1 Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: July 23, 2014 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT AUXILIARY EQUIPMENT ACTION ITEM RECOMMENDATION It is recommended that the Board approve the sale of the four tunnel boring machines (TBMs) and parts to Lovsuns Tunneling Canada Ltd. to be removed from site and transported by the purchaser off site for a total value of $9.200M (excluding tax). From a budget perspective the Executive Task Force (ETF) approved the sale of these TBMs for a minimum of $9.200M on June 25, BACKGROUND The Toronto-York Spadina Subway Extension project is a $2.634 billion infrastructure construction initiative jointly funded by the Government of Canada, the Province of Ontario, the City of Toronto and the Regional Municipality of York. This extension will provide a crucial expansion to the existing Toronto Transit Commission s Line 1 (Yonge-University-Spadina) and for the first time, cross the City of Toronto boundary into the City of Vaughan. The 8.6 km subway extension will provide a high quality rapid transit service connected to the fastest growing region in the Greater Toronto Area and will have six stations along the route with accompanying commuter parking facilities and bus terminals. Two of the stations will be entirely in the Regional Municipality of York and one station and its ancillary structures will straddle the boundary between Toronto and York Region. The Board approved the purchase of four TBMs from Caterpillar Tunnelling Canada Corporation, formerly Lovat Inc., on July 8, 2009 for use in the construction of the Toronto-York Spadina Subway Extension. Tunnelling of the Toronto-York Spadina Subway Extension started on April 2011 and has now been completed. In late 2012 as the conclusion of tunnelling was approaching efforts were initiated to sell the TBMs. This included: Request to prospective purchasers in North America soliciting interest in the purchase of the TBMs. No interest expressed by any firm.
2 AUXILIARY EQUIPMENT Page 2 Caterpillar was contacted and indicated that it had no interest in the buy back. External engineering firm was retained to provide an independent opinion as to the used TBM condition, TBM value and potential. The opinion provided was not favourable given the abandonment of TBM manufacturing, support by Caterpillar and the general market conditions. Four TBMs publicly advertised for sale, soliciting two bids, the highest at $1.487M (tax included) for the TBMs, which was not accepted. Following the public tender process, two offers to purchase were received, the highest for $4.20M, which was not pursued by the prospective purchaser. In February 2014, Caterpillar announced the sale of its TBM assets in Toronto to Liaoning Consecience Industry Co., Ltd., who subsequently adopted a new Canadian corporate name Lovsuns. Two of the four TBM power substations sold to Metrolinx for $0.31M. In May, Lovsuns offered to purchase the four TBMs for $9.0M. TTC staff requested a better price. Lovsuns increased their offer to $9.2M indicating that it would not increase it more and expressed urgency in finalizing the sale. BUDGET IMPACT (EXCLUDING TAX) On July 9, 2009, four TBMs ($12.930M each, excluding tax) were purchased for a total of $51.720M. The expected resale value of the TBMs factored into the TYSSE budget is $15.500M Two TBM power substations sold to Metrolinx ($0.310M) Proposed sale of four TBMs to Lovsuns ($9.200M) Impact of re-sale to TYSSE budget: ($5.990M).
3 DISCUSSION a) Status of TBMs The TBMs are now over four years old and in need of refurbishment and repairs to make them operable. The TBMs are in storage, secured but partly unprotected from the elements, northwest of Toronto. It is expected that the TBMs will progressively degrade with time. There is currently no facility or organization that builds, repairs or maintains similar machines in Canada. The TBMs required maintenance and repairs, as expected throughout the tunnelling operations. When operating, the TBMs performed well, achieving up to 45 meters per day advance on numerous occasions. By comparison, the maximum advance achieved by the Sheppard TBMs was 28 meters per day. There is currently no more technical support available from Caterpillar. However, Lovsuns have verbally indicated that they may be starting some operation at the plant, although this has not been confirmed nor has the nature of this operation. In 2002, a study indicated that retaining the TBMs used to tunnel the Sheppard Subway, on speculation that they could be used on subsequent tunnelling operations, was not advisable. It foresaw that technical improvements and subsequent performance increasing 5 to 8% per year over seven years would render the Sheppard TBMs obsolete. This was confirmed by the performance of TBMs on TYSSE. Both Sheppard TBMs were sold and transported off shore. Also, between the completion of Sheppard and the start of TYSSE, NAFTA fire ventilation standards required an increase in tunnel diameter, rendering the Sheppard TBMs unusable for TYSSE. b) Consideration of Using TYSSE TBMs on the Scarborough Subway Extension As reported to the Board at its meeting of June 24, 2014, work on the Scarborough Subway Extension is now underway and the award of the environmental assessment Consultant Contract is scheduled for August The extension will be a subway, which will require TBMs. Staff reviewed the option of purchasing the TYSSE TBMs, as compared to the purchase of new TBMs. The following issues were considered.
