Identification of Late Deliverables and Their True Impacts to Industrial Construction Projects
|
|
|
- Jocelin Robertson
- 10 years ago
- Views:
Transcription
1 2296 Identification of Late Deliverables and Their True Impacts to Industrial Construction Projects William BARRY 1, Fernanda LEITE 2, and William J. O BRIEN 3 1 MS Student, Construction Engineering and Project Management Program, Department of Civil, Architectural and Environmental Engineering, The University of Texas at Austin, 1 University Station C1752, Austin, TX 78712, [email protected] 2 Assistant Professor, M. ASCE, Construction Engineering and Project Management Program, Department of Civil, Architectural and Environmental Engineering, The University of Texas at Austin, 1 University Station C1752, Austin, TX 78712, [email protected] 3 Associate Professor, M. ASCE, Construction Engineering and Project Management Program, Department of Civil, Architectural and Environmental Engineering, The University of Texas at Austin, 1 University Station C1752, Austin, TX 78712, [email protected] ABSTRACT Given that a construction site is both temporary and unique, the outcome of every construction project is dependent upon having all of the proper resources delivered to the site at the appropriate time. Although construction supply chains, logistics, and materials management systems have been scrutinized in recent years, the full range of potential late deliverables has not yet been investigated. Furthermore, the true impacts of these late deliverables are much more far-reaching and less understood. This paper, part of a larger research project being developed by the Construction Industry Institute Research Team 300, describes the process followed to list and categorize common late deliverables to industrial construction sites using team knowledge, expert interviews, industry surveys, and in-depth case studies as well as a review of the existing literature on the topic. This information will serve as a starting point for an investigation into how these late deliverables impact the cost, schedule, quality, and safety performance of construction projects along with the effects on the organizations involved. The enumeration and classification of these project impacts, incorporating the perspectives of both owners and contractors, are also described in this paper. KEYWORDS Late Deliverables, Impacts, Construction Site INTRODUCTION The construction industry is an integral part of a country s economy, yet it is an industry constantly plagued by poor cost, schedule, and safety performance, low profit margins, poor productivity, compromised quality, price escalation, and a lack of innovation worldwide (Yeo and Ning, 2004). Of the countless factors that lead to these performance issues, materials delivery and handling has been identified as a major concern for the industry. A significant amount of research has been conducted
2 2297 within the field of construction supply chain management, materials management, stakeholder relationships, and work packaging in an attempt to improve the reliability of construction material delivery and coordination on site. However, supply chain materials represent only a fraction of the late deliverables to construction sites that can adversely affect the time, cost, quality, and safety performance of the industry. Very little existing research investigates the full spectrum of resources that must be in place for a project to succeed, and these resources are often poorly tracked throughout a project. Moreover, the broad impact of late deliverables to construction projects is even less understood. Construction projects have multiple and often conflicting objectives that must be met for a project to be considered a success. Both the construction industry and a project s goals are dynamic in nature, and success means different things to different people at different points in a project lifecycle (Chan and Chan, 2004). Typically, time and cost performance are the predominant criteria, but these are not the only indicators of project success or failure. In construction, safety and quality risks, although less often measured, are equally important in determining the outcome of a project. These make up the third and fourth set of objectives that must be managed appropriately for a project to succeed. A fifth set of objectives exists within the realm of the companies and individuals participating on a project. Each stakeholder, from the company involved to an individual laborer, has a set of objectives and expectations that contribute to and are derived from the project s outcomes. These measures for a company can include the profit of the project, the opening of a new market or project capability, technology innovations, and an improved reputation or relationship. For the individual stakeholders, goals can include morale, working relationships, advancement in the company, or recognition. This organizational capacity, along with the aforementioned cost, schedule, quality, and safety goals of a project, comprise the five pillars of project performance being investigated as part of this research. Though the goals and objectives of individual and organizational stakeholders are both abundant and dynamic, they must be collectively managed for a project to succeed. In order to aid the construction industry in successfully meeting these five pillars of project performance, the Construction Industry Institute (CII) has commissioned Research Team 300 to enumerate common late deliverables to the construction site for industrial projects. Further, the research team is challenged to both identify and describe, both qualitatively and quantitatively, the true impacts these late deliverables have throughout a project s lifecycle. The final objective of the research team is to identify, where possible, leading indicators of late construction deliverables. This paper describes in detail the data gathering methods used by the research team in pursuit of these objectives. LITERATURE REVIEW This literature review contains an investigation into the types of late deliverables that affect the construction industry as well as how they have been shown to affect individual projects across all industries and sectors. The study of relevant literature reveals that there is great variety in potential late deliverables, and the impacts caused by each are similarly numerous and diverse. The impacts found in
