OPTIMAL ALLOCATION OF CONSTRUCTION PLANNING RESOURCES
|
|
|
- Antony Fowler
- 10 years ago
- Views:
Transcription
1 OPTIMAL ALLOCATION OF CONSTRUCTION PLANNING RESOURCES By Olusegun O. Faniran, 1 Peter E. D. Love, 2 and Heng Li 3 ABSTRACT: Efficient allocation of resources for construction planning activities requires construction planning resource requirements to be determined on a cost-effective and value-adding basis. However, although some research studies have indicated that increasing resource allocations to construction planning activities will lead to improved project performance, other research studies have indicated that investing in construction planning beyond an optimum point will lead to a deterioration in project performance. This study explored the concept of optimal planning of construction projects by examining 52 projects undertaken in Australia. The relationships between planning input (ratio of planning costs to total project costs) and the probabilities of achieving poor performance and good performance were modeled using logistic, linear, and curvilinear regression analyses. A probable optimum planning input based on the sample studied was derived. It is suggested that any additional planning efforts beyond this optimum point would be essentially wasted because the additional planning costs would not achieve any savings in project cost but merely add to the overhead costs and therefore increase the overall project cost. A model for optimal planning is presented and discussed. INTRODUCTION Construction project planning has a significant impact on the ability of construction firms to achieve success in the implementation of construction projects (Arditi 1985; Clayton 1989; Syal et al. 1992; Hamilton and Gibson 1996). Nevertheless, although researchers in construction management and practitioners in the construction industry realize the importance of construction planning, there is a divergence of opinion on how much effort should actually be invested in construction planning activities and how construction planning efforts should be organized to achieve success in the performance of construction projects. Findings from some research studies have indicated that construction planning effectiveness, and hence construction project performance, can be improved by increasing the amount of resources invested in construction planning activities (Laufer and Cohenca 1990; Faniran et al. 1994a, 1998). However, other studies suggest that investing in construction planning activities beyond an optimum point results in an increase in overall project costs (Neale and Neale 1989). The study reported in this paper focuses on the construction planning undertaken within a construction firm for the purpose of determining appropriate strategies (methods, timing of operations, and required resources) for achieving construction project objectives. This paper addresses the issue of how much effort is required to be invested in construction project planning to achieve success in project performance. This would be of benefit to top management of construction firms in determining how much investment is required to achieve cost-effectiveness in construction planning activities within the firm. This paper also presents and discusses the conceptual framework of a construction planning model that is being developed to address the issue of optimal planning for construction projects. Specific objectives of the paper are to explore the concept of optimal planning for construction projects; to derive a probable value for optimum planning inputs into construction projects; and to present and discuss preliminary 1 Lect. in Constr. Mgmt., School of Arch. and Build., Deakin Univ., Geelong VIC 3217, Australia. [email protected] 2 Sr. Lect. in Constr. Mgmt., School of Arch. and Build., Deakin Univ., Geelong VIC 3217, Australia. 3 Assoc. Prof. of Constr. Mgmt., Dept. of Build. and Real Estate, Hong Kong Polytechnic Univ., Hung Hom, Kowloon, Hong Kong. Note. Discussion open until March 1, To extend the closing date one month, a written request must be filed with the ASCE Manager of Journals. The manuscript for this paper was submitted for review and possible publication on November 3, This paper is part of the Journal of Construction Engineering and Management, Vol. 125, No. 5, September/October, ASCE, ISSN /99/ /$8.00 $.50 per page. Paper No stages of a proposed construction planning model that incorporates optimal planning concepts. CONCEPTUAL FRAMEWORK OF STUDY Efficient allocation of resources for construction planning activities requires that the determination of resource requirements should be undertaken on a value-adding and cost-effective basis. Firdman (1991) proposed the relationships illustrated in Fig. 1 to demonstrate the value of investing the correct amount of planning effort into a project. The relationships illustrated in the figure indicate that too little planning effort results in implementation failures, delays, and reworks. Consequently there is a high probability that the project will not achieve its intended objectives. When the correct amount of planning effort is invested, the project implementation time is optimized, and there is a high probability that the project will achieve its intended objectives. Additional planning effort beyond the optimal level also results in a high probability that the project will achieve its intended objectives. However, this effort is essentially wasted because of the implementation delays that inevitably arise due to the additional time required to complete the planning and the increasing number of planning loops that occur as planners plan and replan minute project details. Neale and Neale (1989) proposed the relationship between project cost and planning input shown in Fig. 2. The figure indicates that as the planning input increases from 0 to (X)%, project costs are reduced. However, as the planning input goes beyond (X)%, project cost begins to increase. Neale and Neale described the low point (X) of the total cost curve as the saturation point of planning beyond which further spending on planning does not achieve any savings in project cost but merely adds to the overhead and therefore increases the overall project cost. The studies outlined above have been mainly qualitative in their approach to exploring the concept of optimal planning. The intention of this study is to adopt a quantitative approach to explore the concept of optimal planning inputs for construction projects. In this study, project performance is based on Ashley et al. s (1987) definition of project success that is summarized as: results much better than expected or normally observed in terms of cost, schedule, quality, safety, and participant satisfaction. Furthermore, it is recognized that there is a high degree of uncertainty in construction project environments, and therefore several other factors apart from construction planning contribute to project success (or failure). Consequently, this study examines the impact of planning efforts on the probability of achieving project success rather than on the actual achievement of project success. It is expected JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999 / 311
2 FIG. 1. Correct Planning FIG. 2. Saturation Planning that the relationship between the probability of project success and planning efforts could take either of the forms shown in Fig. 3: a linear relationship with the probability of project success increasing (or decreasing) at a constant rate as the planning input increases; or a curvilinear relationship with the probability of project success increasing (or decreasing) at a changing rate as the planning input increases. By examining the nature of the relationships, optimum values for planning input can be derived. METHODOLOGY Data Collection A structured questionnaire was used to collect data for the study. The questionnaire contained questions relating to the amount of time invested in construction planning, the amount of time invested in project control, planning engineers salaries, composition of construction planning team, and project costs. The questionnaire was pretested in a pilot study and 312 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999