4 AUXILIARY EQUIPMENT Page 2 COST To compare the costs of new TBMs to the purchase of the TYSSE TBMs, costs to properly store and refurbish the TYSSE TBMs must be considered. The TYSSE TBMs are not refurbished for re-use and not in a suitable location for long term storage. TYSSE had a consultant inspect two of the TBMs in the fall of 2013, which led to an estimate of costs to ship, prepare for storage, storage and ultimately the refurbishment, return and on site assembly of the TYSSE TBMs. Factoring in these costs, there is a net savings of $25.3M for the purchase of the TYSSE TBMs (Table 1 Line A). SCHEDULE The start of construction activities is driven by the EA process and the acquisition of property. Based on the timing of these activities, either refurbished or new TBMs would satisfy the schedule. As a result, there is no opportunity to advance the schedule by use of refurbished TBMs. TECHNOLOGY IMPROVEMENTS As with other technologies, TBMs continue to evolve and as a result, there are improvements in productivity, which is measured as an increase in meters of tunnelling per day. As previously noted in this report, TYSSE achieved a forecasted improvement in productivity of 5-8% over the Sheppard Subway. It is expected that in what will be approximately eight years between the purchase of the TYSSE TBMs and the purchase of new Scarborough subway TBMs, there will be a commensurate improvement. An increase in meters per day translates directly to a schedule reduction. For evaluation, 7km was used for the Scarborough subway and based on a 6.5% improvement (5-8% averaged), there is a possible schedule reduction of approximately 1.7 months. Based on calculations used to escalate the project costs through 2023, a one month delay of the project results in an added cost of $13M. Factoring this over 1.7 months results in a potential savings of $22M. This amount has been factored into Table 1 and results in a net savings of $3.3M for the TYSSE TBMs. It is noted that this is for comparison purposes only and has no impact on the Scarborough subway budget.
5 AUXILIARY EQUIPMENT Page 3 TABLE 1 Description TYSSE TBMS New TBMs Difference A TOTAL COST for 4 TBMs $28.8M $54.1M ($25.3M) B A - B Productivity Improvement of New Technology Cost Factoring in Productivity Improvement NA $22M $22M $28.8M $32.1M ($3.3M) SUMMARY Based on the above, there are no schedule benefits of acquiring the TYSSE TBMs. While cost benefits marginally favour the TYSSE TBMs, the amount is not significant when the risks of refurbished equipment breakdowns or the increased productivity of new TBMS are considered. The preferred option given consideration of all factors is to sell the TYSSE TBMs as recommended
TORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: June 24, 2014 SUBJECT: SCARBOROUGH SUBWAY EXTENSION - UPDATE ACTION ITEM RECOMMENDATION It is recommended that the Board: i. Receive
STAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Scarborough Subway Extension Project Management Services Contract FE85-3 Date: February 25, 2015 To: From: TTC Board Chief Executive Officer Summary
OPG READY TO DELIVER REFURBISHMENT OF DARLINGTON NUCLEAR STATION OPG also planning continued operation of Pickering Station
OPG READY TO DELIVER REFURBISHMENT OF DARLINGTON NUCLEAR STATION OPG also planning continued operation of Pickering Station Toronto - Ontario Power Generation (OPG) is ready to deliver on the Government
Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit
Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session May 31, 2016 Transportation
TORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2014 SUBJECT: CONTRACT B45-2 ACTION ITEM RECOMMENDATION It is recommended that the Board authorize the award of a contract
TRANSPORTATION. Industry Solutions Harness the Power of GIS for Transportation
TRANSPORTATION Industry Solutions Harness the Power of GIS for Transportation Esri solutions support over 30,000 transportation customers worldwide who are using the transforming power of GIS technology
Intelligent Transport for Smart Cities Conference. Bruce McCuaig, President and CEO, Metrolinx
Intelligent Transport for Smart Cities Conference Bruce McCuaig, President and CEO, Metrolinx 2 Transportation Trends 2013 2031 82 minutes spent commuting 109 6.6 9 million residents in the GTHA 3 The
Integrating GO RER and SmartTrack. Leslie Woo, Chief Planning Officer February 10, 2016
Integrating GO RER and SmartTrack Leslie Woo, Chief Planning Officer February 10, 2016 Purpose and Scope To present update on development of options for integrating SmartTrack and GO RER based on the following
City Manager, Deputy City Manager and Chief Financial Officer, Interim Chief General Manager, Toronto Transit Commission
Spadina Subway Extension- Update STAFF REPORT ACTION REQUIRED Date: April 16, 2007 To: From: Wards: Reference Number: Executive Committee City Manager, Deputy City Manager and Chief Financial Officer,
2007 Operating Budget 2007-2016 Capital Budget 2007 Proposed Water and Wastewater Service Rate
2007 Operating Budget 2007-2016 Capital Budget 2007 Proposed Water and Wastewater Service Rate Toronto City Council February 1 5, 2007 Multi-Year Toronto Water Business Plan was approved by Council February
1. RECOMMENDATIONS. It is recommended that:
Clause No. 7 in Report No. 3 of was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 20, 2014. (Mayor Hackson declared an interest in this
LES EXPLOSIFS NORDEX LTEE/NORDEX EXPLOSIVES LTD.
LES EXPLOSIFS NORDEX LTEE/NORDEX EXPLOSIVES LTD. INTERIM MANAGEMENT DISCUSSION AND ANALYSIS of Financial Condition and Results of Operations for the three months ended September 30, 2005 Dated: November
PROJECT EXPERIENCE Development/Transaction Support United States MANAGING DIRECTOR
Peter Abt Mr. Abt is a Managing Director in Black & Veatch s Management Consulting Division. He leads the division s Oil & Gas Strategy practice and holds primary responsibility for client management and
KELT INCREASES PLANNED 2015 CAPITAL EXPENDITURES IN BRITISH COLUMBIA, PROVIDES OPERATIONS UPDATE AND ANNOUNCES $78.8 MILLION EQUITY FINANCINGS
PRESS RELEASE (Stock Symbol KEL TSX) June 15, 2015 Calgary, Alberta KELT INCREASES PLANNED 2015 CAPITAL EXPENDITURES IN BRITISH COLUMBIA, PROVIDES OPERATIONS UPDATE AND ANNOUNCES $78.8 MILLION EQUITY FINANCINGS
Business Plan: Roadway Planning & Design
Business Plan: Roadway Planning & Design How does this service contribute to the results identified in the City of London Strategic Plan? A Strong Economy A Sustainable Infrastructure London s transportation
STAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Change Directive to the Toronto Rocket (TR) Supplier for the Design Provisions for Train Door Monitoring (TDM) System Date: March 26, 2015 To: From:
Siemens Canada Ltd Dr. Donald Wilson Industry DT Large Drives Mining and Minerals
History of Siemens in Canada and Mining Outlook according to Siemens Canadian German Chamber of Industry and Commerce Inc. German Business Delegation to Canada November 12-16, 2012, Toronto, Canada Siemens
How To Improve Your Fleet Maintenance
BUSINESS PLAN: Fleet Management How does this service contribute to the results identified in the City of London Strategic Plan? A strong economy A vibrant and diverse community A green and growing City
Enterprise Asset Management
Enterprise Asset Management Asset Management Strategy April 29, 2014 Craig Stewart, Senior Director Capital Program Metropolitan Transportation Authority Providing public transit is asset-intensive 5/15/2014
Greater Toronto Area Industrial Market Snapshot October 2013
Greater Toronto Area Industrial Market Snapshot October 2013 CBRE Global Research and Consulting LOCATION, LOCATION, AND TRANSPORTATION WHERE IS INDUSTRIAL DEVELOPMENT HEADED? By: Lynn Duong Senior Research
2012 Customer Satisfaction Survey Subway
Customer Satisfaction Survey Subway Methodology Citywide Survey conducted by telephone Random landline and cell phone samples Interviewed 1829 persons 1200 qualified for full survey: At least one subway
Cost Benefits of Extended Warranties for Construction Projects Are Unknown
AUDITOR GENERAL S REPORT ACTION REQUIRED Cost Benefits of Extended Warranties for Construction Projects Are Unknown Date: May 1, 2014 To: From: Wards: Audit Committee Auditor General All Reference Number:
The AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department
The AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department ISTSS 2016 - AMT s conference Jean-Philippe Pelletier, eng.,
4 SPADINA SUBWAY EXTENSION UPDATE
4 SPADINA SUBWAY EXTENSION UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the adoption of the recommendations contained in the following report June 13, 2006, from the
9 Award of Request for Proposal P-15-13 Consulting Retainer Services York Region Transit/Viva Fleet Projects
Clause 9 in Report No. 9 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on May 21, 2015. 9 Award of Request for Proposal
Managing Foreign Exchange Risk
WHITE PAPER Managing Foreign Exchange Risk The Canadian dollar has made the headlines on numerous occasions in recent years. Its value has changed significantly and rapidly many times, greatly impacting
GOING PUBLIC IN CANADA
GOING PUBLIC IN CANADA CASSELS BROCK IN BRIEF Canadian law firm of more than 200 lawyers based in Toronto and Vancouver focused on serving the transaction, advocacy and advisory needs of the country s
Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division
PW8.5 STAFF REPORT ACTION REQUIRED Contract Award Request for Proposal No. 9117-15-7122 Engineering Services for the Detailed Design, Services During Construction, and Post-Construction Services for an
Business Plan: Fleet Services
Business Plan: Fleet Services How does this service contribute to the results identified in the City of London Strategic Plan? A Strong Economy A Green and Growing City Fleet Services owns and manages
5 DISPOSITION OF 2010 OPERATING BUDGET SURPLUS AND CHANGES TO CAPITAL PROJECT FUNDING TO REDUCE DEBT
5 DISPOSITION OF 2010 OPERATING BUDGET SURPLUS AND CHANGES TO CAPITAL PROJECT FUNDING TO REDUCE DEBT The Finance and Administration Committee recommends the adoption of the recommendations contained in
Ontario s s Water and Wastewater Energy Management Best Practices
Ontario s s Water and Wastewater Energy Management Best Practices Erin Cain February 27 th, 2007 AWWA/WEF Joint Management Conference February 25-28, 2007 Introduction What can I take back and apply? Energy
P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project
P3 Value for Money Assessment and Project Report Evan Thomas Water and Wastewater Treatment Facility Project July 2013 Table of Contents 1. Summary: Using a P3 for a Water Treatment Plant - did it work?
Commonly Asked Questions Regarding Ontario Lottery & Gaming Corporation (OLG) Gaming Facility Opportunity
Commonly Asked Questions Regarding Ontario Lottery & Gaming Corporation (OLG) Gaming Facility Opportunity The Ontario Lottery and Gaming Corporation (OLG) has announced their intention to expand private
Barkerville Gold Mines Investor presentation q1 2016. The last great Canadian gold mining camp controlled by a junior mining company.
Barkerville Gold Mines Investor presentation q1 2016 The last great Canadian gold mining camp controlled by a junior mining company. 1 Forward Looking statement This presentation and the material contained
FAYETTEVILLE STATE UNIVERSITY
FAYETTEVILLE STATE UNIVERSITY FIXED ASSETS Authority: Category: Issued by the Chancellor. Changes or exceptions to administrative policies issued by the Chancellor may only be made by the Chancellor. Business,
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS You should read the following management s discussion in conjunction with our unaudited consolidated interim condensed
The role of Experts in Tunnelling projects
The role of Experts in Tunnelling projects Evert Hoek This paper was prepared as a keynote address for a workshop entitled The Tunnels of Egnatia Odos which was held in Ioannina, Greece on 7 December 2001.
SaskPower CCS Global Consortium Bringing Boundary Dam to the World. Mike Monea, President Carbon Capture and Storage Initiatives
SaskPower CCS Global Consortium Bringing Boundary Dam to the World Mike Monea, President Carbon Capture and Storage Initiatives 1 Purpose of Today A. CCS around the world B. What SaskPower is doing C.
General Travel Conditions of Helsinki Region Transport
2015 General Travel Conditions of Helsinki Region Transport Helsinki Region Transport General Travel Conditions 1.1.2015 The Helsinki Region Transport (HSL) Travel Conditions apply to public transport
218 Dancer Dr, Hamilton, NJ 08610
This Property Brochure is STRICTLY for HNPS Investors and associates only. All Properties are normally sold within 14 days from the date listed. Please check the status of the unit with us before beginning
Japan Exchange Group, Inc. and Consolidated Subsidiaries Consolidated financial results for nine months ended December 31, 2012, unaudited
January 3, 213 Japan Exchange Group, Inc. and Consolidated Subsidiaries Consolidated financial results for nine months ended December 31, 212, unaudited Company name: Japan Exchange Group, Inc. (Previous:
The North American Process: Steps Toward Stronger Partnership A Working Symposium
The North American Process: Steps Toward Stronger Partnership A Working Symposium Hyatt Regency, Phoenix March 30-31, 2016 North American Electricity Primer Sapna Gupta Senior Policy Analyst, Morrison
Allianz Insurance plc. Erection All Risks. Product Information. This information is for intermediaries only
Allianz Insurance plc Erection All Risks Product Information This information is for intermediaries only Erection All Risks Insurance Policy Wherever there is the erection or installation of machinery
Sany Tunnel Boring Machines
Sany Tunnel Boring Machines 3 CORPORATE CULTRUE Mission Build a top Company, Foster top employees, Make top contributions Spirit Progress constantly, Develop national industry Core Value Morality first,
ICM Project Station Infrastructure and Equipment
EB 0 00 Schedule B. ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B. I EXECUTIVE SUMMARY 0. Project Description Many Municipal Substations (MS) located outside of downtown
NOT FOR DISSEMINATION TO US NEWS WIRE SERVICES OR DISSEMINATION INTO THE UNITED STATES. FOR IMMEDIATE RELEASE
NOT FOR DISSEMINATION TO US NEWS WIRE SERVICES OR DISSEMINATION INTO THE UNITED STATES. FOR IMMEDIATE RELEASE TREAT SYSTEMS (MEGA SILVER INC.) ANNOUNCES ACQUISITION OF OPTIONS TO EARN INTERESTS IN MEXICAN
Letter to Shareholders
Letter to Shareholders Today we announced a number of shareholder initiatives which, while not directly related to the creation of intrinsic value, are intended to ensure the value of our business trades
CPCS Supply Chain Review. Eastern Canada Logistics Study By CPSC November 2012
CPCS Supply Chain Review Eastern Canada Logistics Study By CPSC November 2012 Disclaimers 1. Study was initially presented in July 2013 in Montreal and may be repetitive for some of you. 2. Some of the
ACCOUNTING FOR NON-ACCOUNTANTS MARGINAL COSTING
ACCOUNTING FOR NON-ACCOUNTANTS MARGINAL COSTING MARGINAL COSTING OBJECTIVE To be able to: Explain the relevance to management decisions of: Fixed costs Variable costs Contribution Prepare an operating
HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS
HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS Quarterly results reflect a number of timing, unusual and unseasonal weather related items while core operations remain strong; Board declares first
STEEL fabrication quality SySTEmS guideline
STEEL fabrication quality systems guideline Copyright 2002 by Canadian Institute of Steel Construction All rights reserved. This book or any part therof must not be reproduced in any form without written
SUMMARY OF CAPITAL EXPENDITURES
Filed: May, EB--00 Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL BUDGET The proposed capital expenditures result from a rigorous business planning and work prioritization process that reflects
Tashman Johnson LLC Consultants in Policy, Planning & Project Management
Tashman Johnson LLC Consultants in Policy, Planning & Project Management AN OVERVIEW OF URBAN RENEWAL Tashman Johnson LLC Jeffrey Tashman 503.245.7828 Nina Johnson 503.245.7416 Fax 503.245.3171 6585 S.W.
FINANCIAL INTRODUCTION
FINANCIAL INTRODUCTION In earlier sections you calculated your cost of goods sold, overhead expenses and capital cost in order to help you determine the sales price of your product. In your business plan,
The BIG Move: Transforming Transportation in the Greater Toronto and Hamilton Area
The BIG Move: Transforming Transportation in the Greater Toronto and Hamilton Area Journée de réflexion December 13 th 2013 Montreal QC Leslie Woo VP Policy, Planning and Innovation 1 Greater Toronto and
Procurement Guiding Principles. Northwest Supply Chain Collaboration. for the. Regional Members of the Northwest Supply Chain
Regional Members of the Northwest Supply Chain Guiding Principles for the Northwest Supply Chain Collaboration NSC Guiding Principles Pamphlet.pub Printed June 2015 20 Table of Contents Introduction..
Integrated Tunnelling Data Management, Analysis and Visualization New IT Tools for Better Projects
Integrated Tunnelling Data Management, Analysis and Visualization New IT Tools for Better Projects K. Chmelina 1, G. Krusche 1, G. Hesina 2 1 Geodata Ziviltechnikergesellschaft mbh, Leoben, Austria; 2
DC Traction Power Supply. Powerful, efficient and safe. siemens.com/mobility
DC Traction Power Supply Powerful, efficient and safe siemens.com/mobility 2 DC traction power supply More people, more challenges, one solution: Complete mobility. Needed more than ever before: Not only
TORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: April 30, 2014 SUBJECT: 2014-2018 TTC MULTI-YEAR ACCESSIBILITY PLAN ACTION ITEM RECOMMENDATIONS It is recommended that the Board: 1.
Economic Impact of Trade & Consumer Shows
Economic Impact of Trade & Consumer Shows R ESEARCH C ONDUCTED BY M ARION J OPPE, P H.D. HS CHRIS C HOI, P H.D. D ONGKOO YUN, P H.D. ON BEHALF OF TOURISM TORONTO IN PARTNERSHIP WITH INTERNATIONAL CENTRE,
TO OUR MULTI-STATE BUSINESS CLIENTS
TO OUR MULTI-STATE BUSINESS CLIENTS The following checklist is designed to help determine whether a company is responsible for filing tax returns in the states in which you do business. Some states may
2) Recommendations and measures taken based on recommendations
4. Recommendations 1) Outline Based on the results of the inspections or the investigations of criminal offenses, the SESC may, if deemed necessary, present recommendations to the Prime Minister and the
2008 TTC OPERATING BUDGET
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: NOVEMBER 14, 2007 SUBJECT: 2008 TTC OPERATING BUDGET RECOMMENDATION It is recommended that the Commission: 1) Approve the
Corporate Finance and Mergers &
Corporate Finance and Mergers & Acquisitions 25 Corporate Finance and Mergers & Acquisitions Canada has well-developed and sophisticated capital markets. The main sources of capital are Canadian chartered
LIFECYCLE MANAGEMENT OF UTILITY ASSETS A PRACTICAL APPROACH
LIFECYCLE MANAGEMENT OF UTILITY ASSETS A PRACTICAL APPROACH Dr. Petros Kolovopoulos (Hydro-Comp Enterprises Ltd, Cyprus), Dr Dinos Constantinides (Hydro-Comp Enterprises Ltd, Cyprus) Key words: Asset Management,
Life Long Learning. Joint OSPE PEO Chapter Professional Development Presentation
Life Long Learning Joint OSPE PEO Chapter Professional Development Presentation This presenta,on can be downloaded at: h4p://www.ospe.on.ca/?page=adv_peochap OSPE PD/CS Committee May 2014 2 Outline of
MORUWASA S STRATEGIC PLAN MATRIX FOR 2007/2008 2021/2022. Strategy Activity Responsibility Time Frame Performance
KRA 1: ORGANIZATION STRUCTURE, POLICIES, REGULATIONS AND PRACTICES Objective 1: Ensuring good governance and sound manag Operational OT 1: targets The organization structure of MORUWASA reviewed after
Ordinary and Extraordinary Annual Shreholders Meeting
Ordinary and Extraordinary Annual Shreholders Meeting April 24th 2014 Abridged Version Group overview Vianini Lavori is one of the main Italian General Contractors and it operates in the large infrastructure,
Investor Presentation February 25, 2004
Investor Presentation February 25, 2004 Some of the statements in this presentation may constitute forward-looking information and future results could differ materially from what is included. Please refer