3 2298 a literature review are far-reaching and difficult to categorize, but the effects have been well documented in a range of studies covering different topics. Early studies in construction motivation reveal that crews were demotivated by a lack of materials and tools, foreman were dissatisfied with poor working arrangements such as missing essential materials and equipment, and superintendents were frustrated by delayed architectural and engineering drawings to the site (Borcherding, 1972). From this, it can be deduced that field workers at all levels are dependent upon proper resource management not only for effective work and productivity, but also for job satisfaction. Along with impacting crews, it is well known that late deliverables can lead to construction delays, and these delays are huge impediments to project success. Knowing this, significant amounts of research have investigated the various causes of construction delays, and several studies have explicitly drawn the link to late deliverables. One study examining the causes of construction delays in Hong Kong attempted to enumerate and rank the most significant factors that delayed building projects using interviews with contractors, clients, and consultants (Kumaraswamy and Chan, 1998). The top ten factors identified as delay causes in the study were ranked by a calculated relative importance revealing that four of the top ten hypothesized factors in the study can be directly associated with late informational or physical deliverables to the construction site. These include delays in design information (#3), lack of communication between consultant and contractor (#4), client-initiated variations (#7), and improper control of site resource allocation (#10). These four factors can all be attributed to a delayed delivery of necessary resources to the construction site (i.e. designs, correspondence, materials, equipment). Perhaps more importantly, of the four primary stakeholders identified (design team, project team, contractor, and client), each is responsible for one of these delay causes. Thus, it is both the opportunity and responsibility of each stakeholder to make resources available to the site at the appropriate times. In assessing the risk to the construction schedule, it is easy to identify additional resources that, if not available at the right time, can delay the project. One study identified 85 specific risks to project schedules, with on-time delivery of resources and one of the highest risk factors for the procurement phase (Mulholland and Christian, 1999). A similar study into the causes of delay to large construction projects revealed 73 causes of delay for projects in Saudi Arabia (Assaf and Al-Hejji, 2006). Lateness and unavailability of resources made up 26% of the observed delay causes for the sample of projects. Of the 73 causes of delay, 19 are attributable to late deliverables, including late payments, designs documents and reviews, decisions by owners, engineers and consultants, site availability, materials, and permits along with shortages of equipment and labor. Of important note from the study is that every project stakeholder can cause delay through late delivery of required information, materials, or human resources (Assaf & Al-Hejji, 2006). One specific late deliverable that can cause serious delays to a construction project is various permits, which can be internal or external to the project. One inquiry found that building permit approvals were the most critical cause of delay for a selection of 380 building projects in the state of Florida (Ahmed et al, 2002). The same research found that late fabricated materials were the third most common cause
4 2299 of construction related delay. Perhaps more revealing is the identification of these two causes of delay as having an occurrence of greater than 50% in the sample of projects (Ahmed et al, 2002). Similarly, a study of 130 residential and small commercial projects also found that late materials and equipment were a major cause of delays along with notices to proceed being later to site (Al-Momani, 2000). Beyond schedule delays, cost overruns are another impact that can hamper project success. Recently, a study into the causes of construction cost overruns in Malaysia found that the late delivery of materials was the tenth most significant factor faced by contractors, and the late delivery of equipment was the eleventh most common source of cost overruns (Rahman, Memom and Karim, 2012). Moreover, lateness of equipment was the highest ranked machinery-related cause of cost performance issues according to the contractors interviewed. However, beyond these causes of cost overruns that explicitly cite late deliveries, late resources may also cause several of the other factors found in the study. These include availability and shortages of materials and equipment along with delays in payments. The same study goes on to indicate that late or irregular delivery or wrong types of material delivered during construction affect the utilization of other resources like manpower and machinery and can lead to poor productivity, time delay and cost overrun (Rahman, Memom and Karim, 2012). Beyond the material and equipment deliverables, the study also cites labor absenteeism and shortages as top twenty causes of cost overruns, either of which could be attributed to late human resources, depending on the situation. Given that cost performance is one of the most tracked indicators of project success, it is important that the connection between these late items and cost performance is established. It has also been shown that late deliverables can impact project quality, along with schedule and cost performance. A study in lean construction found that the late delivery of drawings and materials which lead to contractors pressurizing for quicker response might lower quality performance on fast track projects (Kumar, 2010). The same study found that although schedule buffers can help shield contractors from late deliveries, the shielding is expensive, in both time and money. Similarly, when management attempts to make up for delays by exerting pressure on crews to work faster, implementing overtime, and/or hiring additional crews, the short-term progress may improve but at the expense of several identifiable consequences (Ford, Lyneis and Taylor, 2007). Working faster or for longer hours increases the risk for quality errors and reduces productivity, and increasing staffing levels reduces short-term productivity while new crews are trained as well as long-term productivity from the inherent inefficiencies of a crowded worksite. Beyond these primary impacts, potential secondary knock-on impacts include out of sequence work, trade stacking, increased rework to fix errors, and organizational impacts to turnover and morale. Other research into the procurement of engineered equipment, with its inherent time and schedule uncertainty, has revealed several different project impacts in comparison to late bulk materials. One investigation distinguished engineered equipment, in contrast to bulk materials, as major capital equipment that will be assembled or installed to form an integral part of the constructed system or facility (Yeo and Ning, 2004). Major engineered equipment is characterized by several risks that could provide insight into the root causes of late delivery. These risks include
