STUDY ON THE COST OVERRUNS IN ROAD CONSTRUCTION PROJECTS IN SRI LANKA
|
|
|
- Collin Fox
- 9 years ago
- Views:
Transcription
1 STUDY O THE COST OVERRUS I ROAD COSTRUCTIO PROJECTS I SRI LAKA Eng. S.B. Wijekoon Faculty of Engineering, University of Peradeniya ( [email protected]) Eng. A.M.C.T.K. Attanayake Anuradhapura Provincial Director s Office, Road Development Authority ( [email protected]) Abstract Cost is among the major considerations throughout the project life cycle. The gap between the cost at completion and that originally estimated known as cost overrun can be regarded as one of the most important parameters reflecting the success of projects. Despite its proven importance, it is common to see construction projects failing to complete within the originally estimated cost. Cost overrun is a frequent phenomenon and is associated with most of the projects in the construction industry in Sri Lanka. This trend is seen in the other developing countries where these overruns sometimes exceed 100% of the original cost of the project. The objective of this study are: to identify various factors influencing cost overrun at pre-construction and construction phases of road projects; to rank the factors identified based on their significance and identify the critical factors contributing to cost overruns and to make recommendations to overcome critical identified factors in future road projects Factors influencing cost overruns in road projects were identified during the literature survey and the information gathering sessions and a questionnaire was prepared considering those factors. A survey was carried out to identify significant factors influencing cost overruns in Road Projects. Delays in making payment, delays due to utility relocation, design changes during construction phase, cost escalation and land acquisition related issues have been identified as critical factors influencing cost overruns in road projects. Conclusions and recommendations are made to overcome the critical factors influencing cost overruns in the future road construction projects. Key Words: Cost, Overrun, Construction, Road Projects
2 1. Introduction Road development in the country, which was left behind especially in orthern and Eastern provinces during the last few decades due to the war, has now been considered as a priority item in the government development programme. The ational Road Master Plan has already been prepared, which focuses on the construction and rehabilitation of highways, reduction of traffic congestion, road maintenance and bridge rehabilitation & reconstruction. It has become an urgent necessity for further investment in road network, thus the development of road network has become a major determinant factor in attracting new investments to the country. In line with this allocation of funds for road development has been increased rapidly. Figure 1.1 shows variation of total allocation and expenditure in each year from 2000 to 2010 (Ministry of Highways, 2010). Road Development Authority (RDA) is the state establishment responsible for the maintenance and development of the ational Highway etwork, comprising - the Trunk (A Class) and Main (B Class) roads - planning, designing and construction of new highways, bridges and expressways to augment the existing network. Table 1.1 Shows details of road km in each province in Sri Lanka (Road Development Authority, 2011). Figure 1.1: Allocation of Funds from Year 2000 to 2010 for the Development of Roads Since, the rehabilitation and development of the road network is undertaken mainly from donor funds at a very high cost, the RDA should ensure that adequate economic returns are achieved from the investments made on road development projects. Proper planning should be done to achieve the expected returns and need to consider the factors, which would likely to impact negatively such as,
3 cost overruns, time overruns, scope changes in order to maximize the returns and also to minimize wastage of funds. Table 1.1: ational Road kilometres in Each Province in Sri Lanka Province ational Roads (in Km) Provincial Roads (in Km) Local Roads (in Km) Western province 1,556 1,945 11,295 Southern Province 1,336 1,643 8,201 Sabaragamuwa Province 1,121 1,130 7,254 orth Western Province 1,275 2,118 13,384 Central Province 1,716 2,433 8,283 orth Central Province 1,144 1,771 5,485 Uva Province 1,161 1,839 4,447 orth East (orthern) Province 1,259 orth East (Eastern) Province 1,148 2,653 6,310 Total 11,716 15,532 64,659 It was reported during the data collection stage that majority of projects have not been completed within the agreed time and cost, resulting cost overruns. 2. Objectives Objectives of the study are: To identify various factors influencing cost overrun at pre-construction and construction phases of road projects. To rank the factors identified based on their significance and identify the critical factors influencing cost overruns To make recommendations to overcome the critical factors in future road projects 3. Literature Review Design changes resulted in construction delays can cause critical problems for the developer and the contractor who may incur higher expenses for costs of materials or due to the delays in material deliveries. As a result, all alternatives proposed by the architect or developer should be evaluated and estimated separately from other construction items (Roachanakanan, 2005). Project schedule is a significant element in developing an estimate by identifying the sequence of activities and illustrating the interrelationship of all activities needed to complete the construction. It also shows the availability of project personnel, weather conditions, project resources, and the owner s requirements. One of the main purposes of planning and scheduling a project is to translate the work schedule into a cost schedule or budget (Creedy, 2006).
