Delay Analysis in Construction Project

Size: px
Start display at page:

Download "Delay Analysis in Construction Project"

Transcription

1 Delay Analysis in Construction Project Abstract Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often result of miscommunication between contractors, subcontractors, owners and suppliers. These types of unrealistic exceptions are usually avoided by using a clean and efficient planning mechanism, which clearly specifies the work and timetable to be used. Delays in construction projects are quite expensive; sometimes they may result in severe damages to the involved parties. This dissertation focuses on study of core factors that are causing delays and analyzing the day-to-day records to minimize delays. The current study is undertaken on Construction of New District Jail in Kurnool District of Andhra Pradesh. The project is construction of 2 Nos. of Barracks and is scheduled to complete in 12 Months. The study is being conducted on various factors that were causing the delays in project. The causes, effects and the various methods on how to minimize the delays in the construction site are noted down regularly. Construction delays can be minimized only when their cause are identified in the construction site. The day-to-day data is regularly collected from site. Starting time, Finishing time, and duration is recorded in MS Project differentiating task and critical activity along with the delays caused and reasons for the delays. Using the input data and the Gantt charts generated by MS Project the delays in critical activity of the project are analyzed. A questionnaire is prepared listing out various factors contributing to delay under different categories based on observations at construction site and from several journal papers as reference. The views on the same from various parties involved in a project like the builder/developer, contractor and consultants are sought in the questionnaire. Each factor is given a weight-age arrived at using filled-up questionnaires, using, which the most influential factors are identified Keywords Delays in construction project, causes for delays, impact of delays on Construction project. I. INTRODUCTION In construction, the word delay refers to something happening at a later time than planned, expected, specified in a contract or beyond the date that the parties agreed upon for the delivery of a project. Delay is the slowing down of work without stopping construction entirely and that can lead to time overrun either beyond the contract date or beyond the date that the parties have agreed upon for the delivery of the project. Delays classified into nonexcusable delays, excusable non compensable delays, excusable compensable delays and concurrent delays. Aditi Dinakar 784 Non-excusable delays are delays, which the contractor either causes or assumes the risk for. Excusable noncompensable delays are delays caused by factors that are not foreseeable, beyond the contractor s reasonable control and not attributable to the contractor s fault or negligence. Compensable excusable delays these are compensable delays are excusable delays, suspensions, or interruptions to all or part of the work caused by an act or failure to act by the owner resulting from owner s breach of an obligation, stated or implied, in the contract. Concurrent delays occur when both owner and the contractor are responsible for the delay. I.I Problem Statement Many construction projects have faced various problems and delay of time is one of the major problems. The delay in dispute settlement has manifold effects such as it will give detrimental to the relationship between owner and contractor. The contractor and the owner pay for the extra charge for the completion of the project due to delay in large construction projects. When the completion time of the construction project exceeds the agreed completion time, it is known as construction project delay. It is needed to conduct detailed investigation and identification of delay factors and then selecting the right actions to counter theses delay factors within cost and maintaining quality. The faults and errors due to the contractor cause delays and waste of capital and time The current study focuses on various factors causing the delays particularly in far off places where resources should be transported from far off places which require more time and money and where fresh work need to be done right from the excavation like removing trees and blasting few places which cannot be excavated by machinery. This study attempts to generalize. 1. To identify various causes of the delays 2. How unpredicted delays can cause delays resulting in delays of the total project 3. The effects of the delays on the project 4. Study the causes and effects of the delays at various projects and to find out the most important causes.