3 FIG. 3. Possible Relationships between Probability of Project Success/Failure and Planning Input Project characteristics TABLE 1. Commercial Project Characteristics: Type of Project by Type of Contract and Type of Client Industrial Educational Health institution (5) Type of Project Government administrative (6) (a) Type of contract Defense facility (7) Airport (8) Museum (9) Sports/ recreation center (10) Lump sum Cost plus Design/construct Total (b) Type of client Public Private Total Others (11) Total (12) TABLE 2. Project characteristics Project Characteristics: Project Size Distributions Minimum Range Maximum Mean Project cost (dollars) 350, ,000,000 17,400,000 Project duration (weeks) Total floor area (m 2 ) ,000 12,067.5 Cost per square meter (dollars) ,500 1,830.6 subsequently modified before a final version was produced. Eighty-five construction firms located in New South Wales, Australia, were approached to participate in the study. Fiftytwo of the firms agreed to participate. Participating construction firms were asked to nominate a project completed within the last 5 years and to provide responses to questions contained in the questionnaire with respect to the nominated project. Tables 1 and 2 show the characteristics of the projects included in the sample. The following research variables were used in the study: planning input, cost variance, and time variance. Planning input is a measure of the effort invested in determining appropriate strategies for achieving the project s predefined objectives prior to the commencement of construction work on site. This includes the determination of construction methods, sequence and timing of construction operations, and required resources for project implementation. Cost variance is the extent to which the actual construction cost differs from the value stipulated in the contract documents at the time of award of the contract. Time variance is the extent to which the actual construction time varies from the time originally stipulated in the contract documents at the time of award of the contract. Planning input was measured as the percentage ratio of planning costs to total project cost. Expressing planning costs as percentages of total project costs normalizes differences in planning efforts that may occur due to differences in project size. The cost of planning includes personnel costs, training costs, data processing costs, and administration costs. However, because of scarcity of relevant data available in construction firms, planning costs in this study were computed only on the basis of the cost of employing planning engineers for the projects (i.e., personnel costs). Cost variance was measured as the percentage ratio of the final project cost to the original project cost. Time variance was also measured as the percent- JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999 / 313
4 TABLE 3. Research variables Planning input (%) Descriptive Statistics for Research Variables Mean Standard deviation Coefficient of variation Minimum (5) Range Maximum (6) Cost variance (%) Time variance (%) Quartile Values for Cost Variance and Time Vari- TABLE 4. ance Research variables Q1 (first quartile) Q2 (second quartile/ median) Q3 (third quartile) Cost variance Time variance age ratio of the final project duration to original project duration. Descriptive statistics for the research variables are shown in Table 3. Cost variance and time variance measures were later transformed into three project performance categories: Poor; average; and good. Jaselskis and Ashley (1991) measured project performance in three discrete categories: Achieving overall project success; achieving better-than-expected schedule performance; and achieving better than expected budget performance. However, in Jaselskis and Ashley s study, the performance parameters were measured subjectively on the basis of respondents assessments. In this study the project performance parameters poor performance, average performance, and good performance were derived statistically from the data collected. Data Analysis The data were analyzed using normality tests, logistic regressions, and linear/curvilinear regressions. Normality tests are used to examine the assumption that data come from a normal distribution. Normality testing can be done visually with a normal probability plot and a detrended normal plot or computed with a statistical test such as Shapiro-Wilks test (Norusis 1994). Regression analysis is a statistical technique used to model the relationship between a dependent (or outcome) variable and independent (or explanatory) variables. In logistic regression the dependent (or outcome) variable is discrete and binary with only two values an event occurring or not occurring. Logistic regression is used to estimate the probability that an event occurs (Hosmer and Lemishow 1989; Norusis 1994). The logistic regression model can be defined as y Probability(event) = 1/(1 e ) where y = outcome variable, expressed as the linear combination y = b bx bx bx n n where x 1, x 2,...,x n = covariates or explanatory variables; and b 0, b 1, b 2,...,b n = constants. Unlike the logistic regression model, the linear/curvilinear regression model does not predict the probability of occurrence of a discrete dependent (or outcome) variable but instead indicates the relative effects of independent variables on a continuous dependent variable and the strength of the relationship between the variables. In linear/curvilinear regression the dependent variable is assumed to be continuous. The linear regression equation can be expressed in the same form as. The curvilinear regression equation can be expressed in the form shown in the following: 2 y = b0 bx 1 bx 2 where y = dependent (outcome) variable; x = independent (explanatory variable); and b 0, b 1, and b 2 = coefficients of regression. The concept of optimal planning inputs for construction projects was explored in a four-stage analysis. In the first stage of the analysis, the project performance parameters used in the study cost variance and time variance were tested to determine whether the performances of the construction projects included in the sample followed a normal distribution. It was particularly important to determine whether the cost variance and time variance were normally distributed so that a valid basis could be established for statistically classifying the project performance into discrete categories. The second stage of the analysis consisted of converting the continuous project performance measures into discrete categorical variables. Project performance was classified into the following categories: Poor cost performance; poor time performance; average cost performance; average time performance; (5) good cost performance; and (6) good time performance. Projects with cost variance falling in the interquartile range (i.e., between the first and third quartiles) were classified into the category of average cost performance. Projects with cost variance exceeding the third quartile were classified into the category of poor cost performance, whereas projects with cost variance falling below the first quartile were classified into the category of good cost performance. Time performance was similarly categorized with time variance falling in the interquartile range (i.e., between the first and third quartiles) classified as average time performance, time variance exceeding the third quartile classified into the category of poor time performance, and time variance falling below the first quartile classified into the category of good time performance. Quartile values of cost variance and time variance are presented in Table 4. The categorization of the project performance parameters is illustrated in Fig. 4. In the third stage of the analysis, bivariate logistic regression analyses were performed, and the probabilities of achieving good cost performance, good time performance, poor cost performance, and poor time performance for the planning input of each case in the sample was computed. Linear and curvilinear regression analyses were performed in the fourth stage of the analysis to examine the nature of the relationship between project performance and planning inputs into construction projects. A probable value for optimal planning input was also derived. RESULTS Fig. 5 shows the histograms (with superimposed normal curves) for cost variance and time variance. Figs. 6 and 7 show the normal and detrended normal plots for cost variance and time variance, respectively. Table 5 shows Shapiro-Wilks test statistics for the cost variance and time variance variables. The results from the normality tests indicate that the cost variance and time variance of the projects in the sample can be considered to be approximately normally distributed. The pattern of performance of the projects in the sample can therefore be said to be a good representation of the population from which the sample was selected. Consequently, the classification of the performance of the projects in the sample into the categories of poor performance, average performance, and good performance can be considered to be valid. Figs. 8 and 9 show the fitted regression lines for the relationship between the probability of good cost performance and 314 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999
