QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS
|
|
|
- Kathryn Griffith
- 9 years ago
- Views:
Transcription
1 QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS João Guedes de Miranda Extended abstract Examination Committee Chairperson: Prof. Ana Paula Patrício Teixeira Ferreira Pinto França de Santana Supervisor: Prof. Vítor Faria e Sousa Supervisor: Prof. Nuno Gonçalo Cordeiro Marques de Almeida Members of the Committee: Eng. Sónia Cristina Simões Madeira Domingues May 2014
2 Quantitative Analysis of Time Overruns In transport Infrastructure Projects João Guedes de Miranda Instituto Superior Técnico, Technical University of Lisbon Abstract: Regardless the level of economic development of a country, time overruns are frequent and represent a major problem in construction projects. Regarding road projects, construction time overruns are among the most significant problems. In fact, timely completion of road projects is a priority due to the utility of this type of infrastructures and the sensibility of several of the construction activities involved to the weather conditions. Apart from the precision of project schedule estimation, delays are almost inevitable. Time overruns implications, such as heavy liquidated damages (LDs) for lateness to contractors, leads to an improvement in this investigation. This study intends to gather main causes related to construction projects and analyze if time overruns are explained by specific causes in each project instead of general variables. To provide basis for the hypotheses and to provide a methodology to support the quantitative risk management of time deviations this study is based on data from Virginia road projects, in U.S.A. Based on a sample of 739 transport infrastructure projects, this study aims to connect time overruns with several variables like contract proposals, original contract period, actual contract period, type of project and project size. The methodology fits time overrun data into an adjusted probability distribution. This approach concedes an opportunity to perform a risk management analysis of time delays following alternative practical ways: allows the owner to quantify a contingency fund for project duration, or assist contractors to prepare a proposal. Keywords: risk management; construction management; time overruns; forecasting; statistics; road construction projects. I Introduction For several companies, the main targets are minimizing schedule and costs (Wei, 2010). These targets are applied to transport infrastructure projects. In order to achieve schedule objective, it is essential to have a reliable forecast of project completion time in order to make an accurate forecast of project duration to set the pace of performance and able to revise it through time (Ahuja e Nandakumar, 1985). However, despite an accurate project management, usually there are time overruns in construction projects. Time overruns implications, such as heavy liquidated damages (LDs) for lateness to contractors, leads to an improvement in this investigation. Despite of this concern from stakeholders, time overruns still represent meaningful values. According to an audit by Tribunal de Contas in 2009, the five largest public works projects built between 1999 and 2008 resulted in an increased cost of approximately 241 M to the Portuguese State. In Portugal the deviations of time have been reflected in a general practice, and the delays in these projects were from 1.4 to 4.6 years representing an increase of 25% to 295% of the initial value of the contract. This study intends to analyze if time delays are related to general variables or based on specific causes to each project. Furthermore, it is set to establish a methodology and auxiliary process for risk management in transport infrastructure projects. 1
3 II Project time deviation According to Bordat et al. (2004), a project time delay is the difference between a project s original contract period and the time of bidding and its overall actual contract period at the end of construction. There are countless causes of time deviations, in Table 2 are shown some of the major causes gathered by several authors. When a contractor is responsible for project delays, it may result in liquidated damages, so it is relevant to identify sources and types of delays in order to determine the effect of a delay on the project. Those delays can be categorized in four types: Critical or noncritical; excusable or non-excusable; compensable or non-compensable; concurrent or non-concurrent. Transport infrastructures have their specific conditions and main causes vary from other project types. Based on Ellis e Thomas (2003), in Table 1 are summarized the most frequent causes in transport infrastructure projects, ranked by owners and contractors. Table 1 Most frequent reason for delays according to Ellis e Thomas (2003). Rank Owner Contractor 1º Utility Relocations Utility Relocations 2º 3º Different Site Conditions Errors in Plans and Specifications Errors in Plans and Specifications Different Site Conditions 4º Weather Weather 5º Permitting Issues Owner Requested Changes A contingency fund is the amount of resources beyond the initially estimated required to minimize the risk of overrun of a project. Although not as usual, a contingency period of time can be applied for time overruns. Ranasinghe (1994a) defines a contingency for the duration of a project as the amount of time to be included in a planning to cover unforeseen delays. Despite several authors estimates and quantifications, there isn t a unified quantification to account this contingency period. Assaf e Al-Hejji (2006) studied the causes of delays in construction projects in Saudi Arabia. Analyzed the different perspectives of the owners, contractors and designers and suggested measures to control and minimize delays in construction. As a conclusion of the study, the authors present the following recommendations: Contractors must ensure enough number of labors and keep them motivated to improve productivity; manage his financial resources and plan cash flow by utilizing progress payment; planning and scheduling must be seen as continuing processes during construction and match with the resources and time to develop the work; and site management and supervision have to be assigned as soon as project Is awarded; Owners should pay progress payment on the contractor on time; minimize change orders during construction; avoid delay in reviewing and approving of design documents; and check for resources and capabilities before awarding the contract to the lowest bidder. Designers must set a schedule to produce design documents on time and take special attention to mistakes and discrepancies to avoid redoing designs and drawings. 2
