Developing Critical Path Method Scheduling (CPM)
|
|
- Andrea Blankenship
- 8 years ago
- Views:
Transcription
1 Developing Critical Path Method Scheduling (CPM)
2 Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3
3 Pretest 2. Which is not a widely recognized type of scheduling method? a. CPM b. Linear c. Vertical d. Bar
4 Pretest 3. Which of the following is directly affected by project scheduling? a. Time b. Cost c. Work Flow d. Man Power e. All of the above
5 Pretest 4. Of the three (3) main scheduling methods, which one uses relationships between activities? a) Linear b) CPM c) Bar
6 Pretest 5. Which scheduling method is the most commonly practiced? a) Bar b) Vertical c) Linear d) CPM
7 Pretest 6. Total Float is the amount of time an activity can be delayed without delaying completion date of the project. a) True b) False
8 Pretest 7. TheWork Breakdown Structure (WBS) shouldbe used for identifying the activities and for organizing the schedule. a) True b) False
9 Pretest 8. Which of the following should be used in determining activity durations? a) Historical Data b) Manuals c) Experience d) Field recommendations e) Allof the above
10 Pretest 10. Who should do project scheduling? a) Project Manager b) Owner c) Superintendent d) All of the above
11 Pretest 9. There isalwaysmorethanonecorrect one logicfor completion of a project. a) True b) False
12 Purpose and Background for Construction Schedules Determine reasonable and accurate contract time for construction Contract time is the maximum time allowed in the contract for completion of all work contained in the contract documents. Project Scheduling is the process of: Identifying the activities necessary to complete the project Assigning realistic durations to each activity Establishing start and finish dates for each activity
13 What Does a Schedule Do? Helps the owners in planning during the development of the project Public Notifications Road Closures Construction sequencing, phasing & milestones Alternate bid schedules Tool for comparison
14 Effects of Insufficient Contract Time Bid prices may be higher Unusual number of time overruns Contractor Claims Missed milestones
15 Effects of Excessive Contract Time Cost inefficiencies by the contractor Public may be inconvenienced unnecessarily Travel on unsafe roadways for and extended period of time * If the time set is such that all work on a project may be stopped for an extended periodand the contractor can still complete the project on schedule time allowed was excessive
16 Schedule Guidelines When shouldyou create your first schedule? Schematic Drawings 30% Design Development 50% Submittal Drawings 90% Update the schedule for all PS&E submittals
17 Determining Contract Time Production Rate What is Production Rate? The quantity produced or constructed over a specific time period. Why is this important? Helps determine appropriate completion time. Production rates may vary considerably depending di on project size, location and setting.
18 Determining Contract Time Production Rate Establishing Production Rates Divide the total quantity of an item by the number of days/hours used to complete the item. Base production rates upon a 5 day work week/ 8hr crew days/ our per piece of equipment Historic data DOT data RSMeans Cost Data books
19 Hot Asphalt Concrete Pavement Production Rate: HACP Paving (max) 1,980 tons/day HACP Paving (min) 1,320 tons/day Starting Rate = ( )/2 = 1,650 tons/day (8 hour day) Projects Specifics: Cold Temps Remote Location
20 Other Factors Affecting Contract Times Effects of Traffic Curing Times / waiting periods between paving courses Setup/mobilization/special equipment Seasonal Limitations Conflicting Operations Submittal review Times Fabrication Times Lead times Long lead Items Holidays Number of Crews/crew Size Environmental Temporary construction Soils
21 Steps for Creating CPM Schedules Define the Work Day Define the Project Calendar & Task Calendar Identify, Group and Sequence the Activities iii Set activity Durations Link Activities Documentation Update
22 Defining the Work Day Work hours establish the daily work times. Standard work day is an 8 hour day.
23 Defining the Project Calendar Defines project s work and non work days Saturdays, Sundays, Holidays Other Contractual non work days Local Events Task Calendars define work that can only be performed at a specific time and date.
24 Activities A key factor in any realistic schedule is to include the right activities. Consider each project as unique. Break project scope into individual id activities iti Work Breakdown Structure (WBS) should be used for identifying the activities and for organizing the schedule The number of activities depends upon the complexity of the project Once Activities are identified and grouped, determine the general sequencing of the activities.
