QUT Digital Repository:
|
|
|
- Sheryl Fleming
- 10 years ago
- Views:
Transcription
1 QUT Digital Repository: Al-Kharashi, Adel and Skitmore, Martin (2009) Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1). pp Copyright 2009 Routledge
2 Causes of delays in Saudi Arabian public sector construction projects Adel Al-Kharashi and Martin Skitmore School of Urban Development Queensland University of Technology Gardens Point Brisbane Q4001 Australia Corresponding Author: Professor Martin Skitmore School of Urban Development Queensland University of Technology Gardens Point Brisbane Q4001 Australia Tel: Fax: [email protected] 7 October 2008
3 CAUSES OF DELAYS IN SAUDI ARABIAN PUBLIC SECTOR CONSTRUCTION PROJECTS ABSTRACT Many public construction projects have been undertaken throughout the Kingdom of Saudi Arabia as part of the government s national development plans in the last three decades, with significant public expenditure involved. One of the critical problems concerning these projects is the frequent and lengthy delays that occur. In order to improve the situation, it is first necessary to identify the major causes involved. Several studies have already been reported which do this but all use different sets of variables. Also, none have attempted to identify the extent to which improvements are possible in practice. A new survey is reported that uses all the variables from the previous work and that are measured for both current degree of effect on delays and the extent to which each can be practically improved. These are contained in seven groupings: client, contractor, consultant, materials, labour, contract and relationshiprelated causes. The survey covers a sample of 86 clients, contractors and consultants working in the Saudi construction industry. The analysis reveals some considerable heterogeneity between the cause groupings and respondent groupings in terms of means and correlations, apparently partly due to lack of knowledge of respondents and a tendency for the consultants to blame the contractors for the delays and vice versa. The main results, therefore, are disaggregated to reflect the views of each respondent group concerning each group of causes. In general however, it is found
4 2 that the most influencing current cause of delay is the lack of qualified and experienced personnel attributed to the considerable amount of large, innovative, construction projects and associated current undersupply of manpower in the industry. KEYWORDS Saudi Arabia, delays, heterogeneity. INTRODUCTION Many public construction projects have been undertaken throughout the Kingdom of Saudi Arabia in the last three decades as part of the government s national development plans, and with significant public expenditure involved. According to the Saudi Ministry of Planning, the construction industry contributed between 30% to 40% of the non-oil productive sectors at the end of each National Development Plan from 1980 to 2000 (Cordsman 2000). One of the critical problems faced by the government sector is the frequent and lengthy delays in such projects. Zain Al-Abidien (1983) found that delayed projects accounted for 70% of projects undertaken by the Ministry of Housing and Public Works. Al-Sultan (1987) surveyed time performance of different types of projects in Saudi Arabia and concluded that 70% of public projects experienced time overrun. In a preliminary survey by the Water and Sewage Authority in the Eastern Province in Saudi Arabia, it was found that 45 (59%) out of a total of 76 projects completed
5 3 during the period were delayed (Al-Khalil and Al-Ghafly 1999: 101). In a more recent survey, Kahlil (2004) reported a rose coloured 952 (40%) out of 2379 project in Saudi Arabia to have been delayed, suggesting that some improvements have been achieved over the last decade. In terms of cost and follow-on consequences, project delay is considered to be one of the most serious and frequent problems in the Saudi Arabian construction industry (Faridi and Al-Sayegh 2006). The delay of any construction project affects the direct costs of the project. In the case where the project is a public building or facility, the complications increase as the client is a government department. The effects of delay in such cases may include: confusion regarding the public development plans disturbance of the budget execution plan for the government authority involved public inconvenience resulting from delay of the project. From the contractor s viewpoint, delay is simply an additional liability as: the construction period becomes longer the longer period results in higher overhead costs and expenses the entire contractor's working capital may become trapped in one project. Delays also mean loss of output and revenues, since the contractor cannot become involved in other projects. The profit lost by the contractor, therefore, is equal to the opportunity cost of the projects the contractor misses (O'Brien 1998).
6 4 A common characteristic of construction projects is that they are dynamic and have a high level of uncertainty. This results in a cyclical argument, where delays are accepted as inevitable and is considered by some to be a global phenomenon affecting all the various construction project participants (Sambasivan and Soon 2007). However, considering the above points and the costs resulting from delays, there is a need to take the previous studies one step further to identify the causes of delays that produce the greatest effects and the extent to which these effects can be ameliorated in the Saudi Arabian construction industry. In order to determine the root causes of delay, a thorough analysis is needed of the critical areas involved. The early identification of these critical areas should improve the performance of contractors and increase the chances of successful project completion. Delay management research is a well established area in several industries. In transportation, for example, the delay management problem is to find wait-depart decisions such that the inconvenience over all customers is minimised (e.g., Schöbel 2001), with associated work analysing the occurrence of delays (e.g., Chen and Harker 1990; Higgins and Kozan 1998). In a similar way, delay management algorithms have been developed for Internet applications such as voice-over IP, videoconferencing and video streaming, which have strong delay requirements on their data streams the goal being to optimise service differentiation and prioritisation of the information packets involved (e.g., Dumitrescu and Harju 2004). In sales and marketing on the other hand, capital investment policy models aimed at managing product growth involve market reaction to delivery delay in addition to salesmen and capital equipment expansion (Forrester 1967).
7 5 Many previous studies have been reported that have some relevance to this theme in the construction industry, with the causes of construction delays being identified in a wide range of countries, including Canada, Ghana, Hong Kong, Indonesia, Jordon, Nepal, Nigeria, Thailand, Turkey, and USA (these studies are too numerous to describe in any detail, but summaries are available in Chan (1998), Assaf and Al-Hejji (2006), Sambasivan and Soon (2007) and Lo et al. (2006)). Of these, 10 have identified the causes of delay of construction projects in Saudi Arabia (Al-Mudlej 1984; Al-Hazmi 1987; Al-Ojaimi 1989; Assaf and Mohammed 1996; Al-Ghafly 1995; Al-Khalil and Al-Ghafly 1999; Odeh and Battaineh 2002; Assaf and Al-Hejji 2006; Arain et al. 2006). Combined together, these 10 studies produced 112 causes of delay. Upon inspection, it was found that each of these causes could be allocated to one of Odeh and Battaineh s (2002) seven groupings, comprising: 1. Client-related 2. Contractor-related 3. Consultant-related 4. Materials-related 5. Labour-related 6. Contract-related 7. Contractual relationship-related The 112 causes cited in the previous studies were then investigated further by means of a questionnaire survey. This was targeted at client, consultants and contractors to elicit their views quantitatively on the current extent of effect of each cause and the extent to which improved practices could ameliorate these effects in the future. This
8 6 required responses on a five point scale, comprising 0= No effect to 4= Lot of effect, to 27 client-related causes, 34 contractor-related causes; 12 consultantrelated causes, 9 materials-related causes, 17 labour-related causes, 10 contractrelated causes and 3 contractual-relationship related causes (for the analysis, the last 2 groups were combined into a single group). Table 1 provides an extract from the question concerning client-related factors. An open-ended qualitative question was also added to allow respondents to provide further details. Space limitations prohibit a detailed account at this point of the 112 causes involved. Instead, several of those found to be most significant as a result of the subsequent analysis are described in more detail in the Discussion section below. RESULTS Following a short pilot study, the final questionnaire was sent to potential respondents in Saudi Arabia (by ) in April A convenience sample of five major public construction projects in Saudi Arabia was adopted and a random sample was taken of the client/owners, consultants and contractors involved. Each person was given one month to complete and return the questionnaire. A total of 86 questionnaires were returned during this period, representing a 43% response rate. The respondents comprise contractors (40%), consultants (36%) and clients representatives (24%). The majority (40%) are years of age, with 28% being years of age and 19% over 50. Approximately 81% have at least 10 years experience and 82% have a bachelor's degree as their minimum level of education,
