Procurement Management Challenges in Gas Projects of Iran
|
|
|
- Monica Beasley
- 10 years ago
- Views:
Transcription
1 Proceedings of the 2010 International Conference on Industrial Engineering and Operations Management Dhaa, Bangladesh, January 9 10, 2010 Procurement Management Challenges in Gas Projects of Iran Mohammad Vafaiee, Mohammad Saleh Owlia, and Mohammad Ali Vahdat Dept. of Industrial Engineering Yazd University of Iran Mohsen Vafaiee Senior Expert of Procurement Contracts Abstract Procurement problems are usual in gas projects in Iran, resulting in contractual claims and increased project time and cost. This study was aimed to collect the perceptions of gas projects practitioners on how significant are the procurement problems using mean score method. The results of the study showed that the respondents except suppliers somehow admit their own shortcomings. The client and contractor groups held extremely different perceptions and a quite strong consensus was found between the management contractor and consultant groups on the significance of the various causes of delay. It was also observed that financial problems got the highest significance and contractor problems got the lowest significance in the procurement process of gas projects. Keywords Procurement Management, Delay factors, Gas Projects, Iran 1. Introduction National Iranian Gas Company (NIGC) was established in 1965 as one of the four main companies affiliated to the Ministry of Petroleum of Islamic Republic of Iran. This Company from the beginning of establishment up to now, in line with socioeconomical development growth and utilizing natural gas as one of the important sources in supplying fuel and energy production and obtaining some part of the required exchange, has gradually achieved various capabilities, competences, resources and possibilities including specialized and efficient man power with theoretical and actual insight and nowledge as well as numerous advanced worshops, machinery equipment and tools to arrange companies operations. Before1970 Iranian Islamic revolution, Utilizing natural gas for households and also industrials was limited and the number of natural gas consumers wasn t more than At the present time NIGC as one of the most reliable gas companies endeavor widely in international aspects, besides internal activities and supplying industrial fuels, power plant and household consumers, although complied extensive planning was scheduled to procure the main part of required foreign currency for the country by gas exporting and investment to help the industrial development, by utilizing experts and professional in different sectors million cubic meter of gas is refined daily and ilometer high pressure of transmission pipelines were constructed more than ilometers of gas distribution networing were constructed and more than 7 million branches were installed in 747 cities, gas transmission to industrial regions and delivery of natural gas to 51 power plant units. In accordance with the fifth development plan, the significant role in supplying energy baset is corroborated [1]. This foresight is going to be fulfilled by lots of ongoing and upcoming mega projects that NIGC is considered as their client. Nevertheless, failure to comply with the existing procedures of project procurement processes caused many delays and overruns within these projects. Lots of non-preplanned contracts with too many contractors/suppliers in a great variety of project activities brought about a substantial confusion in handling these projects. Lac of a comprehensive plan for conducting the wor deliveries, from the first project inception up to the project closeout, made it constantly behind the schedule and led to so many side effects on project budget. On the other hand, the excessive delays in supply of standard material, engineered material and engineered equipment faced the construction phase with the undesired delays thereby unwanted extra costs. Procurement-oriented problems are referred to problems arising from inappropriately supplying the goods and services required for a project to be properly proceeded [2]. These problems normally lead to delay and cost overrun in implementation phase [3]. In project procurement process, a delay means a time overrun either beyond the contract date or beyond the date that the parties have agreed upon for the delivery of goods and services required for the project. O'Brien believed that in both cases, a delay is usually a costly situation [4].
2 From the client's point of view, as NIGC is a government agency, a delay generally leads to social inconvenience and loss of revenue, and to extreme affects, such on the national growth rate [5]. It also maes contractors suffer a loss of productivity, high disruption costs, and prolongation costs [6]. Picavance revealed that deficient procurement management can cause project delay and affect productivity [7]. Proper practice is thus essential during the planning and procurement of the goods and services and in the operation of the contract [8]. Many researchers have conducted surveys on the causes of delay in the construction industry; some of these are summarized in Table 1. As it is obvious from this table, in most of the cases "Procurement Problems" is one of the root causes of delay in worldwide construction projects. This problem can be particularly seen in the developing countries. In modern countries such as U.S. and Canada this factor has less intensity. Table 1. Summary of previous studies on causes of delay & cost overrun in construction industry Researchers Country Problems led to delay and cost overrun Baldwin (1971) U.S. 1. inclement weather 2. labor problems Arditi, et al. (1985) Turey 1. procurement problems 2. financial difficulties faced by public agencies and contractors 3. organizational deficiencies 4. delays in design wors 5. frequent change orders / design 6. considerable additional wor Semple et al. (1994) Canada 1. increases in the scope of wors 2. inclement weather 3. restricted access Mansfield et al. (1994) Nigeria 1. improper financial and payment arrangements 2. poor contract management 3. procurement problems 4. inaccurate cost estimates 5. fluctuations in cost Ogunlana et al. (1996) Thailand 1. procurement problems 2. changes of design 3. liaison problems among the contracting parties Mohan R. Manavazhi. et al.(2002) Nepal 1 procurement problems 2. failure to pay for completed wors 3. poor contract management Al-Khall & Al-Ghafly (2006) Saudi Arabia 1. cash flow problems / financial difficulties 2. difficulties in obtaining permits 3. procurement problems Lo T. Y. et al.(2006) Hong Kong 1. delays in payment by agencies to contractors 2. fluctuations in materials, labor and plant costs Murali Sambasivan. et al.(2007) Malaysia 1.Unrealistic contract s conditions 2.Client interfering 3.Slow mae decision G. Sweis. et al. (2008) Jordan 1. financial problems 2. change orders / design 3. inclement weather 4. change public rules 5. procurement problems A preliminary investigation was conducted in early 2005 by the Planning and Development Division of NIGC to examine the main reasons for project delays in gas mega projects in Iran that were completed between 1998 and 2004 [9]. It was observed that no gas mega project was completed within schedule, with average overrun time exceeding 60% and average overrun budget going beyond 20%. This study was aimed to gather the perceptions of gas industry practitioners on how significant the causes of procurement-oriented problems are by using of some statistical analyses. 2. Research Methodology The impacts and causes of procurement-oriented problems of Iranian gas mega projects were first examined and identified through a relevant local literature review and by conducting a pilot study that sought advice from experienced practitioners woring in this field. In order to identify the right persons for interview, the organizational structure for Iranian gas mega projects was initially recognized (see Fig. 1).
