Member Nation Report 2010 from Denmark.
|
|
|
- Sheena Wilson
- 9 years ago
- Views:
Transcription
1 Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City Tunnel project in Germany with 5 underground stations. The second visit and study tour covered a two day visit to tunnels in construction close to the City Centre of Stockholm in Sweden. The first site visit was to the almost 9 km long road tunnel of Norra Länken using drill & blast and cut & covers methods. Secondly a site visit was done to the 300 m long Söderström immersed railwaytunnel under construction next to the immersion site in the City Centre of Stockholm. The tunnel is detailed design by COWI and the contractor is a JV of PIHL (DK) and Züblin (D). Members of the society have participated in the ITA General Assembly in Vancouver, Canada from 14 th to 20 th May 2010 including meetings in two ITA working groups. Members have also participated in activities within COSUF during 2010 and as tutor and lecturer within ITA - CET. One member is an active member of PIARC's tunnel Committee including two working groups on safety and operation of tunnels bringing back news for the Danish tunnel industry. The progress on the Cityringen project continues. The project consist of a completely new Metro with 15 km metro circle line all underground (30 km tunnels) and 17 underground stations and will have its own maintenance and service centre. There will be 5 interchange stations to existing railway and metro lines. In January 2011 the project went from the planning phase to the execution phase by the signing of the contracts for the Civil Works Construction and for the delivery of the Transportation Systems. For the Civil Works the contract was signed with the Copenhagen Metro Team a joint venture of the companies Salini, Trevi and Selli from Italy. The Transportation System contract was signed with Ansaldo, Italy. The contracts are design and build contract. The civil works contract includes construction of 30 km of tunnels, construction of 17 stations and 3 underground chambers for cross - overs and bifurcations of the Metro line. The tunnels will be constructed using four earth pressure balance TBMs in geology varying from competent lime stone to glacial deposits of clay till and sand layers. More than 500 boreholes and 17 km of seismic investigations have been performed in order to investigate the ground conditions and to provide a firm basis for the contract. The ground coverage to the tunnels varies between 5 to 30 m with generally 15 m at stations and 25 m at low points between stations. The stations will be constructed using cut & cover method with retaining walls of either secant piles or diaphragm walls depending on the ground conditions and the depth of the walls. There are 14 so called standard stations and 3 special stations of which one has to be constructed partly in a water canal. The station boxes are generally 22 m side and 70 m long with platform depth of
2 generally 19 m below ground. The civil works contract includes also the mechanical and electrical equipment such as power supply, tunnel and station ventilations and SCADA systems. Works has already started in the City with utilities being relocated and archaeological excavations ongoing which all will be finalized prior to the sites being handed over to the contractor, which will happen gradually from March 2011 and onwards. The project value is 3 billion Euros and the Metro Circle Line is scheduled to open in Figure 1: Archeological site investigations ongoing in the historical city center of Copenhagen. Different alignment studies have been carried out for a new Eastern Bypass around Copenhagen. In February 2009 The Danish Government presented their plan for the Danish Transport Policy until The plan states that the government will initiate a strategy analysis for the Eastern Bypass. Ramboll shall report this study of different alignments in The feasibility of a new Oresund Fixed Link between Elsinore in Denmark and Helsingborg in Sweden has been studied during by IBU-Oresund, an organization consisting of regional and local authorities on both sides of Oresund. The project was partly financed by the European Regional Development Fund. Different alignments for the fixed link have been investigated with bridge and tunnel options. Ramboll has investigated a central city-to-city link
3 and has recommended a bored tunnel for passenger trains. The Swedish Government has initiated a more comprehensive study for the link. This study should be reported mid 2011 For a new Northern Harbour Tunnel two proposals have been developed into preliminary design in 2009 and The first proposal comprises a cut-and-cover tunnel with a length of approximately 1 km, including Ramp structures. The second proposal comprises a bored tunnel with a length of approximately 2.5 km, including ramp structures. In April 2010 the City of Copenhagen selected the proposal with the cut-and-cover tunnel as the continuing project. The project is very complex because the tunnel will be built in dense rural areas passing several heavy trafficked roads and railways. The project is being developed by the City of Copenhagen and Ramboll. The project is planned to be tendered for construction works in February 2011 and is expected to take 5 years to complete. Figure 2: Overview of the portal and ramp area for a new Northern Harbour Link. The first phase of the Marselis Boulevard Tunnel in Aarhus - connecting the Motorway system and Ring Road network with the Port of Aarhus is under construction. The second phase with a 2 km cut & cover tunnel is delayed due to problems with the financial founding's. The contractor PIHL has started the construction of an exceptional underground Maritime Museum located near the famous Kronborg Castle in Elsinore. The architects, B.I.G. (Bjarke Ingels Group), have created a fantastic project utilizing the old dry dock from the shut down Elsinore shipyard. The museum will be located around and inside the old dock. The client is Maritim Museums Byg ApS and consulting engineer is Rambøll.