5 2300 long lead times, incorporation of complex or specialized technology, and lack of inventory buffers. These risks are compounded by the typical location on the critical path and one-of-a-kind nature. The research continued with a survey of industrial/process, building, and civil construction projects with significant engineered equipment requirements. The responses showed that major equipment made up about 36% of the overall procurement costs for the projects, 50% of that equipment was delivered just-in-time, and around 20% was delivered late. Results highlighted the importance of regular communication, expediting, and the necessity of on time delivery for project performance. Beyond the physical construction materials and permits required to complete a project, informational deliverables can have an equally significant impact on a project s success. Dr. Glenn Ballard of the Lean Construction Institute points out that, with the overlap of the design, procurement, and construction phases in EPC projects and lean construction, engineering has become a supplier to construction (Ballard, 1993). The engineering firm must provide drawings and specifications to procurement and construction teams in the same manner as external suppliers. Although these engineering deliverables are critical inputs to construction just like materials, one of Ballard s studies of an industrial project found that, on average, more 30% of engineering deliverables were behind schedule. In addition, the average number of days beyond the scheduled delivery milestones was 56 days, but this project still finished on schedule. Ballard also found the root causes of engineering delays were inadequate materials, non-standardized processes, poor goal setting, and an inability to understand or manage risks on the project. Further, the construction phase was usually able to absorb the late and out-of-sequence delivery of drawings and materials, but at a tremendous cost (Ballard, 1993). However, beyond these cost and schedule impacts, no other pillars were investigated. Significant research has been performed in the fields of construction material management and construction supply chain management. Late deliverables can have substantial impacts on materials management on the construction site. As shipments arrive out of order, material handling may increase and flexibility to accommodate changed work sequences becomes a necessity. In a case study examining a delayed shipment of steel, researchers noted the haphazard unloading of the late shipment with no regards for the construction sequence and, when construction resumed, material handling and the required time increased significantly (Thomas, Sanvido and Sanders, 1989). The storage area became crowded with steel and the condition continued for several days until the erection process was back on track. Meanwhile, the erection crews were forced to demobilize while waiting for the steel to arrive and, upon remobilization, had to work in very crowded and difficult conditions. Another research project investigated how material delivery and availability can impact small and medium sized construction projects. The most common problems with materials for the projects studied included interruption to the work schedule, rework from having the wrong or out-of-order materials, and double handling because of inadequate materials (Donyavi and Flanagan, 2009). These main problems were an effect of materials being delivered at the wrong time and the lack of information provided for materials arriving on site, among others. Additional
6 2301 issues experienced include material deterioration during extended storage periods, expenses associated with crews lacking proper materials, and lost items on or off site. RESEARCH METHODOLOGY This review of existing literature provided the research team with a starting point from which to begin creating a more comprehensive list of both late deliverables and subsequent effects. In order to further develop the list of potential late deliverables and their effects to construction sites, several data gathering methods were employed. These included case studies with Construction Industry Institute (CII) member companies, surveys of construction industry professionals, and interviews with both research team members and other construction experts. Interviews Several interviews were conducted with construction industry experts at various companies that included both owner and contractor organizations. These interviews were not conducted in relation to any particular project, but rather to gather information from the many years of combined experience of the interviewees, who represented several different levels within their respective organizations from construction and project managers up to company executives. The goal of the interviews was to create a starting point from which to build the database of late deliverables and impacts. Using the knowledge of past late deliverables to construction sites, the research team was able to synthesize a first draft of categories to encompass the list of late deliverables. Interviews were also used to create a list of actual and theoretical impacts of late construction deliverables, and these impacts were then synthesized into categories of similar impacts to be refined further. Industry Surveys A second research tool introduced for data collection was a survey of construction industry members. The survey was administered in two mediums: the first during an interactive presentation of the research project and the