3 As indicated in figure 1, client (NIGC) contracts with an external engineering firm to provide design and technical requirements. On the other hand, client contracts directly with an MC to provide overall project management for the project. MC contracts directly with a supplier and a PC (Procurement and Construction) contractor to provide Procurement management and construction/installation management/services for the project. Client (Owner) Engineering Consultant MC (Management Contractor) PC Contractor Supplier Fig.1.Organizational Structure for Iranian Gas Mega Projects In view of the above, the client, the MC, the contractor, the consultant engineering and the supplier were identified as the main staeholders seriously involved in the project procurement processes and thus 30 interviews were arranged with these parties ey contact persons to obtain exact information toward the project procurement-oriented problems. The project main parties at interest in our samples involved in the procurement process that were included in this study are summarized in table 2. Client(NIGC) MC(Management Contractor) Contractors Engineering Consultants Suppliers Table 2. Main parties at interest in the procurement process IGEDC(Iranian Gas Engineering and Development Company) IGCC(Iranian Gas Commercial Company) Ghods Niroo Co. Iran Ertebat Co., Peysa Co, Khatamolanbia Co. Pars Co., Bina Co. Profile Saveh Co., Godahtar Co. It was tried to eep interviews on trac through asing relevant questions in a structured manner. In this regard, interview topics were categorized according to the following items: Major procurement-oriented problems in viewpoint of interviewees. Causes of the problems. As a result, 30 common procurement-oriented problems (see Table 3) related to Iranian gas mega projects were selected for furtherr examination in this study. Based on the information obtained from interviews, a set of questionnaires was formulated in which the procurement-oriented problems were grouped into seven categories, accordingly designated with code names. In this survey, five groups of practitioners were defined, comprising a client group (including IGEDC and IGCC), a consultant group, a MC group, a contractor group (including contractors who can tender for contracts of scope involving both P & C portions and who are listed in the NIGC gazette, listed under the procurement and construction categories for the purpose of carrying out gas mega projects) and a supplier group. The questionnaire contained 30 identified procurement-oriented problems for which the respondents were ased to indicate their perceived magnitude of significance with reference to a corresponding 1-5 scale as following: 1=not significant (NS) 2=slightly significant (SS) 3=moderately significant 4=highly significant (HS) 5=extremely significant (ES) A total of 74 copies of the questionnaire were sent to randomly selected samples. The samples were selected from publicly available sources, including the NIGC and its subsidiaries, also consulting engineering companies
4 and professional contractors as well as MC and suppliers companies woring in the gas industry. As a result, 65 responses (see Table 4) were received, giving a response rate of 88%. Code Name CL1 CL2 CL3 CL4 CL5 CL6 EN1 EN2 EN3 EN4 CN1 CN2 CN3 MS1 MS2 MS3 IS1 IS2 IS3 IS4 IS5 FB1 FB2 FB3 FB4 LC1 LC2 LC3 LC4 LC5 Table 3. List of 30 identified procurement-oriented problems in Iranian gas projects Category of Problem Client Related Consultant Related Contractor Related Supplier Related Infrastructure Financial and Baning Legal and Contractual Procurement-oriented problem statement Slow coordination & seeing of approval from concerned authorities Decentralization purchases and procurement in a little size Exceptionally low bids for E, P or C portions Deficient project management & supervision by MC Taing project from illegal way Unrealism in predicting project duration by NIGC Continual changes in engineering phase To lengthen process of converting one indent to one order Delay in investigation of procurement technical documents Poor basic engineering(design) Inattention about after sales services such as guaranty and warranty Inexperienced contractor (both technically & commercially) Incapable control to logistic processes Difficulties in supplying row material Inactivate R&D department in some suppliers Privatization of some public companies Directors frequent replacement thus company's policy alteration Insufficient supportive legislation forcing local bans to