Q140 Cluster Addendum



Similar documents
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generator Interconnection and Deliverability Study Methodology Technical Paper

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

6. The estimated costs here do not include any applicable ITCC tax

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION FEASIBILITY STUDY FOR PROPOSED XXXXXXXX GENERATION ON THE SIERRA BLANCA-FARMER 69 KV LINE

TERMS AND CONDITIONS

GIP Net Zero Interconnection Service.

ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Effective: September 10, 2006 Vermont Attachment 1 to Rule Public Service Board Page 1 of 6

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

Rule Fast Track Analysis for National Life Insurance Co.

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW

Planning for Arizona s Energy Future

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

How To Operate The Williston Uvls

When this standard has received ballot approval, the text boxes will be moved to the Guidelines and Technical Basis section of the Standard.

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

A Tariff for Reactive Power Christopher Tufon, Alan Isemonger, Brendan Kirby, Senior Member, John Kueck, Senior Member, and Fangxing Li, Senior Member

Guidelines for Large Photovoltaic System Integration

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Overview. Rooftop Solar Challenge SunShot Initiative U.S. DOE. Larry Krom L & S Technical Associates, Inc. LK@LSTechnical.com

GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software

Load Dispatcher (Class Code 5223) Task List

STATCOM Application at VELCO Essex Substation

BPA Network Open Season 2013 Cluster Study

AAPG 2011 Annual Convention & Exhibition April 10, 2011

SCE Experience with PV Integration

Physical Address: City: State: Zip Code:

16 West Coast Regional Plan

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines

Midwest Reliability Organization Procedure For NERC PRC-012

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River

Introduction to The Trans Bay Cable Project

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ) Reliability Technical Conference ) Docket No.

Solar Power Plant Design and Interconnection

OPTIMAL DISPATCH OF POWER GENERATION SOFTWARE PACKAGE USING MATLAB

Distributed Generation Interconnection Collaborative (DGIC) September 24, 2014

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION

Chester Group Solar Farm Panel Purchase and License Quote

Transmission Related Station Power Use at Substations

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

From: Jean Hicks [ ] Sent: May 4, :55 AM To: SiteC Review / Examen SiteC [CEAA] Subject: Public Submission

Before the New Hampshire Public Utilities Commission DE Public Service Company of New Hampshire d/b/a Eversource Energy. Motion to Intervene

Chapter 7 - Appendix A

Actual capital expenditure during the current regulatory period. Project summary

Applicability and Eligibility

This document should be reviewed at least every two years.

Hyperlinks are Inactive

Houston Region Import Capacity Project

Chapter 3 AUTOMATIC VOLTAGE CONTROL

Integrating Renewable Electricity on the Grid. A Report by the APS Panel on Public Affairs

TRANSMISSION AND SUBSTATION PROJECTS

What is the Impact of Utility Demand Charges on a DCFC Host?

Topics. HVDC Fundamentals

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Emergency Response Solution- Keyspan

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

Distributed Generation: Feeder Hosting Capacity. Dean E. Philips, P.E. FirstEnergy Service Corp Manager, Distribution Planning & Protection

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Integration of Renewable Resources

GREENSTONE-MARATHON Integrated Regional Resource Plan

Eagle Mountain Pumped Storage Project No Final License Application Volume 6 of 6. Exhibit G Project Boundary PUBLIC. Palm Desert, California

D.3 South Minneapolis Electric Distribution Delivery System Long-Term Study

LAB1 INTRODUCTION TO PSS/E EE 461 Power Systems Colorado State University

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Northport - Norwalk Harbor Cable (NNC) Tie line

Summary of CIP Version 5 Standards

Rocky Mountain Power Transmission Five Year Study Findings Meeting

Welcome to the SDG&E Renewable Market Adjusting Tariff (Re-MAT) Program Overview Webinar

Bill is the author of 15 papers and lectures on transmission lines and other power system topics.

About Southern California Edison

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

Generation and Transmission Interconnection Process

Operating Security Standards

Jemena Electricity Networks (Vic) Ltd

Distributed Generation: Frequently Asked Questions

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

Item 8: Houston Import RPG Project

Transcription:

Cluster Addendum 1. INTRODUCTION This Interconnection Customer (IC), submitted a Small Generator Interconnection Request (IR) to Arizona Public Service Company (APS) for their proposed project, located south of the Papago Freeway at 33⁰30'29.13"N 113⁰02'10.50"W in Maricopa County, Arizona (approximately 7 miles west of Tonopah, Arizona). The Interconnection Customer (IC) requested Energy Resource Interconnection Service (ERIS), and plans to install 20 MW of photovoltaic solar generation with a requested In-Service Date of October 31, 2012. The project s requested Point of Interconnection (POI) is the Harquahala Tap - Tonopah 69 kv line. The project is Queue Position 140 () in the APS FERC generation interconnection queue. On August 23, 2010, Arizona Public Service Company (APS) filed a request for a one-time waiver of the current study order of Interconnection Requests (IR) to allow a cluster study based in the Gila Bend area. This geographically targeted one-time waiver request of APS current interconnection queue procedure was changed to: 1) allow APS to study all SGIP and LGIP projects submitted in the Gila Bend area in first and second quarter of 2010 as a single cluster, 2) the clustered IRs will share the cost of common upgrades on a pro-rata basis, 3) each project subject to the cluster was given a one-time opportunity to opt out of the cluster, and 4) APS will evaluate projects outside of the cluster as if the clustering never occurred. On September 29, 2010, the Federal Energy Regulatory Commission (FERC) granted this waiver. is one of the projects in the cluster. General cluster results are captured in the general cluster SIS report. This addendum addresses project specific details and results. The Interconnection Customer has chosen to interconnect as an ERIS. Therefore, delivery of the output beyond the POI would be on an as-available basis only. The delivery of the output would be subject to the firm or non-firm transmission capacity that may be available when a transmission service request is made. Nothing in this report constitutes an offer of transmission service or confers upon the Interconnection Customer, any right to receive transmission service. APS may not have the Available Transfer Capability (ATC) to support the Transmission Service for the interconnection described in this report. It should also be noted that the results in this SIS are dependent upon the assumed topology and timing of new projects in the Gila Bend area, which are subject to change. The APS transmission and sub-transmission systems are continuously being evaluated. The planned reinforcements and their in-service dates are often revised depending upon local area load forecasts. A summary of the Interconnection costs and schedule estimates are shown below in Tables 1.1 and 1.2. Page 1 of 11

Table 1.1: Summary of Interconnection Cost and Schedule Estimates Facility 1st Position 2nd Position Costs Timeline Costs Timeline Local Network Upgrades (LNUs) $1,725,000 12 Months $135,000 10 Months Transmission Provider's Interconnection Facilities $141,000 12 Months $141,000 8 Months Total $1,866,000 12 Months $276,000 10 Months Table 1.2: Pro-Rata Share of System Network Upgrade Costs and Schedule Estimate Facility Costs Timeline Pro-Rata Share of System Network Upgrades (SNUs) $7,656,561 43-49 Months Total $7,656,561 43-49 Months There are two different costs shown in Table 1.1 above. Since is sharing the POI with Q154, the cost to interconnect will depend on the order the projects move forward and are constructed. The first project to interconnect will correspond to the 1 st position, and the second project to interconnect will correspond to the 2 nd position. The interconnection costs shown in Table 1.1 above are specifically to interconnect into the APS transmission system. The System Network Upgrades (SNUs), as described in the main report, are shown in Table 1.2 above. The total cost to interconnect into the APS system is $9,522,561 for the 1 st position, and $7,932,561 for the 2 nd position. The total estimated completion time for interconnecting the project is 43 49 Months no matter what position it is interconnected, due to the construction of the SNUs. The actual start of construction would occur when the IC provides written authorization to proceed, provided all interconnection studies are complete, and agreements and funding arrangements are in place. Therefore, the requested In-Service Date of October 31, 2012 cannot be met. will be given the first available In-Service Date once the Interconnection Agreement has been signed, which will be based on the Network Upgrades required at that time. Figure 1.2 below shows a general depiction of the 69 kv system around s proposed POI. The other Cluster projects are not shown, however higher queued projects are shown, as well as any non-ferc 12 kv projects. Page 2 of 11

Figure 1.2: Project Location and 69 kv System Harquahala 20 POI#6 Tonopah BK4 To Buckeye Wintersburg Saddle Mountain 15 #4 To Wintersburg Tap Horn 13.5 Q84 #1 Aztec 17 Q85 20 Hyder 9.4 Q64 County Line To Gila Bend Note: The numbers within the circles represent MW values. # 69kV bus 69kV line 69kV breaker New 69 kv ring bus Cluster generator Non-cluster generator Non-FERC 12 kv projects 2. RESULTS The Cluster report details the overall results. Individual project results will only be noted in the project specific appendix if something is deemed confidential from the remainder of the Cluster or if it specifically affects the project or project model. All other results are included in the main Cluster report. Thermal: The 69/34.5 kv transformer showed N-0 loading levels of 100-101% in all light load cases, and N-0 loading levels of ~100% in the 2013 heavy summer cases. Transient Stability: The project models appeared unaffected by the localized undamped response of the three N-1 contingencies mentioned in the main report. Sample Transient Plots for two contingencies are shown on the following pages. They reflect a 2013 LL case. The first plot (N-1 POIBUS6 - BUCKEYE 69 kv) represents the undamped behavior noted in the main report, prior to mitigation with a dynamic reactive device. The second plot (N-1 SADDLE MTN- HARQAHALA TAP 69 kv) shows a more typical response. Page 3 of 11

N-1 Contingency: POIBUS_6 - Buckeye 69 kv Page 4 of 11

N-1 Contingency: Saddle Mountain - Harquahala Tap 69 kv Page 5 of 11

3. PROJECT MODELING All projects were assumed to be generating at maximum output. Projects consisted of an equivalent generator, equivalent inverter transformer, station transformer, and gen-tie. Individual project collector systems were not modeled. New switching stations were modeled, bisecting existing lines, based on interconnection requirements and locations. Some projects required additional shunt devices to provide the full +/- 0.95 pf at the POI. APS allows the project's reactive support to be made up of dynamic VAr and switched static VAr devices. The reactive devices used to achieve +/- 0.95 power factor as measured at the generator terminal must be dynamic. Any additional reactive support required to compensate for losses between the generator terminals and the POI may be made up of switched static reactive devices and/or any additional reactive capability of the generator beyond 0.95 power factor. has selected the AE Solaron 500-1000V inverters (500 kw). Based on the PQ Diagram provided, the inverter is not able to provide +/- 0.95 pf at the generator terminals for all MW output levels. The dynamic reactive power requirement is based upon the +/- 0.95 power factor requirement and is calculated as follows: In order to meet the dynamic reactive power requirements for the project, elected to install additional inverters to the project, installing a total of forty-two (42) 500 kw inverters, providing 21 MVA. With the additional inverters, the project provides +/- 0.952 pf at Pmax. APS accepted this approximation of the +/- 0.95 pf requirement. (Note: The generator output is still limited to 20 MW.) The additional reactive power requirement to provide +/- 0.95 pf at the POI may be provided by static reactive support. needs to install a 3.7 MVAr shunt capacitor at the 34.5 kv bus, or equivalent. Page 6 of 11

Major components of the equivalent project model include: Gen-tie: 0.1 mile 3/0 ACSR Station Transformer: 1 x 20 MVA, 69/34.5 kv transformer Inverter Transformer: 1 x 21 MVA, 34.5/0.48 kv transformer Generator: 20 MW, equivalent of forty (40) 500 kva AE Solaron inverters, +/- 0.95 pf capability (pf provided by additional inverters) Shunt capacitor: 3.7 MVAr shunt capacitor at 34.5 kva bus to compensate for project losses and achieve +/- 0.95 pf at the POI 1. Figure 3.1: Project Model and POI Harquahala Tap 69 kv New POI BUS Tonopah 69 kv POI 69 kv 34.5 kv 0.48 kv Gen-tie 0.1 miles 3/0 ACSR 20 MVA Z= 8% on 12 MVA X/R= 30 10 x 2 MVA Z= 5.75% on 2 MVA X/R= 7.2 AND 1 x 1 MVA Z= 5.75% on 1 MVA X/R= 7.2 20 MW 1 This value was calculated to meet the minimum power factor requirements, based upon the project model provided. Page 7 of 11

4. TRANSIENT STABILITY MODELING The trip times were updated based on the Extended Ride-Through Option provided in the AE Solaron documentation. Those values are shown in the table below in red. solaron.p Rev 1 10/29/10 PSLF Modeling Rev 1B, 3/3/11 Default PSLF Modeling Rev 1B, 3/3/11 Ext Ride-Through Model 500-1000V rsrc 0 0 0 xsrc 0 0 0 Vratio 1.2 1.2 1.2 Iratio 1.1 1.1 1.1 Tdc 0.003 0.003 0.003 Kpdc 1.8 1.8 1.8 Kidc 22.5 22.5 22.5 Kpq 0.4 0.4 0.4 Kiq 25 25 25 Ilim From Table From Table 1.12 OV1L 1.2 1.2 1.2 OV1T 0.02 0.2 0.2 OV2L 1.1 1.1 1.1 OV2T 2.5 2.5 2.5 UV1L 0.5 0.5 0.5 UV1T 0.02 1.1 1.1 UV2L 0.88 0.88 0.88 UV2T 5 5 5 OFL 60.5 62.5 62.5 OFT 0.02 2 2.0 UFL 57 57 57 UFT 0.02 2 2.0 Page 8 of 11

5. COST AND CONSTRUCTION SCHEDULE ESTIMATES The cost and time estimates represent good faith estimates necessary to interconnect to the system. The non-binding, good faith cost and time estimates are tabulated below. Assumptions: Permit costs are not included in the estimate. All weather access road costs are not included in the estimate. Land acquisition/row costs are not included in the estimate as it was assumed parcel for switchyard would be deeded to APS from the IC. Access & Lay Down Yards are not included in the estimate. Rough grading costs are not included in the estimate. APS will construct, own and operate the 69 kv facilities in the new APS switchyard and the portion of line from the 69 kv bus up to the first structure outside the sub fence. The IC will construct, own and maintain the 69 kv gen-tie from the first structure outside the sub fence to the site. The IC will be responsible for providing a fiber optic communications path from the facility to the new APS switchyard. Line estimates do not include costs to reconfigure APS lines as a result of IC 69 kv route or design. All estimates are in 2012 dollars. Due to sharing an interconnection into a new APS switchyard with another project (Q154), the interconnection costs shown below are separated depending upon the timing of the two generators interconnecting into the system. The first generator to interconnect will pay the larger amount required to build the new switchyard. The second generator to interconnect will only pay for the upgrades required to bring an additional 69 kv line into the switchyard. Tables 5.1 and 5.2 below provide a summary of the Local Network Upgrades (LNUs) and Transmission Provider s Interconnection Facilities (TPIF) cost estimates for both interconnection scenarios. Table 5.3 below shows the pro-rata share of the SNU costs required for this cluster, as well as the estimated construction schedule to complete the upgrades. Table 5.1: Project Cost Summary (1 st Position) Equipment Description Local Network Upgrades (LNUs) Transmission Provider's Interconnection Facilities New APS 69 kv Switchyard $1,475,000 $141,000 Overhead Line Work $105,000 $0 Communications (Leased T1 Line) $145,000 $0 Subtotal $1,725,000 $141,000 Grand Total $1,866,000 Page 9 of 11

. Table 5.2: Project Cost Summary (2 nd Position) Equipment Description Local Network Upgrades (LNUs) Transmission Provider's Interconnection Facilities New 69 kv Line Terminal $91,000 $141,000 Communications (Leased T1 Line) $44,000 $0 Subtotal $135,000 $141,000 Grand Total $276,000 Table 5.3: Pro-Rata Share of System Network Upgrade Costs and Schedule Estimate Facility Costs Timeline Pro-Rata Share of System Network Upgrades (SNUs) $7,656,561 43-49 Months Total $7,656,561 43-49 Months The interconnection costs shown in Tables 5.1 and 5.2 above are specifically to interconnect into the APS transmission system. The System Network Upgrades (SNUs), as described in the main report, are shown in Table 5.3 above. The total cost to interconnect into the APS system is $9,522,561 for the 1 st position, and $7,932,561 for the 2 nd position. The SNU cost responsibility for a specific individual project will be based on the pro-rata share as identified above, and may change (increase or decrease) depending on the remaining projects in the cluster as well as the timing of the specific project s advancement through the APS interconnection process. All network upgrade costs (LNUs and SNUs) are considered APS Network Upgrades, which are typically repaid to the IC, per FERC rules, as transmission credits over a maximum of twenty (20) years. The Transmission Provider s Interconnection Facilities (TPIF) include the necessary switches, bus work, etc needed to bring the generation tie-line into the new APS switchyard. These costs are the sole responsibility of the Interconnection Customer. Unlike Network Upgrades, these costs are not reimbursable. Tables 5.4 and 5.5 below provide a summary of the construction schedules for both interconnection scenarios. The construction schedule for the SNUs can be found in Table 5.3 above. Table 5.4: Construction Schedule Estimate (1 st Position) Facility Schedule New APS 69 kv Switchyard 12 Months Overhead Line Work 9 Months Communications (Leased T1 Line) 8 Months Total 12 Months. Page 10 of 11

Table 5.5: Construction Schedule Estimate (2 nd Position) Facility Schedule New 69 kv Line Terminal 10 Months Communications (Leased T1 Line) 8 Months Total 10 Months The total estimated completion time for interconnecting the project is 43 49 Months no matter what position it is interconnected, due to the construction of the SNUs. The actual start of construction would occur when the IC provides written authorization to proceed, provided all interconnection studies are complete, and agreements and funding arrangements are in place. Therefore, the requested In-Service Date of October 31, 2012 cannot be met. will be given the first available In-Service Date once the Interconnection Agreement has been signed, which will be based on the Network Upgrades required at that time. Note: This cluster SIS may need to be re-studied if all projects studied as part of this cluster do not move forward to the Facilities Study. If this occurs, the required upgrades, the total estimated costs and the pro-rata shares of the estimated costs will be adjusted and the pro-rata costs shown in Table 5.3 may change (network upgrade costs associated with each project could increase or decrease and may result in an increase in cost up to the full amount of total upgrades). Page 11 of 11