second online for distribution to construction industry members. Interactive Presentation Survey The first round of the survey was completed very early in the research project at the 2012 Construction Users Roundtable (CURT) National Conference as an interactive presentation. The outline of the research project was presented with audience questions interspersed throughout. For example, questions asked about how often late deliverables affected construction projects, how often each of the five pillars was impacted, what are the most common late deliverables, and how late deliverables impact planning, management efforts, and labor. The answer choices were not quantitative but rather perception-based. With these responses, the research team was able to further refine the research targets and to gain insight into the industry member s thoughts on late deliverables and the research effort. Online Survey After revisions and the addition of new questions, the survey was made available online and distributed to CII and CURT member companies. The survey questions were developed by the research team to gather information about late
7 2302 deliverables and consequent impacts from the respondent s past experiences. Each respondent was asked to consider a single past project when answering the questions in the survey so relationships between specific late deliverables and their subsequent impacts could be retained. Questions covered general project information such as delivery method, contract type, project sector, and overall cost as well as specific information regarding the use of front-end planning, stage-gate processes, and similar company-specific information. The survey then moved into the types of late on the project and the subsequent impacts along with how these effects were handled by the project team. The information from the online survey was then combined with that of the interviews and literature review to create a more comprehensive list of late deliverables and impacts and begin to define categories of each. Rating Survey A third survey was distributed among CII member companies and at the 2013 CURT National Conference with the purpose of ranking the various types of late deliverables and impacts with respect to commonality and severity. This survey consisted of five questions, with the first being whether the respondent worked for a owner, contractor, or engineering company. The next four questions were based on a one to four scale, and the respondent rated the commonality and severity of each type of late deliverable and impact from late deliverables that the team had developed. Using the 240 responses, the average commonality and severity of each late deliverable and impact category was developed for owners, contractors, and overall. Case Studies Case studies were also employed to investigate late deliverables to construction sites. As part of the data collection, the research team has conducted two types of case studies: mini case studies and in-depth case studies. Mini Case Studies Much like the online industry survey, mini case studies were used to help expand and validate the categories of late deliverables and impacts. The research team conducted a breakout session at the CURT Winter Member Meeting in February 2013, and attendees were asked to complete a questionnaire similar to the online industry survey. Participants were again asked to consider a single project affected by a late deliverable and to list specific impacts to the project. Additional questions regarding contingencies, replanning, the critical path, progress monitoring, turnover, and other related topics were also included, mostly asking for yes or no responses. In-Depth Case Studies The primary method for data collection was in-depth case studies of recently completed or near complete construction projects, which were selected based on several criteria. The primary criterion for the case study selection was to fulfill each late deliverable category. Other secondary criteria were used to maintain variety in the nine case studies selected, and this, as well as the primary late deliverable categories fulfilled, is shown in Table 1 for each case study.
8 2303 Table 1: In-Depth Case Study Development Criteria Sector Location Site Cost Late Deliverable Category Fulfilled Mining Northeast Greenfield $47.0 MM External Permits Oil & Gas Southeast Brownfield $14.5 MM Engineering Documents, Approvals and Responses Oil & Gas Asia Greenfield $1.56 B Fabricated Materials Oil & Gas Southwest Brownfield $51.0 MM Engineered Equipment Power South Brownfield $827 MM Construction Equipment; Engineering Documents Process Midwest Brownfield $58.6 MM Human Resources; Engineering Documents Process Southwest Greenfield $1.00 B Bulk & Fabricated Materials; Prefabricated Assemblies Process Southeast Brownfield $56.7 MM Utilities and Infrastructure Power Southwest Brownfield $120 MM Project Execution Planning; External Permits Each in-depth case study was comprised of several interviews with project team members along with an investigation of relevant project schedules, cost breakdowns, safety reports, change orders, and other project documents. A minimum of three interviews were conducted for each case study with project team members at various hierarchical levels as well as across company divisions, which allowed for varying perspectives and areas of expertise to expand and validate the information gathered during the case study. Standardized cost and schedule data was also gathered along with any pertinent safety information (recordables, near misses, first aids) and quality documents (non-conformance reports, field change notices). This information was supplemented with project team knowledge to create a narrative surrounding each late construction deliverable and its true impacts on the project. FINDINGS By combining the literature review knowledge with the team s research, late deliverable categories and the project impact categories have been developed and finalized as shown in Table 2. Through the case studies and industry surveys, the research team concluded that these categories incorporate all of the potential late deliverables and impacts to constructions sites, and each has been defined to provide further distinction between each and ensure the lists are comprehensive. Furthermore, these categories are force ranked using the product of the severity and commonality rating from the rating survey. Table 2: Late Deliverable and Project Impact Categories Late Deliverable Categories Project Impact Categories 1 Engineering Documents/Approvals 1 Scope Changes 13 Management/Supervisor Work 2 Engineered Equipment 2 Productivity 14 Personnel Turnover 3 Fabricated Materials 3 Engineering/Design Work 15 Procurement and Logistics 4 External Permits 4 Work Resequencing 16 Onsite Team Dynamics 5 Prefabricated Assemblies 5 Overtime and Shift Work 17 Work Relocation 6 Project Execution Planning 6 Critical Path Management 18 Onsite Material Handling 7 Human Resources 7 Commissioning/Start-Up 19 Alternative Suppliers and Vendors 8 Utilities & Infrastructure 8 Rework 20 Claims, Bonuses, LD s 9 Bulk Materials 9 Craft Levels/Density 21 Alternative Tools and Equipment 10 Construction Equipment 10 Downtime 22 Offsite/Company Dynamics 11 Project Risk Changes 23 Damage, Degradation, and Loss 12 Indirect/Overhead Costs 24 Training Resources