9 7 with 16% holding masters qualifications. 50% are executives of various companies, indicating a heavy involvement with the management practicalities as well as toplevel decision-making in the construction industry. Most respondents are involved in projects costing over RS50million (USD$20million). This suggests that a reasonable cross section of respondents were involved in the survey and a concomitant reduction in the likelihood of the results being biased. Homogeneity of responses Previous research has found some significant differences in opinions between the various parties involved. For example, owners and consultants attribute the major causes of delay to be those for which the contractor is responsible and vice versa (Al- Khalil and Al-Ghafly 1999). This is also the case with these data and would be a source of bias if the data are to be aggregated. Figs 1-3 illustrate the differences in mean values recorded for the three groups of respondents and the six groups of causes for the Now, Future and Differences scores, where Now and Future denote the responses to the questions How much do the causes delay Saudi's construction projects at the moment?, and How much do you think they should be causing delays if practice is improved? respectively, with Differences being the simple arithmetic difference between the two. Two-way Analysis of Variance (ANOVA) 1 was conducted with the main independent variables being the 3-factor respondent groupings (1-client, 2-consultant, 3-contractor) and the 6-factor cause groupings (1- client-related, 2-contractor-related, 3-consultant-related, 4-labour-related, 5-materials-
10 8 related, 6-contract/relationship related) and the Now scores as the dependent variable. This showed both the respondent and cause effects and their interaction effects to be significantly different (p<0.05). Using the Future scores as the dependent variable produced the same results. However, using the Differences scores as the dependent variable showed only the respondent and respondent-cause interaction effects to be significant. In terms of correlations, the result is less clear. Table 2a provides the Spearman correlation coefficients for all the pair-wise permutations of the three respondent groupings for each of the six cause groupings for the Now, Future and Difference scores. For example, column three provides the correlation coefficient for the clients versus the contractors, with 0.70 being recorded for the Now scores for the clientrelated causes. Results highlighted in bold and starred are significant (p<0.05). Further inspection of Table 2a indicates that: 1. the contractor-client and contractor-consultant results are the same 2. none agree on the consultant-related Future and to a lesser extent the clientrelated Future 3. client-consultant also do not agree on consultant-related Now and contractorrelated Future. Table 2b provides the results for the Now-Future correlations. For example, the correlation between contractors Now and Future scores for the client-related causes is a low 0.06, while the correlation between the contractors Now scores and clients 1 ANOVA is a parametric method of analysis for interval level data, while Likert scales are intrinsically ordinal. However, ANOVA is known to be robust in nonparametric settings and is regularly used for Likert scales (e.g., Zou and Lee, 2008; Chan and Lee, 2008; Lam et al, 2008)
11 9 Future scores for client-related causes is a significant In general Table 2b indicates that for: 1. Labour-related causes: General agreement that Future is similar to Now 2. Contract/relationship-related causes: Ditto except the consultant s Now is different to client s Future 3. Consultant-related causes: All agree Future different to Now except the consultant s Now and client s Future 4. Contractor-related causes: Contractor s Future similar to all Nows; client s future similar to other s Nows (but not own Now); consultant s future different to all Nows 5. Client-related causes: Consultant s Future similar to his other s Nows (but not own Now); contractor s Future different to all Nows; client s Future a little similar to all Nows 6. Materials-related causes: Contractors Future very different to all Nows; consultants Future similar to contractors Nows (but not own Now); client s Future a little similar to all Nows. The reasons for this pattern of results need to be investigated by further research, but the extent of the heterogeneity involved makes it clear that a simple aggregation of data is likely to be misleading and a group by group analysis is needed. Results for the cause groupings Fig. 4 gives the results for the client-related causes, in terms of Now and Future mean scores for each cause for each respondent grouping, presented in terms of the ordered
12 10 overall mean Future scores. Here, we assume the Future values to be the baseline standard. In other words, the mean Future values are taken to represent the best realistically achievable result. On this basis, the aggregated results suggest the best of these to be Owner s interference, Owner s personality, Negotiation by knowledgeable people, etc., as these are seen to have the least effect with a mean value of around 2.0. The worst of the aggregated baseline results are Key personnel replaced, Owner s poor communication and Slow decision-making by owner with a mean value of around 2.5. However, from the above analysis, we know the mean values differ significantly between each respondent group for the Future scores. Also, the scores are not significantly correlated (Table 2a), which indicates that aggregating results in this way may be misleading. Table 3 gives the results of considering each group of respondents individually. This shows the five causes that have the greatest effect on delays for each respondent group. Therefore, the client response for the client-related causes, Lack of finance to complete the work by the client has the highest Future effect, with a mean score of 2.6. Equal with this is Slow decision-making by the owner, followed by Suspension of work by the owner (2.5), Difficulties in obtaining work permits (2.4) and Non-payment of contractor claim (2.3). The contractor response, on the other hand is Replace key personnel (2.8), Slow decision making by the owner (2.7), Owner s poor communication with the construction parties and government authorities (2.7), Interference by the owner in the construction operations (2.7) and Poor communication by owner and other parties (2.7), with the consultant response as Suspension of work by the owner (2.7), Owner s poor communication with the construction parties and government authorities (2.5), Replace key personnel (2.4),
13 11 Lack of finance to complete the work by the client (2.4) and Delay in approving sample materials by owner (2.4). In contrast, the Now scores are clearly much higher than the Future scores, although they are more correlated than the Future scores. The five causes with the greatest Now effect on delays are again shown in Table 3. As expected due to the higher correlation, some of these occur more frequently across the respondent groups. Lack of finance to complete the work by the client and Delay in progress payments by the owner appear in the list of all three respondent groups. Figs 5-9 contain the results for the remaining five cause groups, with Table 3 again containing the five causes with the greatest effect on delays in terms of both Now and what respondents think should happen in the future. Other causes nominated by respondents In addition to the 112 causes documented in the questionnaire, some respondents also nominated a range of other delay causes, comprising: Quality management system and assurance control The consultant attempting to hide their mistake when the quantity amount changes Insufficient allowance for employees' holidays in the schedule Inadequate original contract duration Lack of clarity of drawings and specifications
14 12 Client need to analyse the causes of change The lack of experienced engineers engaged by consultants for high-tech work Insufficient numbers of contractors to build the increasing number of construction projects in Saudi Arabia Insufficient consideration of the behaviour of people Lack of regular meetings Unclear scope of work to be done by staff contractors High turn-over of personnel in Saudi Arabia Insufficient study of all the details and capacity of the contractor before selection by client Overdependence on the lowest tender amount in contractor selection Discrepancies between bill of quantities, specifications and drawings Level of salary of consultant staff Lack of ethics Delayed salary payments to staff Designer engineer selection of special building materials not available in the local market. These will need to be included in any further studies of this kind. DISCUSSION The heterogeneous nature of the data presents special difficulties in analysis in what would otherwise be a relatively simple task of ranking aggregated mean responses. It
15 13 also brings into question the validity of the responses. Can all respondent groups be correct? If not, which one, if any, is correct, and how should the others be treated? For example, Fig. 3 shows the contractor mean Now response to be higher for all cause groups except the contractor-related group. Is this because the contractors are actually more at fault than the other two respondent groups but are unable or unwilling to admit it? Or is that the contractors understand their own contribution better than the other respondents and therefore have provided the only correct result? Similarly, both client and consultant respondents rate their own effect on delays as less than the other respondents. Again, is this because they are hiding fault or just better (or less) informed? The general trend for the client respondents to be lower than other respondents suggests that perhaps the latter is the case, as clients are expected to have less contact with the realities of construction work than contractors and consultants. If this is the case, then it might also be expected that contractors would have more knowledge of the technical aspects of production management (such as materials and labour handling) than consultants. This would go some way to explaining the results in Fig. 3, where the materials-related and labour-related effects are ranked highest by contractors, followed by the consultants and then clients. This is also possibly the case for contract-related effects, where the client and contractor possibly have a bigger interest than the consultants. This would then leave the contractor-effects and consultant-effects to be explained as a recurrence of that found in Al-Khalil and Al-Ghafly's (1999) study, where the contractor blamed the client and vice versa. In this case, it would seem that the consultant blames the contractor, the contractor blames the consultant, while the consultant and contractor blame the client!