5 FIG. 4. Categorization of Project Performance FIG. 5. Histogram (with Superimposed Normal Curves) of Cost Variances and Time Variances FIG. 6. Normal Probability Plots for Cost Variance planning input and the relationship between the probability of poor cost performance and planning input, respectively. Figs. 10 and 11 show the fitted regression lines for the relationship between the probability of good time performance and planning input and the relationship between the probability of poor time performance and planning input, respectively. DISCUSSION It is interesting to note that none of the projects in the middle spread of the sample had cost or time variances that were below 100%. This is an indicator that cost and time overruns are a norm and confirms the prevalent high level of uncertainty associated with construction projects. Previous research studies have also reported similar findings. In Britain, a study by the Building Cost Information Service (BCIS 1988) found that 47% of projects exceed their planned cost and 71% of projects overrun their planned times. In New Zealand, Soetrick and Foster (1976) reported that time overruns on contract completion are 20% on average. The relationships found between planning input and the probabilities of good cost performance, poor cost performance, good time performance, and poor time performance reveal very interesting trends and provide a useful basis for examining the concept of optimal planning for construction projects. The relationships suggest that the major impact of construction planning efforts is on the cost performance of construction projects rather than the time performance. The relationships JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999 / 315
6 FIG. 7. Normal Probability Plots for Time Variance TABLE 5. Shapiro-Wilks Test for Normality Research variables Statistic df Significance Cost variance Time variance of the fitted regression curve relating the probability of poor cost performance to planning input. The cutoff point is the minimum planning input value corresponding to a zero probability of poor cost performance (Fig. 12). This is determined as follows by solving for a value of zero: FIG. 8. Fitted Regression Line for Relationship between Planning Input and Probability of Good Cost Performance shown in Figs. 8 and 9 indicate that the probability of achieving good cost performance increases as the planning input into a construction project increases. However, after the planning input passes beyond the minimum point of the curve in Fig. 9, the probability of achieving poor cost performance also begins to increase. The relationships shown in Figs. 10 and 11 indicate that increased planning input is associated with an increased probability of achieving good time performance as well as with an increased probability of achieving poor time performance. This implies that construction planning efforts do not have any significant dominant effect on project time performance. These findings are in line with findings from a previous study by Faniran et al. (1998) where planning time was identified as a critical determining factor for the extent to which the actual construction cost varied from the originally stipulated project cost. In Faniran et al. (1998) study, project time performance also was not found to be affected by construction planning efforts. A probable value for optimal planning input can be derived from the results of this study by determining the cutoff point FIG. 9. Fitted Regression Line for Relationship between Planning and Probability of Poor Cost Performance FIG. 10. Fitted Regression Line for Relationship Between Planning Input and Probability of Good Time Performance 316 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999
7 FIG. 11. Fitted Regression Line for Relationship between Planning Input and Probability of Poor Time Performance FIG. 12. Probable Value of Optimal Planning Input x 0.67x 0.34 = 0 where x = 0.72; or x = The probable optimal planning input value derived from this study is therefore 0.72%. The applicability of this value has inherent limitations arising from the sample characteristics and the method of analysis. The sample was geographically restricted to the state of New South Wales, Australia, and consisted of a wide variety of project types. Different types of s, and indeed different types of construction projects, would require different levels of planning input depending on the particular characteristics of the project. The amount of time invested in construction planning was also evaluated on the basis of the subjective assessments of respondents. Similarly, the computation of the planning costs was based solely on the salaries of planning engineers. Other cost factors such as data processing costs and administrative costs were not considered. Despite these limitations, the results of the study have clearly demonstrated that although too little planning is likely to result in poor project performance, and increasing the efforts invested in planning would increase the chances of good performance, excessive planning beyond an optimal level increases the probability of a deterioration in project cost performance. The scope of the present study did not include the identification of specific planning products corresponding to an optimum level of construction planning. Nevertheless, it can be inferred from the results that an optimum planning level for a construction project would be that level of planning input that provides general direction for a project and, at the same time, provides sufficient flexibility for the project to react to change at the lowest possible level and with the least change in the original plan. This and other issues are currently being addressed in a comprehensive research study on construction project planning being undertaken at the School of Architecture and Building, Deakin University, Australia. The study is developing an optimal planning model for construction projects that addresses the issue of optimal planning and seeks to rectify some of the deficiencies in current practices in construction planning. Fig. 13 highlights the difference between the proposed model and current practices in construction planning. Prevailing practices in construction planning can be divided into three broad phases: Pretender phase the period between the receipt of a tender enquiry by a construction firm and submission of a tender; preconstruction phase the period between the award of a contract to a construction firm and commencement of work on site; and construction phase the period between commencement of work on site and completion of site works. Construction plans prepared in the pretender phase are used for preparing the tender and consist mainly of general details of anticipated construction methods and rough estimates of anticipated resource requirements. After the contract has been awarded to the firm and prior to the commencement of work on site (the preconstruction phase), time, cost, and resource schedules are prepared on the basis of a predetermined construction method. After the commencement of work on site (the construction phase) construction planning activities consist mainly of reviewing the progress of the project at regular intervals, identifying deviations from the scheduled progress, and taking corrective measures to bring the project back in line with the original schedule. Prevailing practices in construction planning, as described above, have often been criticized for the following reasons (Erskine-Murray 1972; Laufer and Tucker 1987; Faniran et al. 1994b): 1. Attention paid to the determination of construction methods is insufficient. 