9 2304 Beyond the encompassing list of late deliverable and impact categories created, the research team has made several additional observations thus far. To begin, the team has noted the full range of impacts from late deliverables is rarely understood or tracked on construction projects. Although cost and schedule are consistently tracked on all projects, ties to the quality, safety, and organizational impacts were less often revealed in interviews and required additional research to uncover these relationships. Given the dependence of construction projects on all project pillars, it is essential that both individuals and companies understand the impacts of late deliverables throughout the entire project lifecycle. Furthermore, the research team discovered through the multiple interviews and case studies that knowledge of the impacts of late deliverables is not uniform among those stakeholders and individuals involved on construction projects. To begin, late deliverables affected owner and contractor organizations differently and the knowledge gathered from each, though in many ways similar, had unique aspects. Although common themes among owners and contractors were found, the research team also observed that the impacts noted differed between contractor companies and between owner organizations. Finally, the research revealed that individuals at different levels and positions within a single company focused on specific impacts of late deliverables. For example, most project team members, when interviewed, were predominantly focused on their responsibility within a project. For example, while the project controls manager had detailed insight into specific cost and schedule impacts and the safety manager could recall specific safety risk changes, a project executive who has less knowledge in these more specific aspects could provide greater insight into the internal and external organizational impacts. By gathering all of these complimentary views from various companies and industry professionals into one knowledge base, the research team believes that companies will be able to more fully understand the true impact of late deliverables and improve project team alignment helping ensure project success. CONCLUSIONS AND FURTHER RESEARCH Thus far, CII Research Team 300 has created an encompassing list of late deliverable categories as well as categories of the resulting impacts. These categories were created through a literature review, interviews with construction experts, industry surveys, and project case studies. Using the same method, the team was also able to validate the existing categories as the research progressed; categories evolved, and a clear definition of each was drafted. With this knowledge and a set of standardized definitions for the categories, the team now proceeds into the second half of the research project. It is the goal of this research to create an encompassing list of impacts caused by late deliverables. A database will be formed linking the late deliverables with their observed impacts along with the pillars affected. The final piece of the database will be a set of leading indicators developed by the team and tied to each late deliverable, along with a force ranking of each late deliverable and impact by its commonality and the severity of its impact to a project. The ultimate goal of the research team is to develop a graphical tool for industry use with this data. Then, an owner and a contractor will test a prototype allowing the research team to gain feedback and make any improvements before the research project is finalized.
10 2305 REFERENCES Ahmed S., Azher S., Castillo M., Kappagantula P. (2002). Construction Delays in Florida: An Empirical Study. Final Report, Florida International. Available at: Al-Momani, A.H. (2000). Construction Delay: A Quantitative Analysis. In: International Journal of Project Management, 18, p Assaf, S.A. and Al-Hejji, S. (2006). Causes of Delay in Large Construction Projects. In: International Journal of Project Management, 24, p Ballard, G. (1993). Lean Construction and EPC Performance Improvement. In: Proceedings of the 1 st Annual Conference of IGLC, Finland. Available at: Borcherding, J.D. (1972) An Exploratory Study of Attitudes That Affect Human Resources in Building and Industrial Construction. Technical Report No. 159, Stanford University. Chan, A.P.C. and Chan, A.P.L. (2004) Key Performance Indicators for Measuring Construction Success. In: Benchmarking: An International Journal, 11(2), p Donyavi, S. and Flanagan, R. (2009) The Impact of Effective Material Management on Construction Site Performance for Small and Medium Sized Construction Enterprises. In: Proceedings of the 25 th Annual ARCOM Conference, Nottingham, UK. Ford, D., Lyneis, J., Taylor, T. (2007). Project Controls to Minimize Cost and Schedule Overruns: A Model, Research Agenda, and Initial Results. In: Proceedings of the 2007 International System Dynamics Conference, Boston. Kumar, A. (2010) Lean Construction in the Building Industry. Technical Report, University of Illinois Urbana-Champaign. Kumaraswamy, M. and Chan, D. (1998). Contributors to Construction Delays. In: Construction Management and Economics, 16(1), p Mulholland, B. and Christian, J. (1999). Risk Assessment in Construction Schedules. In: Journal of Construction Engineering and Management, 125, p O Brien, W.J. (1999). Construction Supply Chain Management: A Vision for Advanced Coordination, Costing, and Control. In: NSF Berkeley-Stanford Construction Research Workshop, Stanford, CA. Rahman, I., Memom, A., Karim, A. (2013). Relationship between Factors of Construction Resources Affecting Project Cost. In: Modern Applied Science, 7(1), p Thomas, H.R., Sanvido, V., Sanders, S. (1989). Impact of Material Management on Productivity A Case Study. In: Journal of Construction Engineering and Management, 115, p Yeo, K.T. and Ning, J.H. (2004). Managing Uncertainty in Major Equipment Procurement in Engineering Projects. In: European Journal of Operational Research, 171, p