financially assist gas industry Political constraints such as boycott Impacts of the Act of 51% domestic portion for the project budgetary plan Tremendous domestic inflation rate and its impact on local manufacturers/suppliers productivity Existence of high ban rate Too complicated procedures for opening LC through Iranian issuing bans thereby excessive delays Lac of enough financial resources to finance project Not payment of facilitates to suppliers by domestic bans in return project contract and request self assurance To lengthen of preparing and offering bid s documents To be sideway of NIGC s contracts To request heavy assurance in content of contract Replacement of Bids Law with national petroleum company s regulation and there are some obscurities Inability of adjustment in domestic transaction s contracts Table 4. Summary of Response Rates for Different Groups Group Questionnaire Sent Completed Questionnaire Received Response Rate (%) Client Consultant Contractor MC Supplier Overall Results and Discussion The respondents in the client, MC, consultant, supplier and contractor groups were from different woring positions and their woring experience ranged from 4 to 35 years. It is also noted that the average woring experience of the respondents was 16 years in the gas industry, and thus the opinions are thought to reflect the real situation in the industry. The reliability of a measure illustrates its stability and consistency, which assists in evaluating the goodness of a measure. The reliability coefficient-cronbach's α- obtained with SPSS software, measures how well a set of variables or items measures a single, unidimensional latent construct. If alpha is high (0.70 or higher), then this suggests that all of the items are reliable and the entire test is internally consistent. The measure, therefore, were
5 considered to be reliable. Furthermore to determine the validity of instrument, factor analysis was applied [10]. KMO index was used to test sufficient correlations between each factor s variables to justify the application of factor analysis (if KMO equal or higher than 0.6). Table 5 shows the results of reliability and validity tests. Table 5. Summary of Approval Factor Analysis for different causes of delay Factor number Reliability Alpha Validity of sufficient sampling KMO BT Bartlett's Test of Sphericity d.f Sig ing of Significance and Effectiveness Using Method The following equation is utilized to calculate the mean score for each identified problem: [11] MS i = (f S) (1) N Where S = score given to each problem by the respondents f = frequency of responses to each score for each problem N = total number of responses in the respective groups for the respective problem i = respective problem To suit the case of this study, this formula was adopted to calculate the significance of the procurementoriented problems, and weights were put onto individual scores (ES=5, HS=4, MS=3, SS=2, NS=1). The mean scores of the procurement-oriented problems were calculated and the relative ranings of their significance were obtained in descending order (see Tables 6). The overall mean scores (OMS) and individual ranings are also presented there. These were calculated using the following equation: 5 OMS = MS ij ( Ni ) (2) i=1 N 1 + N 2 + N 3 + N 4 + N 5 Where i = Group 1, 2 5; MS = mean score; Ni = number of respondents in each group j = jth item in a group. The respondents perceptions of the significance of procurement-oriented problems have been summarized in Table 7. In this table, the mean scores of the problems are presented within defined categories and raned according to significance. It was observed that the viewpoints held by the Client, MC, contractor, consultant and supplier groups toward the significance of the various problems were different. This is illustrated by raning of the categories in Table Percentage Agreement and Disagreement Tommy Y. Lo et al. (2006) proposed equations (3) and (4) to evaluate the extent of agreement in raning between different pairs of respondent groups, and called them percentage disagreement (PD), and the percentage agreement (PA) by the following equations: N PD = 100x R i1 R i2 / R x1 R y2 (3) i=1 Where i=1,2,...., N items and Ri1 and Ri2=raning of the ith item in groups 1 and 2, and lastly x and y are represented the raning of the items, y=n x+1 (i.e., if x=1 and N=30, y=30 1+1=30) PA = 100 PD (4) Table 8 shows the results of PA and PD calculations based on the analysis of different staeholders views on the various causes of delay.