4 Critical factors influencing cost overruns are: 1. Unpredictable weather, 2. Inflationary material costs, 3. Inaccurate material estimates, 4. Project complexity, 5. Lack of information about the site geography, 6. Lack of contractors experience on certain type of projects, 7. Unfamiliarity with local regulations, (Roachanakanan, 2005) Possible causes of cost overruns from the beginning of projects include omission of some items and out-of-date cost estimates. The cost information such as labour rates, equipment rates and material costs used in estimating should be accurate. These can be obtained from historical data, past projects, a proprietary database, or current material costs (Roachanakanan, 2005). It was revealed at the informal discussion had with project participants attached to employer, consultant and contractor organizations that: changes to rules and regulations, delay in issuing instructions and approvals, mistakes in the tender documents, land acquisition issues, delay in relocating utilities, insufficient time for bidders to prepare tenders, delays in making advance payments and other payments, errors in the original measurements and poor document management are some of the important factors that influence the cost overruns in road projects. 4. Methodology Questionnaire Survey was carried out to gather data from the selected respondents for the study. Frequency Occurrence Index (FOI), Rank Agreement Factor (RAF), Percentage Disagreement and Percentage Agreement methods were used to analyse the data and to rank the factors influencing the cost overruns. 4.1 Questionnaire Survey Detailed questionnaire was prepared using the information gathered during the literature survey and informal discussions with key project participants and distributed among the selected respondents in the road construction industry such as clients, contractors and consultants in orth Central Province (CP), Central Province (CP) and Western Province (WP). The following factors were included in the Questionnaire to gather information from the respondents: 1. Design errors 2. Scope definition 3. Design changes during construction 4. Bad Weather conditions 5. Project key staff 6. Changes to rules and regulations by the authorities 7. Project complexity 8. Delay in issuing instructions and approvals
5 9. Errors in the BOQ 10. Inaccurate quantities in the BOQ 11. Mistakes in the tender documents 12. Land acquisition issues 13. Delay in shifting existing utilities 14. Insufficient time for bidders to prepare tender 15. Delays in making payments 16. Unrealistic work schedule 17. Errors in original measurements 18. Poor document management 19. Cost escalation Table 4.1 shows the number of Questionnaires distributed among the different divisions of Road Organizations and the numbers received. Table 4.1: Distribution of the Questionnaire and the umbers Received Organization umber of Questionnaires Distributed Road Development Authority CP Road Development Authority WP 14 9 Road Development Authority CP 14 7 Provincial Road Development Authority CP 10 3 Road Development Authority Funded Projects 10 4 Road Development Authority Expressway Projects 5 2 Total umber of Questionnaires Received 4.2 Frequency Occurrence Index The Frequency Occurrence Index (FOI) has been using extensively in research work to rank factors from different groups in a survey (Kandegedera and Malaikrisanachalee, 2008) and therefore this method was used to analyse the responses received. The FOI of the factors contributing to cost overruns in projects as perceived by respondents has been calculated and the factors were ranked according to the FOI. The frequency of occurrence index (FOI) is calculated using the following expression: Frequency of occurance index (0 index 1) A w Where,
6 w = weighting given to each factor by the respondents and it ranges from 1 to 5 where, 1. = Very often 2. = Often 3. = Medium 4. = Rare 5. = ever A = Highest weight (i.e. 5 in this case) = Total number of respondents Where x = Mean value Where SD = Standard Deviation 4.3 Rank Agreement Factor In order to quantify the degree of agreement in ranking between different groups of participants, Rank Agreement Factor (RAF) was used (Kandegedera and Malaikrisanachalee, 2008). This shows the average absolute differences in rank of the factors. For any two groups, let the rank of the i th item in Group 1 be R i1 and in Group 2 be R i2, be the number of items and j = i + 1. Then, the Rank Agreement Factor is defined as: RAF i 1 Ri 1 Ri 2 With a maximum RAF: RAF Max i 1 Ri 1 Rj 2 The Percentage Disagreement is defined as: PD i 1 i 1 R R i1 i1 R R i2 j2 ) *100 The Percentage Agreement is then given as:
