Construction Management Standards of Practice
|
|
|
- Oswald Hensley
- 9 years ago
- Views:
Transcription
1 Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide Jones Branch Drive, Suite 800 McLean, VA USA fax
2 CMAA 2010 Standards of Practice 2.1 Introduction 2.0 Project Management This section discusses the broad subject of project management, which is defined by CMAA as "The use of integrated systems and procedures by a team of professionals during project design and construction. The section focuses on the key components of a Project Management Plan and its development throughout the various project phases. In general terms it outlines key goals and elements of managing a project under the Construction Management format. The general approach addressed here is expanded upon in subsequent Standards of Practice sections on Cost, Time and Quality Management, Contract Administration, Risk Management, Sustainability and Safety. 2.2 Pre-Design Phase Project Organization During this phase of the project the owner must assemble and organize a project team composed of design and Construction Management professionals as well as other key professional, technical and administrative staff necessary to assure the success of the project. This project team must organize its activities to deliver a project that meets the owner's requirements. The project team should include representatives of the owner, the Construction Manager (CM), the design professional, and any specialty professionals that may be required. In some delivery systems, the general contractor is part of the pre-design team. Basic project purposes, goals and parameters of performance particularly cost, time, and quality should be determined and documented by the owner and provided to the project team at the earliest opportunity. The CM and the design professionals should be hired as early as possible. In situations where the CM is hired first, the CM should assist the owner in developing a list of qualified design firms. Additionally, the CM should assist the owner in developing and transmitting the requests for proposals, reviewing the proposals, conducting interviews, evaluating candidates and making recommendations for the award of the design contract. When the design professional is hired first, he may assist the owner in a similar manner in the selection of a CM. The organization of the project should be guided by the following principles: The owner, design professional and CM must establish a relationship of mutual trust and respect. The design professional and CM, while clearly 15
3 having different roles and responsibilities, should function as equals and be so treated by the owner in order to gain the full benefit of the team's collective effort. It is recommended that the procedures outlined in the CMAA document "How to Select a CM" be used in the CM selection process. Each team member must know and understand the other members' responsibilities, in addition to the overall project requirements, prior to signing individual contracts. The best way to accomplish this is by all parties performing a joint review of their respective contracts. The owner, CM, and design professional should then create a responsibility matrix which documents all tasks, action items and authority of all team members. Project Management Plan The CM should work with the owner and the design professional to define the project requirements in the Project Management Plan (PMP). This document, prepared by the CM, should outline the strategies for fulfilling the requirements of the project. The owner should review and approve the PMP before the project proceeds. This document may then be used to measure the performance of the project team and the overall success of the project. Therefore, it is critical that it be understood at the outset by all team members. The PMP typically establishes the scope, budget, schedule, environmental conditions, and the basic systems to be utilized. It also defines the methods and procedures to be followed as well as the basis for claims avoidance on the project. Many conceptual design and estimating iterations may be required before a project meets the owner's time, cost and performance requirements. Once these requirements are established and approved by the owner, the team must be committed to completing the project within those requirements. The PMP and the commitment of all stakeholders to meet its requirements form the foundation for a successful project. Typically, the scope of a project is documented by a combination of conceptual drawings, descriptive narratives, performance parameters, and the budget for the project. The type of information and amount of detail may vary considerably based upon the type of project. Documentation of overall cost and time is the CM's responsibility, with input from the other team members. The establishment of basic systems and procedures by the CM links the task elements of the Plan. A typical PMP may include the following basic components. Some of the components may be developed in later phases of the project as part of the Construction Management Plan: Project description Scope of work Milestone schedule Master schedule Quality management approach Safety management plan Reference to project documents Project organization chart and staffing plan Explanation of roles, responsibilities and authority of team members 16