6 Tables 6. and ing of Significance of Identified Top Ten Procurement-Oriented Problems Identified Procurement-Oriented Problems Description Political constraints such as boycott Tremendous domestic inflation rate and its impact on local manufacturers/suppliers productivity Insufficient supportive legislation forcing local bans to financially assist gas industry Exceptionally low bids for E, P or C portions To lengthen process of converting one indent to one order Difficulties in supplying row material Not payment of facilitates to suppliers by domestic bans in return project contract and request self assurance Deficient project management & supervision by MC Inexperienced contractor (both technically & commercially) Continual changes in engineering phase Cod e Na me Client Consultant Contractor MC Supplier Overall IS IS IS CL 8 EN 2 MS 3 FB 4 CL 10 CN 1 EN Table 7. Overall s and ings of Categorized Procurement-Oriented Problems for Different Groups Procurement-Oriented Problems Client Consultant Contractor MC Supplier Overall Category Code OMS Financial and Baning FB Consultant Related EN Supplier Related MS Infrastructure IS Client Related CL Legal and Contractual LC Contractor Related CN Table 8. Percentage Agreement (PA) and Percentage Disagreement (PD) for Significance of Delay Stocholders Groups Percent Agreement(PA) Percent Disagreement(PD) Client & Contractor Client & Consultant Contractor & Consultant Client & Supplier Contractor & Supplier Client & MC MC & Supplier Supplier & Consultant Contractor & MC MC & Consultant Conclusion Referring to the results of the study based on assessment of top ten causes of delay showed that, respondents except suppliers tended to admit somehow their own shortcomings. The client and contractor groups held extremely different perceptions regarding the significance of various delay causes (with Percent
7 Disagreement=59%).And a quite strong consensus was found between the management contractor and consultant groups on the significance of the various causes of delay (with Percent Agreement=60%). It was also observed that financial problems got the highest significance and contractor problems got the lowest significance in the procurement process of gas projects. Three out of ten of the most significant procurementoriented problems were relevant to infrastructure issues including political constraints such as boycott (IS3), insufficient supportive legislation forcing local bans to financially assist gas industry (IS2), tremendous domestic inflation rate and its impact on local manufacturers/suppliers productivity (IS5). The results show that these problems have a substantial relationship with government and their solutions are out of stocholders authorities. In order to mitigate procurement-oriented problems and improve the overall productivity in the procurement processes of gas industry, the following strategies must be properly situated: 1. In order to force local bans to support gas industry, NIGC authorities are required to propose competent statutes to the parliament for approval enforcing bans to financially assist gas industry. In this regard, bans are demanded to assign suitable lines of credit comprising loans with low interest rate to the gas mega projects against the contract itself not in return of tremendous bonds. 2. To avoid excessive delays resulting from too complicated procedures for opening LC through Iranian issuing bans, bans are to adopt updated methods for opening LC and give up the traditional routine paperwor and administrative formalities. Utilization of E-LC (Electronic Letter of Credit) as applied nowadays in so many countries would help. 3. To prevent shortage of financial resources to finance project procurement activities, client is essential to foresee the entire budget, including contingency, required for the project proper completion and to negotiate the relevant financial institutions to establish necessary lines of credit at the pre-project planning phase. 4. Government authorities had better develop in advance the infrastructures for the location areas of gas mega projects. In this respect, NIGC is required to tae into account this critical issue at the pre-project planning phase to avoid inadequate utilities in the project location area for the procurement processes. 5. Although the price growth of raw material such as steel sometimes cannot be thoroughly predictable, Contractors should expedite ordering for long delivery items as well as engineered material/equipment that are composed of steel as a main component to reduce the impact of international growth in the price of these material. 6. In order to mitigate the side effects of political constraints such as sanction and/or embargo, client is to be more cautious about the technology selection and the licensing agency at the project outset not to include countries politically in conflict with Iran. Correspondingly, government has to establish better trade relationship with the modern countries uninvolved in the sanction/embargo against Iran. The authors believe that findings indicated in this study provide some guidelines and applicable information that gas industry staeholders can utilize to manage the procurement process of their mega projects properly and shed light on the mitigation of procurement-oriented problems and improve the overall productivity in the gas industry. Perhaps setting some milestones and priorities are required with reference to the survey findings so that improvement can be achieved in a progressive manner. References Chan, D. W. M., and Kumaraswamy, M. M. (1996). Reasons for delay in civil engineering projects The case of Hong Kong. Hong Kong Inst. Eng. Trans., 2(3), Baldwin, J. R. et al.. Causes of delay in the construction industry. J. Constr. Div., Am. Soc. Civ. Eng., 97(2), , Assaf, S. A. et al., Causes of delay in large building construction projects. J. Manage. Eng., 11(2), 45 50, Sadi A. Assaf, Sadiq Al-Hejji, Causes of delay in large construction projects, International Journal of Project Management, 24, , Arditi, D., et al., Reasons for delays in public projects in Turey. Constr. Manage. Econom., 3, , A.A. Aibinu, G.O. Jagboro, The effects of construction delays on project delivery in Nigerian construction industry, International Journal of Project Management, 20, , Murali Sambasivan, Yau Wen Soon, Causes and effects of delays in Malaysian construction industry, International Journal of Project anagement, 2007, 25, G. Sweis. Et al., Delays in construction projects: The case of Jordan, International Journal of Project Management, 26, , Ho Robert, Handboo of univariate and multivariate data analysis and Interpretation with SPSS (2006), 1st Ed., Chapman & Hall/CRC, pp Lo T. Y. et al., Construction Delays in Hong Kong Civil Engineering Projects, ASCE J. Constr. Engrg. and Mgmt., 132(6), , 2006.
Fatemeh Akbari* Master of Industrial Engineering Islamic Azad University, Zahedan Brench, Iran
To Design and to Present a Tool to Prevent Extra Expense Incurring in School Reconstruction Projects (A case study: Reconstruction Department affiliated to School Equipment and Development Unit in Sistan
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
Causes and Effects of Delays in Large Construction Projects of. Pakistan
Causes and Effects of Delays in Large Construction Projects of Pakistan M. Haseeb 1, a, Xinhai-Lu 1, Aneesa Bibi 1, Maloof-ud-Dyian 2, Wahab Rabbani 3 1 College of Public Administration, Huazhong University
Causes and effects of delays in Malaysian construction industry
International Journal of Project Management 25 (2007) 517 526 INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT www.elsevier.com/locate/ijproman Causes and effects of delays in Malaysian construction industry
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
International Journal of Project Management 21 (2003) 321 326 www.elsevier.com/locate/ijproman Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN M. Haseeb College of Public Administration, Huazhong University of Science and Technology, Wuhan, P.R. China, 430074.