2. Emphasis is on forecasting project performance before the commencement of work and controlling project performance after the commencement of work. Prospective planning (planning directed toward creating a desired future) is therefore replaced by retrospective planning (planning directed toward correcting deficiencies created by past deficiencies). The proposed optimal planning model is a product-based model of the construction planning process that addresses the deficiencies highlighted above and incorporates the concept of optimal planning. The model focuses on the preconstruction and construction phases of a project. The objective of the model is to provide broad guidelines for project implementation prior to the start of the project and to develop detailed operational plans concurrently with project execution. In the preconstruction phase of a project, an outline schedule and budget is prepared by the contractor s contract management team to serve as a framework for the development of detailed plans (schedules and work assignments) by the site management and production teams. During the construction phase, the site management team divides the project into work packages and assigns production teams to each work package. The production teams are then responsible for developing short-term schedules and work assignments for the individual work packages and monitoring the construction process to ensure that the plans are properly implemented. A key element of the JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999 / 317
8 FIG. 13. Prevailing Approach to Construction Planning and Proposed Optimal Planning Model model is that the construction plans are prepared by the people who are responsible for implementing the plans. This factor has been identified in the general planning literature as being a necessary condition for achieving effectiveness in planning (Ackoff 1970; Kudla 1976). Another key element is that the emphasis on project control in current approaches to construction planning will be replaced by an emphasis on production control. Ballard and Howell (1998) distinguished between project control, which focuses on monitoring performance against specified performance standards, and production control, which focuses on the progressively detailed shaping of the physical production process by the production unit. Further research work is being undertaken to refine and test the model. CONCLUSIONS This paper has explored the concept of optimal planning for construction projects and derived a probable value for optimal planning input into construction projects. Although the applicability of the derived optimum planning input value has inherent limitations, the results have nonetheless demonstrated that investing in construction planning activities beyond an optimum point increases the probability of poor project cost performance and is therefore not likely to be cost-effective. Further research work is required to validate the findings and determine globally guaranteed values of optimal planning inputs for different categories of construction projects. Based on the results obtained from this study, optimal planning can be defined as that level of planning input that provides general direction for a project and, at the same time, provides sufficient flexibility for the project to react to change at the lowest possible level and with the least change in the original plan. A planning model based on the concept of optimal planning was presented and discussed. The model is still under development, and further research work is being undertaken so that it can be refined, evaluated, and implemented. APPENDIX. REFERENCES Ackoff, R. L. (1970). A concept of corporate planning. Wiley, New York. Arditi, D. (1985). Construction productivity improvement. J. Constr. Engrg. and Mgmt., ASCE, 111, Ashley, D. B., Lurie, C. S., and Jaselskis, E. J. (1987). Determinants of construction project success. Proj. Mgmt. J., 18, Ballard, G., and Howell, G. (1998). Shielding production: Essential step in production control. J. Constr. Engrg. and Mgmt., ASCE, 124, BCIS. (1988). Tender sum/final account study. BCIS News, Building Cost Information Service, Royal Institution of Chartered Surveyors, London, (25). Erskine-Murray, P. E. (1972). Construction planning Mainly a question of how. Occasional Paper No. 2, The Institute of Building, London. Faniran, O. O., Oluwoye, J. O., and Lenard, D. (1994a). Effective construction planning. Constr. Mgmt. and Economics, 12, Faniran, O. O., Oluwoye, J. O., and Lenard, D. (1994b). A conceptual process of construction planning for meeting client objectives. J. Real Estate and Constr., Singapore, 4, Faniran, O. O., Oluwoye, J. O., and Lenard, D. (1998). Interactions between construction planning and influence factors. J. Constr. Engrg. and Mgmt., ASCE, 124, Firdman, H. E. (1991). Strategic information systems: Forging the business and technology alliance. McGraw-Hill, New York. Hamilton, M. R., and Gibson, G. E. (1996). Benchmarking preproject planning efforts. J. Mgmt. in Engrg., ASCE, 12, Hosmer, D. W., and Lemeshow, S. (1989). Applied logistic regression. Wiley, New York. 318 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999
9 Jaselskis, E. J., and Ashley, D. B. (1991). Optimal allocation of project management resources for achieving success. J. Constr. Engrg. and Mgmt., ASCE, 117, Kudla, R. J. (1976). Elements of effective corporate planning. Long Range Plng., August, Laufer, A., and Cohenca, D. (1990). Factors affecting construction planning outcomes. J. Constr. Engrg. and Mgmt., ASCE, 116, Laufer, A., and Tucker, R. L. (1987). Is construction project planning really done its job? A critical examination of focus, role and processes. Constr. Mgmt. and Economics, 5, Neale, R. H., and Neale, D. E. (1989). Construction planning. Thomas Telford, London. Norusis, M. J. (1994). SPSS Advanced Statistics 6.1. SPSS Inc., Chicago. Soetrick, F., and Foster, P. (1976). Research into time cost performance of contracts. Rep. No. R22. Building Research Association of New Zealand, Wellington, New Zealand. Syal, M. G., Grobler, F., Willenbrock, J. H., and Parfitti, M. K. (1992). Construction project planning process model for small-medium builders. J. Constr. Engrg. and Mgmt., ASCE, 118, JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER/OCTOBER 1999 / 319
Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries
Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries O O FANIRAN School of Civil and Environmental Engineering The University of New South Wales Sydney
PROJECT CHANGE MANAGEMENT SYSTEM
PROJECT CHANGE MANAGEMENT SYSTEM By C. William Ibbs, 1 Clarence K. Wong, 2 and Young Hoon Kwak 3 ABSTRACT: Changes in projects are common and may be deleterious or beneficial whether you see a change as
Additional sources Compilation of sources: http://lrs.ed.uiuc.edu/tseportal/datacollectionmethodologies/jin-tselink/tselink.htm
Mgt 540 Research Methods Data Analysis 1 Additional sources Compilation of sources: http://lrs.ed.uiuc.edu/tseportal/datacollectionmethodologies/jin-tselink/tselink.htm http://web.utk.edu/~dap/random/order/start.htm
430 Statistics and Financial Mathematics for Business
Prescription: 430 Statistics and Financial Mathematics for Business Elective prescription Level 4 Credit 20 Version 2 Aim Students will be able to summarise, analyse, interpret and present data, make predictions
CRITICAL SUCCESS FACTORS FOR KNOWLEDGE MANAGEMENT STUDIES IN CONSTRUCTION
CRITICAL SUCCESS FACTORS FOR MANAGEMENT STUDIES IN CONSTRUCTION Yu-Cheng Lin Assistant Professor Department of Civil Engineering National Taipei University of Technology No.1.Chung-Hsiao E. Rd., Sec.3,
A Decision-Support System for New Product Sales Forecasting
A Decision-Support System for New Product Sales Forecasting Ching-Chin Chern, Ka Ieng Ao Ieong, Ling-Ling Wu, and Ling-Chieh Kung Department of Information Management, NTU, Taipei, Taiwan [email protected],
Fairfield Public Schools
Mathematics Fairfield Public Schools AP Statistics AP Statistics BOE Approved 04/08/2014 1 AP STATISTICS Critical Areas of Focus AP Statistics is a rigorous course that offers advanced students an opportunity
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
MULTIPLE REGRESSION WITH CATEGORICAL DATA
DEPARTMENT OF POLITICAL SCIENCE AND INTERNATIONAL RELATIONS Posc/Uapp 86 MULTIPLE REGRESSION WITH CATEGORICAL DATA I. AGENDA: A. Multiple regression with categorical variables. Coding schemes. Interpreting
Business Statistics. Successful completion of Introductory and/or Intermediate Algebra courses is recommended before taking Business Statistics.
