

Program Demand Cost Model for Alaskan Schools

Georgia State University. Urban Life Building Roof Replacement

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5

Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study

Western Avenue South Small Business Based on Small Business Improvement Fund (SBIF) Grant Agreements

ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K Commerce Road Renovations Project DATED: February 9, 2015

CHAPTER VII. TITLE: STANDARDS FOR NEW ROOFING July 2015 CONSTRUCTION, RE-ROOFING CONSTRUCTION AND ROOFING SYSTEM GUARANTEE REQUIREMENTS

Memorandum. July 16, To: Plan Commission City of Madison

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

*Aggregate Material Index of the 9 most commonly used building materials Residential

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM Paul Revere School Modernization and Interim Housing ADDENDUM NO.

TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT

REPLACE ROOFING DENVER CENTRAL LIBRARY PHASE I CITY & COUNTY OF DENVER DENVER, COLORADO

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

HEANEY General Contracting, Inc.

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

Lindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Accurate Home Inspection of Illinois. Property Inspection Report For Steve & Jenny Hynek 210 W.Chicago Ave., Westmont, Illinois

Cost Estimating Simplified

NOTICE TO CONTRACTORS

Inspecting to a higher standard.

Estimator: Miami Estimates Business: (305) Date Entered: 04/30/2008

Crescent Valley High School Roof Investigation

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

TruexCullins Architecture Fairfield Center School Bid Documents Kitchen and Bathroom Renovation March 1, 2015

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No December 2014

Bid Package #:

Assessment Report for Windmill Rehabilitation Project. Anne Curren, Town Clerk Town of North Castle 15 Bedford Road Armonk, New York 10504

Estimating Database Checklist

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

CLAIMS BULLETIN. Information Technology Solutions. CLAIMS DATA UPDATE BULLETIN-CADS 1 st Quarter 2015 Symbility Mobile Claims

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

19 Ellis Park Road, Toronto

REBUILDING WOOD TRUSSES WITH STEEL. Despite a major renovation

** PROPRIETARY ** SAMPLE COUNTY DATA CENTER PROJECT BUDGET ** PROPRIETARY **

SECTION EXISTING HAZARDOUS MATERIALS CONDITIONS

ESTIMATING PLUMBING, HEATING, VENTILATING, AND AIR CONDITIONING (HVAC), AND ELECTRICAL WORK

Structural Assessment Report

FEASIBILITY STUDY COST PLAN. for. Fresno Library Feasibility Study Fresno, California

Property Condition Assessment

ESTIMATE ORIG. ESTIMATE: TOTAL: $204,249 DATE: 01/15/08 DESCRIPTION OF WORK QUANTITY DIVISION TOTAL

Water Damage & Repair

DRAPER ELEMENTARY SCHOOL

Dollars & Sense of Compliance!

I NI NP R Inspected Items

Executive Summary. June 2005 Auke Bay Elementary School Condition Survey Report Page 4 of 228

Home Inspection Report

Commission Districts Affected Facilities and Transportation Services Department

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets

How To Bid On A Building Project In San Jose

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client

TARRANT COUNTY DETAIL STANDARDS

Building Condition Assessment Report

Construction Technologies Career Field Pathways and Course Structure

PLAN SUBMITTAL INFORMATION

Total Home Inspection Checklist

Water Management & Damage Prevention:

Transcription:

Wrentham, MA February 4, 2016 Architect: Turowski2 Architecture, Inc. P.O. Box 1290 313 Wareham Road Marion, MA 02738 (508) 758-9777 Cost Estimator: Miyakoda Consulting 300 Black Mallard Road Bridgewater, MA 02324 (617) 799-5832