2 II. DELAYS There are three basic ways to categorize type of delays: Critical and noncritical Excusable and Non-excusable Compensable and non-compensable II.I Critical And Non-Critical Delays Delays that affect the project completion or in some cases a milestone date are considered as critical delays and delays that do not affect the project completion or a milestone date are considered as noncritical delays. If these activities are delayed, the project completion date or a milestone later will be delayed. The determining which activities truly control the project completion date depends on the following: 1. The project itself 2. The contractor s plan and schedule (particularly the critical path) 3. The requirement of the contract for sequence and phasing 4. The physical constraint of the project, i.e. how to build the job from a practical 5. Perspective. II.I Excusable And Non-Excusable Delays All delays are either excusable or non-excusable. An excusable delay is a delay that is due to an unforeseeable event beyond the contractor s or the subcontractor s control. Normally, based on common general provisions in public agency specifications, delays resulting from the following events would be considered excusable: 1. General labor strikes - Strikes and labor unrest are frequent causes of delay on construction projects. However, that not all strikes are considered excusable delays. Generally, a contract clause listing strikes as an excusable delay also carries a qualification that the cause for the delay must have been unforeseen and beyond the control of the contractor. Strikes that are foreseeable at the time of signing the contract are not considered excusable causes of delay. 2. Fires 3. Floods 4. Act of God - An act of God is a natural occurrence caused directly and exclusively by natural forces without any human intervention, which could not have been reasonably foreseen, nor could have been prevented. Earthquakes, landslides, tornados, hurricanes, lightning, floods, etc., are all examples of acts of God. Note, however, that mere bad weather does not qualify as an act of God. 5. Owner-directed changes 6. Errors and omissions in the plans and specifications 7. Differing site conditions or concealed conditions 8. Unusually severe weather Non-excusable delays are events that are within the contractor s control or that are foreseeable. These are some examples or non-excusable delays: 1. Late performance of sub-contractors 2. Untimely performance by suppliers 3. Faulty workmanship by the contractor or subcontractors 4. A project-specific labor strike caused by either the contractor s unwillingness to meet with labor representative or by unfair labor practice II.II Compensable And Non-Compensable Delays A compensable delay is a delay where the contractor is entitled to a time extension and to additional compensation. Relating back to the excusable and non-excusable delays, only excusable delays can be compensable. Noncompensable delays mean that although an excusable delay may have occurred, the contractor is not entitled to any added compensation resulting from the excusable delay. Thus, the question of whether a delay is compensable must be answered. Additionally, a non-excusable delay warrants neither additional compensation nor a time extension. II.III Delay Analysis Techniques Whether or not a delay is compensable depends primarily on the terms of the contract. In the most cases, a contract specifically notes the kinds of delays that are noncompensable, for which the contractor does not receive any additional money but may be allowed a time extension. Delay analysis is a analytical process that should be employed with project documentation along with collected data from project site. The selection of delay analysis depends on the variety of factors and the available records. There are five commonly used delay techniques. 1. Impacted as-planned method 2. Time impact analysis method 3. Collapsed as-built or but-for analysis method 4. Snapshot/windows/time slice analysis method 5. As-planned versus as-built windows analysis method 785

3 III. RESEARCH METHODOLOGY III.I Questionnaire Methodology The Survey is designed based to use Likert Scale on the objective of the study to find out the causes of delays in construction projects and effect of the delays on overall project. The Survey is framed in such a way that the personal view of different people involved in different projects is collected and analyzed. The questionnaire basically consists of four sections as detailed below. 1. Respondent Background - This is to collect the basic information of the respondent 2. Causes of Delays - This is used to collect the data on different causes of the delays happened in that particular project. 3. Effects of Delays - Using these questions the effects of the delays on the project are identified. 4. Measures for Minimizing Delays - The last part of the survey consists of questions regarding the methods they used to reduce the delays if any. The collected data is analyzed using Minitab software to find out the major causes of delay, the effects of the delay and how to minimize the delay of a construction project. III.III Scoring And Analysis After the questionnaire is completed, each item may be analyzed separately or in some cases item responses may be summed to create a score for a group of items. Hence, Likert scales are often called summative scales. Whether individual Likert items can be considered as interval-level data, or whether they should be treated, as ordered-categorical data is the subject of considerable disagreement in the literature, with strong convictions on what are the most applicable methods. This disagreement can be traced back, in many respects, to the extent to which Likert items are interpreted as being ordinal data. There are two primary considerations in this discussion. First, Likert scales are arbitrary. The value assigned to a Likert item has no objective numerical basis, either in terms of measure theory or scale (from which a distance metric can be determined). The value assigned to each Likert item is simply determined by the researcher designing the survey, who makes the decision based on a desired level of detail. However, by convention Likert items tend to be assigned progressive positive integer values. Likert scales typically range from 2 to 10 with 5 or 7 being the most common. Further, this progressive structure of the scale is such that each successive Likert item is treated as indicating a better response than the preceding value. (This may differ in cases where reverse ordering of the Likert Scale is needed). The second, and possibly more important point is whether the distance between each successive item category is equivalent, which is inferred traditionally. For example, in the above five-point Likert item, the inference is that the distance between category 1 and 2 is the same as between category 3 and 4. In terms of good research practice, an equidistant presentation by the researcher is important; otherwise a bias in the analysis may result. For example, a four-point Likert item with categories "Poor", "Average", "Good", and "Very Good" is unlikely to have all equidistant categories since there is only one category that can receive a below average rating. This would arguably bias any result in favor of a positive outcome. On the other hand, even if a researcher presents what he or she believes are equidistant categories, it may not be interpreted as such by the respondent. A good Likert scale, as above, will present symmetry of categories about a midpoint with clearly defined linguistic qualifiers. In such symmetric scaling, equidistant attributes will typically be more clearly observed or, at least, inferred. It is when a Likert scale is symmetric and equidistant that it will behave more like an interval-level measurement. So while a Likert scale is indeed ordinal, if well presented it may nevertheless approximate an interval-level measurement. This can be beneficial since, if it was treated just as an ordinal scale, then some valuable information could be lost if the distance between Likert items were not available for consideration. The important idea here is that the appropriate type of analysis is dependent on how the Likert scale has been presented. Notions of central tendency are often applicable at the item level - that is responses often show a quasi-normal distribution. The validity of such measures depends on the underlying interval nature of the scale. Responses to several Likert questions may be summed providing that all questions use the same Likert scale and that the scale is a defensible approximation to an interval scale, in which case the Central Limit Theorem allows treatment of the data as interval data measuring a latent variable. If the summed responses fulfill these assumptions, parametric statistical tests such as the analysis of variance can be applied. Typical cutoffs for thinking that this approximation will be acceptable is a minimum of 4 and preferably 8 items in the sum. 786