16 14 Again, the reason for the passivity of the client may be due to lack of detailed knowledge of site workings. Interestingly, several of the Future results (Fig. 2) are quite similar to the Now results, except at a reduced level of effect. Again, the contractor-consultant-client ranking occurs for materials-related and labour-related effects, as is the above mentioned Al- Khalil-Al-Ghafly effect for the consultant-related effects. What is more generally apparent, however, is the relatively consistent disparity of the contractor and client responses. The client is clearly more optimistic than the contractor, with the consultant largely coming between. Whether or not this is cynicism on behalf of the contractor or naiveté on behalf of the client is hard to say. Perhaps, something of both applies. Turning to the individual cause items themselves, the largest of the Now effects overall are the contractor-related Poor qualification of the contractor's technical staff (3.87), Poor site management and supervision by contractor (3.78), Contractor experience (3.7) and labour-related Shortage of manpower (skilled, semi-skilled, unskilled labour) all by the consultants. As mentioned above, this may be just another example of the Al-Khalil-Al-Ghafly effect, although these also attracted mean scores of 3.4, 3.5, 3.5 and 3.6 by the contractors. For the contractors, the highest are the client-related Suspension of work by the owner (3.61), the consultant-related Delay in approving major changes in the scope of work by consultant (3.6), materials-related Shortage of construction materials in market (3.6) and labour-related Shortage of manpower (skilled, semi-skilled, unskilled labour) (3.6), which seems to show a more balanced view (but hardly evidence for
17 15 correctness). For the clients, these are the labour-related Shortage of manpower (skilled, semi-skilled, unskilled labour) (3.6) and Poor qualification of the contractor s technical staff assigned to the project (3.5), and the contractor-related Contractor experience (3.57). Of these, Shortage of manpower (skilled, semiskilled, unskilled labour) is common to all three respondent groups, with Poor qualification of the contractor s technical staff assigned to the project and Contractor experience common to both consults and clients inviting the conclusion that experience is all important. These and the other causes with the greatest current effect are discussed in more detail below in terms of the six causation groups involved. 1. Client-related causes Finance issues are of much concern, as evidenced by the results in the study. These are related to the lack of finances, non-payments and delay in progress of payments by the clients. This may be due to a level of underfunding by the Saudi Ministry of Finance. Moreover, many departments need to review each contractor's payment. This is often a long process and has continually affected Saudi public construction projects for the last three decades. For instance, a number of researchers (Al-Mudlej 1984; Al- Hazmi 1987; Al-Subaie 1987; Al-Khalil and Al-Ghafly 1999; Al-Sedairy 2001) found the delay of payments or non-payment to contractors in Saudi Arabia to have become the major cause of delay of public projects. This issue is also illustrated
18 16 comprehensively by Arain et al. (2006) and Assaf et al. (1999), among others, who stress the importance of stabilising the contractors' financial situation. Other client-related concerns include the suspension of work, which has been an acknowledged source of delays since the beginning of the Saudi Arabian construction renaissance 30 years ago (O'Brien 1976). This allows the project owner to suspend any part of the work at any point of time, within reason, to restudy and redesign any part of the project so that necessary modification and corrections can be made. More recently, the issue of change orders has also been noted as a critical factor in delay in public construction in Saudi Arabia (Assaf and Al-Hejji 2006). The other major source of delay is the need for client approval. For example, the contractor has often to obtain the approval of the client to use a certain type of material in the project (Clough and Sears 1994). This cause emerged in previous studies by Al-Hazmi (1987) and Al-Khalil and Al-Ghafly (1999) who also found slow decision-making by the client to be a major cause of delay. The reason appears to be due to the client s low level of technical submittals. This means the contractor is provided with insufficiently well informed studies and recommendations by the consultant, or the client's technical staff have little expertise in handling such technical matters.
19 17 2. Contractor-related causes As mentioned above, contractor inexperience is a major cause of delay. This has emerged only once in previous studies (Al-Ojaimi 1989), which occurred during an economic spurt in Saudi Arabia - reflected in the initiation of several economic projects and a developmental economic boom. Right now, Saudi Arabia is once again experiencing a growth in its economy. The desire of different government sectors to build several mega-projects has been announced recently to the media. Many authors have noted lack of experience as one of the critical causes affecting the performance of the construction sector (e.g., Clough and Sears 1994; O'Brien 1998; Arain et al. 2006). A related issue is the poor qualification of the contractor's technical staff. This was first identified as a cause of delay in the 1980s (Al-Mudlej 1984; Al-Ojaimi 1989). The reason again appears to be the commissioning of huge projects due to the growth of the economy in these periods and the resultant shortage of personnel, as anticipated by Al-Barrak (1993), who advised contractors to engage highly proficient technical staff to ensure they will work effectively during the boom construction period. Contractor difficulty in financing projects has been emerging since the 1990s as a critical cause of delay (Assaf et al. 1995; Al-Khalil and Al-Ghafly 1999; Odeh and Battaineh 2002) and is related to delayed progress payments to the contractor by the client. Since 1987, the government has stopped making advance payments to contractors (which was equal to 20% of the contract value).
20 18 Although Cori (1987) has linked successful construction projects with leadership ability and the right time on the site, no previous studies have shown poor site management and supervision by contractors to be critical causes of delay. It is again likely to be due to contractors in Saudi Arabia being increasingly required to perform large-scale projects in terms of size or in terms of the volume of construction works, and this may have led to contractors losing control of the management of the sites as they not familiar with projects of this scale. The other contractor-related causes are conflict between contractors with other parties, and ineffective scheduling of the project by the contractor. These issues have also emerged previously to some extent. For instance, Al-Ojaimi (1989), Assaf et al. (1995), Al-Khalil and Al-Ghafly (1999) showed that scheduling had become a critical issue in the construction industry in Saudi Arabia. On the other hand, no mention is made in previous studies concerning work conflict between contractors and other parties as causes of delay. Of course, poor scheduling by the contractor may be related to lack of experience or it may relate directly or indirectly to the suspension of work by the client, as discussed earlier. 3. Consultant-related causes As Al-Ghafly (1995) notes regarding Saudi consultants, it is important to recognise consultant performance as a crucial factor in construction projects. However, the majority of previous studies have been limited to just the client and contractor alone. The importance of consultants experience and the delay in review of the design