7 PA = PD A higher value of RAF will suggest a lesser agreement between any two groups. A rank agreement factor of zero would mean perfect agreement. 5. Results and Discussion 5.1 Discussion Respondents were requested to allocate marks from 1-5, for each factor in the questionnaire and using the marks FOI for each factor was calculated. Ranking was done based on the calculated FOI and Table 5.1 shows the top five ranked factors based on FOI. Table 5.1: Top Five Cost Overrun Factors Ranked on FOI Cost overrun factor FOI Rank Payment delays Delay in shifting existing utilities Cost escalation Design changes during construction Issues in Land acquisition Payment delays are ranked as number 1 according to the results in Table 5.1 and the responses confirmed that this is a significant factor in road projects. Most of the road projects are funded by the government, and due to various reasons funds will not be provided in time, causing delays in payment. These delays will eventually affect the contractor s cash flow and finally end up with poor progress of construction works. A delay due to utility relocation is the second highest ranked factor as shown in Table 5.1. Majority of road construction projects start before relocation of utilities and delays to construction works are inevitable due to these reasons. It is very important that during design stage scope of utility relocation to be identified and starts the relocation process to avoid any delays to construction activities. The third ranked cost overrun factor is the cost escalation. Cost escalation refers to the increase in the amount of money required for a project over and above the original budget. Cost escalation is mainly due to changes in the cost of labour, material, plant and other construction activity related costs and no party has a control over the cost escalation. This is mainly due to inflation and is the most critical cost overrun factor among other factors. Increasing of prices for Labour and Material is a common issue. Therefore, to avoid cost escalation, proper planning at the procurement stage is vital. At the construction phase, the contractor should carryout construction works without allowing it to drag unnecessarily. A standard cost escalation formula is included in all construction contracts in Sri Lanka for this purpose and funding provisions under contingencies are used to settle the cost due to cost escalations.
8 Design changes during construction is the fourth ranked cost overrun factor as shown in Table 5.1 Inadequate site investigation is the main cause for design changes. Therefore, adequate investigations are necessary to do a complete and accurate design. If this issue is not addressed at the design stage there will be additional costs incurred by the employer. The fifth ranked cost overrun factor is land acquisition and related issues. Majority of road construction projects are delayed due to the land acquisition and objections from the land owners for take over their lands. Impact on land acquisition in road construction is very serious and it delays the road construction activities significantly resulting cost overruns. Therefore, it is important to introduce mechanisms to overcome this issue at the planning stage. It is essential to introduce a national policy and also to amend the land acquisition related acts and laws to enable the road authorities to carryout land acquisitions faster. Early and timely actions to plan, identify and implement land acquisitions related issues are also important to resolve this problem. Mean value for each factor was calculated using the marks allocated to each factor by the respondents. Table 5.2 shows the Cost overrun Factors ranked based on Mean Values. Table 5.2: Cost Overrun Factors Ranked Based on Mean Value Cost overrun factor Mean value Rank Payment delays Delay in shifting existing utilities Cost escalation Design changes during construction Issues in Land acquisition Both methods used for the analysis show similar results and therefore it can be concluded that the methods used to analyse data are acceptable. Agreement and disagreement between senior engineer s and young engineers are computed and compared. At the group selection it was assumed that those who have ten years experience and more as senior members and others as junior members. Rank agreement factor (RAF) between young engineers and senior engineers is 3.5. The maximum Rank Agreement factor recorded is Therefore, percentage agreement is 65.35%. Hence; the percentage of agreement (PA) is higher than 50%, which means majority of members in both groups are in agreement with the top five ranked factors for cost overruns in road construction projects. 6. Conclusions and Recommendations 6.1 Conclusions Cost overruns are predominant in road construction projects in Sri Lanka and during this study an effort was taken to highlight critical factors influencing project cost overruns, through a Questionnaire Survey. Critical cost overrun factors that were observed according to the respondents perceptions are
9 payment delays, delay in relocation of existing utilities, cost escalation, design changes during construction and issues in land acquisitions. To verify the accuracy of the results, two different methods of analysis were carried out during the study and those methods are: Frequency occurrence index (FOI) and mean value (MW). Further, rank agreement factor (RAF), percentage agreement (PA) and percentage disagreement (PD) factors were used to verify the adequacy of results. RAF and PA between senior engineers and young engineers category were 3.5 and 65.35% respectively which shows higher agreement between the two groups selected. 