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE Yakubu Adisa Olawale, Ph.D., MCIOB and Ming Sun, Ph.D. (Professor) Abstract Despite the availability
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand.
Assessment of Critical Success Factors for Construction Projects in Pakistan
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of
Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria
Journal of Construction in Developing Countries, 18(1), 53 72, 2013 Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Olajide Timothy Ibironke, Timo Olugbenga
Investment Opportunities and Privatization Programs of Iran:
In the Name of God Investment Opportunities and Privatization Programs of Iran: an idea whose time has come Dr. H. Kord Zanganeh Head of Iranian Privatization Organization (IPO) & Deputy Minister of Economic
Time Error in Project Management: A Case Study in Yanbu, Saudi Arabia
Business and Management Studies Vol. 2, No. 1; March 2016 ISSN 2374-5916 E-ISSN 2374-5924 Published by Redfame Publishing URL: http://bms.redfame.com Time Error in Project Management: A Case Study in Yanbu,
QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS
QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS João Guedes de Miranda Extended abstract Examination Committee Chairperson: Prof. Ana Paula Patrício Teixeira Ferreira Pinto
ijcrb.webs.com INTERDISCIPLINARY JOURNAL OF CONTEMPORARY RESEARCH IN BUSINESS NOVEMBER 2013 VOL 5, NO 7 Abstract
Relationship management training to improve the performance of individual public managers in Yazd Seyed Mohammad Reza Madani Department of Public Administration, Science and Research Branch, Islamic Azad
OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.
OTC 12979 Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for
Gharbeya Water and Wastewater Company - Background
Gharbeya Water and Wastewater Company - Background The Gharbeya company is located in the Delta Population: 4,170,000 Water coverage: 90% Water accounts: 730,000 Wastewater coverage: 35% Wastewater accounts:
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
Capital Projects and Construction: Building in Risk Management and Project Controls
Capital Projects and Construction: Building in Risk Management and Project Controls Making Every Dollar Count The global economic crisis sparked by the subprime mortgage debacle, the collapse of the securitized
Material waste in the China construction industry: Minimization strategies and benefits of recognition
INTERNATIONAL JOURNAL OF ENERGY AND ENVIRONMENT Volume 5, Issue 6, 2014 pp.717-722 Journal homepage: www.ijee.ieefoundation.org Material waste in the China construction industry: Minimization strategies
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project
WORKING CAPITAL MANAGEMENT
CHAPTER 9 WORKING CAPITAL MANAGEMENT Working capital is the long term fund required to run the day to day operations of the business. The company starts with cash. It buys raw materials, employs staff
MULTICRITERIA MAKING DECISION MODEL FOR OUTSOURCING CONTRACTOR SELECTION
2008/2 PAGES 8 16 RECEIVED 22 12 2007 ACCEPTED 4 3 2008 V SOMOROVÁ MULTICRITERIA MAKING DECISION MODEL FOR OUTSOURCING CONTRACTOR SELECTION ABSTRACT Ing Viera SOMOROVÁ, PhD Department of Economics and
The Study of Working Capital Strategies in Life Cycle of Companies
2013, World of Researches Publication Ac. J. Acco. Eco. Res. Vol. 2, Issue 4, 77-88, 2013 Academic Journal of Accounting and Economic Researches www.worldofresearches.com The Study of Working Capital Strategies
FACTORS AFFECTING CONSTRUCTION ORGANIZATION QUALITY MANAGEMENT SYSTEM IN THE MALAYSIAN CONSTRUCTION INDUSTRY
FACTORS AFFECTING CONSTRUCTION ORGANIZATION QUALITY MANAGEMENT SYSTEM IN THE MALAYSIAN CONSTRUCTION INDUSTRY Ilias Said 1, Abd Rahman Ayub 2, Arman Abd Razaki 3 & Tee Kuan Kooi 4 1, 3&4 Universiti Sains
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI)
STATE NUCLEAR ENERGY CORPORATION ROSATOM Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI) A. E. Sitnikov Rosatom/ Rosenergoatom Russia Atomex-Asia
IMPROVING THE CRM SYSTEM IN HEALTHCARE ORGANIZATION
IMPROVING THE CRM SYSTEM IN HEALTHCARE ORGANIZATION ALIREZA KHOSHRAFTAR 1, MOHAMMAD FARID ALVANSAZ YAZDI 2, OTHMAN IBRAHIM 3, MAHYAR AMINI 4, MEHRBAKHSH NILASHI 5, AIDA KHOSHRAFTAR 6, AMIR TALEBI 7 1,3,4,5,6,7
Relationship between Factors of Construction Resources Affecting Project Cost
Modern Applied Science; Vol. 7, No. 1; 2013 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Relationship between Factors of Construction Resources Affecting Project
STUDYING OF THE EFFECT OF INFORMATION TECHNOLOGY ON SUPPLY CHAIN PROCESSES AND ORGANIZATIONAL PERFORMANCE (CASE STUDY: PARSIAN GAS REFINERY COMPANY)
Pinnacle Research Journals 1 STUDYING OF THE EFFECT OF INFORMATION TECHNOLOGY ON SUPPLY CHAIN PROCESSES AND ORGANIZATIONAL PERFORMANCE (CASE STUDY: PARSIAN GAS REFINERY COMPANY) KHODAKARAM MOHAMMADI CHESHME
OPTIMAL ALLOCATION OF CONSTRUCTION PLANNING RESOURCES
OPTIMAL ALLOCATION OF CONSTRUCTION PLANNING RESOURCES By Olusegun O. Faniran, 1 Peter E. D. Love, 2 and Heng Li 3 ABSTRACT: Efficient allocation of resources for construction planning activities requires
Construction Delay Analysis under Multiple Baseline Updates
Construction Delay Analysis under Multiple Baseline Updates By Wail Menesi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied
A CONSTRUCTION SCHEDULE CONTROLLING SYSTEM USING WEB-BASED KNOWLEDGE TECHNOLOGY. Will Y. Lin(a) and H. Ping Tserng(b)
;Automation and Robct,cs in Construction XVI 1999 by UC3M r A CONSTRUCTION SCHEDULE CONTROLLING SYSTEM USING WEB-BASED KNOWLEDGE TECHNOLOGY Will Y. Lin(a) and H. Ping Tserng(b) (a)ph.d. Student, Dept.