4 IV. QUESTIONNAIRE The questions about the causes for delays are divided into 7 sections containing 9 questions each. The respondent is asked to rank each of the following questions. Group-A Owner Contributed Factors 1. Delay in progress payments 2. Delay to furnish and deliver the site 3. Change orders by owner during construction 4. Late in revising and approving design documents 5. Delay in approving shop drawing and sample materials 6. Poor communication and coordination 7. Slowness in decision-making process 8. Conflicts between joint-ownership of the project 9. Suspension of work by owner Group-B Contractor Contributed Factors 1. Difficulties in financing project 2. Conflicts in sub-contractors schedule in execution of project 3. Rework due to errors during construction 4. Conflicts between contractor and other parties 5. Poor communication and coordination 6. Ineffective planning and scheduling of project 7. Improper construction methods implement 8. Delays in sub-contractors work 9. Inadequate contractor's work Group-C Consultant Contributed Factors 1. Delay in approving major changes in the scope of work 2. Poor communication and coordination 3. Inadequate experience of consultant 4. Mistakes and discrepancies in design documents 5. Delays in producing design documents 6. Unclear and inadequate details in drawings 7. Insufficient data collection and survey before design 8. Un-use of advanced engineering design software 9. Conflicts with other parties and financial problems Group-D Material Contributed Factors 1. Shortage of construction materials in market 2. Changes in material types during construction 3. Delay in material delivery 4. Damage of sorted material while they are needed urgently 5. Delay in manufacturing special building materials 6. Late procurement of materials 7. Quality problem with procured material Procuring undesired or unwanted material instead 9. Problem with material transport and processing at site Group-E Equipment Contributed Factors 1. Equipment breakdowns 2. Shortage of equipment 3. Low level of equipment-operator's skill 4. Low productivity and efficiency of equipment 5. Lack of heavy equipment when needed 6. Wrong kind or verity of equipment 7. Lack of hi-tech and advanced equipment 8. Unavailability of special equipment 9. Difficulty in transporting equipment Group-F Labor Contributed Factors 1. Shortage of labors 2. Working permit of labors 3. Low productivity level of labors 4. Personal conflicts among labors 5. High labor wages 6. Labor exodus 7. Labor strikes at site 8. Labor health problem when working in hazardous conditions 9. Labor Safety problems Group-G External Factors 1. Effects of subsurface and ground conditions factors 2. Delay in obtaining permits from municipality 3. Weather effect on construction activities 4. Traffic control and restriction at job site 5. Accident during construction 6. Changes in government regulations and laws 7. Delay in providing services from utilities 8. Delay in performing final inspection and certification 9. Civil unrest and public strikes Respondents are also asked to give their opinion on the effects of delays. 6 Questions were asked in this section. 1. Time overrun 2. Cost overrun 3. Dispute 4. Arbitration 5. Total abandonment 6. Litigation The last section includes questions about the steps that should be taken to avoid delays in construction project. 1. This section consists of 12 questions. 2. Frequent progress meeting 3. Use up-to-date technology utilization 4. Use proper and modern construction