4 Al-Kh alil e Al-Gh afly, 1999, Alwi, 2003, Chan e K umaraswamy, 1997, D awood, 1998, Aibinu e Od eyinka, 2006, Al-Kh arash i e Skitmore, 2009, Arditi et al., 1985, Assaf et al., 1995, M D lakwa e F Culpin, 1990, Al T abtab ai, 2002, Abd El-R azek et al., 2008) Table 2 Time overrun causes in several type of projects. ( Cause Type of project Location Author Unforeseen ground conditions Financial difficulties (owners, contractors or subcontractors) Contractors difficulties in receiving plaments from owner Subcontractor issues Inadequate or incomplete designs Lack of resources Inexperienced contractor Fluctuation in labour productivity and price escalation Frequent change orders, calendarizacao inadequada Materials shortage Shortage of laborers Owner slow decision making Interference between client and contractor Poor risk management and supervision Inadequate construction planning Industrial water treatment 3 General Industrial water treatment General Industrial water treatment General South Arabia Al-Khalil e Al-Ghafly 1999 Hong Kong Alwi e Hampson 2003 Indonesia Chan e Kumaraswamy 1997 United Kingdom Dawood 1998 Aibinu e Odeyinka 2006 South Arabia Nigeria Turkey South Arabia Egypt Kuwait Nigeria Al-Karashi e Skitmore 2009 Al-Khalil e Al-Ghafly 1999 Arditi et al 1985 Assaf et al 1995 Aibinu e Odeyinka 2006 Al-Karashi e Skitmore 2009 Al-Khalil e Al-Ghafly 1999 Al-Tabtabai 2002 Assaf et al 1995 El-Razek et al 2008 Nigeria Aibinu e Odeyinka 2006 General United Kingdom Dawood 1998 South Arabia Aibinu e Odeyinka 2006 General General Industrial water treatment General Indonesia Al-Tabtabai 2002 Kuwait Alwi e Hampson 2003 Nigeria Assaf et al 1995 United Kingdom Dawood 1998 Nigeria Hong Kong Turkey South Arabia Kuwait Turkey Aibinu e Odeyinka 2006 Arditi et al 1985 Chan e Kumaraswamy 1997 Al-Khalil e Al-Ghafly 1999 Al-Tabtabai 2002 Arditi et al 1985 Assaf et al 1995 Edificios Nigeria Aibinu e Odeyinka 2006 General United Kingdom Dawood 1998 Al-Karashi e Skitmore 2009 Industrial water treatment General South Arabia Egypt Hong Kong Indonésia Nigeria Turkey Al-Khalil e Al-Ghafly 1999 Alwi e Hampson 2003 Arditi et al 1985 Chan e Kumaraswamy 1997 El-Razek et al 2008 Nigeria Aibinu e Odeyinka 2006 General United Kingdom Dawood 1998 Industrial water treatment General General General South Arabia Kuwait Nigeria Al-Khalil e Al-Ghafly 1999 Al-Tabtabai 2002 Assaf et al 1995 South Arabia Al-Tabtabai 2002 Egypt Alwi e Hampson 2003 Indonesia Arditi et al 1985 Kuwait Assaf et al 1995 Turkey El-Razek et al 2008 South Arabia Assaf et al 1995 Egypt Chan e Kumaraswamy 1997 Hong Kong Nigeria El-Razek et al 2008 Hong Kong Alwi e Hampson 2003 Indonesia Chan e Kumaraswamy 1997 Industrial water treatment South Arabia Al-Khalil e Al-Ghafly 1999 General Nigeria
5 III Data analysis The sample was obtained from Virginia Department of Transportation (VDOT) database. The projects were collected by date, throughout fiscal years of 1999 and 2000, totaling 739 projects. To analyze time delays, the general description is divided into categories such as: project type, road system, project location, chronological order, original contract period, actual contract period. In parallel to project type, it is also considered the number of contract proposals. Table 3 summarizes the descriptive statistics of time delay. Table 3 Descriptive statistics of time delay. Average In light of construction processes, in all those categories mentioned above, project type reveals to be outstanding from others and so, it is assumed that time delays should considered separately. Original Duration (days) Actual Duration (days) Sample 739 Time Delay (%) Minimum % Maximum % Sum Value % Std. Error % Standard Deviation Skewness Kurtosis Value Std. Error Value Erro Padrão Given the focus to project type, when appropriated all analysis are segregated by type. Those types are: new roads; new bridges and viaducts; roads rehabilitation; bridges and viaducts rehabilitation; shoulder and gardens rehabilitation; and others/mixed projects. This sample contains 49.8% of projects which had time overruns. Divided by type of work, the average time overrun for new roads (59 projects) is 13.9%, new bridges and viaducts (37) is 14.7%, rehabilitation of roads (416) is 10.3%, rehabilitation of bridges and viaducts (122) is 7.1% and for other types of roads (42) is 18.6%. Number of contract proposals has an average of 4.8 and 15 proposals as maximum. Projects are separetad in the following road systems: interstate; primary; secondary; other; and various systems. Figure 1 show clearly that majority of projects are primary and secondary roads. In terms of location, the sample is fairly distributed, as it can be seen in Figure 2. Finally to mention chronological order, the range of projects per month is between 14 and 43, with an average of 31 projects per month. Various 4% S 42% IS 14% P 31% O 9% Figure 1 Sample distribution by road system. 4