Analyzing Material Management Techniques on Construction Project Ashwini R. Patil, Smita V. Pataskar
Analyzing Material Management Techniques on Construction Project Ashwini R. Patil, Smita V. Pataskar Abstract The efficient procurement of material represents a key role in the successful completion of
Development of O&M Information Management Framework using Configuration Management for Gas Pipeline Project in Permafrost Areas
Development of O&M Information Management Framework using Configuration Management for Gas Pipeline Project in Permafrost Areas Seo-Kyung Won 1, Choong-Hee Han 2 and Junbok Lee 3 1 Ph.D. Research Professor,
Identification of Late Deliverables and Their True Impacts to Industrial Construction Projects
2296 Identification of Late Deliverables and Their True Impacts to Industrial Construction Projects William BARRY 1, Fernanda LEITE 2, and William J. O BRIEN 3 1 MS Student, Construction Engineering and
Project Risk Management: Methodology Development for Engineering, Procurement and Construction Projects a Case Study in the Oil and Gas Industry
American Journal of Civil Engineering 2015; 3(3): 75-79 Published online April 13, 2015 (http://www.sciencepublishinggroup.com/j/ajce) doi: 10.11648/j.ajce.20150303.14 ISSN: 2330-8729 (Print); ISSN: 2330-8737
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
IMPROVING THE DESIGN-CONSTRUCTION INTERFACE
Improving the Design-Construction Interface IMPROVING THE DESIGN-CONSTRUCTION INTERFACE Luis F. Alarcón 1 and Daniel A. Mardones 2 ABSTRACT In building projects customer requirements, constructive aspects
Evaluation of Factors Affecting on Construction Equipment Acquisition Methods in Malaysia
2011 International Conference on Information and Finance IPEDR vol.21 (2011) (2011) IACSIT Press, Singapore Evaluation of Factors Affecting on Construction Equipment Acquisition Methods in Malaysia Masoud
How To Evaluate The Effectiveness Of A Training Workshop In Aniran
Middle-East Journal of Scientific Research 8 (2): 483-487, 2011 ISSN 1990-9233 IDOSI Publications, 2011 Evaluation of Training Workshop (Near) and Also in Part Due to Technical and Vocational Training
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER. Occupation Specific Technical Requirements
ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER Responsible for performing entry level engineering analysis, design, plan, review and inspection for small to medium projects and/or designated segments of
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
Yemen Aden Telephone Network System Expansion Project. Report date: March 2001 Field survey: August 2000 1. Project Profile and Japan s ODA Loan
Yemen Aden Telephone Network System Expansion Project Report date: March 2001 Field survey: August 2000 1. Project Profile and Japan s ODA Loan Project site Site map: Aden, the Republic of Yemen Installed
Specifics of national debt management and its consequences for the Ukrainian economy
Anatoliy Yepifanov (Ukraine), Vyacheslav Plastun (Ukraine) Specifics of national debt management and its consequences for the Ukrainian economy Abstract This article is about the specifics of the national
Economics Training Series Introductory Course. Cost Estimation
Economics Training Series Introductory Course Cost Estimation 1 Project Cost Estimate: Feasibility/Detailed Design Identify project. Identify individual project components. Classify individual project
Keeping the Supply Chain Moving
C h arl es Lartey Keeping the Supply Chain Moving Supply chain management offers plenty of career opportunities for people with the right skills. W ith the increasingly rapid pace of business, a company
INFLUENCE OF DEMAND FORECASTS ACCURACY ON SUPPLY CHAINS DISTRIBUTION SYSTEMS DEPENDABILITY.