4 CMAA 2010 Standards of Practice Project budget/work breakdown structure Certification under the LEED program (Leadership in Energy and Environmental Design) Logistics including temporary construction support requirements, i.e. laydown or marshalling area Environmental/archeological considerations Reference to project procedures manual Management information system Communications protocol Bid packaging and contracting strategy, and delivery system evaluation Site mobilization and utilization phase Project Procedures Manual The Project Procedures Manual should be developed as a team effort, assembled and edited by the CM. It should be written so that the responsibilities of the team, levels of authority, communication protocol and the systems, methods and procedures to be followed for project execution are clearly defined and understood. The Manual should address: Cost controls and the systems required for monitoring and controlling project costs Quality control and quality assurance program established by the Team and how it is to be implemented The project schedule and how it is to be developed, implemented and maintained Document control and specific project systems, methods and procedures (i.e., bidding, payments, change orders, submittals, correspondence, reports, performance records, claim resolutions, etc.) Functional responsibilities and limits of authority Correspondence distribution matrix Safety program Check lists Listing of meetings (i.e. type, frequency) Sample forms to be used Detailed bidding and construction phase procedures Coordination among various prime contractors LEED requirements Pre-Design Project Conference The CM should plan, conduct and document a pre-design project conference which addresses the Project Management Plan with respect to the design phase. The conference purpose is to achieve commitment to the project goals and procedures from the owner, the design professional, and the CM. Management Information System The CM should establish a management information system that will inform the team 17
5 about the overall project status and forecast compared to the Project Management Plan. This system should address team information needs, data sources and control elements for time and cost. The system should provide a sound basis for managing the project and identifying and evaluating problem areas and variances. Distribution, frequency of reports, and the policy for record retention should also be established. A comprehensive account of the project can be achieved with record keeping systems such as: General correspondence files (in and out) Periodic reports (daily, weekly, monthly) Drawing schedules, submittals (shop drawings, payments, samples) Transmittals Change requests and authorizations Procurement Material control Meeting minutes Confirmation of oral instructions and field directives Controlled inspections Notice of non-conforming contract work Weather conditions Scheduling records Progress photographs The financial status reports must enable both the owner and the CM to control the available funds in the project. The format of reports should accommodate a continuing input of data. This data should serve as a budgeting and cost control tool on a contract phase and total project basis. Financial reporting should cover budgeted, authorized and committed funds, expenditures to date, cost to complete, invoices, payments and retention, change orders, projected total costs and projected cash flow. The CM should coordinate with the owner's and the design professional's staff to determine the format and frequency of reports required by the team members. Information should include schedule and progress reporting, drawing schedules, budget versus cost of services, and change requests (approved and pending) for design services. The first reports should be issued during the pre-design phase and on an agreed frequency thereafter. 2.3 Design Phase During the design phase the team must continually communicate and consult on all substantive issues. As the process proceeds from schematic through final design, the team must consider the issues critical to each particular phase, moving from general decisions in the early phase to detailed decisions as design progresses. There should be periodic constructability reviews by the CM. The owner and the CM should agree on the scope and number of constructability reviews required. The CM should also coordinate with any needed Value Engineering and alternative studies. The goal is to complete a set of documents defining a project which can be bid in the current local marketplace within the owner's budget and time requirements. 18
6 CMAA 2010 Standards of Practice The design professional has total responsibility for design implementation and execution. The role of the CM during this phase should be to assist the team by carrying out the activities listed below. Although the designer is responsible for design decisions to meet the project requirements, the owner as well as CM and other stakeholders can also have decision making responsibility. Design Document Review The CM should review the design documents periodically, focusing on the need for clarity, constructability, consistency and coordination among the trades and contractors as appropriate. Document Distribution The CM should coordinate the distribution of information among all team members and the transmittal of all documents to regulatory agencies. Contract Agreements The CM should develop and/or review appropriate construction contract agreements for inclusion in the bid documents. General and Supplementary General Conditions The CM should develop or review general and special conditions consistent with project requirements. Public Relations The CM should assist the owner in public relations activities, particularly those with respect to the owner's organization and community relations. The CM should assist the owner in developing interest among bidders for the project(s) also. Project Funding The CM should assist the owner in preparation of documents necessary to secure funding for the overall project. Meetings The CM should conduct periodic project meetings to assess progress, verify adherence to the PMP, document performance, plan for completion, and take action to resolve current problems. At a minimum, these meetings should be held at the end of each design phase. A final team review should be conducted prior to release of each bid package. Recommended subjects for each project meeting include: Review of the project budget and a current estimate of what construction costs the drawings and specifications currently represent, making allowances and assumptions for detail not shown or known 19