4 The subsoil is mainly sand and gravel. In the depth m below ground level the limestone starts. When the concrete dry dock was constructed during the 1950ties, a lowering of the ground water level just sufficient for the construction works was achieved, but the quantity of water pumped out into the harbour was huge due to the very permeable subsoil of sand and gravel. A similar lowering of the ground water level for the construction of the new museum was initially deemed impossible considering neighbour buildings and the environment. The main structures including a large number of anchors against uplift and new reinforced concrete structures were then to be installed under water, with all the difficulties resulting from such an execution method. PIHL proposed however to install a cut off wall of bentonite/cement slurry in the sand/gravel around the entire dry dock extending from the ground surface to a number of meters into the limestone. With such a cut off wall installed the main quantity of ground water, when pumping from the enclosure inside the wall, would originate only from the limestone, and the lowering of the ground water level in order to construct the museum in dry would be assumed possible. The method was used for establishment of the dry dock in Kalundborg for the pylon caissons for the Great Belt East Bridge. PIHL was participating as one of the JV partners of GBC. The only place where the cut off wall is not possible is under the dry dock at the entrance to the harbour. In this area the water flow is stopped by a wall of soilcrete columns created by jet grouting in the soil from underside dry dock to limestone surface. When the cut off wall has been completed it is expected that only a relatively small quantity of water shall be pumped in order to lower the ground water to approx. 9.0 m, which is sufficient. All construction works both regarding the modification and anchoring of the old dock and regarding all the new reinforced concrete structures can now be performed in the dry. The necessary measures for this ground water lowering are very expensive, but the savings and the higher quality of the works when these are performed in the dry, more than compensates for this cost. Close to Copenhagen Central Railway Station a new single track railway tunnel with a length of 120 m is under construction. The tunnel will be build as cut-and-cover with a high degree of complexity due to a construction site next to existing main tracks in operation. The construction works started late 2010 and the tunnel will be ready for operation by The Client is the Danish State Railway using COWI and Grontmij - Carl Bro as consulting engineers for the design. The Femern Belt Fixed Link is a proposed permanent road and rail connection between Scandinavia and continental Europe. The Femern Belt Fixed Link will specifically connect Rødbyhavn in Denmark to Puttgarden in Germany and is expected to bring economic benefits to the entire region around the Femern Belt.