5 5. Use appropriate construction methods 6. Effective strategic planning 7. Proper material procurement 8. Accurate initial cost estimates 9. Clear information and communication channels 10. Frequent coordination between the parties involved 11. Proper emphasis on past experience 12. Proper project planning and scheduling 13. Complete and proper design at the right time V. ANALYSIS The collected responses from different categories of people involved in construction project. The mean of each group of question is calculated using ANOVA analysis. The final result showing the contribution of different factors on the delay of a construction project is plotted on a pie chart. From the pie chart the contribution of various parties involved in the project are almost same while contractor is more slightly more for delay. VI. CONCLUSION The responses collected from the respondents make it evident that almost all parties holds nearly equal responsibility for the delays in project. The majority of people rated improper communication between the involved parties as the major problem while external reasons like lack of qualified labor, equipment and material when needed comes next in row. After analyzing the data it is clear that the contribution of Contractor in delay of the construction project is more than the client and consultant side. And the external factors contribute the least in delay of construction project. REFERENCES [1] Aibinu, A. A. and Jagboro,G.O.(2002).The Effects of Construction Delays on Project Delivery in Nigerian Construction Industry. International Journal of Project Management, Volume 20, Issue 8, November 2002, Pages [2] Arditi, D. and Pattanakitchamroon, T. (2006). Selecting a Delays Analysis Method in Resolving Construction Claims. International Journal of Project Management, Elsevier. 21 : [3] Alaghbari, W. et al. (2007). The Significant Factors Causing Delay of Building [4] Construction Project in Malaysia. [5] Chan DWM, Kumaraswamy MM. (1997). A comparative study of causes of time overruns in construction project. Hong Kong. Int J project manage. 15 (1): [6] Ahuja, H.N. Dozzi, S.P., and Abourizk, S.M. (1994). Project Management: Techniques in planning and controlling construction projects, 2nd Ed., New York. [7] Assaf, S.A., Al-Khalil, M. and Al-Hazmi, M. (1995). Causes of Delay in Large Building Construction Projects. Journal of Project Management in Engineering ASCE, 2; [8] Al-Momani, A.H. (2000).Construction delay: a quantitative analysis, Journal of Project Management 18, [9] Contracts. International Journal of Project Management, Elsevier.20:67-73 [10] Manavazhia MR, Adhikarib DK. Material and Equipment Procurement Delays in Highway Projects in Nepal. International Journal Project Management 2002; 20: [11] Theodore J. Trauner Jr. et al. (2009). Types of Construction Delays. Construction Delays (Second Edition), 2009, Pages [12] Young, J., and Jinijoo, L. (1998). Factors influencing the success of management consulting projects. International Project Management Journal 788

Causes, Effects and Minimization of Delays in Construction Projects

Causes, Effects and Minimization of Delays in Construction Projects Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi

More information

Who pays the Money for the Time?

Who pays the Money for the Time? Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

Causes and effects of delays in Malaysian construction industry

Causes and effects of delays in Malaysian construction industry International Journal of Project Management 25 (2007) 517 526 INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT www.elsevier.com/locate/ijproman Causes and effects of delays in Malaysian construction industry

More information

Causes and Effects of Delays in Large Construction Projects of. Pakistan

Causes and Effects of Delays in Large Construction Projects of. Pakistan Causes and Effects of Delays in Large Construction Projects of Pakistan M. Haseeb 1, a, Xinhai-Lu 1, Aneesa Bibi 1, Maloof-ud-Dyian 2, Wahab Rabbani 3 1 College of Public Administration, Huazhong University

More information

PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN

PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN M. Haseeb College of Public Administration, Huazhong University of Science and Technology, Wuhan, P.R. China, 430074.

More information

Causes and Effects of Delays in Indian Construction Projects

Causes and Effects of Delays in Indian Construction Projects Volume: 03 Issue: 04 Apr-2016 wwwirjetnet p-issn: 2395-0072 Causes and Effects of Delays in Indian Construction Projects Dinesh Kumar R ME Construction Engineering and Management student, Meenakshi Sundararajan

More information

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts 11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Risk Allocation in Construction Contracts Risks 2 In the absence of a contract, all risks are the owner's Contracting is

More information

Study of Delay in Project Planning and Design Stage of Civil Engineering Projects

Study of Delay in Project Planning and Design Stage of Civil Engineering Projects International Journal of Engineering and Advanced Technology (IJEAT) ISSN: 2249 8958, Volume-2, Issue-3, February 2013 Study of Delay in Project Planning and Design Stage of Civil Engineering Projects

More information

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed

More information

CONTRACTOR DEFAULT & SURETY PERFORMANCE:

CONTRACTOR DEFAULT & SURETY PERFORMANCE: CONTRACTOR DEFAULT & SURETY PERFORMANCE: A PRACTICAL GUIDE FOR UNDERSTANDING AND NAVIGATING A BOND DEFAULT SITUATION TEXAS CITY ATTORNEYS ASSOCIATION SUMMER CONFERENCE JUNE 9-11, 2010 SOUTH PADRE ISLAND,