21 19 documents found here might be interpreted as again reflecting the existence of numerous current projects of a vastly different nature from previous projects, demanding technical requirements with which consultants are unable to deal with successfully. In addition, delays in reviewing design documents may be related to the low level of standard technical service offered by contractors to the consultant, or to the fact that the number of consultancy staff is usually quite small, as clients often identify the lack of consultant staff as a problem. 4. Materials-related causes The shortage of construction materials in the market and of other materials required has also been found by Assaf et al. (1995) to be a critical cause of delay. It is obvious that this phenomenon is a result of the booming construction industry in Saudi Arabia. That procurement delays are also important is new to Saudi Arabia, although it has been mentioned in the general literature (Arain et al. 2006; Fisk 1997). This may be because of changes in currency exchange rates for imported materials. There may also be connections between this factor and client/consultant delays in making the final decision for selection of materials. 5. Labour and equipment-related causes Shortage of manpower and low skill levels have been shown to be important causes of delay in previous research (Al-Mudlej 1984; Al-Ojaimi 1989; Assaf et al. 1995; Odeh
22 20 and Battaineh 2002), with Faridi and El-Sayegh (2006) and Al-Mansouri (1988) noting that in particular, low skills of the labourers had led to delays. The shortage of local labour in Saudi Arabia has resulted in contractors using imported labour and therefore reducing their ability to judge the level of skill of their employees. Moreover, the quality of labour available is generally quite poor, which leads to low productivity and poor quality of work. There has also been an unstable workforce in the Saudi Arabian construction industry for a long time. 6. Contract-related and contractual relationship causes Although the duration of the contract figures prominently in the results, it has not been raised in other recent studies. Al-Ghafly s 1995 study, however, showed the difficulties involved in completing projects based on an unrealistic timeframe. Once again, it is likely that the current complex environment in Saudi Arabia is a major determining factor. The novel projects currently being required by clients need experienced staff to determine a realistic construction duration period. CONCLUSIONS The stated objective of this paper is to identify the causes of delays that produce the greatest effects and the extent to which these effects can be ameliorated in the Saudi Arabian construction industry. These are summarised in Figs 4-9, where the perceived extent of the effects are shown both now and how they could be in the
23 21 future if appropriate corrective action is taken. However, as discussed at some length, these results need to be treated with care as they are confounded to some extent by significant differences of opinion, particularly between the contractors and consultants each tending to blame the other to some extent. One thing that is clear though, is that the dominant view of the cause of construction delay concerns the shortage of qualified and experienced manpower, most likely brought about by the current boom in construction activity involving large, innovative, projects. Several implications emerge that indirectly affect the duration of construction projects in the Saudi public construction industry. Three can be singled out as having major implications: 1. The failure to develop strategic plans for scheduling future construction projects has led to a current crisis in the construction sector. The issues relating to materials and labour are of significant concern. For example, the availability of construction labour, materials and equipment is greatly affected by demand in the currently booming Saudi Arabian construction industry. The development of future strategies and plans by the Saudi government sectors should help avoid confusion in the construction sector in the future. From these strategies, the government could then, for example, distribute projects more evenly over a number of years to help alleviate the situation. 2. The level of involvement and participation of each party to the construction process is widely different. For example, the client, in this case the government, is often unaware of technical issues and simply passes on its tasks to the consultant. This matter has led the client to be unaware of what is happening on the site itself. This aspect reduces the ability of the client to take
24 22 decisions that may facilitate the construction process. Poor daily communication between the client and consultant and lack of experience of the client's technical staff tend to exacerbate the situation. It may be beneficial for the Saudi government to offer greater encouragement for contractors and consultants to cooperate with external companies with more experience than local companies to improve the level of local experience. 3. The current disagreement between the three parties on the sources of delays, especially in relation to technical and management causes, may be due to the lack of a single system of measurement of each s progress or quality of work. It is possible that this may be overcome to some extent by the use of more modern management methods to measure the range of intangible issues involved. REFERENCES Al-Barrak, A. A. (1993), 'Causes of contractors' failures in Saudi Arabia', MS Thesis, King Fahd University of Petroleum and Minerals. Al-Ghafly, M. A. A. (1995), 'Delay in the construction of public utility projects in Saudi Arabia', MS Thesis, King Fahd University of Petroleum and Minerals. Al-Hazmi, M. H. (1987), 'Causes of delay in large building construction projects', MS Thesis, King Fahd University of Petroleum and Minerals. Al-Khalil, M. and Al-Ghafly, M. A. (1998), 'Important causes of delay in public utility projects in Saudi Arabia'. Construction Management and Economics, 17(5):647
25 23 Al-Khalil, M. I. and Al-Ghafly, M.A. (1999), 'Delay in public utility projects in Saudi Arabia'. International Journal of Project Management, 17(2) Al-Mansouri, O. H. (1998), 'The relationship between the designer and the contractor in the eastern province of Saudi Arabia,'MS Thesis, University of Reading. England. Al-Mudlej, K. (1984), 'Causes of delays and overruns of construction projects in Saudi Arabia', MS Thesis, King Fahd University of Petroleum and Minerals (last accessed 30 August 2007). Al-Ojaimi, S. (1989), 'Delay execution of projects on time in construction and building sector', MS Thesis, King Fahd University of Petroleum and Minerals,. Al-Sedairy, S. T. (2001), 'A change management model for Saudi construction industry'. International Journal of Project Management, 19(3): Al-Sultan, S. (1987), 'Determination of construction contract duration for public projects in Saudi Arabia', MS Thesis, King Fahd University of Petroleum and Minerals. Arain, F. M., Pheng, L. S. and Assaf, S. (2006), 'Constructors' views of potential causes of inconsistencies between design and construction in Saudi Arabia'. Performance of Constructed Facilities, 20(1): Al-Subaie (1987), 'Construction claims in residential houses in Saudi Arabia', MS Thesis, King Fahd University of Petroleum and Minerals. Assaf, S. A. and Al-Hejji, S. (2006), 'Causes of delay in large construction projects'. International Journal of Project Management, 24(4): Assaf, S. A., Al-Khalil, M, and Al-Hazmi, M. (1995), "Causes of Delay in Large Building Projects", ASCE, Journal of Management in Engineering, 11(2):45-50, March/April.
26 24 Assaf, S. A., Bubshait, A., Atiyah, S. and Al-Shahri, M. (1999), 'Project overhead costs in Saudi Arabia'. Cost Engineering, 41(4):33 Assaf, S.A. and Mohammed, A. (1996), 'Causes of delay in large building construction projects'. Journal of Management in Engineering, 11(2): 27-55; Chan, D.W. (1998), Modelling construction durations for public housing in projects in Hong Kong, PhD thesis, The University of Hong Kong, Hong Kong. Chan, E.H.W. and Lee, G.K.L. (2008), Applicability in Hong Kong of London s experiences on urban redevelopment practices. Property Management. 26(2): Chen, B. and Harker, P. (1990), Two moments estimation of the delay on singletrack rail lines with scheduled traffic. Transportation Science 24: Clough, R. H. and Sears, G. A. (1994), Construction contracting, Wiley New York. Cordsman, A. H. (2000), Saudi Arabia enters the 21 st century V: economic, demographic and social challenges. Center for Strategic and International Studies, 1800 K Street NW, Washington DC Cori, K. A. (1987), 'The project team: Vehicle for reaching the project goals'. Projects Management Institute, pp Dumitrescu, A. and Harju, J. (2004), Delay management in core-stateless networks. Proceedings of NEW2AN, pp (accessed 3 September 2008). Faridi, A. S. and El-Sayegh, S. M. (2006), 'Significant factors causing delay in the UAE construction industry'. Construction Management and Economics, 14: Fisk, E. R. (1997), Construction project administration, Prentice-Hall, USA.