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by
APICS INSIGHTS AND INNOVATIONS UNCOVERING CHRONIC DISRUPTION IN SUPPLY CHAIN AND OPERATIONS MANAGEMENT
APICS INSIGHTS AND INNOVATIONS UNCOVERING CHRONIC DISRUPTION IN SUPPLY CHAIN AND OPERATIONS MANAGEMENT APICS INSIGHTS AND INNOVATIONS ABOUT THIS REPORT Sudden, acute supply chain disruptions such as those
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009
LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS
LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS Antonio Sergio Itri Conte 1 ABSTRACT The paper describes the experience of a civil engineering company of a small town in São Paulo State
Construction Supply-Chain Management: A Vision for Advanced Coordination, Costing, and Control
Construction Supply-Chain Management: A Vision for Advanced Coordination, Costing, and Control Dr. 1 Overview Construction supply-chain management offers new approaches to reduce the cost of and increase
Dynamic Change Management for Fast-tracking Construction Projects
Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations
Project Management Topics
S E C T I O N II T W O Project Management Topics SECTION II: PROJECT MANAGEMENT TOPICS TABLE OF CONTENTS Introduction 3 1. PROJECT TRIAGE 5 1.1 Gather the Data 7 1.2 Review and Analyze the Data 10 1.3
Knowledge-Based Sustainable Decision-making Framework for the Implementation of Innovative Technologies in the Malaysian Construction Industry
Knowledge-Based Sustainable Decision-making Framework for the Implementation of Innovative Technologies in the Malaysian Construction Industry ROHANA MAHBUB Faculty of Architecture Planning and Surveying
Delivering Energy Projects Predictably
Delivering Energy Projects Predictably Pete Luan & John Wray, Westney Consulting Group Knut Eriksen and Greg Dodson, NATCO Group 1 Introduction Project delivery systems are those business processes that
Technical and Management Assistance & Consulting
Technical and Management Assistance & Consulting Since 1995 www.tmacdfw.org TMAC PROVIDES SOLUTIONS FOR Executive Leadership...5 Accounting & Finance...7 Product Development...10 Sales & Marketing...12
Implementing Lean Construction: Stabilizing Work Flow *
Implementing Lean Construction: Stabilizing Work Flow * GLENN BALLARD Department of Civil Engineering, University of California, Berkeley, CA 94720 GREG HOWELL Department of Civil Engineering, University
Helping our clients win in the changing world of work:
Helping our clients win in the changing world of work: Recruitment Process: Why Outsource? A Manpower Insights Paper The future of RPO looks strong despite or perhaps aided by the current global recession.
Tapping the benefits of business analytics and optimization
IBM Sales and Distribution Chemicals and Petroleum White Paper Tapping the benefits of business analytics and optimization A rich source of intelligence for the chemicals and petroleum industries 2 Tapping
Computer Science Department CS 470 Fall I
Computer Science Department CS 470 Fall I RAD: Rapid Application Development By Sheldon Liang CS 470 Handouts Rapid Application Development Pg 1 / 5 0. INTRODUCTION RAD: Rapid Application Development By
IMPROVING THE DESIGN-CONSTRUCTION INTERFACE
Improving the Design-Construction Interface IMPROVING THE DESIGN-CONSTRUCTION INTERFACE Luis F. Alarcón 1 and Daniel A. Mardones 2 ABSTRACT In building projects customer requirements, constructive aspects
Schedule Acceleration Techniques Using a CM
College of Engineering Schedule Acceleration Techniques Using a CM By PI: Dr. Jesús M. de la Garza, Vecellio Professor Graduate Student: Ms. Daniela Escobar Hidrobo Final Report September 1, 2006 Invent
Management of Uncertainty In Supply Chain
Management of Uncertainty In Supply Chain Prof.D.P.Patil 1, Prof.A.P.Shrotri 2, Prof.A.R.Dandekar 3 1,2,3 Associate Professor, PVPIT (BUDHGAON), Dist. Sangli(M.S.) [email protected] [email protected]
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Project Management Issues in the Finance Transformation Arena
Project Management Issues in the Finance Transformation Arena Projects, and the ability to deliver them on time and on budget, not only represent an ongoing challenge for any organization, but also require
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
A Simple Guide to Material Master Data Governance. By Keith Boardman, Strategy Principal
A Simple Guide to Material Master Data Governance By Keith Boardman, Strategy Principal DATUM is an Information Management solutions company focused on driving greater business value through data. We provide
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
Time Error in Project Management: A Case Study in Yanbu, Saudi Arabia
Business and Management Studies Vol. 2, No. 1; March 2016 ISSN 2374-5916 E-ISSN 2374-5924 Published by Redfame Publishing URL: http://bms.redfame.com Time Error in Project Management: A Case Study in Yanbu,
OCCUPATIONAL STANDARD (For use in the development of supply chain related job descriptions, performance evaluations, career development plans, etc.
OCCUPATIONAL STANDARD (For use in the development of supply chain related job descriptions, performance evaluations, career development plans, etc.) Description of Position (As defined by the CSCSC Stakeholder
Supply Chain Maturity and Business Performance: Assessment and Impact
Supply Chain Maturity and Business Performance: Assessment and Impact Abstract When evaluating your supply chain, no gap should exist between where your suppliers capabilities end and your capabilities
Training Programs for Enterprise-Wide Change
Training Programs for Enterprise-Wide Change Top Five Requirements for Programs that Deliver Prepared by VisionCor, Inc. 1 Contents Summary... 3 Before We Get Started... 3 Program Principles... 4 Business
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
OCCUPATIONAL STANDARD (For use in the development of supply chain related job descriptions, performance evaluations, career development plans, etc.