6 Actual Period (days) V Statistical analysis Bristol Culpeper IV.1 General factors analysis The previous sample had several statistical 13% 16% 14% 8% 15% 11% 1 8% 5% Fredericksburg Hampton Roads Lynchburg Northern Virginia Richmond Salem outliers, without those outliers our new sample has 657 projects to be analyzed. This chapter aims to verify if the assumption that time overruns can t be explained by independent variables common to all projects. Staunton Figure 2 Sample distribution by location. Original contract period and actual contract period are illustrated in Figure 3 sectioned by half a year, one, two, four and over four years. Approximately 87% of projects had an original contract time less than one year. In Figure 4 is illustrated time delay by duration intervals, it is possible to observe a project with 725% time delay as maximum > 1460 Contract Period (days) Figure 3 Distribution of contract period by intervals Original period Figure 5 displays the relation between original contract period and actual contract period. In this relation, a linear regression model is has the following equation: (4.1) In addition we obtained a coefficient of determination of Actual Period Original Period (days) Figure 5 Linear regression of actual contract period and original contract period. Figure 6 represents the histogram, in logarithmic scale, of number of projects in function of time delays. It can be seen clearly a positive skewness and there is a tendency for the actual contract period to be longer than original contract period. Figure 4 Boxplot of time delay by duration intervals. In Figure 7 is represented the influence of project size in time overrun. For better understanding, size is classified into 4 classes. There might be a slight indication that a higher class (larger project considering original contract time) has less time overruns, but a linear regression obtains a coefficient of 5
7 Time delay (%) Time delay (%) Time delay (%) Time Delay (%) Time delay (%) Time delay (%) Numberm of projects Time delay (%) determination of It can t be assumed that time delays are explained by project size y = 8E-08x + 0, R² = 0, $- $1,0 $2,0 $3,0 - Proposals standard deviation (millions) Figure 9 Delay by proposals standard deviation Time Delay (%) Figure 6 Histogram of time delays Figure 7 Distribution of time delay by project size. Contract proposals are analyzed considering the amount of proposals, standard deviation, maximum value, minimum value, medium value and range of values. In FIGURES 5 through 10, is illustrated the lack of relation between these variables and time delay, unable to explain any delay. y = 0,0276x + 0,0055 R² = 0, ,00 1,00 2,00 3,00 4, Classes of project size y = -0,0135x + 0,1091 R² = 0, Number of proposals Figure 8 Distribution of delay by number of proposals y = 4E-08x + 0,0093 R² = 0, $- $2 $4 $6 $8 Proposals maximum value (millons) Figure 10 Delay by proposals maximum value Figure 11 Delay by proposals minimum value. Figure 12 Delay by proposals average value. y = 6E-08x + 0,008 R² = 0, $- $5 $10 - Proposals minimum value (milions) y = 5E-08x R² = 0, $- $5 - Proposals average value (millions) y = 4E-08x + 0,0356 R² = 0, $- $2,0 $4,0 - Proposals value range (millions) Figure 13 Distribution of delay by proposals range values. 6
8 Previous analysis proves the main hypothesis. Time delays can t be explained or predicted by common factors to all projects, however, the actual contract time can be considered, approximately, 7% larger than original contract time. IV.2 Time overrun management Based on the assumption that time deviations may be caused by specific factors associated to each project, it is intended to provide a methodology and a basis to support the quantitative risk management of time deviations. It is admitted that, in similar projects, it is possible to forecast time overrun based on historical data. Standing on this hypothesis, this chapter pretends to fit time overrun into an adjusted probability distribution, using Oracle Crystal Ball software. In this analysis the focus is set relating current project with previous ones and knowledge of probable causes capable of leading to a time delay is useful. By fitting a probability distribution it is possible to estimate time overrun linked to a probability density value. The criteria to select a density probability value can be established based on risk management variables. Main causes for time delays can be used, for example, to set a risk level to current project by considering combinations between those causes. distribution, defined by average 1% and scale 18%. Figure 14 Statistical adjustment of time overruns of general contracts. For road rehabilitation projects, the distributions which gives the best fitting resutls is logistic distribution, defined by average 1% and scale 18%. Can be illustrated in Figure 15. Figure 15 Statistical adjustment of time overruns of road rehabilitation contracts. For bridges and viaducts rehabilitation projects, the distributions which gives the best fitting resutls is logistic distribution, defined by average -1% and scale 15%. Can be illustrated in Figure 16. Given the fact that project conditions may be different in each project type, it is important fit distributions to each type. Figure 14 displays adjusted fits of probability distributions and probability density distributions for general projects. For general projects, the distributions which gives the best fitting resutls is logistic Figure 16 Statistical adjustment of time overruns of bridges and viaducts rehabilitation contracts. 7