INFLUENCE OF DEMAND FORECASTS ACCURACY ON SUPPLY CHAINS DISTRIBUTION SYSTEMS DEPENDABILITY. Natalia SZOZDA 1, Sylwia WERBIŃSKA-WOJCIECHOWSKA 2 1 Wroclaw University of Economics, Wroclaw, Poland, e-mail:
PRACTICE NOTES FOR QUANTITY SURVEYORS
PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
INVESTIGATION OF EFFECTIVE FACTORS IN USING MOBILE ADVERTISING IN ANDIMESHK. Abstract
INVESTIGATION OF EFFECTIVE FACTORS IN USING MOBILE ADVERTISING IN ANDIMESHK Mohammad Ali Enayati Shiraz 1, Elham Ramezani 2 1-2 Department of Industrial Management, Islamic Azad University, Andimeshk Branch,
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
CRITICAL SUCCESS FACTORS FOR KNOWLEDGE MANAGEMENT STUDIES IN CONSTRUCTION
CRITICAL SUCCESS FACTORS FOR MANAGEMENT STUDIES IN CONSTRUCTION Yu-Cheng Lin Assistant Professor Department of Civil Engineering National Taipei University of Technology No.1.Chung-Hsiao E. Rd., Sec.3,
Document Management Systems in Small and Medium Size Construction Companies in Jordan
Document Management Systems in Small and Medium Size Construction Companies in Jordan Abstract Hesham Ahmad 1, Maha Ayoush 2 and Subhi Bazlamit 3 Document management systems (DMS) are now becoming more
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
Application of Fuzzy Logic in Delay Analysis in Construction
Application of Fuzzy Logic in Delay Analysis in Construction Shruti Singh 1 Dr. M.K. Trivedi 2 2 Civil department MITS Gwalior 474005, India 1 Civil Department MITS Gwalior, India Abstract This paper describes
Power Project - Debt Financing. Bill Sutherland Senior Managing Director Project Finance April 9, 2014
Power Project - Debt Financing Bill Sutherland Senior Managing Director Project Finance April 9, 2014 Project Finance Investment Manulife Project Finance Defined Principal Risks / Mitigates Challenges
J. Appl. Environ. Biol. Sci., 5(12S)134-141, 2015. 2015, TextRoad Publication
J. Appl. Environ. Biol. Sci., 5(12S)134-141, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Relationship between Maintenance Knowledge
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
MALAYSIA S GOVERNMENT PROCUREMENT REGIME
MALAYSIA S GOVERNMENT PROCUREMENT REGIME 1. INTRODUCTION The prime objective of the Malaysian Government procurement is to support Government programmes by obtaining value for money through acquisition
PERCEPTION OF BUILDING CONSTRUCTION WORKERS TOWARDS SAFETY, HEALTH AND ENVIRONMENT
Journal of Engineering Science and Technology Vol. 2, No. 3 (2007) 271-279 School of Engineering, Taylor s University College PERCEPTION OF BUILDING CONSTRUCTION WORKERS TOWARDS SAFETY, HEALTH AND ENVIRONMENT
Role of Project Manager from the Client s Side on the Performance of a Construction Project
International Journal of Engineering and Advanced Technology (IJEAT) Role of Project Manager from the Client s Side on the Performance of a Construction Project Shruti Wadalkar, S.S. Pimplikar Abstract
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
STUDY ON THE COST OVERRUNS IN ROAD CONSTRUCTION PROJECTS IN SRI LANKA
STUDY O THE COST OVERRUS I ROAD COSTRUCTIO PROJECTS I SRI LAKA Eng. S.B. Wijekoon Faculty of Engineering, University of Peradeniya (email: [email protected]) Eng. A.M.C.T.K. Attanayake Anuradhapura Provincial
RELATIONSHIP BETWEEN INVENTORY MANAGEMENT AND INDUSTRIES BECOMING SICK, ESPECIALLY IN THIRD WORLD COUNTRIES
Relationship between inventory management and industries becoming sick, especially in third world countries 7 RELATIONSHIP BETWEEN INVENTORY MANAGEMENT AND INDUSTRIES BECOMING SICK, ESPECIALLY IN THIRD
THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)
PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.
Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management
COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS
COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS By Chabota Kaliba A dissertation submitted to the University of Zambia in fulfilment of the requirements for the Degree
The Relationship between Performance Management and Job Motivation of the Staff Working in Petrochemical Company
International Journal of Psychology and Behavioral Research. Vol., 3(6), 620-625, 2014 Available online at http:// www. ijpbrjournal.com ISSN 2322-4002 2014 Victor Quest Publications The Relationship between
Developing a framework model of Supply Chain Management : A case study on a Mega construction project in Myanmar.
Proposal for PhD Research Yadanar Soe ID: 1140937 Course Title: PhD Research (Construction Management) [email protected], [email protected] Lead Supervisor: Dr M An Co Supervisor: Dr J Yang Title Developing
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
OVERSIGHT OF CAPITAL PROJECT PLANNING & PROCUREMENT
AGLG Perspectives Series Accessible Tools Audit Topic 3 Tool 1 (April, 2014) OVERSIGHT OF CAPITAL PROJECT PLANNING & PROCUREMENT Key Considerations for Local Government Council and Board Members Relating
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Plan for the audit of the 2011 financial statements
INTERNATIONAL TRAINING CENTRE OF THE ILO Board of the Centre 73rd Session, Turin, 3-4 November 2011 CC 73/5/2 FOR INFORMATION FIFTH ITEM ON THE AGENDA Plan for the audit of the 2011 financial statements
Delay Analysis in Construction Project
Delay Analysis in Construction Project Abstract Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often result of
Position Classification Standard for Medical Records Administration Series, GS-0669
Position Classification Standard for Medical Records Administration Series, GS-0669 Table of Contents SERIES DEFINITION... 2 SERIES COVERAGE... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES...