More information

The Principles of Schedule Impact Analysis

The Principles of Schedule Impact Analysis College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923

More information

LOGGING SUBCONTRACT. Recital

LOGGING SUBCONTRACT. Recital LOGGING SUBCONTRACT This Logging Contract (this Contract ) is entered as of the day of, 200, by and between ("Contractor") and ("Subcontractor") as follows: Recital The owners of certain timber growing

More information

A Study On Factors Influencing Construction Contract Claim Management

A Study On Factors Influencing Construction Contract Claim Management A Study On Factors Influencing Construction Contract Claim Management K.Sundhar #1, N.Nandhini #2 #1 PG Student (M.E Construction Engineering and Management), #2 Assistant Professor ( Department of civil

More information

Study of Delay Management in a Construction Project - A Case Study

Study of Delay Management in a Construction Project - A Case Study Study of Delay Management in a Construction Project - A Case Study B. Indhu 1, P. Ajai 2 1 M.tech, Student, 2 Assistant professor, Dept of Civil Engineering, SRM University Abstract The problem of delays

More information

American College of Real Estate Lawyers Tucson, Arizona March 18, 2005. FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W.

American College of Real Estate Lawyers Tucson, Arizona March 18, 2005. FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W. American College of Real Estate Lawyers Tucson, Arizona March 18, 2005 FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W. Trainor An excusable delay, or force majeure, clause is an important element

More information

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge

Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge 1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table

More information

Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria

Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Journal of Construction in Developing Countries, 18(1), 53 72, 2013 Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Olajide Timothy Ibironke, Timo Olugbenga

More information

Method for Calculating Schedule Delay Considering Lost Productivity

Method for Calculating Schedule Delay Considering Lost Productivity Method for Calculating Schedule Delay Considering Lost Productivity Hyun-Soo Lee, M.ASCE 1 ; Han-Guk Ryu 2 ; Jung-Ho Yu 3 ; and Jae-Jun Kim, M.ASCE 4 Abstract: A delay claim often occurs when a difference

More information

CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY

CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY KASIMU ALHAJI MOHAMMED DEPT OF QUANTITY SURVEYING, FEDERAL POLYTECHNIC, BIDA. NIGERIA ABUBAKAR DANLADI ISAH DEPT OF ARCHITECTURE, FEDERAL UNIVERSITY OF

More information

Terms and Conditions for Purchase Orders for Recycling Materials

Terms and Conditions for Purchase Orders for Recycling Materials Terms and Conditions for Purchase Orders for Recycling Materials This Agreement is made by and between AEROJET-GENERAL CORPORATION, an Ohio corporation with a place of business at Rancho Cordova, California

More information

ROUSH PERFORMANCE - Limited Warranty

ROUSH PERFORMANCE - Limited Warranty ROUSH PERFORMANCE - Limited Warranty ROUSH PARTS AND ACCESSORIES* WHO IS COVERED ROUSH's warranty obligations for ROUSH Parts and Accessories (individually and collectively Part(s) ) is limited to defects

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

Scheduling Best Practices

Scheduling Best Practices RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding

More information

Priori ty ... ... ...

Priori ty ... ... ... .Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared

More information

CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT

CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal

More information

Document Comparison. AIA Documents A134 2009 and A131CMc 2003

Document Comparison. AIA Documents A134 2009 and A131CMc 2003 Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...

More information

Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals

Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Journal of Construction in Developing Countries, Vol. 16(1), 41 67, 2011 Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Visuth Chovichien

More information

QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS

QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS QUANTITATIVE ANALYSIS OF TIME OVERRUNS IN TRANSPORT INFRASTRUCTURE PROJECTS João Guedes de Miranda Extended abstract Examination Committee Chairperson: Prof. Ana Paula Patrício Teixeira Ferreira Pinto

More information

Construction Delay Analysis under Multiple Baseline Updates

Construction Delay Analysis under Multiple Baseline Updates Construction Delay Analysis under Multiple Baseline Updates By Wail Menesi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied

More information

How To Accept A Delivery From A Customer

How To Accept A Delivery From A Customer General Selling, Service, Delivery and Payment Conditions of BORGERS USA Corp., Vance, Alabama ( GSC ) (March 2015) 1. General Provisions These General Selling, Service, Delivery and Payment Conditions

More information

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Approved March 23, 2011 Purpose: While the traditional Design-Bid-Build