27 URL: evier.nl/l ocate/entcs/volume50.html based on Mi xed-integer-programmi ng 25 Forrester, J.W. (1967) Market growth as influenced by capital investment. 9 th Annual Paul 0. Converse Awards Symposium, 13 April, University of Illinois. (accessed 3 September 2008) Higgins, A. and Kozan, E. (1998), Modeling train delays in urban networks. Transportation Science 32: Lam, P.T.I., Wong, F.W.H. and Chan, A.P.C. (2006), Contributions of designers to improving buildability and constructability. Design Studies 27(4) Lo, T. Y., Fung, I. W. H., Tung, K. C. F. (2006), Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management 132(6) O'Brien, J. (1998), Construction change orders, McGraw-Hill, New York. O'Brien, J. (1976), Construction delays: Responsibilities risk and litigation Chaness Book International, Boston. Odeh, A. M. and Battaineh, H. T. (2002), 'Causes of construction delay: traditional contracts'. International Journal of Project Management, 20(1): Sambasivan, M. and Soon, Y.W. (2007), Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Management, 25: Schöbel, A. (2001), A model for the delay management problem based on mixed integer programming. Electronic Notes in Theoretical Computer Science 50(1). Proc ATMOS (accessed 3 September 2008)
28 26 Zain Al-Abidien, H.M. (1983), About the effect of delay penalty on the construction of projects and modification proposal, Proceedings of the First Engineering Conference, May, King Abdulaziz University, Jeddah. Zou, Yi and Lee, Sang-Hoon (2008), The impacts of change management practices on project change cost performance, Construction Management and Economics, 26(4):
29 27 CAPTIONS TO TABLES AND FIGURES Tables 1: Extract from questionnaire 2a: Spearman s correlation coefficients 2b: Spearman s future/now correlation coefficients 3: Top 5 results Figures 1: Mean difference results 2: Mean future results 3. Mean Now results 4: Client-related causes of delay 5: Contractor-related causes of delay 6: Consultant-related causes of delay 7: Materials-related causes of delay 8: Labour-related causes of delay 9: Contract/relationship-related causes of delay
30 The list below contains causes of delays. For each of these causes you are kindly requested to express your opinion by answering the following three questions and placing ( ) in the appropriate box: In a public construction project in Saudi Arabia How much do the causes delay Saudi's construction projects at the moment? How much do you think they should be causing delays if practice is improved? How much do you think it will cost to improve practice to bring this about? Client-related Factors Answers What is happening now Causes of Delay Answers What should be happening in future How much money you think will cost to modify it Lack of finance to complete the work by the 1. client 2. Non-Payment of contractor claim 3. Owners interference 4. Replace key personal 5. Negotiation by knowledgeable people Delay to furnish and deliver the site to the 6. contractor by the owner Delay in the settlement of contractor claims by 7. the owner 8. Suspension of work by the owner 9. Delay in issuance of change orders by the owner 10. Slow decision making by the owner Interference by the owner in the construction 11. operations Uncooperative owner with the contractor 12. complicating contract administration 13. Delay in progress payments by the owner Owner s poor communication with the 14. construction parties and government authorities 15. Owner s failure to coordinate with Government No effect 0 Very little 1 Little effect 2 Some effect 3 Lot of effect 4 I don t know No effect 0 Very little 1 Little effect 2 Some effect 3 Lot of effect 4 I don t know RS
31 2 authorities during planning Table 1: Extract from questionnaire
32 Cause Client- Client- Contractor- Contractor Consultant Consultant Client-related 0.70* 0.53* 0.62* Contractor-related 0.52* 0.41* 0.56* Consultant-related Materials-related 0.67* 0.89* 0.67* Labour-related 0.76* 0.92* 0.70* Contract/relationship-related 0.60* * Client-related Contractor-related 0.52* * Consultant-related Materials-related Labour-related 0.87* 0.76* 0.67* Contract/relationship-related 0.69* 0.67* 0.82* Client-related Contractor-related Consultant-related Materials-related 0.86* Labour-related 0.70* 0.75* 0.54* Contract/relationship-related * *Significant at p<0.05 Table 2a: Spearman s correlation coefficients Now Future Differences
33 2 Future Cause Client-related Contractor-related Consultant-related Materials-related Labour-related Contract/relationshiprelated *Significant at p<0.05 Table 2b: Spearman s future/now correlation coefficients Now Client Contractor Consultant Client * 0.33 Contractor Consultant 0.46* 0.40* 0.21 Client * 0.52* Contractor 0.38* 0.44* 0.46 Consultant Client * Contractor -0.60* Consultant Client Contractor Consultant * 0.08 Client * 0.30 Contractor 0.50* 0.62* 0.33 Consultant 0.70* 0.89* 0.61* Client Contractor 0.64* 0.88* 0.68* Consultant * 0.40
34 3 Cause Client now Avg Client future Avg Contractor now Avg Contractor future Avg Consultant now Avg Consultant future Avg Lack of finance to Lack of finance to Delay in progress Suspension of work Replace key Suspension of work by complete the 3.29 complete the work by payments by the 3.59 by the owner personal the owner work by the the client owner 2.7 client Client-related Contractor-related Non-Payment of contractor claim Slow decision making by the owner Delay in progress payments by the owner Uncooperative owner with the contractor complicating contract administration Contractor experience Ineffective scheduling of project by contractor Delay in the preparation of contractor submissions Improper technical study by the contractor during the bidding stage Poor qualification of the Slow decision making by the owner Suspension of work by the owner Difficulties in obtaining work permits Non-Payment of contractor claim Difficulties in financing project by contractor Poor qualification of the contractor's technical staff Contractor experience Poor site management and supervision by contractor Ineffective planning by contractor Non-Payment of contractor claim Lack of finance to complete the work by the client Late in revising and approving design documents by owner Delay in approving sample materials by owner Contractor experience Difficulties in financing project by contractor Poor site management and supervision by contractor Conflicts between contractor and other parties (consultant and owner) Poor qualification of the contractor's technical staff Slow decision making by the owner Owner s poor communication with the construction parties and government authorities Interference by the owner in the construction operations Poor communication by owner and other parties Contractor experience Frequent change of sub-contractors because of their inefficient work Poor qualification of the contractor's technical staff Inefficient Workbreak down structure Difficulties in financing project by contractor Lack of finance to complete the work by the client Delay in approving sample materials by owner Late in revising and approving design documents by owner Delay to furnish and deliver the site to the contractor by the owner Poor qualification of the contractor's technical staff Poor site management and supervision by contractor Contractor experience Difficulties in financing project by contractor Ineffective control of the project progress by the contractor 3.45 Owner s poor communication with the construction parties and government authorities Replace key personal Lack of finance to complete the work by the client Delay in approving sample materials by owner Poor communication by contractor with other parties Ineffective scheduling of project by contractor Contractor experience Poor qualification of the contractor's technical staff Ineffective control of the project progress by the contractor
35 4 Consultant-related Materials-related Lab ourrelat ed contractor's technical staff Late in reviewing and approving design documents by consultant Delay in performing inspection and testing by consultant Delay in approving major changes in the scope of work by consultant Inflexibility (rigidity) of consultant Replace key personnel Shortage of construction materials in market Shortage of materials required Late procurement of materials Delay in materials delivery Damage of sorted material while they are needed urgently Shortage of manpower (skilled, semi Inadequate experience of consultant Delay in approving major changes in the scope of work by consultant Frauds Company organisation Replacement of key personnel Shortage of materials required Shortage of construction materials in market Delay in manufacturing special building materials Changes in materials prices Delay in materials delivery Low skill of manpower Delay in approving major changes in the scope of work by consultant Late in reviewing and approving design documents by consultant Inflexibility (rigidity) of consultant Inadequate experience of consultant Delay in performing inspection and testing by consultant Shortage of construction materials in market Shortage of materials required Late procurement of materials Delay in manufacturing special building materials Delay in materials delivery Shortage of manpower (skilled, semi-skilled, Conflicts between consultant and design engineer Replacement of key personnel Frauds Inadequate experience of consultant Internal company problems Delay in manufacturing special building materials Shortage of construction materials in market Changes in materials prices Late in selection of finishing materials due to availability of many types in market Shortage of materials required Low skill of manpower Inadequate experience of consultant Late in reviewing and approving design documents by consultant Delay in approving major changes in the scope of work by consultant Replace key personnel Internal company problems Late in reviewing and approving design documents by consultant Frauds Inflexibility (rigidity) of consultant 2.7 Frauds 3 Company organisation Shortage of materials required Shortage of construction materials in market Delay in materials delivery Late procurement of materials Damage of sorted material while they are needed urgently Shortage of manpower (skilled, semi-skilled, unskilled Delay in manufacturing special building materials Shortage of construction materials in market Shortage of materials required Late procurement of materials Late in selection of finishing materials due to availability of many types in market The required labour skills are not available