7 Review of the Master Schedule, Milestone Schedule and any additional detailed sub schedules for the project Discussion and resolution of any issues which have become evident through previous review of documents and/or team discussion and have not been addressed Cost Control During the design process the CM develops and maintains cost control procedures to monitor and control project expenditures, both current and projected, within the allocated budget. Schedule Control During the design process the CM develops, implements, and modifies the master schedule and the milestone schedule, periodically updating them to reflect actual performance to date. The CM also establishes forecast dates for the completion of the project and advises the owner and designer relative to performance against that baseline. LEED Compliance Either the CM or the LEED Professional shall provide guidance and oversight during design to assure the established LEED goals are being addressed. The CM should have a LEED accredited professional on staff. Ongoing Consulting Activities The CM makes recommendations to team members regarding constructability, cost, phasing and sequencing of construction, construction duration, impact of alternative construction methods and separation of contract categories. At the end of the design phase, designated representatives of each team member review all design documents and concur that they are complete, coordinated, adequately representative of the owner's needs, and suitable for construction. 2.4 Procurement Phase The goal in this phase is to secure bidders for each bid package who are qualified, competitive, interested in the work, and capable of doing the work within the project time requirements. Bidding and Contracting Process The bidding and contracting process is a key element in the success of the project. The CM is responsible for performing or assisting the owner with the following procurement phase activities: Solicitation and pre-qualification of bidders and guidelines by which bidders will be evaluated Notices and advertisements 20
8 CMAA 2010 Standards of Practice Bidders interest campaign Delivery of bid documents Information to bidders Issuance of addenda Bid opening and evaluation Monitoring compliance with and execution of construction contracts Arrangement for owner purchased equipment and materials Provision for permits, insurance and labor affidavits Meetings The following meetings may be part of the bid and award process: Pre-bid meetings Bid openings Pre-award conferences Each of the above tasks and meetings are described in more detail in Section 6.0, Contract Administration. 2.5 Construction Phase The goal in this phase is to expedite and improve the efficiency of the construction process through professional planning and execution of project activities, all focused upon fulfilling the owner's scope, cost, quality, and time requirements. Prior to construction, the CM should develop a project specific Construction Management Plan that clearly identifies the roles, responsibilities and authority of the project team and the procedures to be followed during construction. Below is an outline of key construction phase activities. A detailed identification of separate elements is presented in Section 6.0, Contract Administration. On-Site Facilities The CM should verify that office facilities and site work required for general access and utilities to all on-site organizations are provided. The cost of the work may be paid directly by the owner or by the CM as a reimbursable cost. Alternatively, some or all of the work may be included in individual construction contracts. Coordination The CM provides coordination and leadership of the individual professionals and contractor(s) in meeting the project requirements. To help accomplish this, all communications with professionals and contractor(s) are either through the CM or with his prior knowledge. There is no circumventing of formally established lines of communication by the owner, design professional or individual contractor(s). 21
9 Meetings There are three (3) basic categories of meetings involved in the construction phases: pre-construction, progress, and special meetings. The purpose of pre-construction meetings is to orient all on-site contractors to project procedures and site utilization requirements and to review near term and long term activity plans. The CM will discuss a comprehensive list of contract communication, administrative and coordination requirements including the lines of communication, shop drawing procedures, and general written communication protocol. Progress meetings are designed to monitor compliance with schedules and the requirements of the contract documents to coordinate the contractor(s) efforts and to allow short- and mid-term planning and problem solving. The CM organizes, conducts, and records regularly scheduled progress meetings involving the CM, contractor's principal personnel, the design professional, and the owner, as required. Meetings may be conducted weekly, bi-weekly or at least once a month. Special meetings are called, as necessary, to resolve issues of an immediate or short term planning nature that cannot wait until the regularly scheduled progress meetings, or to discuss issues requiring detailed discussions not suitable for the progress meeting. Although the CM has primary responsibility for determining the need for these meetings, the owner, design professional or contractor may call a special meeting through the CM. Time Management The CM establishes procedures for planning and monitoring compliance with the project time line, which relates to the master and detailed construction schedules. This procedure involves the owner and design professional at appropriate time intervals. It is important that this process also involve the on-site contractors in the development and updating of project schedules. The CM should generate cooperation and obtain commitment from each contractor to complete the project within the owner's time requirements and as required by the contract documents. The CM should also look for opportunities to recover schedule slippages as appropriate. The time management process also forms the basis for evaluating and resolving time related contract claims. Budget and Cost Monitoring For the benefit of the owner, the CM maintains responsibility for tracking, projecting, and monitoring costs through the construction phase. As contracts are awarded, the individual line item estimates are replaced with actual committed amounts, plus cost estimates for any unknowns or contingencies. The goal is to manage the incurred costs, estimated costs and costs to complete in order to stay within the budget. 22
10 CMAA 2010 Standards of Practice Payment Requests The CM should implement procedures for processing contractor's payments in conformance with contract requirements. Monthly meetings should be scheduled to review and discuss the pay request. Change Orders The specific, documented procedures for initiating and approving contractor change orders are implemented by the project team. The CM should take the lead in administering this procedure. Claims Management The CM establishes methods and procedures to minimize the impact of claims through prompt and equitable resolution with minimal disruption to the ongoing construction effort. Procedures should address receiving and disposition of claims submitted, merit evaluation, entitlement evaluation, negotiation and settlement procedures, handling of disputes, and appeal procedures. All claims and potential claims should be discussed weekly at the progress meetings. Quality Management The CM monitors contractor compliance with the quality level expected for the project. The CM develops procedures for monitoring the quality of work being performed. The CM's responsibilities for quality control or quality assurance should be clearly spelled out in the CM's contract. In most cases the construction contractor is responsible for the quality control function and compliance with the quality required by the contract documents. The CM arranges for and coordinates field testing which is not a part of individual contractor's work scope. Acceptance and Performance Testing If so required by the contract, the CM will monitor the acceptance and performance testing to see that it is conducted in accordance with contract requirements. The contractor will need to provide opportunity for observation of these tests by the CM as well as filing all appropriate test reports. Final Inspection and Punch Lists After receiving written requests from the contractor, the inspection staff will consider whether the contract work is substantially complete and will conduct a final inspection with the contractor, project staff and owner s representatives. During the final inspection, the CM develops the project punch list of remaining contract work. If the remaining items are not critical to occupancy or use, the contract will be declared substantially complete. The CM must monitor the completion of the remaining punch list items which should be completed by the time frame specified in the bid 23
11 documents. Upon completion of the punch list, the CM will issue a final inspection report. Owner Occupancy (Partial Acceptance/Beneficial Occupancy) Upon declaring the contract substantially complete, the CM will assist the owner in taking beneficial occupancy of the project. This may include filing of the appropriate reports and approvals before governing boards or other owner representatives. In certain circumstances, partial acceptance can be taken for project elements that are substantially complete. Owner Purchased Materials and Equipment Prior to construction, the CM should identify long lead materials and equipment for pre-purchasing, and other materials and equipment, which could be direct purchased to the owner's advantage. During construction, the CM coordinates scheduling, onsite delivery and storage, and installation and start-up requirements for these materials and equipment. Record Drawings Record drawings should be provided by the contractor(s) doing the work and, minimally, be in the form of a dedicated set of contract drawings and specifications marked up as the work is installed. The CM should monitor the record drawing process monthly during construction in conjunction with review of contractor application for payment, and should receive these drawings at the completion of construction for transmittal to the owner, together with a set of specifications. Record Keeping A smooth, efficient and expeditious flow of paperwork is critical to project operations. The CM should establish systems for flow of all project related paperwork. Management Reporting The CM has a responsibility for establishing a management reporting system to keep the various team members informed on project status. The CM should determine the type, format, frequency and distribution of information and reports required in accordance with the Construction Management Plan and the Project Procedures Manual. LEED Management The CM shall establish a tracking system to monitor compliance with the established LEED goals for the project. Closely associated with acceptance and performance testing is commissioning for the purposes of LEED certification. The CM should be familiar with these requirements and is referred to in the United States Green Building Council publications for reference. The CM, in coordination with the project designer, oversees the commissioning process when an independent commissioning agent is retained. Otherwise, the CM will be responsible for the commissioning 24
12 CMAA 2010 Standards of Practice process. While commissioning is underway, the CM must complete and submit all LEED documentation for certification of points obtainable during the construction process and in accordance with contract documents. It is strongly recommended that, for a LEED project, the CM have a LEED Accredited Professional on staff as an integral part of the project management team. 2.6 Post-Construction Phase Expeditious and effective project close-out is a critical element of a successful project. The CM's responsibility in this phase typically consists of the following: Obtaining LEED certification Completion of punch list items not required for substantial completion Facilitating owner occupancy Assembling record drawings for as-built documentation Warranty, guaranty, and operation and maintenance manuals Pursuing resolution of warranty items Documentation of final pay quantities and costs Preparing contract files for transfer to owner Final payment and contract acceptance Assembling Record Drawings for As-Built Documentation As indicated in the previous section, record drawings are maintained by the contractor and should be inspected monthly during the construction process to ensure the timely submittal of complete documentation to the owner at project completion. These record drawings are then submitted to the owner or design team for generation of the as-built documentation. The CM must ensure that accurate and timely as-built drawings and specifications are provided to the owner as soon after completion of construction as possible. Warranty, Guaranty, and Operation and Maintenance Manuals Prior to project close-out, the CM must gather all warranty, guaranty and O&M manuals, ensure that all comply with contract requirements and submit these to the owner. If specialized training is required, the CM oversees training by the contractor, which usually must occur before formal acceptance of the project. Warranty Administration If requested by the owner, the CM should manage the resolution of all issues identified as warranty issues, including evaluating whether the issue is in fact a warranty issue, notification of the prime contractor and appropriate sales and suppliers, and verification that warranty work is satisfactorily completed. Documentation of Final Pay Quantities and Costs The CM must compile documentation to support final quantities and final payment of unit price items and change order work. Documentation must be sufficient for audit purposes. 25
13 Preparing Contract Files for Transfer to Owner The CM must prepare the contract files in accordance with the owner s requirements to facilitate their transfer to the owner for archiving. Final Payment and Contract Acceptance The CM should support the owner to accept the contract as complete and process the final payment. Final Payment and Closing the Contract The CM assembles all documents relating to final payment, including retention, unresolved change orders and unpaid invoices, for approval by the owner. Once approval is received for the final payment, which resolves all outstanding financial obligations with the contractor, the payment is processed and the contract closed. If there are any claims or adjustments requested by the contractor, the contract cannot be closed until these are completely resolved. Additional information can be found in the sections on Cost Management, Time Management, and Contract Administration for specifics and detail. 26
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
PROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
Manage Deliverables - Construction Step 6. July 12, 2012
Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS
EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS 1.0 SCOPE OF SERVICES 1.1 General Information LAUSD requires construction management services to manage and expedite
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION
REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES Article I Article II Article III Article IV Article V Article VI Article VII Article VIII Article IX Responsibilities of Construction Manager Scope of Construction
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT CONSTRUCTION AUDIT PROGRAM
GENERAL: Some of the Districts largest capital expenditures are from new construction, facility upgrades, and renovations. A single project can run into the millions of dollars, involving engineering,