More information

H o w t o W r i t e a J u d g e m e n t

H o w t o W r i t e a J u d g e m e n t H o w t o W r i t e a J u d g e m e n t A) Function of a Judgement: Being the final result of a legal procedure a judgement shall provide a balanced conflict solution. An ideal judgement enables both conflict

More information

Terms and Conditions. 3012436v2 12285.01010

Terms and Conditions. 3012436v2 12285.01010 Terms and Conditions ACCEPTANCE. Except as otherwise agreed in a written agreement signed by both parties, these Terms and Conditions will govern Buyer s purchase order. BI Technologies acceptance of Buyer

More information

WELCOME Best Practices for Managing Construction Delay and Interference Claims

WELCOME Best Practices for Managing Construction Delay and Interference Claims WELCOME Best Practices for Managing Construction Delay and Interference Claims Kenneth A. Slavens 314.345.6419 Husch Blackwell LLP Topics to be covered Delay Acceleration Disruption Delay Impact on Project

More information

STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS

STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand.

More information

GENERAL CONDITIONS OF SALE AND DELIVERY LAURA METAAL HOLDING BV LAURA METAAL EYGELSHOVEN BV LAURA STAALCENTER MAASTRICHT BV

GENERAL CONDITIONS OF SALE AND DELIVERY LAURA METAAL HOLDING BV LAURA METAAL EYGELSHOVEN BV LAURA STAALCENTER MAASTRICHT BV GENERAL CONDITIONS OF SALE AND DELIVERY OF LAURA METAAL HOLDING BV LAURA METAAL EYGELSHOVEN BV LAURA STAALCENTER MAASTRICHT BV Clause 1 - Applicability 1.1. These General Conditions of Sale and Delivery

More information

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Contents Foreword Acknowledgements Chapter 1 International Contractual Alliance ITC

More information

Client Contracts: Business Risk, Professional Liability & Insurance Coverage

Client Contracts: Business Risk, Professional Liability & Insurance Coverage Hanover Architects & Engineers Advantage Client Contracts: Business Risk, Professional Liability & Insurance Coverage Many client-drafted contracts endeavor to transfer unreasonable risk to the design

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

A Guide to Small Works. A brief explanation

A Guide to Small Works. A brief explanation A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here

More information

EASY LED Oy General Terms of Sale

EASY LED Oy General Terms of Sale EASY LED Oy General Terms of Sale 1. Scope of application These General Terms of Sale (hereinafter referred to as the Terms ) shall be applied to the sale and supply of lighting products manufactured by

More information

DOCUMENT. General Purchase Conditions

DOCUMENT. General Purchase Conditions 1. Scope 1.1 These general purchase conditions (hereinafter the GPC ) shall apply to all kinds of materials, articles, products and services related to them, (hereinafter Products ), offered, sold or supplied

More information

Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects

Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects Dr. Rashad Zakieh (PMP) 27 April, 2010 Copyright Saudi Aramco, 2010. All rights reserved.

More information

Effective Root Cause Analysis For Corrective and Preventive Action

Effective Root Cause Analysis For Corrective and Preventive Action Effective Root Cause Analysis For Corrective and Preventive Action Manuel Marco Understanding Key Principles Requirement need or expectation that is stated, generally implied, or obligatory Generally implied

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

Guide on drawing up contracts for large industrial works

Guide on drawing up contracts for large industrial works Guide on drawing up contracts for large industrial works Topic: Construction, installation of plant, engineering Source: United Nations Economic Commission for Europe Palais des Nations Genève, Switzerland

More information

Application of Fuzzy Logic in Delay Analysis in Construction

Application of Fuzzy Logic in Delay Analysis in Construction Application of Fuzzy Logic in Delay Analysis in Construction Shruti Singh 1 Dr. M.K. Trivedi 2 2 Civil department MITS Gwalior 474005, India 1 Civil Department MITS Gwalior, India Abstract This paper describes

More information

GSX14, GSX16, VSX13, VSX14, GSZ13, GSZ14, VSZ13, VSZ14, GPH, GPC

GSX14, GSX16, VSX13, VSX14, GSZ13, GSZ14, VSZ13, VSZ14, GPH, GPC LIMITED WARRANTY Who Is Providing The Warranty? This warranty is provided to you by Goodman Manufacturing Company, L.P. ( Goodman ), which warrants all parts of this heating or air conditioning unit, as

More information

Central Plumbing (Wellington) Limited

Central Plumbing (Wellington) Limited TERMS OF TRADE Central Plumbing (Wellington) Limited The terms of trade set out below govern all supplies of goods and services from Central Plumbing (Wellington) Limited ( Central Plumbing (Wellington),

More information

CHAPTER 3.0: PROCUREMENT AND CONTRACTING

CHAPTER 3.0: PROCUREMENT AND CONTRACTING CHAPTER 3.0: PROCUREMENT AND CONTRACTING This chapter outlines the requirements for using Federal funds to purchase materials, products, or services under the CDBG Entitlement program. Whether you are

More information

These Terms & Conditions may only be used by members of Koninklijke Metaalunie.