5 Figure 3: Location of the Femern Belt Fixed Link. The opening of the Femern Belt Fixed Link will significantly reduce the travel time between continental Europe and Scandinavia. A bridge and an immersed tunnel option are being designed. These designs are undertaken by separate groups of consultants commissioned by the state owned Femern A/S. Ramboll (Denmark), Arup (UK) and TEC Tunnel Engineering consultants (The Netherlands) (RAT) have designed the tunnel project option for the Femern Belt Fixed Link. The crossing of the Femern Belt will be one of the deepest and by far the longest immersed tunnel in the world. Femern A/S has in 2010 recommended the RAT immersed tunnel solution as this entails the fewest risks during the construction period and when in operation. The recommendation is based on a preliminary, comprehensive assessment of environmental and safety issues including navigational safety but also technical, traffic, time and financial issues. Latest news and status for the planning of the combined new 18 km road and railway link crossing the Baltic Sea between Rodby (Denmark) and Puttgarden (Germany) refer to:
6 Figure 4: Femern Belt Fixed Link. Tunnel entrance and exit.
The Danish Transport System. Facts and Figures
The Danish Transport System Facts and Figures 2 The Ministry of Transport Udgivet af: Ministry of Transport Frederiksholms Kanal 27 DK-1220 København K Udarbejdet af: Transportministeriet ISBN, trykt version:
COWI s Role in the Copenhagen Metro Project
COWI s Role in the Copenhagen Metro Project On the occasion of the award by the Copenhagen Cultural Foundation for COWI A/S part in the implementation of Phase 1 of the Copenhagen Metro 2 COWI s Role in
Tunnelling & Underground. Specialists
Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering
BUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
Söderströmtunnel: immersion in downtown Stockholm, Sweden
Söderströmtunnel: immersion in downtown Stockholm, Sweden J. Glückert Dipl.-Ing, Züblin Ground Engineering, Stuttgart, Germany N.H.J. Vink MSe, M. Reijm BSc, P.T. van Westendorp BSc Strukton Immersion
The Follo Line Project
The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the
The Danish Road Directorate Evaluation of test with European Modular System
Trafikudvalget 2010-11 TRU alm. del Bilag 99 Offentligt The Danish Road Directorate Evaluation of test with European Modular System Midway Report in cooperation with May 2010 Midway Report The Danish Road
The Copenhagen Metro Circle Line-Tunnelling and Station Construction Challenges in Urban Conditions
The Copenhagen Metro Circle Line-Tunnelling and Station Construction Challenges in Urban Conditions Søren Degn Eskesen COWI A/S, Copenhagen, Denmark David Whittles Arup, Copenhagen, Denmark Jørgen Krogh
Engineering Insurance Exposure related to Wet Risks
Engineering Insurance Exposure related to Wet Risks IMIA Conference Tokyo, 2007 Chairman: Xavier Touzé, XL Re Europe Working Group: Hans Mahrla, Infrassure Thomas Boertzler, Munich Re Maarton Keuning,
Road freight transport across a fixed Fehmarn Belt link
Road freight transport across a fixed Fehmarn Belt link Per Homann Jespersen 1 Draft version Introduction A fixed link between Denmark and Germany was agreed upon by the Danish and German governments on
A Greener Transport System in Denmark. Environmentally Friendly and Energy Efficient Transport
A Greener Transport System in Denmark Environmentally Friendly and Energy Efficient Transport Udgivet af: Ministry of Transport Frederiksholms Kanal 27 DK-1220 København K Udarbejdet af: Transportministeriet
GOWANUS EXPRESSWAY TUNNEL PRIMER
GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a
Milan M5 metro extension the construction of Lotto station
Milan M5 metro extension the construction of Lotto station Giuseppe LUNARDI, Rocksoil S.p.A., Italy [email protected] Luca MANCINELLI, Rocksoil S.p.A., Italy, [email protected] Massimiliano
Industry industrial buildings production and processing plants oil and gas health, safety and environment environmental and social due diligence.