Request of Qualification Proposal for Construction Management Services
Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications
Construction Management/ General Contractor Alternative Contracting Process
Clean Water State Revolving Fund Loan Program Construction Management/ General Contractor Alternative July 2011 Last Updated: 08/03/2011 By: Larry McAllister DEQ 11-WQ-027 Prepared by: Clean Water State
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES This Professional Design Services (this "Agreement"), made as of 20 by and between the University of Cincinnati (the "University") by the Division of Administration
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES This Master Agreement made this 11 day of December, 2012, by and between the St. Lucie County School Board (hereinafter referred to as the School Board
CONTRACT FOR PROJECT MANAGEMENT SERVICES (Green Repair Program)
CONTRACT FOR PROJECT MANAGEMENT SERVICES () This Contract is made this day of in the year between (day) (month) (year) the, (Owner), Massachusetts (City) (State), (Zip Code) hereinafter called "the Owner"
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
CHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
Construction Manager at Risk
Request for Qualifications (RFQ) Construction Manager at Risk Beaufort County Jail and Sheriff s Office Jim Chrisman, Assistant County Manager/Finance Officer Beaufort County Government Beaufort County
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201
PURCHASE ORDER ATTACHMENT Q-201A Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 1. A qualified employee shall be selected by the Software Quality Manager
Attachment 5 Electrical Engineering
A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or
GUIDELINE. Professional Engineers Providing Project Management Services. Published by Association of Professional Engineers of Ontario
GUIDELINE Professional Engineers Providing Project Management Services 1991 Published by Association of Professional Engineers of Ontario CONTENTS FOREWORD...3 1.0 GENERAL INFORMATION AND DEFINITIONS...3
Design Consultant Project Management Requirements
Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"
Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State
AGREEMENT FOR PROGRAM MANAGEMENT SERVICES WITH SINGLE GENERAL CONTRACTOR DELIVERY (Ocean View Elementary School Project)
AGREEMENT FOR PROGRAM MANAGEMENT SERVICES WITH SINGLE GENERAL CONTRACTOR DELIVERY (Ocean View Elementary School Project) This Program Management Services Agreement ( Agreement ) is made and entered into
COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR
COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR CONSTRUCTION MANAGEMENT SERVICES FOR ORANGE COAST COLLEGE BUSINESS, MATH, COMPUTING CENTER December 14, 2012 PROPOSALS DUE: By 4 p.m. -
AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR
DB-BIM Contract No. 5890 07/14 Project No. 02-3210 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract
Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame
1.0 Inception 1.1 Project Request from Client / User 1.2 Assignment 1.3 1.4 1.5 1.6 1.7 1.8 Preliminary Project Charter Submit Project Charter to Obtain internal project number Initial Project Authorization
MONITORING PERFORMANCE
MONITORING PERFORMANCE Monitoring the performance of the contractor is a key function of proper contract administration. The purpose is to ensure that the contractor is performing all duties in accordance
Local Government Energy Efficiency Resources Guidebook 5: Project Management
Local Government Energy Efficiency Resources Guidebook 5: Project Management Prepared for: Los Angeles County ISD 1100 North Eastern Ave Los Angeles, CA 90063 Prepared by: The Energy Coalition 523 W. Sixth
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way
Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
THIS AGREEMENT is made effective as of this day of in the year of.
STANDARD FORM OF CONSTRUCTION MANAGEMENT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER (Where the basis of payment is Cost of the Work with a guaranteed maximum price) THIS AGREEMENT is made effective
Volume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES
1.0 SCOPE CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES This document establishes the minimum quality program requirements for a contractor providing equipment, material, and construction
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
Exhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
Vendor Performance Evaluation Requirements
Vendor Performance Evaluation Requirements The awarded vendor should note that the Contract Administrator will document the contractor s performance by completing a Vendor Performance Evaluation based
You & Your Architect A GUIDE FOR A SUCCESSFUL PARTNERSHIP.
A GUIDE FOR A SUCCESSFUL PARTNERSHIP. YOU AND YOUR ARCHITECT Architecture isn t only for museums, corporations, and the very wealthy. Whether you are remodeling a kitchen, creating your dream home, or
CONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
REAL ESTATE DEVELOPMENT AND MANAGEMENT CONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PROJECT NO: (Project Number) STATE FLAIR CODE: (Payment Code) PROJECT NAME AND LOCATION: (Project
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE STATE OF IDAHO DEPARTMENT OF ADMINISTRATION DIVISION OF PURCHASING REVISED 01 01 14 Table of Contents I. Purpose... 1 II. Overview of Contract Management and
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program SECTION 1 - GENERAL INFORMATION The Greenville-Spartanburg
Project Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.
Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management
Acquisition Guide Chapter 42.5 Attachment 1 CMP Template. CONTRACT MANAGEMENT PLAN TEMPLATE (Optional) CONTRACT MANAGEMENT PLAN
CONTRACT MANAGEMENT PLAN TEMPLATE (Optional) CONTRACT MANAGEMENT PLAN CONTRACTING ACTIVITY NAME CONTRACT NUMBER DATE Name Contracting Officer Office Symbol, Telephone Number Date Name Head of Contracting
CLASS FAMILY: Business Operations and Administrative Management
OCCUPATIONAL GROUP: Business Administration CLASS FAMILY: Business Operations and Administrative Management CLASS FAMILY DESCRIPTION: This family of positions includes those which perform administrative
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES (Construction Manager At-Risk) FOR PROJECTS IN THE CENTER UNIFIED SCHOOL DISTRICT April 7, 2005 The ( District ) is seeking Statements
San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM
ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for
Generic CMMS Quality Assurance Plan
Generic CMMS Quality Assurance Plan Scope In accordance with the Quality Policy, the Quality System of CMMS is based upon the requirements and structure of ISO (the International Organization for Standardization)
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Recognition of Prior Learning (RPL) Kit. BSB51407 Diploma of Project Management
Recognition of Prior Learning (RPL) Kit BSB51407 Diploma of Project Management Applicant: Date: Diploma of Project Management RPL Kit 1 Applicant declaration: I have completed the following RPL application
Contractor s Guide. April 2016
Contractor s Guide April 2016 The Minnesota Housing Finance Agency does not discriminate on the basis of race, color, creed, national origin, sex, religion, marital status, status with regard to public
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
REQUIREMENTS FOR CERTIFICATION BODIES TO DETERMINE COMPLIANCE OF APPLICANT ORGANIZATIONS TO THE MAGEN TZEDEK SERVICE MARK STANDARD
REQUIREMENTS FOR CERTIFICATION BODIES TO DETERMINE COMPLIANCE OF APPLICANT ORGANIZATIONS TO THE MAGEN TZEDEK SERVICE MARK STANDARD Foreword The Magen Tzedek Commission has established a standards and certification
Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
Public Works Contract Completion
I. Policy A. The Port will formally identify when public works construction contracts are completed in order to administer payments in accordance with Washington statutes and in order to identify warranty
Texas Department of Transportation
Consultant Errors & Omissions Correction and Collection Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection Procedures 1.0 Consultant Contract Administration... 2 2.0
Sample Examination Questions
Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes
A COMPARISON OF PRINCE2 AGAINST PMBOK
Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the
NZQA registered unit standard 25872 version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract
Page 1 of 5 Title Develop and implement a project plan to deliver on an Infrastructure works contract Level 5 Credits 15 Purpose People credited with this unit standard are able to: explain relationship
R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.
2 of 34 Revision Summary Revision Number Date Description of Revisions Initial issue of the document. Table of Contents Item Description Page 1. Introduction and Purpose... 5 2. Project Management Approach...
Work Breakdown Structure Element Dictionary Construction
Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET UCC and CPC MDOS Letters to FileNet PROJECT MANAGER STATEMENT OF WORK (SOW)
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET UCC and CPC MDOS Letters to FileNet PROJECT MANAGER STATEMENT OF WORK (SOW) A Pre-Qualification Program was developed to provide a mechanism for
The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)
The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) is the processes required to ensure that the various elements of the project are properly coordinated. the processes required to ensure
DIRECTORATE OF ESTATES & FACILITIES
DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
CHAPTER 5 - Construction Project Management Contents Introduction... 2 Construction Contract Management... 2 CEI Contracts... 3 Community Awareness Plan... 7 Alternative Contracting Methods... 8 Warranty
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS The North Colonie Central School District invites your firm to submit
Layton Construction Co., Inc. Quality Management Manual
Layton Construction Co., Inc QUALITY MANAGEMENT PLAN 1 Layton Construction Co., Inc. Quality Management Manual [ 2015 ] PHOENIX PHOENIX BOISE BOISE IRVINE IRVINE SALT LAKE CITY SALT ORLANDO LAKE CITY HAWAII
PRIME CONSULTANT SERVICES
GUIDELINES FOR Professional Engineers providing PRIME CONSULTANT SERVICES 1.0 INTRODUCTION 1.1 PURPOSE OF GUIDELINES The "Guidelines for Professional Engineers providing Prime Consultant Services" have
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
MONTGOMERY COLLEGE JOB CLASS SPECIFICATION
MONTGOMERY COLLEGE JOB CLASS SPECIFICATION Title: Project Manager I (Facilities) Grade: J FLSA: Nonexempt Financial Disclosure: No Job Class Level: This includes performance level positions in the Project
SAMPLE CONTRACT FOR CONSTRUCTION WITH GUARANTEED MAXIMUM PRICE (GMP) BETWEEN
CONTRACT FOR CONSTRUCTION WITH GUARANTEED MAXIMUM PRICE (GMP) BETWEEN SEMINOLE TRIBE OF FLORIDA A Federally Recognized Indian Tribe Under 25 U.S.C. 476 ( OWNER ) AND ( CONTRACTOR ) FOR ( PROJECT ) Part
Revised Work Scope Dated April 23 rd, 2015
Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March
Document Management Operations Audit Checklist
PROJECT PLANNING AND START-UP 1. Do document management personnel have copies of reference materials: a. Document Management Standard Practices? b. Computerized Tracking System User Manual? 2. Are document