Business Course Text Bowerman, Bruce L., Richard T. O'Connell, J. B. Orris, and Dawn C. Porter. Essentials of Business, 2nd edition, McGraw-Hill/Irwin, 2008, ISBN: 978-0-07-331988-9. Required Computing
DESCRIPTIVE STATISTICS AND EXPLORATORY DATA ANALYSIS
DESCRIPTIVE STATISTICS AND EXPLORATORY DATA ANALYSIS SEEMA JAGGI Indian Agricultural Statistics Research Institute Library Avenue, New Delhi - 110 012 [email protected] 1. Descriptive Statistics Statistics
1) Write the following as an algebraic expression using x as the variable: Triple a number subtracted from the number
1) Write the following as an algebraic expression using x as the variable: Triple a number subtracted from the number A. 3(x - x) B. x 3 x C. 3x - x D. x - 3x 2) Write the following as an algebraic expression
RECOMMENDATIONS ON BUSINESS PLAN PREPARATION
RECOMMENDATIONS ON BUSINESS PLAN PREPARATION 1. General provisions Business plan must contain: name of the investment project, as well description of its essence and feasibility; substantiation of the
Cash flow is the life line of a business. Many start-up
PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and
DESCRIPTIVE STATISTICS. The purpose of statistics is to condense raw data to make it easier to answer specific questions; test hypotheses.
DESCRIPTIVE STATISTICS The purpose of statistics is to condense raw data to make it easier to answer specific questions; test hypotheses. DESCRIPTIVE VS. INFERENTIAL STATISTICS Descriptive To organize,
International Statistical Institute, 56th Session, 2007: Phil Everson
Teaching Regression using American Football Scores Everson, Phil Swarthmore College Department of Mathematics and Statistics 5 College Avenue Swarthmore, PA198, USA E-mail: [email protected] 1. Introduction
South Carolina College- and Career-Ready (SCCCR) Probability and Statistics
South Carolina College- and Career-Ready (SCCCR) Probability and Statistics South Carolina College- and Career-Ready Mathematical Process Standards The South Carolina College- and Career-Ready (SCCCR)
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY By Mohammad A. Ammar 1 and Emad Elbeltagi 2 ABSTRACT: Scheduling of construction projects that have multiple units, wherein activities
Descriptive Statistics
Descriptive Statistics Primer Descriptive statistics Central tendency Variation Relative position Relationships Calculating descriptive statistics Descriptive Statistics Purpose to describe or summarize
APPLICATION OF LOGISTIC REGRESSION ANALYSIS OF HOME MORTGAGE LOAN PREPAYMENT AND DEFAULT RISK. Received August 2009; accepted November 2009
ICIC Express Letters ICIC International c 2010 ISSN 1881-803X Volume 4, Number 2, April 2010 pp. 325 331 APPLICATION OF LOGISTIC REGRESSION ANALYSIS OF HOME MORTGAGE LOAN PREPAYMENT AND DEFAULT RISK Jan-Yee
CHAPTER 13 SIMPLE LINEAR REGRESSION. Opening Example. Simple Regression. Linear Regression
Opening Example CHAPTER 13 SIMPLE LINEAR REGREION SIMPLE LINEAR REGREION! Simple Regression! Linear Regression Simple Regression Definition A regression model is a mathematical equation that descries the
Course Text. Required Computing Software. Course Description. Course Objectives. StraighterLine. Business Statistics
Course Text Business Statistics Lind, Douglas A., Marchal, William A. and Samuel A. Wathen. Basic Statistics for Business and Economics, 7th edition, McGraw-Hill/Irwin, 2010, ISBN: 9780077384470 [This
Chapter 13 Introduction to Linear Regression and Correlation Analysis
Chapter 3 Student Lecture Notes 3- Chapter 3 Introduction to Linear Regression and Correlation Analsis Fall 2006 Fundamentals of Business Statistics Chapter Goals To understand the methods for displaing
Simple Predictive Analytics Curtis Seare
Using Excel to Solve Business Problems: Simple Predictive Analytics Curtis Seare Copyright: Vault Analytics July 2010 Contents Section I: Background Information Why use Predictive Analytics? How to use
Schools Value-added Information System Technical Manual
Schools Value-added Information System Technical Manual Quality Assurance & School-based Support Division Education Bureau 2015 Contents Unit 1 Overview... 1 Unit 2 The Concept of VA... 2 Unit 3 Control
Institute of Actuaries of India Subject CT3 Probability and Mathematical Statistics
Institute of Actuaries of India Subject CT3 Probability and Mathematical Statistics For 2015 Examinations Aim The aim of the Probability and Mathematical Statistics subject is to provide a grounding in
ALGORITHM FOR SCHEDULING WITH MULTISKILLED CONSTRAINED RESOURCES
ALGORITHM FOR SCHEDULING WITH MULTISKILLED CONSTRAINED RESOURCES By Tarek Hegazy, 1 Member, ASCE, Abdul Karim Shabeeb, 2 Emad Elbeltagi, 3 and Tariq Cheema 4 ABSTRACT: Scheduling with constrained resources,
Forecasting cash flow expenditure at pre-tender stage: Case studies in New Zealand construction projects
Forecasting cash flow expenditure at pre-tender stage: Case studies in New Zealand construction projects Andrew Heaps School of Engineering and Advanced Technology, Massey University [email protected]
STATISTICA Formula Guide: Logistic Regression. Table of Contents
: Table of Contents... 1 Overview of Model... 1 Dispersion... 2 Parameterization... 3 Sigma-Restricted Model... 3 Overparameterized Model... 4 Reference Coding... 4 Model Summary (Summary Tab)... 5 Summary
DISCRIMINANT FUNCTION ANALYSIS (DA)
DISCRIMINANT FUNCTION ANALYSIS (DA) John Poulsen and Aaron French Key words: assumptions, further reading, computations, standardized coefficents, structure matrix, tests of signficance Introduction Discriminant
Diagrams and Graphs of Statistical Data