9 For shoulders and gardens rehabilitation projects, the distributions which gives the best fitting resutls is log-normal distribution, defined by average 16%, standard deviation 46% and localisation -58%. Can be illustrated in Figure 17. Figure 19 Statistical adjustment of time overruns of new bridges and viaducts construction contracts. Figure 17 Statistical adjustment of time overruns of shoulders and gardens rehabilitation contracts. For mixed/other projects, the distributions which gives the best fitting resutls is Gumbel distribution, defined by likeliest -8% and scale 33%. Can be observed in Figure 20. For road construction projects, the distributions which gives the best fitting resutls is Gumbel distribution, defined by likeliest -12% and scale 28%. As shown in Figure 18. Figure 20 Statistical adjustment of time overruns of mixed and other constructions contracts. Figure 18 Statistical adjustment of time overruns of new roads construction contracts. For bridges and viaducts construction projects, the distributions which gives the best fitting resutls is logistic distribution, defined by average 12% and scale 15%. As illustrated infigure 19. In every project type, the fitting revealed to be weak by applying Anderson Darling, Kolmogorov-Smirnov, and Chi-squared tests. Despite weak fittings, the adopted methodology is still useful. In case of future developments, the sample can be extended and fittings can slightly improve. But still, with the actual sample, it is possible to obtain decent results from the probability density distributions. 8
10 V Conclusions This dissertation aimed to contribute to a better understanding of time overrun causes and related factors. In addition is set to provide a methodology and a basis to support the quantitative risk management of time deviations. A correlation between time overruns and several factors common to all projects revealed to be null. As result, it is presumed that these variables aren t statistically relevant to time delay. As an exception, actual project duration appears to be approximately 7% larger than original project duration. Although there is no statistical relationship between the different factors and time delay, it is proposed that it is possible to use historical information of time delay from previous projects to forecast time delays in future projects. This approach concedes an opportunity to perform a risk management analysis of time delays following alternative practical ways: Converting qualitative risk analyses into statistically representative quantitative amounts for each type of project by matching each level of the qualitative scale used to a time overrun distribution probability As another practical example, it is able to verify results of quantitative risk analyses, by analyzing whether the percentile of the time overrun distribution is coherent with the specific characteristics of the contract. References ABD EL-RAZEK, M., BASSIONI, H. & MOBARAK, A Causes of Delay in Building Construction Projects in Egypt. Journal of Construction Engineering and Management, 134, AHUJA, H. N. & NANDAKUMAR, V Simulation model to forecast project completion time. Journal of construction engineering and management, 111, AIBINU, A. & ODEYINKA, H Construction Delays and Their Causative Factors in Nigeria. Journal of Construction Engineering and Management, 132, AL-KHALIL, M. I. & AL-GHAFLY, M. A Delay in public utility projects in Saudi Arabia. International Journal of Project Management, 17, AL-KHARASHI, A. & SKITMORE, M Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27, AL TABTABAI, H. M Causes for delays in construction projects in Kuwait. ALWI, S. H., K Identifying the important causes of delays in building construction projects. Proceedings The 9th East Asia- Pacific Conference on Structural Engineering and Construction, Bali, Indonesia. ARDITI, D., AKAN, G. T. & GURDAMAR, S Reasons for delays in public projects in Turkey. Construction Management and Economics, 3, ASSAF, S., AL-KHALIL, M. & AL-HAZMI, M Causes of Delay in Large Building Construction Projects. Journal of Management in Engineering, 11, BORDAT, C., SINHA, K. C. & LABI, S An Analysis of Cost Overruns and Time Delays of INDOT Projects, Joint Transportation Research Program. CHAN, D. W. M. & KUMARASWAMY, M. M A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15, DAWOOD, N Estimating project and activity duration: a risk management approach using network analysis. Construction Management and Economics, 16, ELLIS, R. D. & THOMAS, H. R. The root causes of delays in highway construction. 82nd Annual meeting of the transportation research board, M DLAKWA, M. & F CULPIN, M Reasons for overrun in public sector construction projects in Nigeria. International Journal of Project Management, 8, WEI, K. S Causes, Effects and Methods of Minimizing Delays in Construction Projects. Bachelor, Universiti Teknologi Malaysia, Skudai. 9
Causes and Effects of Delays in Large Construction Projects of. Pakistan
Causes and Effects of Delays in Large Construction Projects of Pakistan M. Haseeb 1, a, Xinhai-Lu 1, Aneesa Bibi 1, Maloof-ud-Dyian 2, Wahab Rabbani 3 1 College of Public Administration, Huazhong University
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
International Journal of Project Management 21 (2003) 321 326 www.elsevier.com/locate/ijproman Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria
Journal of Construction in Developing Countries, 18(1), 53 72, 2013 Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Olajide Timothy Ibironke, Timo Olugbenga
Delay Analysis in Construction Project
Delay Analysis in Construction Project Abstract Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often result of
Causes and effects of delays in Malaysian construction industry
International Journal of Project Management 25 (2007) 517 526 INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT www.elsevier.com/locate/ijproman Causes and effects of delays in Malaysian construction industry
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project
Construction Delay Analysis under Multiple Baseline Updates
Construction Delay Analysis under Multiple Baseline Updates By Wail Menesi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN M. Haseeb College of Public Administration, Huazhong University of Science and Technology, Wuhan, P.R. China, 430074.