6.2 Recommendations In order to avoid payment delays in road projects, it is recommended to provide a realistic time period in the conditions of contract clearly indicating the specific time periods for each party to prepare, recommend and certify the claims. Also to prepare an accurate financial plan indicating the amounts of funds required with the dates of disbursement and regular update of these plans. Identification of the scope of utility relocation with the assistance and the support of the utility authorities at the pre construction stage is recommended to avoid these delays. Further it is recommended to form an effective Utility Committee comprising of members representing all project groups including representatives from the utility authority. A realistic cost escalation factors should be calculated by accurate prediction of the future cost escalation and the amount of funds required should be included in project estimates. Sufficient time period should be provided for the designs and especially for the design review to avoid design changes during construction. Early identification of the lands to be acquired for the project is an important requirement to avoid these delays. Providing training on Land Acquisition Procedure for the project staff and effective coordination with the authorities e.g. Divisional Secretary are recommended. References Assaf, S.A. and Al-Kahalil, M. (1995). Causes of Delay in Large Building Construction Projects, Journal of Project Management in Engineering, ASCE, 2; Bent, F. and Mette, K. (2005). What Causes Cost Overrun in Transport Infrastructure Projects, Buhl Department of Development and Planning: Aalborg University: Aalborg, Denmark. Chung-li, T. (2006). Managing Cost Overrun Risk in Project Funding Allocation, Department of Engineering Management & Systems Engineering: University of Missouri-Rolla, Rolla,
10 Creedy, G.D. (2006). Risk factors leading to cost overrun in the delivery of Highway construction projects, Queensland University of Technology, 1: Daniel, W.M.C. and Kumaraswamy, M.M. (1996). A comparative study of causes of time overruns in Hong Kong construction projects, Department of Civil and Structural Engineering: The University of Hong Kong: Pokfulam Road, Hong Kong. Fedric, G. (1997). Managing the Construction Process, Upper Saddle River: Prentice Hall. Frederick, H. and Lieberman, G. (2001). Introduction to Operations Research, 7th edi: Boston. Institute for Construction Training and Development, (ICTAD), 2004 Publication o ICTAD/SBD/01, ICTAD/SBD/02 and ICTAD/SBD/03. Kandegedera, P.M.S.B. and Malaikrisanachalee, S. (2008). Analysis of Delays in Highway construction projects In Sri Lanka, Faculty of Engineering: Kasetsart University, Bangkok. Killingsworth, R. (1988). Cost Control in Building Design. Martin, B. (2006). Swedish Construction Clients Forum R&D and University Relations, Byggherre Forum Vasagatan 52: Stockholm. Maurice, M. M. (2000). A Statistical Analysis of Determinants of Project Success: Strategic Planning and Research Department and Steve Kayizzi-Mugerwa, Department of Economics: Göteborg University. Ministry of Highways: Performance of Progress of Road and Bridge Projects (2010). Munns, A.K. (1996). The role of project management in achieving project success, university of Dundee: Department of Civil Engineering, Dundee, Scotland DD1 4H, UK 1, Project Management Institute (PMI) (2008). A guide to the Project Management Body of Knowledge, Fourth Edition, PMBOK: Atlanta. Roachanakanan, K. (2005). A case study of cost overruns in a Thai condominium Project Texas: A&M University.5-7, Road Development Authority. (2011). ational Highways in Sri Lanka, Available at Saleh, A.H.T. (2009). Causes of delay in construction industry in Libya, School of Housing: Building and Planning: University Sains Malaysia, Malaysia.
11 Sri Lanka Strategy for Sustainable Development. (2007). Ministry of Environment and atural Resources. Vidalis, S.M. and ajafi, F.T. (2002). Cost and time overruns in highway construction, Department of Civil and Coastal Engineering: University of Florida.
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
Characteristics of the Participants
3 Financial Analysis for Replacement of Construction Equipment in Saudi Arabia Ali A. Shash (Center for Engineering Research, Research Institute, King Fahd University of Petroleum & Minerals, Saudi Arabia)
2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines
2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects
Cost Deviation in Road Construction Projects: The Case of Palestine
Cost Deviation in Road Construction Projects: The Case of Palestine Ibrahim Mahamid and Amund Bruland, (Norges Teknisk-Narurvitenskapelige Universitet, Norway) Abstract This paper investigates the statistical
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
Power Sector. Managing EPC Power Project
Power Sector Managing EPC Power Project ABSTRACT Engineering, procurement and construction (EPC) Contract are the most common form of Project used to undertake construction works by the Public and private
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
International Journal of Project Management 21 (2003) 321 326 www.elsevier.com/locate/ijproman Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project
Ex-Ante Evaluation (for Japanese ODA Loan)
Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Democratic Socialist Republic of Sri Lanka Project: New Bridge Construction Project over the Kelani River
Value for Money Unit Local Government Audit Service
Value for Money Unit Local Government Audit Service Report on Spot Checks of Capital Projects funded by the Department of the Environment, Heritage and Local Government and undertaken by Local Authorities
Developing a framework model of Supply Chain Management : A case study on a Mega construction project in Myanmar.