Diagrams and Graphs of Statistical Data One of the most effective and interesting alternative way in which a statistical data may be presented is through diagrams and graphs. There are several ways in
Geostatistics Exploratory Analysis
Instituto Superior de Estatística e Gestão de Informação Universidade Nova de Lisboa Master of Science in Geospatial Technologies Geostatistics Exploratory Analysis Carlos Alberto Felgueiras [email protected]
Northumberland Knowledge
Northumberland Knowledge Know Guide How to Analyse Data - November 2012 - This page has been left blank 2 About this guide The Know Guides are a suite of documents that provide useful information about
Silvermine House Steenberg Office Park, Tokai 7945 Cape Town, South Africa Telephone: +27 21 702 4666 www.spss-sa.com
SPSS-SA Silvermine House Steenberg Office Park, Tokai 7945 Cape Town, South Africa Telephone: +27 21 702 4666 www.spss-sa.com SPSS-SA Training Brochure 2009 TABLE OF CONTENTS 1 SPSS TRAINING COURSES FOCUSING
Foundation of Quantitative Data Analysis
Foundation of Quantitative Data Analysis Part 1: Data manipulation and descriptive statistics with SPSS/Excel HSRS #10 - October 17, 2013 Reference : A. Aczel, Complete Business Statistics. Chapters 1
When to Use a Particular Statistical Test
When to Use a Particular Statistical Test Central Tendency Univariate Descriptive Mode the most commonly occurring value 6 people with ages 21, 22, 21, 23, 19, 21 - mode = 21 Median the center value the
II. DISTRIBUTIONS distribution normal distribution. standard scores
Appendix D Basic Measurement And Statistics The following information was developed by Steven Rothke, PhD, Department of Psychology, Rehabilitation Institute of Chicago (RIC) and expanded by Mary F. Schmidt,
Multiproject Scheduling in Construction Industry
Multiproject Scheduling in Construction Industry Y. Gholipour Abstract In this paper, supply policy and procurement of shared resources in some kinds of concurrent construction projects are investigated.
Sun Li Centre for Academic Computing [email protected]
Sun Li Centre for Academic Computing [email protected] Elementary Data Analysis Group Comparison & One-way ANOVA Non-parametric Tests Correlations General Linear Regression Logistic Models Binary Logistic
Overview Classes. 12-3 Logistic regression (5) 19-3 Building and applying logistic regression (6) 26-3 Generalizations of logistic regression (7)
Overview Classes 12-3 Logistic regression (5) 19-3 Building and applying logistic regression (6) 26-3 Generalizations of logistic regression (7) 2-4 Loglinear models (8) 5-4 15-17 hrs; 5B02 Building and
STATS8: Introduction to Biostatistics. Data Exploration. Babak Shahbaba Department of Statistics, UCI
STATS8: Introduction to Biostatistics Data Exploration Babak Shahbaba Department of Statistics, UCI Introduction After clearly defining the scientific problem, selecting a set of representative members
Biostatistics: DESCRIPTIVE STATISTICS: 2, VARIABILITY
Biostatistics: DESCRIPTIVE STATISTICS: 2, VARIABILITY 1. Introduction Besides arriving at an appropriate expression of an average or consensus value for observations of a population, it is important to
Algebra 1 Course Information
Course Information Course Description: Students will study patterns, relations, and functions, and focus on the use of mathematical models to understand and analyze quantitative relationships. Through
Section A. Index. Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1. Page 1 of 11. EduPristine CMA - Part I
Index Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1 EduPristine CMA - Part I Page 1 of 11 Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting
Description. Textbook. Grading. Objective
EC151.02 Statistics for Business and Economics (MWF 8:00-8:50) Instructor: Chiu Yu Ko Office: 462D, 21 Campenalla Way Phone: 2-6093 Email: [email protected] Office Hours: by appointment Description This course
Lean Six Sigma Analyze Phase Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY
TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY Before we begin: Turn on the sound on your computer. There is audio to accompany this presentation. Audio will accompany most of the online
Concepts in Investments Risks and Returns (Relevant to PBE Paper II Management Accounting and Finance)
Concepts in Investments Risks and Returns (Relevant to PBE Paper II Management Accounting and Finance) Mr. Eric Y.W. Leung, CUHK Business School, The Chinese University of Hong Kong In PBE Paper II, students
RUNNING A PROFITABLE CONSTRUCTION COMPANY: REVISITED BREAK-EVEN ANALYSIS
PEER-REVIEWED PAPER RUNNING A PROFITABLE CONSTRUCTION COMPANY: REVISITED BREAK-EVEN ANALYSIS By Joon H. Paek 1 ABSTRACT: Many companies have a tendency to spread out their operations into branches and/or
Module 3: Correlation and Covariance
Using Statistical Data to Make Decisions Module 3: Correlation and Covariance Tom Ilvento Dr. Mugdim Pašiƒ University of Delaware Sarajevo Graduate School of Business O ften our interest in data analysis
Assessment of Critical Success Factors for Construction Projects in Pakistan
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
Statistics in Retail Finance. Chapter 6: Behavioural models
Statistics in Retail Finance 1 Overview > So far we have focussed mainly on application scorecards. In this chapter we shall look at behavioural models. We shall cover the following topics:- Behavioural
Introduction to Statistics and Quantitative Research Methods
Introduction to Statistics and Quantitative Research Methods Purpose of Presentation To aid in the understanding of basic statistics, including terminology, common terms, and common statistical methods.