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE Yakubu Adisa Olawale, Ph.D., MCIOB and Ming Sun, Ph.D. (Professor) Abstract Despite the availability
Business Statistics. Successful completion of Introductory and/or Intermediate Algebra courses is recommended before taking Business Statistics.
Business Course Text Bowerman, Bruce L., Richard T. O'Connell, J. B. Orris, and Dawn C. Porter. Essentials of Business, 2nd edition, McGraw-Hill/Irwin, 2008, ISBN: 978-0-07-331988-9. Required Computing
ijcrb.webs.com INTERDISCIPLINARY JOURNAL OF CONTEMPORARY RESEARCH IN BUSINESS OCTOBER 2013 VOL 5, NO 6 Abstract 1. Introduction:
Impact of Management Information Systems to Improve Performance in Municipalities in North of Jordan Fawzi Hasan Altaany Management Information Systems Department, Faculty of Administrative Sciences, Irbid
Qualitative analysis: Analyzing the construction schedule. 2014 Baker Tilly Virchow Krause, LLP
Qualitative analysis: Analyzing the construction schedule 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
Monte Carlo analysis used for Contingency estimating.
Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4
Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries
Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries O O FANIRAN School of Civil and Environmental Engineering The University of New South Wales Sydney
Quantitative Methods for Finance
Quantitative Methods for Finance Module 1: The Time Value of Money 1 Learning how to interpret interest rates as required rates of return, discount rates, or opportunity costs. 2 Learning how to explain
Study of Delay in Project Planning and Design Stage of Civil Engineering Projects
International Journal of Engineering and Advanced Technology (IJEAT) ISSN: 2249 8958, Volume-2, Issue-3, February 2013 Study of Delay in Project Planning and Design Stage of Civil Engineering Projects
Course Text. Required Computing Software. Course Description. Course Objectives. StraighterLine. Business Statistics
Course Text Business Statistics Lind, Douglas A., Marchal, William A. and Samuel A. Wathen. Basic Statistics for Business and Economics, 7th edition, McGraw-Hill/Irwin, 2010, ISBN: 9780077384470 [This
CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY
CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY KASIMU ALHAJI MOHAMMED DEPT OF QUANTITY SURVEYING, FEDERAL POLYTECHNIC, BIDA. NIGERIA ABUBAKAR DANLADI ISAH DEPT OF ARCHITECTURE, FEDERAL UNIVERSITY OF
MTH 140 Statistics Videos
MTH 140 Statistics Videos Chapter 1 Picturing Distributions with Graphs Individuals and Variables Categorical Variables: Pie Charts and Bar Graphs Categorical Variables: Pie Charts and Bar Graphs Quantitative
Fairfield Public Schools
Mathematics Fairfield Public Schools AP Statistics AP Statistics BOE Approved 04/08/2014 1 AP STATISTICS Critical Areas of Focus AP Statistics is a rigorous course that offers advanced students an opportunity
Forecasting cash flow expenditure at pre-tender stage: Case studies in New Zealand construction projects
Forecasting cash flow expenditure at pre-tender stage: Case studies in New Zealand construction projects Andrew Heaps School of Engineering and Advanced Technology, Massey University [email protected]
Factors Affecting Time Overruns in Public Construction Projects: The Case of Jordan
International Journal of Business and Management; Vol. 8, No. 23; 2013 ISSN 1833-3850 E-ISSN 1833-8119 Published by Canadian Center of Science and Education Factors Affecting Time Overruns in Public Construction
Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) 848-2424 ext. 8779; FAX (514) 848-7965; email:
Rehabilitation Scenarios for Sustainable Water Mains Khaled Shahata 1 ; Tarek Zayed 2 ; and Saad Al-Jibouri 3 1 Graduate Student, Department of Building, Civil, and Environmental Engineering, Concordia
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
QUT Digital Repository: http://eprints.qut.edu.au/
QUT Digital Repository: http://eprints.qut.edu.au/ Al-Kharashi, Adel and Skitmore, Martin (2009) Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics,
Introduction to Statistics and Quantitative Research Methods
Introduction to Statistics and Quantitative Research Methods Purpose of Presentation To aid in the understanding of basic statistics, including terminology, common terms, and common statistical methods.