Proposal for PhD Research Yadanar Soe ID: 1140937 Course Title: PhD Research (Construction Management) [email protected], [email protected] Lead Supervisor: Dr M An Co Supervisor: Dr J Yang Title Developing
CAPITAL PROJECTS IMPLEMENTATION
CAPITAL PROJECTS IMPLEMENTATION 2.4 Over the years, I have been reporting on the shortcomings encountered during implementation of projects. These include, among others, excessive delays, variation costs,
Hansani Chathurika Dassanayake a a University of Peradeniya, Sri Lanka. [email protected]. Abstract
Reshaping Management and Economic Thinking through Integrating Eco-Friendly and Ethical Practices Proceedings of the 3 rd International Conference on Management and Economics 26-27 February 2014 Faculty
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING
EFFECTIVENESS OF COMPUTER APPLICATIONS IN MANAGEMENT OF BUILDING CONSTRUCTION PROJECTS IN SRI LANKA
EFFECTIVENESS OF COMPUTER APPLICATIONS IN MANAGEMENT OF BUILDING CONSTRUCTION PROJECTS IN SRI LANKA By GEORGE PREMAN JEYAWEERASINGHAJVI cgte3q9 IMS Q Q S A PROJECT REPORT SUBMITTED IN PARTIAL FULFILLMENT
A Road Map for Disaster Risk Management
Towards a Safer Sri Lanka A Road Map for Disaster Risk Management December 2005 Disaster Management Centre Ministry of Disaster Management Government of Sri Lanka Supported by U N D P United Nations Development
P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project
P3 Value for Money Assessment and Project Report Evan Thomas Water and Wastewater Treatment Facility Project July 2013 Table of Contents 1. Summary: Using a P3 for a Water Treatment Plant - did it work?
Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals
Journal of Construction in Developing Countries, Vol. 16(1), 41 67, 2011 Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Visuth Chovichien
Technical Report Documentation Page. 2. Government Accession No. 3. Recipient's Catalog No. 1. Report No. FHWA/TX-13/0-6737-1
1. Report No. FHWA/TX-13/0-6737-1 4. Title and Subtitle EXECUTIVE REPORT: TOLL ROADS, TOLL RATES, AND DRIVER BEHAVIOR 2. Government Accession No. 3. Recipient's Catalog No. Technical Report Documentation
Causes and effects of delays in Malaysian construction industry
International Journal of Project Management 25 (2007) 517 526 INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT www.elsevier.com/locate/ijproman Causes and effects of delays in Malaysian construction industry
BALANCE SCORE CARD - A STRATEGIC PROJECT MANAGEMENT TOOL FOR INFRASTRUCTURE DEVELOPMENT PROJECTS
BALANCE SCORE CARD - A STRATEGIC PROJECT MANAGEMENT TOOL FOR INFRASTRUCTURE DEVELOPMENT PROJECTS Eng. Udana Amarasuriya Department of Civil Engineering, University of Moratuwa, Sri Lanka; Associate Member,
INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073
INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073 Audit of maintenance and building services provided by the Office of Central Support Services at Headquarters Overall results relating to the Office of Central
PROJECT MANAGEMENT INFORMATION SYSTEMS FOR CONSTRUCTION MANAGERS (CM): CURRENT CONSTITUENTS AND FUTURE EXTENSIONS
PROJECT MANAGEMENT INFORMATION SYSTEMS FOR CONSTRUCTION MANAGERS (CM): CURRENT CONSTITUENTS AND FUTURE EXTENSIONS Youngsoo Jung 1 *, Heea Kim 1, and Mihee Joo 2 1 College of Architecture, Myongji University,
Cost Control Techniques Used On Building Construction Sites in Uganda
Cost Control Techniques Used On Building Construction Sites in Uganda George Otim 1, Fiona Nakacwa 2, Michael Kyakula 3 1 PhD Student, Faculty of Technology, Makerere University, P. O. Box 7062, Kampala,
Public Administration Leadership and Management Academy
Vote 8 Public Administration Leadership and Management Academy Budget summary 2009/10 2010/11 2011/12 Total to be Current Transfers and Payments for R million appropriated payments subsidies capital assets
Elevated Roads for Sri Lanka
Elevated Roads for Sri Lanka M.T.R. Jayasinghe (Senior Professor, Structural Engineering, University of Moratuwa) Senior Professor M.T.R. Jayasinghe is a Professor of Structural Engineering, University
Material waste in the China construction industry: Minimization strategies and benefits of recognition
INTERNATIONAL JOURNAL OF ENERGY AND ENVIRONMENT Volume 5, Issue 6, 2014 pp.717-722 Journal homepage: www.ijee.ieefoundation.org Material waste in the China construction industry: Minimization strategies
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects Dr. Rashad Zakieh (PMP) 27 April, 2010 Copyright Saudi Aramco, 2010. All rights reserved.