These Terms & Conditions may only be used by members of Koninklijke Metaalunie. METAALUNIE CONDITIONS General delivery and payment conditions of Koninklijke Metaalunie (the Dutch organisation for small and medium-sized enterprises in the metal industry), referred to as the METAALUNIE

More information

Document Comparative

Document Comparative Document Comparative AIA Documents A401 2007 and A401 2007 SP AIA Document A401 2007 SP, Standard Form of Agreement Between Contractor and Subcontractor, for use on a Sustainable Project, establishes the

More information

NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING

NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING This Agreement is hereby entered into by and between Piedmont Triad Regional Council (herein Contractor ) and (Subcontractor)

More information

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004) Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament

More information

Contract Language and Documentation

Contract Language and Documentation Contract Language and Documentation Charles A. Ray, IV Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 [email protected] www.lanierford.com 2014 1 Agenda

More information

North London Plumbing & Heating Terms and Conditions

North London Plumbing & Heating Terms and Conditions North London Plumbing & Heating Terms and Conditions Christopher Michael Darby North London Plumbing & Heating 2 Perth Road Wood Green London N22 5RB 0203 592 4340/07400 616 686 [email protected] 1 DEFINITIONS

More information

SolarEdge Technologies Ltd.

SolarEdge Technologies Ltd. SolarEdge Technologies Ltd. GENERAL TERMS AND CONDITIONS 1. General. This document, entitled General Terms and Conditions (referred to herein as the Agreement ), forms an integral part of the quotation

More information

Infineon Technologies North America Corp. Terms and Conditions of Sale

Infineon Technologies North America Corp. Terms and Conditions of Sale Infineon Technologies North America Corp. Terms and Conditions of Sale 1. GENERAL 1.1 Contract Terms. These Terms and Conditions of Sale (the Agreement ) shall apply to any offer made by Infineon Technologies

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 20xx (the Effective Date ), by and between The Owner: M D Anderson Cancer Center c/o Sourcing

More information

Anglo American Procurement Solutions Site

Anglo American Procurement Solutions Site Anglo American Procurement Solutions Site Event Terms and Conditions Anglo American Procurement Solutions Site Event Terms and Conditions Event Terms and Conditions 3 1. Defined terms 3 2. Interpretation

More information

CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS

CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS 1. Definitions 1.1 In these Conditions: "Contract" means the contract between Peak Waste Recycling

More information

PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction

PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction Below are instructions for use with the Home Improvement Model Contract Standard Form, which

More information

HAWAII STANDARD GENERAL CONDITIONS FOR FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

HAWAII STANDARD GENERAL CONDITIONS FOR FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR HAWAII STANDARD GENERAL CONDITIONS FOR FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR TABLE OF ARTICLES 1 AGREEMENT 2. SCOPE OF WORK 3. SUBCONTRACTOR S RESPONSIBILTIES 4. CONTRACTOR'S RESPONSIBILITIES

More information

Comparing Procurement Methods for Design-Build Projects

Comparing Procurement Methods for Design-Build Projects Comparing Procurement Methods for Design-Build Projects by Marwa A. El Wardani Technical Report No. 45 Copyright May 2004 Computer Integrated Construction Research Program Department of Architectural Engineering

More information

CONTRACT CONDITIONS FOR LOGISTICS (2014)

CONTRACT CONDITIONS FOR LOGISTICS (2014) CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member

More information

1 OF 7. there will be few "surprises" as the work progresses.

1 OF 7. there will be few surprises as the work progresses. 1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result

More information

As used in sections 327A.01 to 327A.07, the terms in this section shall have the meanings assigned to them.