36 5 Contract/relationship-related skilled, unskilled labour) Poor qualification of the contractor s technical staff assigned to the project Low skill of manpower Shortage of technical professionals in the contractor s organization The required labour skills are not available Original contract duration is too short Major disputes and negotiations Ineffective delay penalties Inappropriate overall organization structure linking all parties to the project Type of project bidding and award (negotiation, lowest bidder) The required equipment and tools are not available Shortage of manpower (skilled, semi-skilled, unskilled labour) Poor qualification of the contractor s technical staff assigned to the project The required labour skills are not available Major disputes and negotiations Lack of communications between the parties Original contract duration is too short Type of construction contract Type of project bidding and award (negotiation, lowest bidder) unskilled labour) Low skill of manpower Shortage of technical professionals in the contractor s organization The required labour skills are not available The required equipment and tools are not available Original contract duration is too short Major disputes and negotiations Lack of communications between the parties Legal disputes between various parts The scope of work the contractor is not well defined Shortage of manpower (skilled, semi-skilled, unskilled labour) Poor qualification of the contractor s technical staff assigned to the project The required labour skills are not available The required equipment and tools are not available Major disputes and negotiations Original contract duration is too short Inappropriate overall organization structure linking all parties to the project Lack of communications between the parties Conflict between contract documents labour) Shortage of technical professionals in the contractor s organization Poor qualification of the contractor s technical staff assigned to the project Low skill of manpower The required labour skills are not available Original contract duration is too short Lack of communications between the parties The scope of work the contractor is not well defined Conflict between contract documents Major disputes and negotiations Shortage of manpower (skilled, semi-skilled, unskilled labour) The required equipment and tools are not available Low skill of manpower Poor qualification of the contractor s technical staff assigned to the project Inappropriate overall organization structure linking all parties to the project Original contract duration is too short Lack of communications between the parties Inadequate definition of substantial completion Major disputes and negotiations
37 Table 3: Top 5 results 6
38 7 1.5 Fig 1: Difference results Vertical bars denote 0.95 confidence intervals Difference Client-related Consultant-related Labour-related Contractor-related Materials-related Contract-related Client Contractor Consultant
39 8 3.6 Fig 2: Future results Vertical bars denote 0.95 confidence intervals Future Client-related Consultant-related Labour-related Contractor-related Materials-related Contract-related Client Contractor Consultant
40 9 3.6 Fig 3: Now results Vertical bars denote 0.95 confidence intervals Now Client-related Consultant-related Labour-related Contractor-related Materials-related Contract-related Clients Contractors Consultants
41 10 Fig 4: Client-related causes of delay Key personal replaced Owner's poor communication with construction parties and government authorities Slow decision making by owner Lack of finance to complete the work by client Poor communication by owner and other parties Interference by owner in the construction operations Non-payment of contractor claim Owner's failure to coordinate with Government authorities during planning Delay in issuance of change orders by owner Uncooperative owner with contractor complicating contract administration Delay in approving shop drawings by owner Delay in approving sample materials by owner Suspension of work by owner Variations in quantities Difficulties in obtaining work permits Delay to furnish and deliver the site to contractor by owner Conflicts between joint-ownership of the project Poor coordination by owner and other parties Delay in the settlement of contractor claims by owner Clarity of scope of change Excessive bureaucracy by owner's administration Poor coordination by owner with the various parties during construction Late in revising and approving design documents by owner Delay in progress payments by owner Negotiation by knowledgeable people Owner's personality Owner's interference Total future Client future Consultant future Contractor future Total now Client now Consultant now Contractor now
42 11 Fig 5: Contractor-related causes of delay Contractor experience Poor qualification of the contractor's technical staff Inefficient Work-break down structure Frauds Frequent change of sub-contractors because of their inefficient work Ineffective control of the project progress by the contractor Difficulties in financing project by contractor Poor coordination by contractor with other parties Poor communication by contractor with other parties Poor communication by contractor with the parties involved in the project Inadequate contractor's work Contractor's poor coordination with the parties involved in the project Conflicts in sub-contractors' schedules in execution of project Conflicts between contractor and other parties (consultant and owner) Delay of field survey by contractor Replacement of key personal Ineffective contractor head office involvement in the project Ineffective planning by contractor Improper technical study by contractor during the bidding stage Delay in the preparation of contractor submissions Delays in sub-contractors' work Poor site management and supervision by contractor Increase in contractor's overheads Increased number of projects Inefficient quality control by contractor Improper construction methods implemented by contractor Cash flow management Ineffective scheduling of project by contractor Loose safety rules and regulations within the contractor's organisation Other work on hold Company organisation Internal company problems Delay in site mobilisation Rework due to errors during construction Total future Client future Consultant future Contractor future Total now Client now Consultant now Contractor now
43 12 Fig 6: Consultant-related causes of delay Inadequate experience of consultant Internal company problems Frauds Conflicts between consultant and design engineer Replacement of key personnel Company organisation Inflexibility (rigidity) of consultant Late in reviewing and approving design documents by consultant Poor communication between consultant and other parties Poor coordination between consultant and other parties Delay in approving major changes in the scope of work by consultant Delay in performing inspection and testing by consultant Total future Client future Consultant future Contractor future Total now Client now Consultant now Contractor now
44 13 Fig 7: Materials-related causes of delay Delay in manufacturing special building materials Shortage of construction materials in market Late in selection of finishing materials due to availability of many types in market Shortage of materials required Changes in materials specifications Changes in materials prices Damage of sorted material while they are needed urgently Late procurement of materials Delay in materials delivery Total future Client future Consultant future Contractor future Total now Client now Consultant now Contractor now
45 14 Fig 8: Labour-related causes of delay Low skill of manpower The required equipment and tools are not available The required labour skills are not available Poor qualification of the contractor's technical staff assigned to the project Shortage of manpower (skilled, semi-skilled, unskilled labour) Lack of high-technology mechanical equipment Low level of equipment-operator's skill Low productivity and efficiency of equipment Shortage of supporting and shoring installations for excavations Failure of equipment Shortage of equipment required Shortage of technical professionals in the contractor's organisation Inadequate equipment used for the works Nationality of labour Personal conflicts among labour Shortage of contractor's administrative personnel Low productivity level of labour Total future Client future Consultant future Contractor future Total now Client now Consultant now Contractor now
46 15 Fig 9: Contract/relationships-related causes of delay Major disputes and negotiations Inappropriate overall organisation structure linking all parties to the project Original contract duration is too short Lack of communications between the parties Inadequate definition of substantial completion Type of project bidding and award (negotiation, lowest bidder) Conflict between contract documents Type of construction contract The scope of work is not well defined Legal disputes between various parties The objective of the project is not well defined Unavailability of incentives for contractor for finishing ahead of schedule Ineffective delay penalties Total future Client future Consultant future Contractor future Total now Client now Consultant now Contractor now
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
Causes and effects of delays in Malaysian construction industry
International Journal of Project Management 25 (2007) 517 526 INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT www.elsevier.com/locate/ijproman Causes and effects of delays in Malaysian construction industry
PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY
Lyons, Terry and Skitmore, Martin (2004) Project risk management in the Queensland engineering construction industry: a survey. International Journal of Project Management 22(1):pp. 51-61. Copyright 2004
Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria
Journal of Construction in Developing Countries, 18(1), 53 72, 2013 Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Olajide Timothy Ibironke, Timo Olugbenga
Fatemeh Akbari* Master of Industrial Engineering Islamic Azad University, Zahedan Brench, Iran
To Design and to Present a Tool to Prevent Extra Expense Incurring in School Reconstruction Projects (A case study: Reconstruction Department affiliated to School Equipment and Development Unit in Sistan
QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS
QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS João Guedes de Miranda Extended abstract Examination Committee Chairperson: Prof. Ana Paula Patrício Teixeira Ferreira Pinto
Study of Delay in Project Planning and Design Stage of Civil Engineering Projects
International Journal of Engineering and Advanced Technology (IJEAT) ISSN: 2249 8958, Volume-2, Issue-3, February 2013 Study of Delay in Project Planning and Design Stage of Civil Engineering Projects
PERCEPTION OF BUILDING CONSTRUCTION WORKERS TOWARDS SAFETY, HEALTH AND ENVIRONMENT
Journal of Engineering Science and Technology Vol. 2, No. 3 (2007) 271-279 School of Engineering, Taylor s University College PERCEPTION OF BUILDING CONSTRUCTION WORKERS TOWARDS SAFETY, HEALTH AND ENVIRONMENT
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
International Journal of Project Management 21 (2003) 321 326 www.elsevier.com/locate/ijproman Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana
Time Error in Project Management: A Case Study in Yanbu, Saudi Arabia
Business and Management Studies Vol. 2, No. 1; March 2016 ISSN 2374-5916 E-ISSN 2374-5924 Published by Redfame Publishing URL: http://bms.redfame.com Time Error in Project Management: A Case Study in Yanbu,
Analysis of Project Failure Factors for Infrastructure Projects in Saudi Arabia: A Multivariate Approach
Journal of Construction in Developing Countries, 19(1), 35 52, 2014 Analysis of Project Failure Factors for Infrastructure Projects in Saudi Arabia: A Multivariate Approach 1* Dubem I. Ikediashi, Stephen
CAPACITY PLANNING IN A SUGARCANE HARVESTING AND TRANSPORT SYSTEM USING SIMULATION MODELLING. ANDREW HIGGINS 1 and IAN DAVIES 2
CAPACITY PLANNING IN A SUGARCANE HARVESTING AND TRANSPORT SYSTEM USING SIMULATION MODELLING By ANDREW HIGGINS 1 and IAN DAVIES 2 1 CSIRO Sustainable Ecosystems, Level 3, QBP, 306 Carmody Road, St Lucia,
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand.