Procurement requirements for reducing waste and using resources efficiently
Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction
National Electric Power Regulatory Authority
National Electric Power Regulatory Authority MECHANISM FOR DETERMINATION OF TARIFF FOR HYDROPOWER PROJECTS Preamble Conservative estimates show total hydroelectric potential in the country to be 45000
Ashghal (or the Public Works Authority) is the government organisation responsible for providing major infrastructure for the State of Qatar.
Quantity Surveyor Summary of Position To support Commercial & Procurement section of the Expressway Department of Ashghal, in pre-contract and post contract functions required within the team. This includes
Case Studies in Engineering Economics for Electrical Engineering Students
Case Studies in Engineering Economics for Electrical Engineering Students Robert Barsanti 1 Abstract Undergraduate students are often faced with the challenge of trying to relate the theories and concepts
Feasibility. A guide to feasibility planning for junior mining companies
Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Feasibility A guide to feasibility planning for junior mining companies
TRAINING NEEDS IN CONSTRUCTION PROJECT MANAGEMENT IN PORTUGAL
INTERNATIONAL CONGRESS ON PROJECT ENGINEERING VALENCIA, September 13-15, 2006 TRAINING NEEDS IN CONSTRUCTION PROJECT MANAGEMENT IN PORTUGAL J. C. Teixeira (s), B. R. Pires Abstract Training in construction
A CASE STUDY OF COST OVERRUNS IN A THAI CONDOMINIUM PROJECT
A CASE STUDY OF COST OVERRUNS IN A THAI CONDOMINIUM PROJECT A Dissertation by KWANCHAI ROACHANAKANAN Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of the requirements
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Evaluating the effects of communication in construction project delivery in Nigeria
Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5): pp 048-054, June, 2014. Copyright 2014 Spring Journals Full Length Research Paper Evaluating the effects of communication
AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts
11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Risk Allocation in Construction Contracts Risks 2 In the absence of a contract, all risks are the owner's Contracting is
1. Project Profile and Japan s ODA Loan
Sri Lanka Transmission and Grid Substation Development Project 1. Project Profile and Japan s ODA Loan Report Date: September 2002 Field Survey: July/August 2001 Site Map: Sri Lanka Site Photo: Matara
A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
Construction Claims in
Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial
The automotive manufacturing sector is
BUILDING A SUSTAINABLE WORKFORCE: APPRENTICESHIP IN THE CANADIAN AUTOMOTIVE INDUSTRY The Canadian Automotive Manufacturing Industry at a Glance The automotive manufacturing sector is struggling in the
Understanding and Monitoring the Cost-Determining Factors of Infrastructure Projects. A User's Guide
Understanding and Monitoring the Cost-Determining Factors of Infrastructure Projects A User's Guide Table of contents 1. Introduction 3 2. Understanding The Project Development Process 4 3. Initial Project
Review of Business Information Systems Second Quarter 2009 Volume 13, Number 2
An Investigation Into Computerized Estimating Software Used In Accounting For Cost Estimates By Residential Builders Mark D. Law, Bloomsburg University, USA Gary S. Robson, Bloomsburg University, USA ABSTRACT
V1.0 - Eurojuris ISO 9001:2008 Certified
Risk Management Manual V1.0 - Eurojuris ISO 9001:2008 Certified Section Page No 1 An Introduction to Risk Management 1-2 2 The Framework of Risk Management 3-6 3 Identification of Risks 7-8 4 Evaluation
REPORT OF THE ACTING MUNICIPAL MANAGER 1. INTRODUCTION / BACKGROUND TO REPORT
GOOD GOVERNANCE: SUPPLY CHAIN MANAGEMENT REPORT: IMPLEMENTATION OF THE SUPPLY CHAIN MANAGEMENT REGULATIONS WITHIN THE PERIOD 01 JULY 2014 TO 30 JUNE 2015 (2014//2015 FINANCIAL YEAR) REPORT OF THE ACTING
Contract Management. Brief 22. Public Procurement. September 2011
Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This
THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge
Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside
Technical note. 1. Background. 2. Document Purpose. Project: A350 Chippenham Dualling
Project: A350 Chippenham Dualling Subject: Benefits Realisation Plan & Monitoring and Evaluation Plan Date: 14 February 2013 1. Background Restrictions to the capacity of the A350 to the north of Chippenham
Assessment of Critical Success Factors for Construction Projects in Pakistan
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of
Budgetary Planning. Managerial Accounting Fifth Edition Weygandt Kimmel Kieso. Page 9-2
9-1 Budgetary Planning Managerial Accounting Fifth Edition Weygandt Kimmel Kieso 9-2 study objectives 1. Indicate the benefits of budgeting. 2. State the essentials of effective budgeting. 3. Identify
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: [email protected] 2 Asso.