As used in sections 327A.01 to 327A.07, the terms in this section shall have the meanings assigned to them. 327A.01 DEFINITIONS. Subdivision 1.Scope. As used in sections 327A.01 to 327A.07, the terms in this section shall have the meanings assigned to them. Subd. 2.Building standards. "Building standards" means

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

GENERAL CONDITIONS OF LATVIAN NATIONAL ASSOCIATION OF FREIGHT FORWARDERS and LOGISTIC LAFF

GENERAL CONDITIONS OF LATVIAN NATIONAL ASSOCIATION OF FREIGHT FORWARDERS and LOGISTIC LAFF GENERAL CONDITIONS OF LATVIAN NATIONAL ASSOCIATION OF FREIGHT FORWARDERS and LOGISTIC LAFF Effective as of January 1, 2007 These conditions taking effect on January 1, 2007, have been agreed between the

More information

How to Write the Construction Management RFQ/RFP

How to Write the Construction Management RFQ/RFP 2011-06-07 How to Write the Construction Management RFQ/RFP Setting Up a Project for Success Today's Objectives The Art of RFQ/RFP writing First things first Determining the optimum Project Delivery Method

More information

ABFF 04. General Conditions of Contract for Work in Property Management and Facility Management

ABFF 04. General Conditions of Contract for Work in Property Management and Facility Management ABFF 04 General Conditions of Contract for Work in Property Management and Facility Management Comments on this publication and suggested amendments and additions for inclusion in the next addition will

More information

AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES

AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES This agreement is made and entered into, on day the. of, 1991 by and between: Mr/. of P.O. Box.. hereinafter refereed to as the "Owner" on

More information

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction

More information

How To Perform An As-Built But For Schedule Delay Analysis

How To Perform An As-Built But For Schedule Delay Analysis LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

Engineering Council of South Africa

Engineering Council of South Africa Government Gazette No. 26180, 2 April 2004 Page 1 of 30 Board Notice 42 of 2004 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the

More information

Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time

Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time Peter D Aeberli Barrister - Arbitrator - Mediator Adjudicator The Waiting Game: Extensions of Time Determining extensions of time can be as sophisticated an art as designing a building in the first place.

More information

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement

More information

FREE SOFTWARE LICENSING AGREEMENT CeCILL

FREE SOFTWARE LICENSING AGREEMENT CeCILL FREE SOFTWARE LICENSING AGREEMENT CeCILL Notice This Agreement is a free software license that is the result of discussions between its authors in order to ensure compliance with the two main principles

More information

Scheduling Best Practices

Scheduling Best Practices The eighth article in the Scheduling Best Practices series is How to Handle the Weather. Our colleague Beth Blair, a managing consultant in Warner s Disputes Resolution Group, has over 20 years of experience

More information

Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria.

Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria. ISSN: - Vol. Issue, January - Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria. Abdulrahman Haruna, Sani Usman Kunya, Musa Mohammed Department of Building Technology

More information

CRITICAL PATH ANALYSIS AND GANTT CHARTS

CRITICAL PATH ANALYSIS AND GANTT CHARTS CRITICAL PATH ANALYSIS AND GANTT CHARTS 1. An engineering project is modelled by the activity network shown in the figure above. The activities are represented by the arcs. The number in brackets on each

More information

Insurance and Post Project Dispute Resolution

Insurance and Post Project Dispute Resolution CONSTRUCTION LAW 2014 PAPER 4.1 Insurance and Post Project Dispute Resolution These materials were prepared by Craig A. Wallace, P.Eng., and Matthew Stainsby, both of Shapiro Hankinson & Knutson Law Corporation,

More information

STUDY ON THE COST OVERRUNS IN ROAD CONSTRUCTION PROJECTS IN SRI LANKA

STUDY ON THE COST OVERRUNS IN ROAD CONSTRUCTION PROJECTS IN SRI LANKA STUDY O THE COST OVERRUS I ROAD COSTRUCTIO PROJECTS I SRI LAKA Eng. S.B. Wijekoon Faculty of Engineering, University of Peradeniya (email: [email protected]) Eng. A.M.C.T.K. Attanayake Anuradhapura Provincial

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

1.1 The contract shall be deemed to have been entered into upon receipt of supplier s written acknowledgement stating its acceptance of the order.

1.1 The contract shall be deemed to have been entered into upon receipt of supplier s written acknowledgement stating its acceptance of the order. Kendrion (Switzerland) AG Albisstrasse 26 CH-8915 Hausen am Albis of Contract (Rev. 1, valid from 01.01.2013) 1 General 1.1 The contract shall be deemed to have been entered into upon receipt of supplier

More information

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 [email protected].

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att. The Job of the Project Manager Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 [email protected] For any organization and for any project manager it is vitally important

More information

ENERGY PERFORMANCE CONTRACT

ENERGY PERFORMANCE CONTRACT DATED DAY OF ENERGY PERFORMANCE CONTRACT THE CUSTOMER SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT -AND- THE ESCO SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT [This document is a DRAFT provided only

More information