Wrentham, MA INTRODUCTION Project Description: 1 The project consists of roof replacement to Delaney-Vogel Elementary School 2 Replace existing asphalt roof shingles and EPDM Project Particulars: 3 is based on drawings dated January 20, 2016 from Turowski2 Architecture 4 Detailed quantity takeoff from these documents where possible 5 Experience with similar projects of this nature 6 Unit rates using recent bid results Project Assumptions: 7 The project will be publicly bid to Roofing Contractors under Chapter 149 8 Our costs assume that there will be at least three subcontractors submitting unrestricted bids in only painting sub trade 9 The Total Construction Cost reflects the fair construction value of this project in a competitive bidding market 10 Unit rates are based on current dollars 11 An allowance for escalation to start of construction at a rate of 5% per year has been carried in the Main Summary. Start of construction has been carried as June 2016 13 General Conditions and Requirements value covers Sub-Contractor's bond, site office overheads, and building permit applications 14 Overhead and profit markup is calculated on a percentage basis of direct construction costs. The value covers Contractor's bond, insurance and profit 15 Design and Pricing Contingency markup does not include allowance for unforeseen design issues, design detail development and specification clarifications. THIS IS NOT A CONSTRUCTION CONTINGENCY (FOR CHANGE ORDERS) Exclusions: 16 Design fees and other soft costs 17 Interest expense 18 Owner's project administration 19 Construction of temporary facilities 20 Relocation expenses 21 Printing and advertising 22 Site or existing condition surveys and investigations 23 Utility company back charges 24 Police details and street/sidewalk permits 25 Work beyond the boundary of the site 26 Testing & commissioning 27 Hazardous Waste Abatement 28 Repointing to existing Introduction Page 2 of 5

7 ELEMENT QUANTITY UNIT UNIT RATE TOTAL 8 02 06 00 Selective Site Demolition and Removals 9 Remove existing roof system: 10 Low slope roof type #1 including insulation 21,606 SF $2.00 $43,212 11 Low slope roof type #2 including insulation 3,130 SF $2.00 $6,260 12 Medium slope roof type #3 insulation to remain 6,023 SF $1.75 $10,540 13 Medium slope roof type #4 no insulation 21,619 SF $1.75 $37,833 14 Remove existing wood framed window & louver (21' L x 5'0" H) 1 LOC $1,190.00 $1,190 15 Note 3: Remove existing HVAC equipment 28 EA $35.00 $980 16 Note 3: Remove existing HVAC equipment (larger) 6 EA $500.00 $3,000 17 Note 4: Remove roof drains 7 EA $35.00 $245 18 Allow for cutting and patching 1 LS $5,000.00 $5,000 19 02 06 00 Selective Site Demolition and Removals Subtotal $108,261 20 21 04 10 00 Masonry (Filed Sub Bids Not Required) 22 Allow for chimney repairs 1 LS $15,000.00 $15,000 23 Flashing 260 LF $200.00 $52,000 24 Repointing at existing chimney 1,500 SF $15.00 $22,500 25 Allow for scaffolding 1 LS $7,500.00 $7,500 26 04 10 00 Masonry (Filed Sub Bids Not Required) Subtotal $97,000 27 28 06 10 00 Carpentry 29 Perimeter blocking 3,287 LF $5.00 $16,435 30 Blocking at new window wall 62 LF $6.50 $403 31 Allow for rough carpentry 41 LOC $100.00 $4,100 32 06 10 00 Carpentry Subtotal $20,938 33 34 07 20 00 Insulation 35 Insulation included with roofing $0 36 07 20 00 Insulation Subtotal $0 37 MSBA Accelerated Projects 2015 38 07 50 00 Roofing (Filed Sub Bids Required) 39 Ridge at roof type #3 54 LF $9.00 $486 40 Ridge at roof type #4 113 LF $9.00 $1,017 41 Replace asphalt shingles 27,642 SF $8.00 $221,136 42 Type 1: New PVC roofing and tapered insulation 21,606 SF $17.00 $367,302 43 Type 2: New PVC roofing 3,130 SF $15.00 $46,950 44 Ice and water shield 4,086 SF $0.50 $2,043 45 Replace pipe boots 27 EA $35.00 $945 46 Flashing 2,858 LF $15.00 $42,870 47 New roof drains 4 LOC $350.00 $1,400 48 Connection to new roof drains 4 LOC $75.00 $300 49 Allow for step flashing as required; premium 1 LS $5,000.00 $5,000 50 07 50 00 Roofing (Filed Sub Bids Required) Subtotal $689,449 Page 3 of 5

51 52 07 72 00 Roof Accessoriea 53 Roof hatch 1 EA $3,500.00 $3,500 54 Ladder 1 EA $1,500.00 $1,500 55 07 72 00 Roof Accessoriea Subtotal $5,000 56 57 07 92 00 Joint Sealants (Filed Sub Bids Not Required) 58 Allow for joint sealant 1 LS $7,500.00 $7,500 59 07 92 00 Joint Sealants (Filed Sub Bids Not Required) Subtotal $7,500 60 61 08 50 00 Window 62 Window frame replacement 1 EA $3,150.00 $3,150 63 08 50 00 Window Subtotal $3,150 64 65 08 80 00 Glazing 66 Window replacement 105 SF $60.00 $6,300 67 08 80 00 Glazing Subtotal $6,300 68 69 08 90 00 Louvers 70 Louver 1 EA $1,050.00 $1,050 71 08 90 00 Louvers Subtotal $1,050 72 73 22 00 00 Plumbing (Filed Sub Bids Not Required) 74 P1: Remove the exist roof drain strainer, flashing collar & bolts 7 EA $75.00 $525 75 P2: Extend 2" cast iron VTR to min. 24" above proposed roof elev. 1 EA $130.00 $130 76 P3: Extend 3" cast iron VTR to min. 24" above proposed roof elev. 3 EA $132.00 $396 77 P4: Extend 4" cast iron VTR to min. 24" above proposed roof elev. 19 EA $134.00 $2,546 78 P5: Remove & dispose of exist. scupper type roof drain 1 EA $35.00 $35 79 P6: Extend 6" PVC VTR to min. 24" above proposed roof elev. 3 EA $136.00 $408 80 New roof drains at existing locations 7 EA $250.00 $1,750 81 New roof drain 1 EA $500.00 $500 82 Cast iron piping 10 LF $65.00 $650 83 Insulation to horizontoal piping above floor 1 LS $750.00 $750 84 New scupper drain 1 EA $600.00 $600 85 Miscellaneous plumbing allowance 1 LS $1,800.00 $1,800 86 Permits Included 87 22 00 00 Plumbing (Filed Sub Bids Not Required) Subtotal $10,090 88 89 23 00 00 HVAC Subtotal (Filed Sub Bids Not Required) 90 K-1 Remove centrifical roof mtd exhaust fan 19 EA $500.00 $9,500 91 K-2 Remove air cooled condensing unit 4 EA $1,000.00 $4,000 92 New attic ventilation, louver and new exhaust fan 1 LS $5,000.00 $5,000 93 Reinstall roof mtd exhaust fans 19 EA $1,000.00 $19,000 94 Reinstall air cooled condensing unit 4 EA $1,800.00 $7,200 95 Miscellaneous HVAC allowance 1 LS $10,000.00 $10,000 96 23 00 00 HVAC Subtotal (Filed Sub Bids Not Required) Subtotal $54,700 Page 4 of 5

97 98 26 00 00 Electrical (Filed Sub Bids Not Required) 99 Reconnect exhaust fans 19 EA $350.00 $6,650 100 Reconnect air cooled condensing units 4 EA $1,000.00 $4,000 Miscellaneous electrical items 1 LS $3,500.00 $3,500 102 26 00 00 Electrical (Filed Sub Bids Not Required) Subtotal $14,150 103 104 32 12 16 Asphalt Paving 105 Patch existing asphalt paving 47 SF $25.00 $1,175 106 Sawcut existing bit conc walkway 19 LF $15.00 $285 107 32 12 16 Asphalt Paving Subtotal $1,460 108 109 33 41 00 Storm Utility Drainage Piping 110 Subsurface Infiltration Chambers 1350 CF 1,350 CF $42.00 $56,700 111 6"PVC Pipe 9 LF $60.00 $540 112 4"PVC Pipe 7 LF $55.00 $385 113 Trenching and backfill 16 LF $35.00 $560 114 Connect to existing downspout 1 EA $50.00 $50 115 Subsurface Infiltration Chambers 740 CF 740 CF $72.00 $53,280 116 Trenching and backfill Subtotal $111,515 117 118 Subtotal $1,130,563 119 120 Design Contingency 10.00% $1,130,563 $113,056 121 122 Subtotal $1,243,619 123 124 General Conditions and Requirements 3 MONTHS $30,000 $90,000 125 Insurance 1.10% $1,333,619 $14,670 126 GC Bonds 0.65% $1,348,289 $8,764 127 Permits 1.50% $1,357,053 $20,356 128 Fee 3.00% $1,377,409 $41,322 129 Escalation to June 2016 2.50% $1,418,731 $35,468 130 131 TOTAL $1,454,199 132 133 Deduct Alternate #1: No Reroof to Type #1 Roof -$389,000 134 Deduct Alternate #2: No Reroof to Type #2 Roof -$50,000 135 Deduct Alternate #3: No Window Replacement at South Wall -$11,000 136 137 Page 5 of 5