THE RELATIONSHIP BETWEEN CLASSROOM MANAGEMENT STYLES OF TEACHERS AND THE OCCURRENCE OF DISCIPLINE PROBLEMS IN INTERNATIONAL SCHOOLS BANGKOK, THAILAND
THE RELATIONSHIP BETWEEN CLASSROOM MANAGEMENT STYLES OF TEACHERS AND THE OCCURRENCE OF DISCIPLINE PROBLEMS IN INTERNATIONAL SCHOOLS BANGKOK, THAILAND NESSRINE CHELLAL, [email protected] Advisors:
photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada
photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada For more than 200 years and with few exceptions, Canada s municipal
PRACTICE NOTES FOR QUANTITY SURVEYORS
PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong
Delay Analysis in Construction Project
Delay Analysis in Construction Project Abstract Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often result of
Capital Projects and Construction: Building in Risk Management and Project Controls
Capital Projects and Construction: Building in Risk Management and Project Controls Making Every Dollar Count The global economic crisis sparked by the subprime mortgage debacle, the collapse of the securitized
Project Time Management an essential element to project success
Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects
The Overview of Tanzania Legal Framework on Contract Management
The Overview of Tanzania Legal Framework on Contract Management OUTLINE 1. Introduction; 2. Public Procurement System; 3. Legal and Regulatory Framework; 4. Contract Formation; 5. Construction Contract
CONTEMPORARY HUMAN RESOURCES MANAGEMENT IN DEFENSE SYSTEM. Gajić Željko. Strategic Planning Department, Ministry of Defense, Serbia
CONTEMPORARY HUMAN RESOURCES MANAGEMENT IN DEFENSE SYSTEM Gajić Željko Strategic Planning Department, Ministry of Defense, Serbia Abstract: The way the human resources are managed is becoming a decisive
Texas Department of Transportation
Consultant Errors & Omissions Correction and Collection Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection Procedures 1.0 Consultant Contract Administration... 2 2.0
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
LONDON CORPORATE ASSET MANAGEMENT PLAN 2014
LONDON CORPORATE ASSET MANAGEMENT PLAN 2014 ACKNOWLEDGEMENT Acknowledgement The Corporate Asset Management office would like to acknowledge the efforts of the staff of the individual City of London Service
The World Bank. 1 System choice
Selecting road management systems (Source: Robinson, R, 1995. Rethinking policy, strategy and information under severe budget constraints: management information and tools to prioritise works. In: World
Cost components. Why estimate? You may ask; why do we need estimates? Estimating can help to: Total project costs. Profit added FINAL BID
Estimating costs for infrastructure projects is a very complex task which requires a lot of experience. It is important that you understand at least the principles of costing. Why estimate? You may ask;
Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases
Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases Contents Background.............................................................. 183 Scope...................................................................
American Journal Of Business Education July/August 2012 Volume 5, Number 4
The Impact Of The Principles Of Accounting Experience On Student Preparation For Intermediate Accounting Linda G. Carrington, Ph.D., Sam Houston State University, USA ABSTRACT Both students and instructors
Sri Lanka Accounting Standard -LKAS 11. Construction Contracts
Sri Lanka Accounting Standard -LKAS 11 Construction Contracts -405- Sri Lanka Accounting Standard -LKAS 11 Construction Contracts Sri Lanka Accounting Standard LKAS 11 Construction Contracts is set out
Developing a Public-Private Partnership Framework: Policies and PPP Units
Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework
The FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand.