Ch.3 Demand Forecasting.
Part 3 : Acquisition & Production Support. Ch.3 Demand Forecasting. Edited by Dr. Seung Hyun Lee (Ph.D., CPL) IEMS Research Center, E-mail : [email protected] Demand Forecasting. Definition. An estimate
HYPOTHESIS TESTING: CONFIDENCE INTERVALS, T-TESTS, ANOVAS, AND REGRESSION
HYPOTHESIS TESTING: CONFIDENCE INTERVALS, T-TESTS, ANOVAS, AND REGRESSION HOD 2990 10 November 2010 Lecture Background This is a lightning speed summary of introductory statistical methods for senior undergraduate
Students' Opinion about Universities: The Faculty of Economics and Political Science (Case Study)
Cairo University Faculty of Economics and Political Science Statistics Department English Section Students' Opinion about Universities: The Faculty of Economics and Political Science (Case Study) Prepared
Manhattan Center for Science and Math High School Mathematics Department Curriculum
Content/Discipline Algebra 1 Semester 2: Marking Period 1 - Unit 8 Polynomials and Factoring Topic and Essential Question How do perform operations on polynomial functions How to factor different types
A PROJECT MANAGEMENT CAUSAL LOOP DIAGRAM T. Michael Toole 1
A PROJECT MANAGEMENT CAUSAL LOOP DIAGRAM T. Michael Toole 1 Accepted for the 2005 ARCOM Conference, London, UK, Sep 5-7. System dynamics principles and analytical tools have the potential to alleviate
AN ANALYSIS OF WORKING CAPITAL MANAGEMENT EFFICIENCY IN TELECOMMUNICATION EQUIPMENT INDUSTRY
RIVIER ACADEMIC JOURNAL, VOLUME 3, NUMBER 2, FALL 2007 AN ANALYSIS OF WORKING CAPITAL MANAGEMENT EFFICIENCY IN TELECOMMUNICATION EQUIPMENT INDUSTRY Vedavinayagam Ganesan * Graduate Student, EMBA Program,
The relative advantages and disadvantages of the causal and non-causal approaches to tourism demand forecasting.
The relative advantages and disadvantages of the causal and non-causal approaches to tourism demand forecasting. By Kostas E. Sillignakis The aim of this essay is to discuss the relative advantages and
Descriptive statistics Statistical inference statistical inference, statistical induction and inferential statistics
Descriptive statistics is the discipline of quantitatively describing the main features of a collection of data. Descriptive statistics are distinguished from inferential statistics (or inductive statistics),
STAT355 - Probability & Statistics
STAT355 - Probability & Statistics Instructor: Kofi Placid Adragni Fall 2011 Chap 1 - Overview and Descriptive Statistics 1.1 Populations, Samples, and Processes 1.2 Pictorial and Tabular Methods in Descriptive
Lecture 2: Descriptive Statistics and Exploratory Data Analysis
Lecture 2: Descriptive Statistics and Exploratory Data Analysis Further Thoughts on Experimental Design 16 Individuals (8 each from two populations) with replicates Pop 1 Pop 2 Randomly sample 4 individuals
11. Analysis of Case-control Studies Logistic Regression
Research methods II 113 11. Analysis of Case-control Studies Logistic Regression This chapter builds upon and further develops the concepts and strategies described in Ch.6 of Mother and Child Health:
BASIC STATISTICAL METHODS FOR GENOMIC DATA ANALYSIS
BASIC STATISTICAL METHODS FOR GENOMIC DATA ANALYSIS SEEMA JAGGI Indian Agricultural Statistics Research Institute Library Avenue, New Delhi-110 012 [email protected] Genomics A genome is an organism s
Algebra 1 2008. Academic Content Standards Grade Eight and Grade Nine Ohio. Grade Eight. Number, Number Sense and Operations Standard
Academic Content Standards Grade Eight and Grade Nine Ohio Algebra 1 2008 Grade Eight STANDARDS Number, Number Sense and Operations Standard Number and Number Systems 1. Use scientific notation to express
Descriptive Statistics
Y520 Robert S Michael Goal: Learn to calculate indicators and construct graphs that summarize and describe a large quantity of values. Using the textbook readings and other resources listed on the web
Center: Finding the Median. Median. Spread: Home on the Range. Center: Finding the Median (cont.)
Center: Finding the Median When we think of a typical value, we usually look for the center of the distribution. For a unimodal, symmetric distribution, it s easy to find the center it s just the center
Example G Cost of construction of nuclear power plants
1 Example G Cost of construction of nuclear power plants Description of data Table G.1 gives data, reproduced by permission of the Rand Corporation, from a report (Mooz, 1978) on 32 light water reactor
In this chapter, you will learn improvement curve concepts and their application to cost and price analysis.
7.0 - Chapter Introduction In this chapter, you will learn improvement curve concepts and their application to cost and price analysis. Basic Improvement Curve Concept. You may have learned about improvement
Section Format Day Begin End Building Rm# Instructor. 001 Lecture Tue 6:45 PM 8:40 PM Silver 401 Ballerini
NEW YORK UNIVERSITY ROBERT F. WAGNER GRADUATE SCHOOL OF PUBLIC SERVICE Course Syllabus Spring 2016 Statistical Methods for Public, Nonprofit, and Health Management Section Format Day Begin End Building
A Primer on Forecasting Business Performance
A Primer on Forecasting Business Performance There are two common approaches to forecasting: qualitative and quantitative. Qualitative forecasting methods are important when historical data is not available.