Malaysian Tourism and Hospitality Graduates Competencies: Exploring the Human Resource Managers Perceptions
Malaysian Tourism and Hospitality Graduates Competencies: Exploring the Human Resource Managers Perceptions Nurhazani Mohd Shariff 1, Azlan Zainol Abidin 2 1 School of Tourism, Hospitality & Environmental
Competitive Advantage of Libyan Business Environment
Economics World, ISSN 23287144 May 2014, Vol. 2, No. 5, 325332 D DAVID PUBLISHING Competitive Advantage of Libyan Business Environment Salem Abdulla Azzaytuna University, Tripoli, Libya The economic development
Utilities Webinar Asset Lifecycle Management and Capital Projects & Infrastructure
Utilities Webinar Asset Lifecycle Management and Capital Projects & Infrastructure October 31, 2013 Agenda 1. Context - the Utility CEO s Agenda 2. Asset Lifecycle Management and Utilities 3. What s at
THE QUALITY MANAGEMENT AND FOOD SAFETY PREPAREDNESS OF THE SMALL AND MEDIUM-SIZED FOOD INDUSTRY ENTERPRISES IN SERBIA, BEFORE THE EU ACCESSION
PhD Thesis THE QUALITY MANAGEMENT AND FOOD SAFETY PREPAREDNESS OF THE SMALL AND MEDIUM-SIZED FOOD INDUSTRY ENTERPRISES IN SERBIA, BEFORE THE EU ACCESSION Kovács Sárkány Hajnalka Superviser: Prof. Dr. Győri
MU2E PROCUREMENT MANAGEMENT PLAN
MU2E PROCUREMENT MANAGEMENT PLAN Version 1.1 June 29, 2012 Mu2e-doc-xxx Approved By: R. Ray date Mu2e Project Manager J. Collins date Fermilab Procurement Department Head G. Bock date Fermilab Associate
ijcrb.webs.com INTERDISCIPLINARY JOURNAL OF CONTEMPORARY RESEARCH IN BUSINESS OCTOBER 2013 VOL 5, NO 6 Abstract 1. Introduction:
Impact of Management Information Systems to Improve Performance in Municipalities in North of Jordan Fawzi Hasan Altaany Management Information Systems Department, Faculty of Administrative Sciences, Irbid
CONSTRUCTION CLAIMS AND DISPUTES: CAUSES AND COST/TIME OVERRUNS
CONSTCTION CAIMS AND DISPTES: CASES AND COST/TIME OVENS By Cheryl Semple, ~ Francis T. Hartman, 2 and George Jergeas 3 AnsrACT: Avoiding construction claims and disputes requires understanding of the contractual
Identification of Critical Success Factors for Successful TQM Implementation in Textile Industries, Pakistan
Global Advanced Research Journal of Management and Business Studies (ISSN: 2315-5086) Vol. 3(10) pp. 473-478, October, 2014 Available online http://garj.org/garjmbs/index.htm Copyright 2014 Global Advanced
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and
Project Procurement Management
Project Procurement Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note
TIER II STANDARD FOR AUDITORS
Job Classification Manual Page 1 of 37 TIER II STANDARD FOR AUDITORS INTRODUCTION 1. This grade level standard illustrates the application of the ICSC Master Standard (Tier I) to a specific field of work
Checklist for Credit Risk Management
Checklist for Credit Risk Management I. Development and Establishment of Credit Risk Management System by Management Checkpoints - Credit risk is the risk that a financial institution will incur losses
CHALLENGES AND SOLUTIONS IN SKILLS AND EMPLOYMENT TRAINING DEVELOPMENT
ISSN: 0976-2876 (Print) ISSN: 2250-0138(Online) CHALLENGES AND SOLUTIONS IN SKILLS AND EMPLOYMENT TRAINING DEVELOPMENT LEILA KHAZAEE a, HASSAN NODEHI b1, MASOOMEH VEJDANI c AND MAHBOOBEH HOSEINI BARDASKAN
Worldwide Anti-Corruption Policy
Worldwide Anti-Corruption Policy I. PURPOSE The laws of most countries make the payment or offer of payment or even receipt of a bribe, kickback or other corrupt payment a crime, subjecting both Eaton
CODE OF PRACTICE. Safety Management. Occupational Safety and Health Branch Labour Department CODE OF PRACTICE ON SAFETY MANAGEMENT 1
CODE OF PRACTICE On Safety Management Occupational Safety and Health Branch Labour Department CODE OF PRACTICE ON SAFETY MANAGEMENT 1 This Code of Practice is prepared by the Occupational Safety and Health
QUT Digital Repository: http://eprints.qut.edu.au/
QUT Digital Repository: http://eprints.qut.edu.au/ Al-Kharashi, Adel and Skitmore, Martin (2009) Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics,