TUNNEL boring was originally attempted over 150 years



Similar documents
Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

TBMs for Norwegian Hydropower projects. Sindre Log The Robbins Company

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

The role of Experts in Tunnelling projects

A Conceptual Methodology and Practical Guidelines for Managing Data and Documents on Hydroelectric Projects

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Integrated Tunnelling Data Management, Analysis and Visualization New IT Tools for Better Projects

Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Linear Schedules for Tunnel Projects

GOWANUS EXPRESSWAY TUNNEL PRIMER

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

1 Introduction. 1.1 General. 1.2 Historical development

Repair or Replacement - Band-Aids vs. Surgery

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Project Portfolio. Tunnels & Shafts

The Performance Prediction of A TBM in Difficult Ground Condition

Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy

The Follo Line Project

Sany Tunnel Boring Machines

STRUCTURAL HEALTH MONITORING AT ROME UNDERGROUND, ROMA, ITALY

AEG-ASCE SHORT COURSE

A methodology for evaluation and classification of rock mass quality on tunnel engineering

A study on the causes of troubles in shield tunneling site with numerical analysis

PhD project description The use of TBM in future Norwegian infrastructure projects

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM

DIMENSIONING TUNNEL SUPPORT BY DESIGN METHODOLOGY

Tunnelling & Underground. Specialists

How To Build The New Irvington Tunnel

53km. Deliver the New Era Network. Island Line Extension. will be added to our Hong Kong network. New Railway Projects are in progress

ITA Working Group Conventional Tunnelling

New advances in planning a bore Software helps take out the guesswork

Coxwell Sanitary Trunk Sewer Emergency Repair: By-pass Sewer Tunnel Construction Final Report

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

Project and site organization of a NATM tunnel project on the example of the Koralm tunnel. Hanns Wagner OBB Austrian Federal Railways

by Morgan Anamoah & Martin Feeney

TBM CROSSING OF STATIONS

Design Guidelines for Sequential Excavations Method (SEM) Practices for Road Tunnels in the United States

Milan M5 metro extension the construction of Lotto station

METHOD OF STATEMENT FOR STATIC LOADING TEST

RECORD TURKISH HIGHWAY

Member Nation Report 2010 from Denmark.

Tunnelling in the Himalayas: Risk assessment and management for tunnelling in extreme geological conditions

TORONTO TRANSIT COMMISSION REPORT NO.

Nuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso

Development of Tunnel Electrical Resistivity Prospecting System and its Applicaton

MINIMIZING DEFECTS OCCURRENCES ON SFRC TUNNEL SEGMENT OF KLANG VALLEY MRT PROJECT

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Moving Small Mountains Vesuvius Dam Rehab

Culvert Rehabilitation A presentation by ms consultants, inc. engineers, architects, planners

Structural Design Criteria & Design Loads on Delhi Metro Rail and Checking of Safety of Radial Joints in Tunnel Lining Segments

Alphington sewer replacement

Emergency repair of Bridge B421

The Performance Prediction of a TBM in Tuzla - Dragos Sewerage Tunnel

Membrane for tunnels and underground construction

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No M (Supersedes Report No.

Numerical analysis of boundary conditions to tunnels

AFTES POST-GRADUATE SPECIALISED MASTER S DEGREE TUNNELS AND UNDERGROUND STRUCTURES. from design to operation.

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Value Engineering vs. Alternate Designs in Bridge Bidding

Rock Support and Reinforcement Practice in Mining

SOME EXPERIENCE FROM THE SOFT GROUND TUNNELLING IN URBAN AREA

DR. DONALD ALEXANDER BRUCE. GEOGRAPHIC BASE: Pittsburgh, PA. TYPE OF COMPANY: Sole Proprietor RESUMÉ

SUPPORT IN UNDERGROUND HARD ROCK MINES

Let s talk about innovative risk solutions for your tunnel projects

Quality and Risk Management Considerations for Very Shallow Soft Ground Conventional Tunnelling in Urban Settings

Kuala Lumpur conquers the underground. Using pioneering tunnelling technology made in Germany.

Risk oriented design and construction of tunnels

Design-Build Services for Parallel Thimble Shoal Tunnel Project. 1.b. Executive Summary. Section 1.b. Executive Summary

(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT Nina Tveiten Norwegian National Rail Administration

Safe & Sound Bridge Terminology

Engineering Survey System for TBM (Tunnel Boring Machine) Tunnel Construction

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Outlet stabilization structure

Why measure in-situ stress?

Reliability of Estimated Anchor Pullout Resistance. Yasser A. Hegazy, M. ASCE 1

Procedure for Working in or around Excavations

School of Engineering

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

Planning and Scheduling Consideration and Constraints in Automated Construction Environment. Chotchai Charoenngam, Ph.D. ABSTRACT

Developing Critical Path Method Scheduling (CPM)

Specification for tunnelling third edition. The British Tunnelling Society and The Institution of Civil Engineers

P.O. Box 416 Winlock WA

HELSINKI EXPERIENCE WITH MASTER PLANNING FOR USE OF UNDERGROUND SPACE

Transmission Foundations Case History : Helical piles Hydro One Networks Inc.

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Solutions for tunneling and mining. Waterproofing. Expanding Horizons Underground. Expanding horizons underground

Identifying and Managing Project Risk, Second Edition 2008 Tom Kendrick. The PERIL Database

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

Chaudière Crossing Bridge Rehabilitation

On-line Certificate in Tunneling

Raise boring equipment

Transcription:

The advantages of tunnel boring : a qualitative/quantitative comparison of D&B and TBM excavation by Peter J Tarkoy, PhD, Geotechnical and Tunnel Construction Consultant and James E Byram, PhD, Senior Research Scientist Introduction Historical perspectives TUNNEL boring was originally attempted over 150 years ago, simultaneously yet independently in England, Europe and North America. The original attempts are generally considered failures, except for the 1.5km Shakespeare tunnel in Dover, a part of the original Channel tunnel, bored over 100 years ago. The imagination of scientists and engineers were far ahead of the technology necessary to turn their concepts into practical reality. Another major attempt to establish tunnel boring was made in the United States during the early 1950s and continuing into the 1960s with some success in very soft rocks. With advances in technology and a desire to excavate harder and harder rock, success was not always realized. Nevertheless, the use of Tunnel Boring Machines (TBMs) increased into the 1960s and 1970s with technological advances that allowed successful tunnel boring in harder as well as less competent rock. With each advance in technology and success in the field, unsuccessful projects were not uncommon. As the use of TBMs increased worldwide, they were also used in labour-rich and capital-poor countries because of inherent advantages and because overseas TBM contractors became very competitive with local D&B excavation. In the late 1960s and early 1970s, the question often asked was: "Can the tunnel be excavated by TBM?" Today, the question has become: "Can you afford not to excavate with a TBM?" Yet to remain impartial, TBMs cannot alone be considered a solution for concerns or problems of tunnel excavation, overbreak, support, dealing with difficult ground or timely completion. Fig 1 Tunnels begun each year by Robbins TBMs Avoidance of problems can only be accomplished with project coordination, management and planning while using the short lead times available for beginning conventional (drill most suitable methods and equipment. That the most appropriate and blast) tunnelling methods most often consist of tunnel boring, does not in itself As we speak, a new TBM is being built and a used TBM is guarantee successful tunnel boring. being re-furbished to begin excavation in Hong Kong in less With this in mind, let us look at the qualitative and quantita- than six months. tive advantages of tunnel boring. Former advantages of D&B excavation Recent developments Rock hardness greater than that found in Hong Kong and up Tunnelling and especially tunnel boring has had a particular to 400 MPa has been successfully bored in other parts of the fascination for engineers and contractors alike. The use of tunnel world in the past 10-15 years. Hard rock boring has become boring has increased through the last two decades to the extent more and more economical as a result of the increase in cutter that more than 20 tunnel projects are begun each year by new diameters (by a factor of 1.5), cutterhead gauge velocities (by a and used TBMs worldwide (Fig 1). factor of 2), cutter load capacity (by a factor of 7), and improvements Although tunnel boring accounts for 80 to 90% of all civil in cutter metallurgy. tunnel excavation in North America and an ever increasing portion The availability of labour has dwindled in many countries. In of tunnels worldwide, tunnel boring has not been the Hong Kong the shortage of labour may be attributable to the method of choice in many parts of the world. For example, in many public works projects currently underway. Consequently, Hong Kong, reasons that have prevented the implementation of the cost and scarcity of skilled labour has dramatically increased. tunnel boring, until recently, were: Furthermore, with the increase in the number of ongo- the existence of hard granitic and volcanic rock ing projects, Castle Peak Tunnel (9km), Hong Kong Electric's plentiful and low cost labour Second Cable Tunnel (5km), Tolo Harbour Effluent Export

1 Crown 2 - Fam 3 Springline to PROFILE Fig 2 Face and work area stability considerations A-Crown B - Springlinc C - Invert Scheme (7.5km), Highway 3 (20km), the Master Sewerage Scheme (total of 30km of tunnels), it is expected that labour shortages, particularly skilled labour necessary for D&B excavation, will become crucial. A summary of anticipated projects have been summarized by Wallis (1989). The short lead times can be dealt with in the following ways: use of reconditioned machines (short refurbishment time) early order of new machines partial pre-order of major machine components by the contractor A study of TBM excavation rates will reveal that excavation by machine may allow time for the manufacture of the TBM, a delayed start of excavation, while still maintaining a timely project completion with less risk. Basis of comparison A simple comparison intended to identify the major cost considerations associated with drill and blast excavation and mechanical tunnel boring will be the subject of this pa per. The comparison of conventional (D&B) and mechanical ('113M) excavation will be made on the basis of similar physical, labour, level of skill, mechanical and other conditions. Wherever possible, assumptions will reflect appropriate conditions and localexperience will be used for construction performance, excavation rates and workmanship. Basic assumptions When comparing D&B and' IBM excavation costs, project assumptions will be the same, namely in terms of tunnel length and diameter. The only differences will be in terms of: number of working headings the excavation advance rate (per working heading) qualitative differences between D&B and TBM excavation Fig 3 Recessed cutterhead and fully shielded TBM access structures (as needed only) Case history data utilized D&B advance rate experience is based on average Hong Kong excavation rates. The TBM advance rate is based on two reported case histories (Tarkoy, 1988; Tarkoy, 1989) and one recently visited site. Case history "TLHP" and "SRT" (Tarkoy, 1989) represent easily attainable advance rates possible under geological conditions similar to Hong Kong. Case "TLHP" represents advance rates without effective and ambitious project management, whereas, project "SRT" represents effective planning, rigorous project management and ambitious construction excavation. Similarly, the "SHEP" project is averaging nearly lkm per month. Major cost items Major cost items affected by the excavation method and considered in this analysis, are: cost savings resulting from qualitative advantages of mechanical excavation l'bm excavation rates four to six times higher than D&B excavation overbreak (cost of delivered concrete, wastage and labour to fill overbreak) labour crew costs equipment costs (drills, jumbos, muckers, cars, trains, TBM, etc) associated supplies (drill bits, TBM cutters, blasting agent) support costs elimination of temporary construction structures (access adits and/or shafts) The cost comparison has been prepared to be applicable only in Hong Kong. A full and realistic construction estimate should be prepared for establishing the method of excavation and support. Operational advantages There are a number of inherent advantages to tunnel boring which are difficult to quantify yet have a considerable impact on the outcome of excavation rates and costs. These are difficult to value in a tender. These advantages cannot fully be appreciated except from firsthand tunnel boring excavation experience. Some of these are: structural stability and safety at the face and work area continuous (non-cyclic) operation 0

Fig 4 Stability in work area (water inflow) consistent, less skilled and easily trained operations (labour is assigned to limited tasks that are repetitive, become routine, and may even produce competition among the labourers) safer and more pleasant working environment than in D&B Structural stability and safety The stability and safety at the excavation face, heading, work area and the lifeline out of the tunnel has always been of great concern in tunnelling. Current technology and tunnelling techniques provide the ability to provide safe and stable conditions in all areas illustrated in Fig 2. There is an inherent level of stability in having a tunnel boring machine at the heading, supporting the work area or blocking possible inrush of materials into the work area. For example, many sudden failures at the heading (typical in fault zones in Taiwan) occur as a result of an excavation blast initially in rock, transgressing into unstable material, soil or a fault zone. The final blast in competent ground triggers the deteriorating ground conditions and a full blown collapse or tunnel inrush may occur even under the watchful eye of the engineer (eg - second Tienlun Power Tunnel). The avoidance of blasting and the stabilizing effect of a full face machine has often been immeasurable, yet striking. The major zones of concern are at the tunnel face, ahead and around the TBM cutterhead and in the work area, as illustrated in Fig 2. These areas of concern may be summarized as follows: Heading Face - full face cutterhead Fig 5 Stability behind work area (water inflow) Crown cutterhead shield Work area Crown finger shield, full Springline arch shield, full shield Invert invert shoe, full shield Behind the work area temporary support rock bolts, strapping, channels, and mesh shotcrete steel ribs and lagging pre-cast segments (primary and/or final) permanent support (pre-cast segments or cast-in-place close behind the excavation face) Stability and safety is of particular significance in the heading and work area and recent TBM designs, such as illustrated in Fig 3 have maneuvered some of the most adverse ground conditions successfully. The most common solution developed for very difficult rock conditions such as flowing sand, swelling claystones or squeezing rock has been the use of various types of recessed cutterhead and shielded tunnel boring machines as illustrated in Fig 3. Fig 4 illustrates the same TBM having encountered 3001/sec flowing from the invert. Had the same tunnel been driven by D&B it would certainly have been impossible to work safely at the heading above voids with flowing water that were safely bridged, first by the shield and later by the pre-cast segments. Fig 6 Stability behind work area (flowing sand) 0

D&B and TBM Excavation Rate Experience Compiled by CeoConSol, Inc. / Peter J. Tarkoy 75 DkB d \ 50 - TBY (Adverse) TBY (Successful) 41 s Q L 0 Y A i 0 I Project Designation Fig 7 D&B and TBM excavation rate experience Shielded machines as illustrated in Fig 3 have also been used, with and without temporary and final continuous pre-cast concrete lining, to protect against damage by water inflow (Fig 5) and support totally decomposed sandstone, some of which has entered the tunnel through grout holes (Fig 6). Continuity of operation 15 Tunnel excavation is linear and TBM work crews perform consistent activities. For example, in conventional excavation, the entire crew generally performs cyclical operations including the drilling, loading, wiring, blasting, venting, scaling, installing support and mucking. This requires a variety of well developed competences and skills. In comparison, TBM crew members are generally assigned a much more limited and consistent set of tasks or responsibilities, such as: TBM operator mechanics and electricians general labour installation of rail, utilities and support maintenance train operation All require fewer skills that are performed repetitively. An added benefit of TBM excavation is that it does not interfere or conflict with installation of support or mucking. Advantages in terms of skilled labour requirements 20 -I I I W 0 I N I I- I - N There are unique advantages and a lower labour skill requirements for TBM excavation because of its continuous nature and assignment of crew members to specific and limited responsibilities. First, the training of unskilled labour is easier than for I I Fig 8 Illustration of overbreak (TDLR) comparative conventional excavation for the following reasons: each crew member has limited responsibilities and therefore is required to learn fewer skills since the operation is continuous and the activities of crew members repetitive, learning is continually reinforced and accelerated fewer high skill level tasks (machine operator, mechanic, electrician) Performance advantages TBM performance advantages can be directly related to quantitative benefits and differences which easily translate into costs and are amenable to direct comparisons. Quantitative performance and cost comparisons can be made for: excavation rates overbreak support labour equipment supplies elimination of temporary structures High excavation rates One of the most significant advantages of tunnel boring are the high excavation rates which can be attained (four to six times higher than local D&B advance rates). D&B experience in 0 Fig 9 Illustration of overbreak (LD&T)

Overbreak Experience Compiled by CeoConSol, Inc. / Peter J. Tarkoy T max J. min X avg tained in D&B and TBM tunnels is shown in Figs 8 and 9. Fig 8 illustrates a transition from good rock excavated by drill and blast and weak rock excavated by TBM and lined by pre-cast segments. Fig 9 illustrates a D&B tunnel excavation where in some cases the overbreak exceeded 60% of the face area. This overbreak will eventually have to be filled with concrete, require building of special bulkheads, result in additional concrete wastage, and sustain a greater wastage, leading to substantial additional costs. Overbreak experience for several projects is illustrated in Fig 10. Support costs Tunnels excavated through similar geological conditions (portals starting from opposite sides of a river valley) have consistently required much more support when excavated by D&B than by TBM as illustrated in Fig 11. A study of seven sites where excavations by D&B and TBM encountered similar geological conditions, revealed that the average steel rib support in TBM excavated tunnels is 1/12 that of D&B tunnels as illustrated in Fig 12. Since there is generally 90-95% less steel rib support required for mechanically excavated tunnels, a considerable cost saving can be realized with mechanical excavation. The cost saving thus calculated will be for the steel ribs only, however, similar reduction of rock-bolt, shotcrete, NATM and other types of support can also be realized. Labour cost savings associated with differences in support will not be included since they will be taken into account in advance rate comparisons and differences Fig 10 Overbreak experience Hong Kong and TBM experience under similar conditions in other parts of the world are illustrated in Fig 7. Overbreak Overbreak is generally influenced by the following factors: lithology rock (intact and mass) properties quality of the blasting practices Typically, no less than 10% overbreak should be anticipated in drill and blast excavation. However, in ideal conditions, using controlled blasting practices, a lower percentage of overbreak can be attained. Most commonly, however, the overbreak in Hong Kong, Taiwan, and where poor blasting practices are used, is quite high. Comparative illustrations between overbreak sus- Fig 11 Illustration of D&B and TBM steel supports HONG KONG ENGINEERIJANUARY 1991