Simple Predictive Analytics Curtis Seare
Using Excel to Solve Business Problems: Simple Predictive Analytics Curtis Seare Copyright: Vault Analytics July 2010 Contents Section I: Background Information Why use Predictive Analytics? How to use
Additional sources Compilation of sources: http://lrs.ed.uiuc.edu/tseportal/datacollectionmethodologies/jin-tselink/tselink.htm
Mgt 540 Research Methods Data Analysis 1 Additional sources Compilation of sources: http://lrs.ed.uiuc.edu/tseportal/datacollectionmethodologies/jin-tselink/tselink.htm http://web.utk.edu/~dap/random/order/start.htm
Descriptive Statistics
Descriptive Statistics Primer Descriptive statistics Central tendency Variation Relative position Relationships Calculating descriptive statistics Descriptive Statistics Purpose to describe or summarize
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
OPTIMAL ALLOCATION OF CONSTRUCTION PLANNING RESOURCES
OPTIMAL ALLOCATION OF CONSTRUCTION PLANNING RESOURCES By Olusegun O. Faniran, 1 Peter E. D. Love, 2 and Heng Li 3 ABSTRACT: Efficient allocation of resources for construction planning activities requires
Time Error in Project Management: A Case Study in Yanbu, Saudi Arabia
Business and Management Studies Vol. 2, No. 1; March 2016 ISSN 2374-5916 E-ISSN 2374-5924 Published by Redfame Publishing URL: http://bms.redfame.com Time Error in Project Management: A Case Study in Yanbu,
Study of the Importance and Applicability of the Factor "Mark-up in the Budgeting of Construction
Study of the Importance and Applicability of the Factor "Mark-up in the Budgeting of Construction Abstract Forming the price of a service and the subsequent finding of the value of the proposal is based
Investigate Relation between Available infrastructure of Internet Financial Reporting and Corporate Governance Structure
nvestigate Relation between Available infrastructure of nternet Financial Reporting and Corporate Governance Structure Mohsen Moradi 1, Mostafa Hashemi 2 * 15, Ali Sohrabi 3, Ali Alizadeh 4 1. Assistance
CHAPTER 20 Project Development Cost Estimates Table of Contents
Chapter 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates... 20-3 SECTION 1 Project Cost
STATS8: Introduction to Biostatistics. Data Exploration. Babak Shahbaba Department of Statistics, UCI
STATS8: Introduction to Biostatistics Data Exploration Babak Shahbaba Department of Statistics, UCI Introduction After clearly defining the scientific problem, selecting a set of representative members
DATA ANALYSIS. QEM Network HBCU-UP Fundamentals of Education Research Workshop Gerunda B. Hughes, Ph.D. Howard University
DATA ANALYSIS QEM Network HBCU-UP Fundamentals of Education Research Workshop Gerunda B. Hughes, Ph.D. Howard University Quantitative Research What is Statistics? Statistics (as a subject) is the science
COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS
COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS By Chabota Kaliba A dissertation submitted to the University of Zambia in fulfilment of the requirements for the Degree
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT M. Salama 1, H. Abd El Aziz 2, H. El Sawah 3 and A. El Samadony 3 1School of Built Environment, Heriot Watt University,
International Institute of Business Analysis. Salary Survey Report
International Institute of Business Analysis Salary Survey Report December 15, 2013 Introduction International Institute of Business Analysis (IIBA) is the independent, nonprofit, professional association
The Study of Chinese P&C Insurance Risk for the Purpose of. Solvency Capital Requirement
The Study of Chinese P&C Insurance Risk for the Purpose of Solvency Capital Requirement Xie Zhigang, Wang Shangwen, Zhou Jinhan School of Finance, Shanghai University of Finance & Economics 777 Guoding
Introduction to Quantitative Methods
Introduction to Quantitative Methods October 15, 2009 Contents 1 Definition of Key Terms 2 2 Descriptive Statistics 3 2.1 Frequency Tables......................... 4 2.2 Measures of Central Tendencies.................
Unit 31 A Hypothesis Test about Correlation and Slope in a Simple Linear Regression
Unit 31 A Hypothesis Test about Correlation and Slope in a Simple Linear Regression Objectives: To perform a hypothesis test concerning the slope of a least squares line To recognize that testing for a
Application of Fuzzy Logic in Delay Analysis in Construction
Application of Fuzzy Logic in Delay Analysis in Construction Shruti Singh 1 Dr. M.K. Trivedi 2 2 Civil department MITS Gwalior 474005, India 1 Civil Department MITS Gwalior, India Abstract This paper describes
DESCRIPTIVE STATISTICS AND EXPLORATORY DATA ANALYSIS
DESCRIPTIVE STATISTICS AND EXPLORATORY DATA ANALYSIS SEEMA JAGGI Indian Agricultural Statistics Research Institute Library Avenue, New Delhi - 110 012 [email protected] 1. Descriptive Statistics Statistics
MULTIPLE REGRESSION EXAMPLE
MULTIPLE REGRESSION EXAMPLE For a sample of n = 166 college students, the following variables were measured: Y = height X 1 = mother s height ( momheight ) X 2 = father s height ( dadheight ) X 3 = 1 if
AVOIDING COST OVERRUNS IN CONSTRUCTION PROJECTS IN THE UNITED KINGDOM
AVOIDING COST OVERRUNS IN CONSTRUCTION PROJECTS IN THE UNITED KINGDOM By Susana Gomez Arcila Supervisor: Mr Michael Newton Dissertation submitted in partial fulfilment for the of Degree of Master of Science
A Primer on Forecasting Business Performance
A Primer on Forecasting Business Performance There are two common approaches to forecasting: qualitative and quantitative. Qualitative forecasting methods are important when historical data is not available.