Tunnel engineering COWI A/S COWI A/S is a leading international consulting company founded in 1930. COWI is privately owned and entirely independent of any manufacturer, supplier or contractor. The COWIfonden
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
LIGHT RAIL ON RING 3 NOVEMBER 19 TH 2014. Supplier Workshop. Islevbro station (Rødov
LIGHT RAIL ON RING 3 NOVEMBER 19 TH 2014 Supplier Workshop Islevbro station (Rødov 1 Agenda In the Auditorium: 1. Welcome and programme; purpose of the day 2. Ring 3 in Brief 3. Vision of Light Rail on
Fehmarnbelt Forecast 2014 - Update of the FTC-Study of 2002
Fehmarnbelt Forecast 2014 - Update of the FTC-Study of 2002 for Femern A/S 2014 Intraplan Consult GmbH Orleansplatz 5a Wentzingerstr. 19 81667 München 79106 Freiburg BVU Beratergruppe Verkehr + Umwelt
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
53km. Deliver the New Era Network. Island Line Extension. will be added to our Hong Kong network. New Railway Projects are in progress
53km will be added to our Hong Kong network Deliver the New Era Network 4 New Railway Projects are in progress Island Line Extension opened in December 2014 Executive Management s Report Hong Kong Network
The Gotthard Base Tunnel
The Gotthard Base Tunnel The tunnel On 11 December 2016, the Gotthard Base Tunnel will come into scheduled operation. At 57 kilometres in length, it is the longest rail tunnel in the world. It has virtually
PROPOSAL FOR CONTRACTORS ALL RISKS
PROPOSAL FOR CONTRACTORS ALL RISKS 1. Title of contract (If project consist of several sections, specify section(s) to be insured) 2. Location of site Country/Province/district City/town/village 3. Name
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 [email protected]
Design-Build Services for Parallel Thimble Shoal Tunnel Project. 1.b. Executive Summary. Section 1.b. Executive Summary
Design-Build Services for Parallel Thimble Shoal Tunnel Project Executive Summary 1.b. Executive Summary Section 1.b 1.b. Executive Summary CBBT s goal of adding operational flexibility through providing
ources of Drinking Water
The drop on water Sources of Drinking Water Did you know that 40 per cent of Nova Scotians get their water privately from a drilled well, a dug well, or a surface water source? The other 60 per cent rely
Building Pit Roche Building 1 Basel, Switzerland
Building Pit Roche Building 1 Basel, Switzerland Implenia Spezialtiefbau GmbH Infrastructure - Central Branch Mannheim Office Diffenéstraße 14 D-68169 Mannheim GERMANY T +49 621 70014-250 F +49 621 70014-260
QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE
GA Insurance House, Ralph Bunche Road, P O Box 42166-00100 Nairobi, Kenya. Telephone: 2711633 Fax 2714542 E-mail: [email protected] QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE AGENT:
Integrated Tunnelling Data Management, Analysis and Visualization New IT Tools for Better Projects
Integrated Tunnelling Data Management, Analysis and Visualization New IT Tools for Better Projects K. Chmelina 1, G. Krusche 1, G. Hesina 2 1 Geodata Ziviltechnikergesellschaft mbh, Leoben, Austria; 2
Undergrounding high voltage electricity transmission. The technical issues
Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.
Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle
Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,
URBAN INFRASTRUCTURE METRO
URBAN INFRASTRUCTURE METRO WORKSHOP BOGOTA 2012-03-27 CONSULTING DESIGN PROJECT MANAGEMENT SITE SUPERVISION WORKSHOP BOGOTA STRUCTURE 2 Structure 1. Presentation of Mr. Dieter Stephan and of consulting
Unit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
TBM CROSSING OF STATIONS
TBM CROSSING OF STATIONS Eng. Marco Barbanti Astaldi S.p.A. Eng. Tommaso Grosso Astaldi S.p.A. 18-11-2011 In the presence of groundwater the permeability of the ground is of great interest. It is important
Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the
Tame Urban Pollution Management Foxton Road & Sir Johns Road CSOs - collaborative working to deliver innovative solutions Severn Trent Water Ltd has undergone a massive investment programme in the River
Jan Schönbeck, Head of Strategic Contracts and Procurement. Seminar in Berlin 13 June 2012
Jan Schönbeck, Head of Strategic Contracts and Procurement Seminar in Berlin 13 June 2012 The task of the Swedish Transport Administration is responsible for the long-term planning of the transport system
COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2
(PREVIEW) SP 36 (Part 2) : 1988 COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2 IS 1893 : 1979 (Reaffirmed 1987) CODE OF PRACTICE FOR SUBSURFACE INVESTIGATION FOR FOUNDATIONS 1.1 This code deals
Geotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
NEW BLUE LINE CONNECTIONS
Washington Metropolitan Area Transit Authority NEW BLUE LINE CONNECTIONS 3/31/2014 A Major Capital Project of Momentum s Metro 2025 Program In support of its new strategic plan, Metro has considered the
REHABILITATION AND EXTENSION PROJECT FOR PORT OF LOBITO
REHABILITATION AND EXTENSION PROJECT FOR PORT OF LOBITO Advantages of Port Lobito (1) Predominant geological locations Facing the Atlantic, Port Lobito locates around 30km north to Beguela City, and it
Construction Technology 3
www.beautiful-basements.co.uk Construction Technology 3 Assignment 2: Basement Construction Dr. Patrick Tang, School of Architecture and the Built Environment Michael Dernee C3089219 Abstract: In the brief
EXECUTIVE SUMMARY. Salini Impregilo / Healy / GLF Joint Venture
EXECUTIVE SUMMARY statement of qualifications chesapeake bay bridge and tunnel district EXECUTIVE SUMMARY With extensive international tunneling and marine design and construction experience, Salini Impregilo/Healy/GLF
Role of the Environmental Management Representative (EMR)
Legacy Way Project Role of the Environmental Management Representative (EMR) What is Legacy Way The project consists of the following key elements: Two 4.2 km road tunnels connecting the Western Freeway
The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT 07.06.2016. Nina Tveiten Norwegian National Rail Administration
(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT 07.06.2016 Nina Tveiten Norwegian National Rail Administration The study has been conducted on behalf of: The Ministry of Transport and Communications The Municipality
Business Unit. Tunnelling & Civil Engineering. Infrastructure solutions from a single source.
Business Unit Tunnelling & Civil Engineering Infrastructure solutions from a single source. 6 14 20 4 Innovative solutions on a sound basis 6 Tunnelling Setting new standards Transportation tunnels Power
Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.
Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most
C9 - BIM implementation on Stockholm Bypass Project Using PowerCivil. Trafikplats Akalla och Häggvik, ÅF-URS.
C9 - BIM implementation on Stockholm Bypass Project Using PowerCivil. Trafikplats Akalla och Häggvik, ÅF-URS. Track: Civil Presenter: Mateusz Nettmann AGENDA 1. Introduction: A. URS Company B. People involved
Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.
Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing
LETBANE PÅ RING 3. Information about the public procurement process
Information about the public procurement process Document ID: L3-X-LB-PRE-0001 Version: 2.0 Issue date: 2015-11-10 Issued by: Ring 3 Letbane I/S Approved by: AGF Anne-Grethe Foss Checked by: PAMA Patrik
90 Brighton Road, Surbiton, Surrey
90 Brighton Road, Surbiton, Surrey Civil and Structural Engineering Basement Feasibility Report Mixed Use Scheme 108802-REP-002 March 2015 Contents 1. Executive Summary... 3 2. Site Description and Constraints...
This is why the Swedish Transport Administration was formed
This is why the Swedish Transport Administration was formed An approach that embraces all means of transportation A clearer customer perspective Strong regional ties A more efficient organisation To support
Chapter 13 Route Window C11 Isle of Dogs station. Transport for London
Chapter 13 Route Window C11 Isle of Dogs station ISLE OF DOGS STATION 13 Route Window C11 Isle of Dogs station Introduction 13.1 The Crossrail Line lies completely in tunnel through this section, just
Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations
Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Cambridge City Council - East Cambridgeshire District Council - Fenland District Council, Huntingdonshire
Appendix E Construction Methods
Appendix E Construction Methods Administrative Draft Environmental Impact Statement/Environmental Impact Report E-i Appendix E Construction Methods Table of Contents APPENDIX E CONSTRUCTION METHODS...
Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy
Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy ITA CBT Seminario SAT2008 Sao Paolo, June 25 2008 1 Contents Peculiar aspects of Tunnelling in urban areas
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,
Let s talk about innovative risk solutions for your tunnel projects
Strong visions, good connections Let s talk about innovative risk solutions for your tunnel projects TARGETED SOLUTIONS Insurance covers tailored to your needs Covers at a glance The international engineering
Buildings Construction Procurement Strategy
Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides
Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
Executive Summary. Executive Summary. Port of Miami Tunnel
Executive Summary Executive Summary Port of Miami Page 1 of 5 BTM JV shares the Chesapeake Bay Bridge and District s vision to develop a parallel tunnel beneath the Thimble Shoal Channel. By any standard,
Inframodel 3 (4-5) InfraFINBIM / buildingsmart Infra Seminar 19 November 2013. Juha Hyvärinen, Senior Scientist
InfraFINBIM / buildingsmart Infra Seminar 19 November 2013 Inframodel 3 (4-5) Juha Hyvärinen, Senior Scientist VTT Technical Research Centre of Finland 2 The Finnish Inframodel To improve information exchange
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF
Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
A GUIDEBOOK TO THE CHANGES IN BUILDING CONTROL 2007/2008. Building and Construction Authority
A GUIDEBOOK TO THE CHANGES IN BUILDING CONTROL 2007/2008 Building and Construction Authority For reference, this is the version as of 31 Mar 2009 Copyright @ 2009 Building and Construction Authority, Singapore.
Frequently asked questions July 2014
Carlton Main Sewer Frequently asked questions July 2014 We understand you might have some questions for us, so we ve prepared a selection of FAQs to provide you with some general information. If you would
Selected aspects of the Danish repository program
www.oeko.de Selected aspects of the Danish repository program Views from the outside potentially (hopefully) helpful to improve the Danish discussion Gerhard Schmidt Dialogue Meeting Copenhagen, March
AARHUS LIGHT RAIL PROJECT
AARHUS LIGHT RAIL PROJECT Integrating Land Use and Public Transportation Planning Workshop, 10 October, 2012 Ole Sørensen Project Manager Light Rail Secretariat Established in 2007 by 8 municipalities
CONTRACTORS ALL RISKS INSURANCE PROPOSAL FORM CONTRACTORS ALL RISKS INSURANCE PROPOSAL FORM
Allied Cooperative Insurance Group (ACIG) شركة املجموعة املتحدة للتاأمني التعاوين ) أ سيج( CONTRACTORS ALL RISKS INSURANCE Call us: 920012331 www.acig.com.sa CONTRACTORS ALL RISKS INSURANCE UCONTRACTORS
FEHMARN BELT Forecast 2002
Trafikministeriet, København Bundesministerium für Verkehr, Bau- und Wohnungswesen, Berlin FEHMARN BELT Forecast 2002 April 2003 FTC Fehmarnbelt Traffic Consortium FTC Fehmarnbelt Traffic Consortium BVU
Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples
Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: [email protected]
CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST
CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,
VEHICLE CROSSOVER INFORMATION PACK
VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)
Getec. The Geo Structural Monitoring Experts
Getec The Geo Structural Monitoring Experts Getec Getec specialises in providing instrumentation and monitoring solutions for a wide range of applications. We focus on producing reliable, repeatable data
Permafrost in Marine Deposits at Ilulissat Airport in Greenland, Revisited
NICOP IX International Conference on Permafrost University of Alaska Fairbanks 2008 Session 28: Cold Regions Infrastructures and Transportation Permafrost in Marine Deposits at Ilulissat Airport in Greenland,