Causes and Effects of Delays in Large Construction Projects of. Pakistan
Causes and Effects of Delays in Large Construction Projects of Pakistan M. Haseeb 1, a, Xinhai-Lu 1, Aneesa Bibi 1, Maloof-ud-Dyian 2, Wahab Rabbani 3 1 College of Public Administration, Huazhong University
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
Prioritising Project Scope Definition Elements in Public Building Projects
Prioritising Project Scope Definition Elements in Public Building Projects Mohammed K. Fageha, Ajibade A. Aibinu (University of Melbourne, Australia) Abstract A complete definition of the scope of a project
Guidance on Framework Agreements
1. Introduction Guidance on Framework Agreements The purpose of this document is to provide guidance to public purchasers on the operation of framework agreements as provided for under current public procurement
Procurement of Goods, Services and Works Policy
Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March
PRACTICE NOTES FOR QUANTITY SURVEYORS
PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
ACCESS TO JUSTICE: A COMPARATIVE ANALYSIS OF CUTS TO LEGAL AID THE CHANGING FACE OF THE LEGAL PROFESSION
ACCESS TO JUSTICE: A COMPARATIVE ANALYSIS OF CUTS TO LEGAL AID THE CHANGING FACE OF THE LEGAL PROFESSION A short paper presented on 19 th March 2014 to a symposium organised by the University of Warwick
Using Analytic Hierarchy Process (AHP) Method to Prioritise Human Resources in Substitution Problem
Using Analytic Hierarchy Process (AHP) Method to Raymond Ho-Leung TSOI Software Quality Institute Griffith University *Email:[email protected] Abstract In general, software project development is often
THE RELATIONSHIP BETWEEN CONTRACT ADMINISTRATION PROBLEMS AND CONTRACT TYPES Bill Davison and Richard J. Sebastian*
INTERNATIONAL PUBLIC PROCUREMENT CONFERENCE PROCEEDINGS 21-23 September 2006 THE RELATIONSHIP BETWEEN CONTRACT ADMINISTRATION PROBLEMS AND CONTRACT TYPES Bill Davison and Richard J. Sebastian* ABSTRACT.
Characteristics of the Participants
3 Financial Analysis for Replacement of Construction Equipment in Saudi Arabia Ali A. Shash (Center for Engineering Research, Research Institute, King Fahd University of Petroleum & Minerals, Saudi Arabia)
Procurement Strategy and Contract Selection
GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works
SUPPLIER PREQUALIFICATION QUESTIONNAIRE FORM
SUPPLIER PREQUALIFICATION QUESTIONNAIRE FORM BRIEF This Supplier Pre Qualification Questionnaire is provided for the following project types of ALARGAN PROJECTS: 1) Supply of Construction Materials 2)
So You Want to Do Business with the Saudi Government
So You Want to Do Business with the Saudi Government Doing business with the Saudi government can be as cumbersome and time consuming as dealing with any national government. Moreover, doing business with
Procurement guidance Prequalifying suppliers
Procurement guidance Prequalifying suppliers Procurement guidance: Prequalifying suppliers Page 2 of 21 Table of contents Table of contents... 2 Purpose of this Guide... 4 Who should read this Guide?...
An Overview of Quality and Accreditation in the Health Sector within Saudi Arabia
International Journal of Health Research and Innovation, vol. 1, no. 3, 2013, 1-5 ISSN: 2051-5057 (print version), 2051-5065 (online) Scienpress Ltd, 2013 An Overview of Quality and Accreditation in the
Guaranteed Maximum Price contracts in Western Australia
Guaranteed Maximum Price contracts in Western Australia P. R. Davis 1, D. Stevenson 2 1 Curtin University of Technology Perth WA 2 Project Director INCOLL - Project Management Consultants Corresponding
Comparative Study on Quality Assurance of Construction Project in Taiwan and Japan
Comparative Study on Quality Assurance of Project in Taiwan and Japan Tsung Chieh, T. National Yunlin University of Science & Technology, Taiwan (email: [email protected]) Furusaka, S. Kyoto University,
Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice
Department of Health PFU & PPP Forum Benchmarking and market testing in NHS PFI projects Code of Best Practice This Code of Best Practice provides guidance and advice on good practice to NHS Trusts, Project
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN M. Haseeb College of Public Administration, Huazhong University of Science and Technology, Wuhan, P.R. China, 430074.
Assessment of Critical Success Factors for Construction Projects in Pakistan
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of
M.A. Programme in Mass Communication Improved Programme for 2007
M.A. Programme in Mass Communication Improved Programme for 2007 1. Programme Title Master of Arts Programme in Mass Communication 2. Degree Full Title: Abbreviated Title: Master of Arts (Mass Communication)
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: [email protected] 2 Asso.
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project
Contract Management. Brief 22. Public Procurement. September 2011
Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This
Author: Hamid A.E. Al-Jameel (Research Institute: Engineering Research Centre)
SPARC 2010 Evaluation of Car-following Models Using Field Data Author: Hamid A.E. Al-Jameel (Research Institute: Engineering Research Centre) Abstract Traffic congestion problems have been recognised as
Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy
Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal
The Impact of Implementing SAP System on Human Resource Management: Application to Saudi Electricity Company
International Journal of Business and Management; Vol. 9, No. 12; 2014 ISSN 1833-3850 E-ISSN 1833-8119 Published by Canadian Center of Science and Education The Impact of Implementing SAP System on Human
Multiproject Scheduling in Construction Industry
Multiproject Scheduling in Construction Industry Y. Gholipour Abstract In this paper, supply policy and procurement of shared resources in some kinds of concurrent construction projects are investigated.
Evaluation of Factors Affecting on Construction Equipment Acquisition Methods in Malaysia
2011 International Conference on Information and Finance IPEDR vol.21 (2011) (2011) IACSIT Press, Singapore Evaluation of Factors Affecting on Construction Equipment Acquisition Methods in Malaysia Masoud
A Study On Factors Influencing Construction Contract Claim Management
A Study On Factors Influencing Construction Contract Claim Management K.Sundhar #1, N.Nandhini #2 #1 PG Student (M.E Construction Engineering and Management), #2 Assistant Professor ( Department of civil
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
The business case for lowest price tendering?
The business case for lowest price tendering? Health Warning. The use of lowest price tendering may seriously damage your financial health and reputation and may have undesirable and unexpected side effects.