Relationship between Factors of Construction Resources Affecting Project Cost
Modern Applied Science; Vol. 7, No. 1; 2013 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Relationship between Factors of Construction Resources Affecting Project
Prioritising Project Scope Definition Elements in Public Building Projects
Prioritising Project Scope Definition Elements in Public Building Projects Mohammed K. Fageha, Ajibade A. Aibinu (University of Melbourne, Australia) Abstract A complete definition of the scope of a project
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Dongfeng Li. Autumn 2010
Autumn 2010 Chapter Contents Some statistics background; ; Comparing means and proportions; variance. Students should master the basic concepts, descriptive statistics measures and graphs, basic hypothesis
International Education Index comparative perspective from 21 countries. Janet Ilieva, PhD EDUCATION INTELLIGENCE
International Education Index comparative perspective from 21 countries Janet Ilieva, PhD Background Rapid growth in participation in tertiary education across the world, in the number of students pursuing
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
Statistics I for QBIC. Contents and Objectives. Chapters 1 7. Revised: August 2013
Statistics I for QBIC Text Book: Biostatistics, 10 th edition, by Daniel & Cross Contents and Objectives Chapters 1 7 Revised: August 2013 Chapter 1: Nature of Statistics (sections 1.1-1.6) Objectives
STUDY ON THE COST OVERRUNS IN ROAD CONSTRUCTION PROJECTS IN SRI LANKA
STUDY O THE COST OVERRUS I ROAD COSTRUCTIO PROJECTS I SRI LAKA Eng. S.B. Wijekoon Faculty of Engineering, University of Peradeniya (email: [email protected]) Eng. A.M.C.T.K. Attanayake Anuradhapura Provincial
Assessment of Critical Success Factors for Construction Projects in Pakistan
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of
Method for Calculating Schedule Delay Considering Lost Productivity
Method for Calculating Schedule Delay Considering Lost Productivity Hyun-Soo Lee, M.ASCE 1 ; Han-Guk Ryu 2 ; Jung-Ho Yu 3 ; and Jae-Jun Kim, M.ASCE 4 Abstract: A delay claim often occurs when a difference
Identification of Late Deliverables and Their True Impacts to Industrial Construction Projects
2296 Identification of Late Deliverables and Their True Impacts to Industrial Construction Projects William BARRY 1, Fernanda LEITE 2, and William J. O BRIEN 3 1 MS Student, Construction Engineering and
Who pays the Money for the Time?
Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency
Statistics Review PSY379
Statistics Review PSY379 Basic concepts Measurement scales Populations vs. samples Continuous vs. discrete variable Independent vs. dependent variable Descriptive vs. inferential stats Common analyses
August 2012 EXAMINATIONS Solution Part I
August 01 EXAMINATIONS Solution Part I (1) In a random sample of 600 eligible voters, the probability that less than 38% will be in favour of this policy is closest to (B) () In a large random sample,
International Statistical Institute, 56th Session, 2007: Phil Everson
Teaching Regression using American Football Scores Everson, Phil Swarthmore College Department of Mathematics and Statistics 5 College Avenue Swarthmore, PA198, USA E-mail: [email protected] 1. Introduction
Software Development Risk Assessment
Software Development Risk Assessment Note: The purpose of this prompt list is to provide project managers with a tool for identifying and planning for potential project risks. It is process-based and supports
Data Analysis: Analyzing Data - Inferential Statistics
WHAT IT IS Return to Table of ontents WHEN TO USE IT Inferential statistics deal with drawing conclusions and, in some cases, making predictions about the properties of a population based on information
4.1 Exploratory Analysis: Once the data is collected and entered, the first question is: "What do the data look like?"
Data Analysis Plan The appropriate methods of data analysis are determined by your data types and variables of interest, the actual distribution of the variables, and the number of cases. Different analyses
THE IMPACT OF USING ACCOUNTING INFORMATION SYSTEMS ON THE QUALITY OF FINANCIAL STATEMENTS SUBMITTED TO THE INCOME AND SALES TAX DEPARTMENT IN JORDAN
THE IMPACT OF USING ACCOUNTING INFORMATION SYSTEMS ON THE QUALITY OF FINANCIAL STATEMENTS SUBMITTED TO THE INCOME AND SALES TAX DEPARTMENT IN JORDAN Ahmad Adel Jamil Abdallah, PhD, Assistance Prof. Accounting,
Ctry / Area Award Achievement Awarded by Gold - Best Own Call Center Operation 4th Place in the PECC Ranking
Gold - Best Own Call Center Operation 4th Place in the PECC Ranking Brazil Customer Service Executive of the Year Customer Service Department of the Year Airlines Distribution & Transportation Canada Chile
practical problems. life) property) 11) Health Care Insurance. 12) Medical care insurance.