OCCUPATIONAL STANDARD (For use in the development of supply chain related job descriptions, performance evaluations, career development plans, etc.) Description of Position (As defined by the CSCSC Stakeholder
A comparison of supply chain risk perceptions in Original Equipment Manufacturers and Tier One suppliers: A case-study in the aerospace industry.
011-0290 A comparison of supply chain risk perceptions in Original Equipment Manufacturers and Tier One suppliers: A case-study in the aerospace industry. Naomi Brookes Amrik Singh Aston Business School
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
2012 Higher Education Survey
Consulting Higher Education 2012 Higher Education Survey The State of HR Effectiveness Highlights About this Survey The Challenge For HR leaders in higher education, the challenge increasingly is how to
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
Project Zeus. Risk Management Plan
Project Zeus Risk Management Plan 1 Baselined: 5/7/1998 Last Modified: N/A Owner: David Jones/Zeus Project Manager Page Section 1. Introduction 3 1.1 Assumptions, Constraints, and Policies 3 1.2 Related
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects Dr. Rashad Zakieh (PMP) 27 April, 2010 Copyright Saudi Aramco, 2010. All rights reserved.
Project Knowledge Areas
From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.
Workforce Insights Employee Satisfaction Surveying
Workforce Insights Employee Satisfaction Surveying Overview One significant factor in your call center s success is how happy and satisfied the employees are. Employee satisfaction has an extremely high
Building a Business Case for Industrial Software Projects Helps Ensure Success
APRIL 18, 2013 Building a Business Case for Industrial Software Projects Helps Ensure Success By Ralph Rio Keywords EAM, CMMS, Business Case Overview To get executive support for your next project, tie
Available online at www.sciencedirect.com. ScienceDirect. The 4th International Conference on Electrical Engineering and Informatics (ICEEI 2013)
Available online at www.sciencedirect.com ScienceDirect Procedia Technology 11 ( 2013 ) 220 226 The 4th International Conference on Electrical Engineering and Informatics (ICEEI 2013) The Benefits of Enterprise
Effective Materials Management
WHITE PAPER Effective Materials Management Reducing Costs and Improving Procurement Efficiency Contents 1. Introduction... 1 2. Industry Challenges... 2 3. Business Benefits... 3 3.1 Managing Reference
12090c 12090c. Is Cloud the way forward for Manufacturing Industries?
12090c 12090c Is Cloud the way forward for Manufacturing Industries? Table of Contents Introduction Challenges in the Manufacturing Industry So how can these Critical Business Imperatives be addressed
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
DISCHARGE FOCUS PUTS HOSPITAL CAPACITY ISSUE TO BED By Terry Maher, Healthcare Practice Leader, USC Consulting Group
DISCHARGE FOCUS PUTS HOSPITAL CAPACITY ISSUE TO BED By Terry Maher, Healthcare Practice Leader, USC Consulting Group The exploding demand for healthcare in the U.S. is nothing new. But the growing critical
Project Management for Development Organizations
Project Management for Development Organizations Doing the Right Projects, Doing the Projects Right The Skills of a Project Manager Managerial Skills The evolution of development projects has changed the
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
Accenture Management Consulting. Open Roles
Accenture Management Consulting Open Roles Who are we? Accenture s Consulting workforce is involved in business consulting, process design work and the application of technologies to business. Management
Fixing First-Time Fix: Repairing Field Service Efficiency to Enhance Customer Returns
Fixing First-Time Fix: Repairing Field Service Efficiency to Enhance Customer First-time fix is one of the most vital metrics in gauging field service performance. While workforce utilization, productivity,
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
ITIL Service Lifecycles and the Project Manager
1 ITIL Service Lifecycles and the Project Manager The intersection of IT Service and Project Delivery Presented to: Kansas City Mid-America PMI Chapter Mark Thomas January 17, 2011 1 Agenda 2 Introduction
Recruitment Process: Why Outsource?
Recruitment Process: Why Outsource? Open House November 2010 Think differently about work. John Loukas Manpower Business Solutions Director 2 RPO - Agenda RPO Overview - Definition RPO as a Talent Acquisition
WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?
WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,
Developing Greater Professionalism in GIS Project Management
Bill Haaker Senior Project Manager ASI Technologies 1935 Jamboree Drive Colorado Springs, CO 80920 Developing Greater Professionalism in GIS Project Management Introduction Project management is widely
APPENDIX X1 - FIFTH EDITION CHANGES
APPENDIX X1 FIFTH EDITION CHANGES The purpose of this appendix is to give a detailed explanation of the changes made to A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Improving the Predictability of the CapEx Portfolio
Improving the Predictability of the CapEx Portfolio Spring 2009 Westney Consulting Group, Inc. www.westney.com If the whipsaw of product price and project cost over the past 12 months has taught anything,
Ensuring Reliability in Lean New Product Development. John J. Paschkewitz, P.E., CRE
Ensuring Reliability in Lean New Product Development John J. Paschkewitz, P.E., CRE Overview Introduction and Definitions Part 1: Lean Product Development Lean vs. Traditional Product Development Key Elements
Process-Based Business Transformation. Todd Lohr, Practice Director
Process-Based Business Transformation Todd Lohr, Practice Director Process-Based Business Transformation Business Process Management Process-Based Business Transformation Service Oriented Architecture
Manufacturing Flow Management
Manufacturing Flow Management Distribution D Distribution Authorized to Department of Defense and U.S. DoD Contractors Only Aim High Fly - Fight - Win Supply Chain Management Processes Information Flow
Introduction to Business Process Improvement
Introduction to Business Process Improvement Learning Objectives By the end of this chapter, you should be able to: Define a business process. State the objectives of business process improvement. Explain
Gateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
MANAGING THE EMPLOYEE LIFECYCLE
MANAGING THE EMPLOYEE LIFECYCLE Current Position Jose Laurel Experience & Expertise 16 years experience in management, operations, marketing and international commerce Prior to G&A, served as country manager
Project Management: Back to Basics
About this research note: Technology Insight notes describe emerging technologies, tools, or processes as well as analyze the tactical and strategic impact they will have on the enterprise. Project Management:
Department of Management
Department of Management Course Student Learning Outcomes (ITM and MGMT) ITM 1270: Fundamentals of Information Systems and Applications Upon successful completion of the course, a student will be able
The Drake Suite of Talent Management Solutions. Increasing the Return on your Human Capital Investment
The Drake Suite of Talent Management Solutions Increasing the Return on your Human Capital Investment Increasing the Return on your Human Capital Investment An integrated and comprehensive approach to
MSc in Construction Management (Cycle 2, level 4)
(Cycle 2, level 4) is a 2 year full-time graduate study program of 120 ECTS credits (4 semesters, 30 ECTS each semester). Students generally take 90 ECTS in specialized courses and a 30 ECTS thesis. In
Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E
Global Journal of HUMANSOCIAL SCIENCE: H Interdisciplinary Volume 15 Issue 5 Version 1. Year 215 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals Inc. (USA) Online
ATTACHMENTS: 1. CUSTOMER EXPERIENCE PROGRAM CHART
INFORMATION REPORT REPORT TITLE: ITEM NUMBER: 1176 DATE OF MEETING: 14 JULY 2014 AUTHOR: JOB TITLE: RESPONSIBLE OFFICER: JOB TITLE: COMMUNITY GOAL: CUSTOMER EXPERIENCE PROGRAM ANNABEL SHINKFIELD MANAGER
Benefits of conducting a Project Management Maturity Assessment with PM Academy:
PROJECT MANAGEMENT MATURITY ASSESSMENT At PM Academy we believe that assessing the maturity of your project is the first step in improving the infrastructure surrounding project management in your organisation.
Risk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
Business Analysis Capability Assessment
Overview The Business Analysis Capabilities Assessment is a framework for evaluating the current state of an organization s ability to execute a business automation effort from and end-to-end perspective..
Evaluating the effects of communication in construction project delivery in Nigeria
Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5): pp 048-054, June, 2014. Copyright 2014 Spring Journals Full Length Research Paper Evaluating the effects of communication
The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2
The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 1 Curtin University of Technology, Perth, Western Australia 2 Broad Construction Services, Perth, Western
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Application of Quality Tools to Improve Quality: A Case Study of a Building Remediation Contractor
Application of Quality Tools to Improve Quality: A Case Study of a Building Remediation Contractor Kamalesh Panthi, Ph.D. Candidate Florida International University Miami, Florida Syed M. Ahmed, Ph.D.
Shared Value Chain Cost Reduction Through Innovative Supplier Relationships
Shared Value Chain Cost Reduction Through Innovative Supplier Relationships Jimmy Anklesaria President, CEO Anklesaria Group, Inc. Del Mar, CA 92014 (858) 755-7119 www.anklesaria.com [email protected]
REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN
212 REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN ABSTRACT Sangwoo Cho 1 and Martin Fischer 2 Supply chain management in construction has evolved in response to various
CONTRACTOR MANAGEMENT BEST PRACTICES: USING DATA FOR IMPROVED DECISION MAKING
CONTRACTOR MANAGEMENT BEST PRACTICES: USING DATA FOR IMPROVED DECISION MAKING D.Yemenu, K.McCartin ISN Software Australia Pty Ltd. PO Box 1215 Australia Square, NSW 1215 [email protected] Abstract Global
The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management.
Knowledge Areas The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management. These are: Project Integration Management Project Scope
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Software Engineering. Objectives. Designing, building and maintaining large software systems
Software Engineering Objectives Designing, building and maintaining large software systems To define software engineering and explain its importance To discuss the concepts of software products and software
Integrating Continuity of Operations (COOP) into the Enterprise Architecture
Volume 1, Issue 2 August 2007 Continuity of Operations Leadership Series for Government Integrating Continuity of Operations (COOP) into the Enterprise Architecture Pillar COOP Leadership Series for Government
An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan
An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan Of interest to students of Paper P5 Integrated Management. Increasingly, there seems to be a greater recognition of the