Linking Management Information Systems (MIS) Applications with High Performance: A Case Study of Business Organizations in Saudi Arabia
International Journal of Business and Social Science Vol. 5 No. 1; January 2014 Linking Management Information Systems (MIS) Applications with High Performance: A Case Study of Business Organizations in
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
North American Development Bank. Model Bidding Document: Consultant Services
North American Development Bank Model Bidding Document: Consultant Services MODEL DOCUMENTS Sample letter of invitation Outline for typical Terms of Reference Supplementary information for consultants
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria.
ISSN: - Vol. Issue, January - Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria. Abdulrahman Haruna, Sani Usman Kunya, Musa Mohammed Department of Building Technology
Delay Analysis in Construction Project
Delay Analysis in Construction Project Abstract Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often result of
SPECIALISED ENGINEERING OCCUPATIONS
SPECIALISED ENGINEERING OCCUPATIONS Submission to Skills Australia 31 March 2010 Contact: Andre Kaspura Policy Analyst, International & National Policy, Engineers Australia 11 National Circuit Barton ACT
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
Delay, Disruption and Acceleration Costs
Project Services Pty Ltd Delay, Disruption and Acceleration Costs Patrick Weaver FAICD, MCIOB, PMP Introduction Delay and disruption costs are common in the construction and engineering industries and
A Survey Instrument for Identification of the Critical Failure Factors in the Failure of ERP Implementation at Indian SMEs
A Survey Instrument for Identification of the Critical Failure Factors in the Failure of ERP Implementation at Indian SMEs ABSTRACT Dr. Ganesh L 1, Arpita Mehta 2 Many quantitative and qualitative studies
How has outsourcing affected public service delivery in Hong Kong? Illustrate with relevant cases.
How has outsourcing affected public service delivery in Hong Kong? Illustrate with relevant cases. By Brenda Chan, David Wong, Hooly Leung, Olga Chan and Boris Siu Outsourcing through the eyes of Government
Module 2 An Introduction to. The Performance Appraisal System
Module 2 An Introduction to The Performance Appraisal System Introduction THE PERFORMANCE APPRAISAL SYSTEM: We all want to get better results from the work we do - as individuals, as teams and as an organisation.
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the
Client Skills: Skills required by Government as the Construction Industry Client
Client Skills: Skills required by Government as the Construction Industry Client APCC MEMBER AUTHORITIES AS AT JULY 2002 Department of Public Works and Services New South Wales Building Commission Victoria
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
A Guidance Note to. Conditions of Contract for Consultancy Services (2005)
A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Capital Works Management Framework
POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset
National Commission for Academic Accreditation & Assessment. Standards for Quality Assurance and Accreditation of Higher Education Institutions
National Commission for Academic Accreditation & Assessment Standards for Quality Assurance and Accreditation of Higher Education Institutions November 2009 Standards for Institutional Accreditation in
Date: 7 February 2013
Item No. Report title: Classification: Open Ward(s) or groups affected: From: Date: 7 February 2013 Meeting Name: Deputy Leader and Cabinet Member for Housing Management GW2: Leasehold and Ancillary Properties
A NEEDS ASSESSMENT FOR GRADUATE PROGRAMS IN EDUCATION FACULTIES
A NEEDS ASSESSMENT FOR GRADUATE PROGRAMS IN EDUCATION FACULTIES Assist. Prof. Dr. Mustafa Cansiz Artvin Çoruh University Education Faculty Artvin - TURKEY [email protected] Dr. Nurcan Cansiz Atatürk
Study of Delay Management in a Construction Project - A Case Study
Study of Delay Management in a Construction Project - A Case Study B. Indhu 1, P. Ajai 2 1 M.tech, Student, 2 Assistant professor, Dept of Civil Engineering, SRM University Abstract The problem of delays
Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E
Global Journal of HUMANSOCIAL SCIENCE: H Interdisciplinary Volume 15 Issue 5 Version 1. Year 215 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals Inc. (USA) Online
Business & Administration
Business & Administration Student Handbook Level 3 By Anthony Lapsley C o n t e n t s Unit TITLE Page Business resources 1 Agree a budget 1 2 Order products and services 19 Business support services 3
Executive Summary. Paying the Professoriate. A Comparison of Academic Remuneration and Contracts in 28 Countries. Philip Altbach et.al.
Executive Summary Paying the Professoriate A Comparison of Academic Remuneration and Contracts in 28 Countries Philip Altbach et.al. Universities are a privileged space for the production and dissemination
NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT
NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT FINN FAGERVIK 1, PETTER PLASSBAK 1 and TEO TIONG YONG 2 1 Sintef-Tritech-Multiconsult (STM) Consortium, Singapore E-mail:[email protected]
Important Factors for Success of Public Construction Projects
2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Important Factors for Success of Public Construction Projects S. Z. S. Tabish1,
Service Risk Assessment. Consultant PQC
Service Risk Assessment Consultant PQC For further information or additional copies of this document contact either: Principal Policy Manager Building Policy Unit Works Division Telephone 07 3224 5482
COVER SHEET. Copyright 2006 School of Engineering and Technology, Asian Institute of Technology. Accessed from http://eprints.qut.edu.
COVER SHEET Veronika, Alin and Riantini, Leni S and Trigunarsyah, Bambang (2006) Corrective action recommendation for project cost variance in construction material management. In Kanok-Nukulchai, Worsak
Computer-Aided Facilities Management - A Logical Trend
Computer-Aided Facilities Management - A Logical Trend Two major organisational changes are part of the modern pharmaceutical industry scene. Firstly, mergers as companies seek to consolidate resources
Contents Foreword 1 Introduction by Patrick Reeve Executive summary 1. Business confidence and growth ambitions 2. Availability of finance
2014 Contents Foreword 1 Introduction by Patrick Reeve 3 Executive summary 4 1. Business confidence and growth ambitions 4 2. Availability of finance 6 3. Management skills 8 4. Apprenticeships 9 5. Optimists
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and
REQUEST FOR QUALIFICATIONS PROPERTY APPRAISAL SERVICES. Prepared by. City of Richmond Finance Department. February 18, 2016 RESPONSES DUE:
REQUEST FOR QUALIFICATIONS PROPERTY APPRAISAL SERVICES Prepared by City of Richmond Finance Department February 18, 2016 RESPONSES DUE: 2:30 P.M., Monday, March 7, 2016 REQUEST FOR STATEMENTS OF QUALIFICATIONS
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE Yakubu Adisa Olawale, Ph.D., MCIOB and Ming Sun, Ph.D. (Professor) Abstract Despite the availability
Composite performance measures in the public sector Rowena Jacobs, Maria Goddard and Peter C. Smith
Policy Discussion Briefing January 27 Composite performance measures in the public sector Rowena Jacobs, Maria Goddard and Peter C. Smith Introduction It is rare to open a newspaper or read a government
Definitions used in these Grant Conditions can be found at paragraph 13.
GRANT CONDITIONS These Grant Conditions, together with the Award Letter and the Policies and Positions Statements, set out the terms and conditions on which the Grant is made by the Funders to the Host
Introduction to Warranty and Indemnity Insurance 18 October 2012
Introduction to Warranty and Indemnity Insurance 18 October 2012 Mergers & Acquisitions Insurance Group Adrian Furlonge Assistant Vice President Svetlana Soroka Senior Underwriter Introduction Background
Case Study: Ten Document Needs for Schedule Litigation Support
Case Study: Ten Document Needs for Schedule Litigation Support Tulio Sulbaran, Ph.D 1 Abstract - This paper will present record keeping documentation of the construction schedule with regard to litigation.
Network Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
A CASE STUDY ON SOFTWARE PROJECT MANAGEMENT IN INDUSTRY EXPERIENCES AND CONCLUSIONS
A CASE STUDY ON SOFTWARE PROJECT MANAGEMENT IN INDUSTRY EXPERIENCES AND CONCLUSIONS P. Mandl-Striegnitz 1, H. Lichter 2 1 Software Engineering Group, University of Stuttgart 2 Department of Computer Science,