25 Staking Typical Activity Inclusions & Exclusions Only show staking tasks that are necessary to start the project (e.g., clearing limits and slope stakes). Clearing & Grubbing Show only work needed to begin major activities Erosion Control In place items before major grading operations Earthwork Break out rock excavation asa a separate activity
26 Typical Activity Inclusions & Exclusions Pavement Structure Items Combine associated items as one work activity Separate major structure items such as; base course and asphalt Bridge Activities Show by phase of construction foundation, substructure, superstructure Sub Excavation Combine into one activity it Drainage Show individual culverts
27 Typical Activity Inclusions & Turf Establishment Show as one item Signage & Striping Exclusions Combine all permanent traffic control signing and striping into one activity. Guardrail Combine into one activity
28 Activity Durations Setting durations is a critical step to creating a reasonable schedule. Factors effecting time should be taken into consideration. Adjust activity ii durations based on production rates. Try and limit the duration for any activity to 20 days.
29 Link Activities Determine activity relationships Late Finish (LF): The latest time an activity can be finished. Late Start (LS): The latest time an activity can be started without delaying completion of the project. LS = LF D Total Float: The amount of time an activity can be delayed without delaying completion date of the project. TF = LF EF + LS ES Free Float: The amount of time an activity can be delayed without delaying early start time of the following activity Critical Path: A series of connected activities with each activity having zero float (free, and total) time.
30 Link Activities The order in which activities will be performed is called logic How one activity relates to another activity is called logical relation Finish to Start Finish to Finish Start to Start Defining proper logic requires understanding of the project There is always more than one correct logic for completion of a project.
31 Documentation Document any assumptions: Production rates Equipment Types Quantities Crews Follow the logic
32 Update A Schedule is only a tool!
33 Check List Reviews/Submittals Are there critical submittals? What Time is needed? Are there critical testing periods & how long? Are there critical review times & how long? What are the assigned calendars for submittals & review times? What are the logical connections between review activities and contractor s actual work? Procurement activities Time for reviewing false work plans, shop drawings, post tensioning plans, mix designs, etc.
34 Check List Permits Are permits required? Time to obtain necessary permits?
35 Check List Specific Activity Requirements Additional time for obtaining specialty items or materials with long lead requirements (i.e. Traffic Signal Equipment) Curing time and waiting periods between successive paving courses or between concrete operations Embankment settlement periods orembankment surcharges. Coordination with Utilities False work & Shoring activities Punch list and cleanup activities
36 Check List Material/Product Testing and Delays Government/Owner furnished material Trial shafts or piles Sample walls Time of fabrication fbi of structural t steel and other specialty items Staining, painting or other samples needing approvals
37 Check List Construction Limitations and Requirements Haul characteristics Type of earthwork (sliver cuts, benching) Work area restrictions Equipment congestion Allowable bad weather days Material availability Labor shortages and resource loading Traffic Volumes Traffic staging events (closures, detours) Critical interface activities (utilities, RR) Restrictions for nighttime and weekend operations Conflicting operations of adjacent projects, both public and private Are the NTP and Project Closeout activities shown?
38 Check List Project Commitments ts Environmental Commitments Winter season Clearing, grubbing, grading restrictions Noise restriction SWPPP Seasonal limitations for certain activities Project Calendar Requirements Work kweek Holidays Other non working times
39 Check List Does the final schedule include/show: Critical Path? NTP date and completion date Entire scope of work, all activities in plans and specs? Construction Staging and mobilization? Realistic duration of individual activities? Maximum 20 day duration for any one activity? Activities have at least one predecessor and 1 successor? No negative lag for activities/ Project Duration, Interim Milestones, Black out dates, contract work days?
CFL Guidelines for Developing October 2006 Critical Path Method Schedules (CPMs)
CFL Guidelines for Developing Critical Path Method Schedules (CPMs) Table of Contents SECTION 1 INTRODUCTION 1.1 Purpose and Background for Construction Schedules 1.2 Construction Schedule Submittal Guidelines
More informationCRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
More information763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
More informationFLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR
FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration
More informationS-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.