D&B & TBM Steel Rib Support (7 Sites) Compiled by CeoConSol, Inc. / Peter J. Tarkoy Major Costs for D&B/TBM Excavation Compiled by GeoConSol, Inc. / Peter J. Tarkoy 60 56M1 DkB DkB 6 m/day IBM IBM 20m/day TBM 40m/day 159 0kB TBM Fig 14 Major cost for D&B and TBM excavation Fig 12 D&B & TBM steel rib support in crew composition. Labour costs Cost comparisons of D&B and TBM excavation must inevitably include the following differences in labour requirements: only one crew is required for a single TBM working face (TBM excavation rate roughly equivalent to four D&B working faces) the TBM crew will be larger (1 foreman, 1 operator/mechanic, 1 electrician, 2 labourers for utilities/rails/support, 1 conveyor operator, 2 locomotive operators, 2 brakemen for a total of 10 labourers at the heading and train; on a recent project in Norway, the same crew functions were per- Fig 13 Unnecessary and unwanted access structure formed by only 4 men) less skill and more easily trainable because operations are more consistent and continuous Cost of equipment and supplies The major equipment costs in multiple D&B headings are associated with the drilling jumbo, mucking equipment and other support plant (air, water, discharge pumps, etc). This is particularly costly when needed for isolated headings, access adits or shafts in remote areas. In addition, D&B excavation would include cost of supplies such as spares, drill bits, drill steel and blasting powder and caps. In contrast, TBM excavation costs will be for the boring machine (partial depreciation of a new machine or leasing costs for a rebuilt machine) and the cutter costs. It is unusual that a new machine can completely be depreciated on a single project. The purchase of a TBM requires long term investment for use of a machine in more than just one project. Elimination of temporary construction structures The single most extraordinary saving that.can be realized with TBM excavation is in the possibility of eliminating temporary excavation structures such as access adits, tunnels and shafts. This becomes possible with a single'1. BM heading having the same rate of excavation advance as four D&B Dings. In Hong Kong, the cost of an access adit or shaft, with associated workings, has been bid at about HK$50 million (for a 3-3.5m tunnel) recently. Some temporary access structures and associated blasting may also be highly undesirable to local surroundings as for example in the residential neighbourhood of Hong Kong illustrated in Fig 13. 0

Quantitative cost comparisons The results of the cost comparisons are presented in Fig 14. It is evident that TBM excavation has substantial cost advantages when temporary structures are eliminated. TBM excavation costs in Fig 14 reflect a savings of nearly HK$50 million for the elimination of a temporary access structure. The initial capital investment for tunnel boring equipment and its backup system is sizable. The cost comparisons were based on partial depreciation of a new TBM or alternatively on the full leasing cost of a refurbished TBM. Conclusions TBM excavation offers major cost advantages at low progress rates with the major cost savings from the elimination of temporary construction structures. TBM excavation provides considerable advantages at high progress rates with some cost savings from the elimination of temporary construction structures. Inclusion of the cost saving associated with the elimina- tion of temporary excavation structures provides a substantial cost advantage to TBM excavation. References 1) Tarkoy, P J and Wagner, J R (1988). Backing up a TBM. Tunnels and Tunnelling 20(10):27-32 (October). 2) Tarkoy P J (1988). The Stuff that Claims Are Made Of. World Tunnelling 1(3):249-253 (September). 3. Tarkoy P J (1989). Differing Site Conditions Often Generate Claims. The Military Engineer 81(531):72-75 (September/October). 4. Tarkoy P J (1989). A Tale of Two Tunnel Bores, Proceedings International Congress on Progress and Innovation in Tunnelling, Toronto, Canada, September 9-14, pp 1045-105 1. 5 Tarkoy P J (1990). Estimating and Improving Excavation Performance, 1990 Transactions of the American Association of Cost Engineers, 34th Annual Meeting, June 24-27, Boston. 6. Wallis S (1989). Hong Kong and its underground strategy, Tunnels & Tunnelling, January.