Problem of the Month Through the Grapevine
The Problems of the Month (POM) are used in a variety of ways to promote problem solving and to foster the first standard of mathematical practice from the Common Core State Standards: Make sense of problems
The Bass Model: Marketing Engineering Technical Note 1
The Bass Model: Marketing Engineering Technical Note 1 Table of Contents Introduction Description of the Bass model Generalized Bass model Estimating the Bass model parameters Using Bass Model Estimates
Week 1. Exploratory Data Analysis
Week 1 Exploratory Data Analysis Practicalities This course ST903 has students from both the MSc in Financial Mathematics and the MSc in Statistics. Two lectures and one seminar/tutorial per week. Exam
PROJECT MANAGEMENT INFORMATION SYSTEMS FOR CONSTRUCTION MANAGERS (CM): CURRENT CONSTITUENTS AND FUTURE EXTENSIONS
PROJECT MANAGEMENT INFORMATION SYSTEMS FOR CONSTRUCTION MANAGERS (CM): CURRENT CONSTITUENTS AND FUTURE EXTENSIONS Youngsoo Jung 1 *, Heea Kim 1, and Mihee Joo 2 1 College of Architecture, Myongji University,
How To Write A Data Analysis
Mathematics Probability and Statistics Curriculum Guide Revised 2010 This page is intentionally left blank. Introduction The Mathematics Curriculum Guide serves as a guide for teachers when planning instruction
LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS
LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS Antonio Sergio Itri Conte 1 ABSTRACT The paper describes the experience of a civil engineering company of a small town in São Paulo State
The Effect of Dropping a Ball from Different Heights on the Number of Times the Ball Bounces
The Effect of Dropping a Ball from Different Heights on the Number of Times the Ball Bounces Or: How I Learned to Stop Worrying and Love the Ball Comment [DP1]: Titles, headings, and figure/table captions
MBA 611 STATISTICS AND QUANTITATIVE METHODS
MBA 611 STATISTICS AND QUANTITATIVE METHODS Part I. Review of Basic Statistics (Chapters 1-11) A. Introduction (Chapter 1) Uncertainty: Decisions are often based on incomplete information from uncertain
Analyzing Material Management Techniques on Construction Project Ashwini R. Patil, Smita V. Pataskar
Analyzing Material Management Techniques on Construction Project Ashwini R. Patil, Smita V. Pataskar Abstract The efficient procurement of material represents a key role in the successful completion of
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
9 Hedging the Risk of an Energy Futures Portfolio UNCORRECTED PROOFS. Carol Alexander 9.1 MAPPING PORTFOLIOS TO CONSTANT MATURITY FUTURES 12 T 1)
Helyette Geman c0.tex V - 0//0 :00 P.M. Page Hedging the Risk of an Energy Futures Portfolio Carol Alexander This chapter considers a hedging problem for a trader in futures on crude oil, heating oil and
DETERMINANTS OF PROJECT MANAGEMENT SUCCESS
DETERMINANTS OF PROJECT MANAGEMENT SUCCESS Gary Walker, Dr Shamil Naoum and Professor Rod Howes South Bank University, School of Construction, London. SW8 2JZ One of the features of the construction industry
Vertical Alignment Colorado Academic Standards 6 th - 7 th - 8 th
Vertical Alignment Colorado Academic Standards 6 th - 7 th - 8 th Standard 3: Data Analysis, Statistics, and Probability 6 th Prepared Graduates: 1. Solve problems and make decisions that depend on un
2. Simple Linear Regression
Research methods - II 3 2. Simple Linear Regression Simple linear regression is a technique in parametric statistics that is commonly used for analyzing mean response of a variable Y which changes according
Better decision making under uncertain conditions using Monte Carlo Simulation
IBM Software Business Analytics IBM SPSS Statistics Better decision making under uncertain conditions using Monte Carlo Simulation Monte Carlo simulation and risk analysis techniques in IBM SPSS Statistics
SPSS TRAINING SESSION 3 ADVANCED TOPICS (PASW STATISTICS 17.0) Sun Li Centre for Academic Computing [email protected]
SPSS TRAINING SESSION 3 ADVANCED TOPICS (PASW STATISTICS 17.0) Sun Li Centre for Academic Computing [email protected] IN SPSS SESSION 2, WE HAVE LEARNT: Elementary Data Analysis Group Comparison & One-way
USING LOGIT MODEL TO PREDICT CREDIT SCORE
USING LOGIT MODEL TO PREDICT CREDIT SCORE Taiwo Amoo, Associate Professor of Business Statistics and Operation Management, Brooklyn College, City University of New York, (718) 951-5219, [email protected]
UNIVERSITY of MASSACHUSETTS DARTMOUTH Charlton College of Business Decision and Information Sciences Fall 2010
UNIVERSITY of MASSACHUSETTS DARTMOUTH Charlton College of Business Decision and Information Sciences Fall 2010 COURSE: POM 500 Statistical Analysis, ONLINE EDITION, Fall 2010 Prerequisite: Finite Math
EXPLORING SPATIAL PATTERNS IN YOUR DATA
EXPLORING SPATIAL PATTERNS IN YOUR DATA OBJECTIVES Learn how to examine your data using the Geostatistical Analysis tools in ArcMap. Learn how to use descriptive statistics in ArcMap and Geoda to analyze
Regression Analysis: A Complete Example
Regression Analysis: A Complete Example This section works out an example that includes all the topics we have discussed so far in this chapter. A complete example of regression analysis. PhotoDisc, Inc./Getty
MTH 140 Statistics Videos
MTH 140 Statistics Videos Chapter 1 Picturing Distributions with Graphs Individuals and Variables Categorical Variables: Pie Charts and Bar Graphs Categorical Variables: Pie Charts and Bar Graphs Quantitative
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
Topic 9 ~ Measures of Spread
AP Statistics Topic 9 ~ Measures of Spread Activity 9 : Baseball Lineups The table to the right contains data on the ages of the two teams involved in game of the 200 National League Division Series. Is
SAS Software to Fit the Generalized Linear Model
SAS Software to Fit the Generalized Linear Model Gordon Johnston, SAS Institute Inc., Cary, NC Abstract In recent years, the class of generalized linear models has gained popularity as a statistical modeling