BaltMet Network. Mayors of major metropolises in the Baltic Sea Region unified for the competitiveness and innovation of the Region
BaltMet Network Mayors of major metropolises in the Baltic Sea Region unified for the competitiveness and innovation of the Region Berlin Copenhagen Helsinki Malmö Oslo Riga Stockholm St.Petersburg Tallinn
MELBOURNE METRO RAIL NEWSLETTER
Commercial Rd MELBOURNE METRO RAIL NEWSLETTER SHAPING MELBOURNE S RAIL FUTURE Welcome to the first edition of Melbourne Metro Rail News. This newsletter will keep you up-to-date on progress of the Melbourne
Technical feasibility of the reconfiguration of 8-m class telescopes
Bulletin de la Société Royale des Sciences de Liège, Vol. 74, 5-6, 2005 Technical feasibility of the reconfiguration of 8-m class telescopes M. Kraus European Organisation for Astronomical Research in
State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work
Description of work Sicily Tunnel Caltanissetta Year: 2013 In progress Client: Anas s.p.a. Contractor: Empedocle 2 s.c.p.a. Total length: 28 km Works amount: 175.000.000,00 Activities: Construction design
PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions
PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY Introduction and Assumptions 1. The existing section 27 Mineral Extraction of the Zoning Ordinance would remain and continue
Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain
Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37
DATA MANAGEMENT SYSTEM FOR TUNNELLING
DATA MANAGEMENT SYSTEM FOR TUNNELLING A working tool for data acquisition, visualization AND Reporting 2 IRIS Integrated Risk and Information System A single software solution for integrated data management
Design and Construction of Auger Cast Piles
Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN [email protected] - www.geotill.com CONTENTS 1.
WTM ENGINEERS. Consulting Engineers
WTM ENGINEERS Consulting Engineers WTM COMPANY PROFILE FEATURES foundation 1936 employees 230 projects 12.000 turnover 20.000.000 SERVICES consulting / structural design / project design / geotechnical
Banebranchen New line Copenhagen-Ringsted
Banebranchen New line Copenhagen-Ringsted 11th May 2011 High speed Copenhagen-Ringsted High speed Copenhagen Ringsted first phase of The one-hour target Caracteristics Denmark s first High-Speed railway,
Flat-land large-scale electricity storage (FLES) Lecture at the European Energy Conference 2012, Maastricht
EPJ Web of Conferences 33, 04010 (2012) DOI: 10.1051/ epjconf/ 20123304010 C Owned by the authors, published by EDP Sciences, 2012 Flat-land large-scale electricity storage (FLES) Lecture at the European
Kuala Lumpur conquers the underground. Using pioneering tunnelling technology made in Germany.
Herrenknecht All Around Multi-mode TBM Story Page 1 / Story Kuala Lumpur conquers the underground. Using pioneering tunnelling technology made in Germany. Author: Adrian Greeman Photography: Ming Thein
ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill
ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION
How do we plan for the future Øresund region?
How do we plan for the future Øresund region? VISION FOR THE ØRESUND REGION 2070 Skanska in brief Founded in 1887 International presence since 1897 Listed on Nasdaq Stockholm 2014 revenue: SEK 145 billion
REPORT FEHMARNBELT FIXED LINK. Financial Analysis - February 2003. Main Results. March 2003. Prepared by Sund & Bælt / Femer Bælt
REPORT FEHMARNBELT FIXED LINK Financial Analysis - February 23 Main Results Prepared by Sund & Bælt / Femer Bælt March 23 A division of Sund & Bælt Holding A/S Vester Søgade 1 DK-161 Copenhagen V Tel.
Railway Development in Ethiopia
Ethiopian Railways Corporation (ERC) Railway Development in Ethiopia Yehualaeshet Jemere (MSc. CEng) Addis Ababa-Djibouti Railway Project Manager Railway Development in Ethiopia Introduction National Railway