Training Courses Busisness Soluation For The Insurance Services Industry First: Professional Insurance Programs 1) Fundamental of Risk &Insurance. 2) Individual life Insurance Policies. 3) Group life Insurance
Lecture 2: Descriptive Statistics and Exploratory Data Analysis
Lecture 2: Descriptive Statistics and Exploratory Data Analysis Further Thoughts on Experimental Design 16 Individuals (8 each from two populations) with replicates Pop 1 Pop 2 Randomly sample 4 individuals
Concepts in Investments Risks and Returns (Relevant to PBE Paper II Management Accounting and Finance)
Concepts in Investments Risks and Returns (Relevant to PBE Paper II Management Accounting and Finance) Mr. Eric Y.W. Leung, CUHK Business School, The Chinese University of Hong Kong In PBE Paper II, students
Risk Workshop Overview. MOX Safety Fuels the Future
Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification
State Practices for Administering Schedule Issues
State Practices for Administering Schedule Issues At the August 2011 Subcommittee Meeting in Virginia Beach, the members of the Contact Administration Section agreed to pursue a task regarding State practices
DESCRIPTIVE STATISTICS. The purpose of statistics is to condense raw data to make it easier to answer specific questions; test hypotheses.
DESCRIPTIVE STATISTICS The purpose of statistics is to condense raw data to make it easier to answer specific questions; test hypotheses. DESCRIPTIVE VS. INFERENTIAL STATISTICS Descriptive To organize,
Institute of Actuaries of India Subject CT3 Probability and Mathematical Statistics
Institute of Actuaries of India Subject CT3 Probability and Mathematical Statistics For 2015 Examinations Aim The aim of the Probability and Mathematical Statistics subject is to provide a grounding in
Subcontractor Selection Using Analytic Hierarchy Process
Volume 3 Number 3 2012 pp. 121-143 ISSN: 1309-2448 www.berjournal.com Subcontractor Selection Using Analytic Hierarchy Process Vesile Sinem Arıkan Kargı a Ahmet Öztürk b Abstract: Turkish textile firms
SIMPLE LINEAR CORRELATION. r can range from -1 to 1, and is independent of units of measurement. Correlation can be done on two dependent variables.
SIMPLE LINEAR CORRELATION Simple linear correlation is a measure of the degree to which two variables vary together, or a measure of the intensity of the association between two variables. Correlation
MSW Application Requirements. General Requirements...2. Additional Requirements by Program 4. Admissions Essays...5. International Applicants 7
MSW Application Requirements Page General Requirements...2 Additional Requirements by Program 4 Admissions Essays.....5 International Applicants 7 Statistics Requirement.... 8 1 General Requirements All
Organizing Your Approach to a Data Analysis
Biost/Stat 578 B: Data Analysis Emerson, September 29, 2003 Handout #1 Organizing Your Approach to a Data Analysis The general theme should be to maximize thinking about the data analysis and to minimize
Degree Title Master of Science in IT Strategic Management. University Universitat Pompeu Fabra
ISA Master s in Business & Finance Degree Title Master of Science in IT Strategic Management University Universitat Pompeu Fabra University Overview Founded in 1990, the Pompeu Fabra University is the
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
Quantitative Investment Analysis. 2nd Edition. CFA Institute Investment Series
Brochure More information from http://www.researchandmarkets.com/reports/2242340/ Quantitative Investment Analysis. 2nd Edition. CFA Institute Investment Series Description: Praise for Quantitative Investment
2012-20 CS Awards in Americas
2012-20 CS Awards in Americas Brazil Excellence in Contact Center Bronze -The Art of Customer Relations Canada Customer Service Leader of the Year Customer Service Trainer of the Year Colombia Portafolio
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
THE RELATIONSHIP BETWEEN WORKING CAPITAL MANAGEMENT AND DIVIDEND PAYOUT RATIO OF FIRMS LISTED IN NAIROBI SECURITIES EXCHANGE
International Journal of Economics, Commerce and Management United Kingdom Vol. III, Issue 11, November 2015 http://ijecm.co.uk/ ISSN 2348 0386 THE RELATIONSHIP BETWEEN WORKING CAPITAL MANAGEMENT AND DIVIDEND
How To Test For Significance On A Data Set
Non-Parametric Univariate Tests: 1 Sample Sign Test 1 1 SAMPLE SIGN TEST A non-parametric equivalent of the 1 SAMPLE T-TEST. ASSUMPTIONS: Data is non-normally distributed, even after log transforming.
Description. Textbook. Grading. Objective
EC151.02 Statistics for Business and Economics (MWF 8:00-8:50) Instructor: Chiu Yu Ko Office: 462D, 21 Campenalla Way Phone: 2-6093 Email: [email protected] Office Hours: by appointment Description This course
Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada
DIRECT TESTIMONY OF GERRY SHEERIN, P. ENG ON BEHALF OF PIEDMONT ENVIRONMENTAL COUNCIL BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA CASE NOS. PUE-00-0001 AND PUE-00-000 1 1 1 1 1 1 1 1 1 Q: PLEASE
Final Exam Practice Problem Answers
Final Exam Practice Problem Answers The following data set consists of data gathered from 77 popular breakfast cereals. The variables in the data set are as follows: Brand: The brand name of the cereal