S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. 1803.1 All SCHEDULES A General Requirements This section contains
More informationMODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
More informationSpec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
More informationMATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
More informationMnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationChapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
More informationEXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
More informationWILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)
BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset
More informationScheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
More information108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
More informationCollaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
More informationSPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
More informationPN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
More informationProject Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
More informationTest Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
More informationTest Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
More informationSECTION 01310 COST LOADED CRITICAL PATH SCHEDULE
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in
More information01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationMnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
More informationThe CM Perspective. Preconstruction Phase
The CM Perspective The Elements of Project Management Preconstruction Phase Preconstruction: Setting the Project Up to Succeed Project Plan Critical Milestones Define all major deadlines and critical dates
More informationMemorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
More informationCalifornia Department Of Transportation. Class # G0C094
California Department Of Transportation ADVANCED CPM SCHEDULING WITH SURETRAK Class # G0C094 ADVANCED CPM SCHEDULING WITH SURETRAK September 2003 SureTrak is a registered trademark of Primavera Systems,
More informationProject Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
More informationSECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationDashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
More informationModule 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
More informationTime Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
More informationSECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project
More informationThe Change in Status is used to start, suspend or resume time charges on a project or to indicate that the project is completed.
CONSTRUCTION STATUS The Change in Status is used to start, suspend or resume time charges on a project or to indicate that the project is completed. Depending on the type of completion date shown in the
More informationImportance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationPrecedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
More informationMECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework
More informationAppendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
More informationU.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I
VA U.S. Department of Veterans Affairs Facilities Management Critical Path Method design DECEMBER 2012 Volume I Design Manual for & TABLE OF CONTENTS, Volume I 1. INTRODUCTION... 3 1.1. Purpose and Scope...
More informationBUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS
Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development
More informationStructures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
More informationChapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
More informationScheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group
Scheduling Best Practices Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Paul Brough has experience in multiple phases of project management, including
More informationScope of Work Construction Inspection and Materials Testing Services
Glenwood Resident Engineer 202 Centennial Drive Glenwood Springs, CO 81601 Scope of Work Construction Inspection and Materials Testing Services Estimated Start Date: November 1, 2015 Region 3 Project:
More informationLinear Schedules for Tunnel Projects
Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationCRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING
CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can
More informationFDOT Specifications List
FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...
More informationCost Estimating Guideline December, 2015
Cost Estimating Guideline December, 2015 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -
More informationPROJECT CONTROLS NEWSLETTER SCHEDULING BEST PRACTICES SERIES
PROJECT CONTROLS NEWSLETTER SCHEDULING BEST PRACTICES SERIES The sixth article in the Scheduling Best Practices series is Multiple Calendars Blessing or a Curse. Our colleagues, Jodi Staub, Senior Consultant
More informationPROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
CHAPTER 5 - Construction Project Management Contents Introduction... 2 Construction Contract Management... 2 CEI Contracts... 3 Community Awareness Plan... 7 Alternative Contracting Methods... 8 Warranty
More informationBUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS
Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development
More informationSECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More information8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
More informationHow to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013
How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table
More informationSCHEDULING AND PROJECT MANAGEMENT
SCHEDULING AND PROJECT MANAGEMENT Chapter Survey Scheduling Process Scheduling Methods Scheduling and cash management Who is the Project Manager Project Supervisory Team Project Life Cycle Tracking the
More informationME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
More informationConstruction Planning & Scheduling
University of Delaware Department of Civil and Environmental Engineering CIEG 467-013 Construction Planning & Scheduling Bob Muir, PE Construction Planning & Scheduling Necessity for Good Scheduling Time
More informationCSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
More informationSOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule
Contract No. CPM Schedule Project Id SOUTH FLORIDA WATER MANAGEMENT DISTRICT General Contractor CPM Schedule Project Name NTP DATE Data Date CONTRACT DURATION 0 ORIGINAL CONTRACT AMOUNT Date Schedule Received
More informationCONSTRUCTION COST MODELS
CONSTRUCTION COST MODELS Prepared by: The New England Environmental Finance Center For the Maine Department of Transportation Office of Environmental Planning November 1, 2010 The following are a series
More informationAn Introduction to the Management Principles of Scheduling
College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923
More informationStatewide Scheduling Engineers Meeting August 8-9, 2006 Turkey Lake Plaza
Statewide Scheduling Engineers Meeting August 8-9, 2006 Turkey Lake Plaza Attendees: Richard Massey(SCO), Brenda Haygood(D-2), Jimmy Miller(D-3), Robert McCracken(PBS&J-D-3), Abel Sierra(D-5), Luis Lopez(D-6),
More informationScheduling Best Practices
In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules
More informationCHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS
33 CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS 4.1 BASICS OF LINEAR SCHEDULING The LSM is a graphical technique in which the locations or the length of the linear project is indicated
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationSE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
More informationCONSTRUCTION PERMIT REQUIREMENTS
CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department
More informationEgypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationPERCEPTION PERT-PAC Using Microsoft Project 2000
PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000
More informationAlexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE
SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.
More informationCambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationBasic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
More informationChapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationReview of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs
Agenda Topics: 1. Oracle/Primavera buyout Within the last year, Oracle bought Primavera. Primavera support has been tailored to Oracle s standard. stead of initially speaking to a support representative,
More informationWORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
More informationAgenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016
CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision
More informationInformation Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
More informationFDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES
NAICS CODE Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway (includes 300, 320, 327, 330, 334, 336, 337, 338) Application of prime and tack coats, leveling surfaces and
More informationScheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
More informationThe work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
More informationBaseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015
Donald R. McNatty, PSP FAACE November 18, 2015 1 Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order to preserve the quality of the audio for all attendees.
More informationOperational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
More informationProject Scheduling. with Primavera P6. Training Manual
Project Scheduling with Primavera P6 Training Manual Development History June 2003, CPM Scheduling with SureTrak training materials developed by URS Corporation for Caltrans. SureTrak is a registered trademark
More informationNOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW
NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in
More informationSITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)
More informationCAREY L. STECKLER HIGHLAND ELEMENTARY SCHOOL ADVISOR: DR. RILEY TECHNICAL ASSIGNMENT 3 15 NOVEMBER 2004 CONTENTS
CAREY L. STECKLER HIGHLAND ELEMENTARY SCHOOL ADVISOR: DR. RILEY TECHNICAL ASSIGNMENT 3 15 NOVEMBER 2004 CONTENTS A. SUMMARY... 1 B. SITE LAYOUT PLANNING... 2 C. TEMPORARY UTILITIES... 2 D. DETAILED SYSTEMS
More information2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the
More informationShould I Resource Load My Schedule?
Should I Resource Load My Schedule? th Annual International Integrated Program Management Conference November -, Copyright All Rights Reserved The Goals Of Project Management: to make the most effective
More informationHow To Build A Road In A Townhouse
FDOT DBE CERTIFICATION SPECIALTY/ SHEET WITH CAP SIZES Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway $ 22.41 Application of prime and tack coats, leveling surfaces and
More informationState of Louisiana. Department of Transportation and Development CONSTRUCTION CONTRACT ADMINISTRATION
State of Louisiana Department of Transportation and Development CONSTRUCTION CONTRACT ADMINISTRATION AUGUST 2005 TABLE OF CONTENTS I. General Information Page Numbers 1.1 Introduction 1 1.2 Expectations
More informationExhibit A Scope of Work
Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW
More informationHelen Mercury Mine EE/CA OPINION OF PROBABLE COST
G Cost Estimates Helen Mercury Mine EE/CA Alternative 2: Limited Action 3 Minor Road Improvements 4 Clear & Grub diversion channel areas 5 Surveying 6 Cleanup & Demobilization 7 Pull back of material 8
More informationState Materials Laboratory 2013 Performance Measures. Quality Assurance Section
The State Materials Laboratory provides specialized materials testing and engineering expertise in construction materials, and materials quality acceptance programs in support of the state highway system
More informationLOCAL AGENCY CONTRACT ADMINISTRATION CHECKLIST
LOCAL AGENCY CONTRACT ADMINISTRATION CHECKLIST The following checklist has been developed to ensure that all required aspects of a project approved for Federal funding have been addressed and a responsible
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More information1. Interpretation of this Schedule
Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer
More information02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.
C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate
More informationSTORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local
More information