Poverty Indicators Household Income and Expenditure Survey - 2006/07 Department of Census and Statistics Ministry of Finance and Planning Sri Lanka
ISSN 1391-4695 March 2008 Poverty Indicators Household Income and Expenditure Survey - 2006/07 Department of Census and Statistics Ministry of Finance and Planning Sri Lanka Introduction The Household
GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses
GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses Office of Government Procurement Cost Control: Price Variation Clauses Document Reference GN 1.5.2 v1.0 22 January 2016 2016 Department of Public
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
PROJECT COST ESTIMATING GUIDELINES
PROJECT COST ESTIMATING GUIDELINES Version 01.02 September 30, 2013 Ministry of Transportation and Infrastructure Project Management Support Services Planning and Programming Branch 5C 940 Blanshard Street
Efficiency Review by Sir Philip Green
Efficiency Review by Sir Philip Green Key Findings and Recommendations The Government is failing to leverage both its credit rating and its scale 1 Introduction I was asked by the Prime Minister in mid
Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting
Rebuilding Flood Damaged Roads in South East Queensland in the middle of the Coal Seam Gas Expansion/Explosion - A Local Governments Experience and Learning's David Pemberton [email protected] Mobile
Annual Meeting of Senior PPP Officials 2010
Paris _ 12th of April 2010 PPP Risk Pricing PPPs Vs Traditional Procurement PPPs Strengths PPPs around the World Best PPPs Practices PPP Risk Pricing DESIGN DIFFERENT PPP DELIVERY MODELS BOT BUILD FINANCE
Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP
Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting
Construction Bond Audit Report. Office of Auditor General
Construction Bond Audit Report (This page was left blank) TABLE OF CONTENTS Executive Summary 5 Background, Scope and Objectives, and Methodology....7 Audit Findings, Recommendations, and Management s
Causes and Effects of Delays in Large Construction Projects of. Pakistan
Causes and Effects of Delays in Large Construction Projects of Pakistan M. Haseeb 1, a, Xinhai-Lu 1, Aneesa Bibi 1, Maloof-ud-Dyian 2, Wahab Rabbani 3 1 College of Public Administration, Huazhong University
edms 5. THAILAND 5.1 Water Resources Management Policies and Actions
5. THAILAND 5.1 Water Resources Management Policies and Actions In Thailand, the Office of Natural Resources and Environmental Policy and Planning issued the State of Environment Report 2004, which has
Auditing Capital Projects and Project Controls. March 2013
Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate
Project Implementation Plan (PIP) User Guide
eea financial mechanism Project Implementation Plan (PIP) User Guide 23 November 2007 norwegian financial mechanism Page 2 of 20 1 Introduction The Project Implementation Plan (PIP) is a representation
Capital Procurement Checklist - Overview
Checklist - Overview The Ministry of Finance has recently implemented a capital procurement checklist to support the Asset Management Framework (CAMF) and related provincial policies for capital projects.
Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery
Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery By Bob Prieto Design Bid Build (DBB) and Design Build Finance Operate Maintain (DBFOM) project delivery differ
Early Cost Estimating for Road Construction Projects Using Multiple Regression Techniques
Early Cost Estimating for Road Construction Projects Using Multiple Regression Techniques Ibrahim Mahamid, (Hail University, Saudi Arabia) Abstract The objective of this study is to develop early cost
Incorporating Risk Assessment into Project Forecasting
Incorporating Risk Assessment into Project Forecasting Author: Dione Palomino Conde Laratta, PMP Company: ICF International - USA Phone: +1 (858) 444-3969 [email protected] Subject Category: Project
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
Impact of Credit Risk Management on the Performance of Commercial Banks in Sri Lanka
Impact of Credit Risk Management on the Performance of Commercial Banks in Sri Lanka Abstract: MS. SUJEEWA KODITHUWAKKU Department of Business Finance, Faculty of Management, University of Peradeniya Sri
BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi
BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value Professor Mustafa Alshawi Improving Project Performance Current Project Portfolio 1.83 B UAED ($500M) Award Winning
What went wrong? Unsuccessful information technology projects
Brenda Whittaker Senior Consultant, KPMG Consulting, Toronto, Canada words Computer software, Information technology, Project control, Project management, Software development Abstract Information technology
Guidelines for the UN.GIFT Call for Proposals from Civil Society Organizations
Guidelines for the UN.GIFT Call for Proposals from Civil Society Organizations 1. INTRODUCTION... 3 1.1. Objective of the guidelines... 3 1.2. UN.GIFT... 3 1.3. UN.GIFT Small Grants Facility... 3 1.4.
July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services
John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services
CHAPTER 2 CONTRACT STRATEGY
CHAPTER 2 CONTRACT STRATEGY At the early stage of a project and once a project manager is selected, the main issue that faces the owner is to decide on the contract strategy that best suits the project
