STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS

Size: px
Start display at page:

Download "STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS"

Transcription

1 STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand. ABSTRACT This research aims at examining and identifying the cost components of construction claims and necessary data for substantiating and pricing claims. The research was done by identifying and analyzing the cost components for each contractual claim type handled by employers. The availabilities, the appropriate method for calculation, and the data required in substantiating and pricing process of each cost component were analyzed. In addition, the ranks of the important cost components and the contract provisions are also identified. The required data collected from the analysis were then classified into subgroups by their sources. It was found that there are a number of cost components, which can be classified into either the employers claim cost components or the contractors claim cost components. The availabilities of each component of each contractual claim type were also presented. The data required in substantiating and pricing claims handled by the employers were classified into seven groups by their sources and their topics. The strategic data acquired from this research, especially that are necessary for substantiating and pricing high ranked contractual claims and their related cost components, should be paid high level of attention in order to enhance the effectiveness in the employers claim management process and to reduce the project time and cost. Keywords: Construction claim, contract, construction data, FIDIC INTRODUCTION Construction claim is the seeking of consideration or change by one of the parties involved in the construction process [Arditi and Patel, (1989)]. Several research works show the order of magnitude of the effects of construction claims on cost and time of the projects. For example, the results of the survey of the claims in 24 construction projects in Western Canada in 1994 found that the large majority of claims involved some delays and in a lot of cases delays exceeded the original contract durations by over 100%. As to the project cost, more than half of the claims were additional costs of at least 30% of the original contract values [Semple, Hartman, and Jergeas, (1994)]. In addition, a study shows that transit agencies in the United States and Canada experienced an average cost overrun of 7% of contract values from settlement of disputes and claims from heavy civil contracts [Callahan, (1998)]. In Thailand, the survey of the claim behaviors of 21 construction companies showed that the average cost overrun from contract value caused

2 548 Strategic data for emplyer s construction claims by claims was about 7% [Khanchitvorakul, 2000], close to Callahan s finding. Nowadays, the substantially increasing volume of claims are the result of the rising complexity of the projects, the price structure of the construction industry and the legal approach taken by many employers and contractors [Levin, (1998)]. Although construction claims have significant effects on the projects, they are not always given adequate considerations. For example, a study shows that records available on sites seldom allow an as-built schedule to be constructed easily [Scott and Assadi, (1999)]. The daily report is often given the least amount of attention although it may be the most important document on the project [Pogorilich, (1992)]. A survey of construction claim management practices in Thai construction companies showed that the lack of awareness of on-site people is considered the major problem of claim management. Inadequacies of supporting evidences, stemming from unaware project personnel as well as improperly designed documentation systems, are the next serious shortcomings causing loss of chances to recover incurred damages. The management level was also recommended to pay more attention to these aspects for having an effective claim management system [Surawongsin, (2002)]. From the employers point of view, it is appropriate that they should establish an effective claim management system so that they can be aware of the potentially adverse job conditions and have opportunities to take proper actions to protect or remedy the works in advance instead of simply complying with contractor s claims. From literature review, it can be seen that the majority of the claim management systems focus on supporting the contractors claim process. Because of the difference between the employers and the contractors roles, rights, duties, availabilities of the information, their relevant types and aspects of claims, and methods of analyzing and pricing claims, the management system that is suitable for them must also be different. While the contractors always claim against the employers for the delays, changes in scope-of-work, acceleration, and differing site conditions, the types of claims generally claimed by the employers against the contractors are claims for delayed project completion, defective work, and abandonment of the project [McDonald, (1984)]. This research presents the results of analyzing the required data for the employers to manage their claims in accordance with The Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer ( The Construction Contract ) prepared by the Federation Internationale des Ingenieurs-Counseils (FIDIC) in 1999, which is one of the most accepted standard forms of construction contract. In addition, this research examined the strategy of identifying the cost components of the employers claims, cost component quantification, and acquisition of necessary data for substantiating and pricing the claims. RESEARCH METHODOLOGY The steps to examine and acquire the data necessary for the claim substantiating and pricing processes consist of: 1. Identifying and analyzing the components of cost claimed for each employers and contractors claim type specified in The Construction Contract [FIDIC, 1999]. In this

3 Strategic data for emplyer s construction claims 549 step, the types of contractors claim cost components for each type of the contractors claims presented by [Adrian (1988)] were used as a framework in identifying and analyzing the employers claim cost components. 2. Analyzing the availability, the appropriate method for substantiating or pricing, and the data required in substantiating or pricing or recognizing each cost component of claims. 2.1 Analyzing the availability of each claim cost component for each claim-related contract provision. In this analysis, the list of contractual claim in FIDIC s forms of contracts proposed by [Booen (2001)] and the types of contractors claim cost components for each type of contractors claims [Adrian, 1988] were used. Each claim cost component was labeled as Not Included, Sometimes Included, and Always Included for each employers or contractors claim-related provision. 2.2 Finding the ranks of the most frequently found cost components and contract provisions by representing Not Included by 0, Sometimes Included by 1, and Always Included by 2. Then the summation of such values for each cost component and each contract provision are calculated. 2.3 Reviewing and Selecting the appropriate method for substantiating or pricing each claim cost component from literature. The criteria for selecting the appropriate method of calculation were the correctness of result, advantage, disadvantage or limitation, and acceptance. The discussion of each selection is, however, beyond the scope of this paper. 2.4 From the substantiating or pricing method selected in 2.2, analyzing the data necessary to be inputted into the relevant calculation process of each method. Some data were classified into the same group in order to reduce the number of the data. 3. Analyzing the sources of each required data. Four sources of data, e.g. the employer, the contractor, the engineer, and sources, were used in this analyzing step. 4. Identifying the availability to the employer and the engineer (as an employer s representative) of each data by considering its sources. The data which are not available to the employer or the engineer were then replaced with another alternative data that are directly or indirectly available to those parties. 5. Classifying the data collected from the above analysis into eight subgroups according to their sources(data directly and indirectly acquired by the employer or the engineer) and their relationships with the construction process (data related to the employer and the engineer, contractor and the subcontractor, project, and miscellaneous respectively). Employers and Contractors Contractual Claims In order to determine the standard contract management process used in this research, the process specified in The Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer or The Construction Contract prepared by Federational Internationale des Ingenieurs-Conseils (FIDIC) was adopted as a framework for the analysis. This form of contract is recommended for building or

4 550 Strategic data for emplyer s construction claims engineering works designed by the Employer or by the Engineer, as his representative, and the Contractor has obligations to construct the works in accordance with a design provided by the employer [FIDIC, 1999]. The former edition of this form of contract, Conditions of Contract for Works of Civil Engineering Construction (Fourth Edition) or The Red Book (Fourth Edition), was mandated in the World Bank Standard Bidding Document for the Procurement of Works published in January 1995, and then was recommended by the World Bank for the purpose of drafting the new edition [Bowcock, (1998)]. This is a reason why this form of contract has become one of the most accepted contract forms, which has been used worldwide. There are several provisions related to the construction claims, both against employer and contractor, in The Construction Contract (1999). [Booen(2001)] listed the sub-clauses related to several types of claims, as shown in Table 1. It also presents the party against whom each provision claims and the purposes for which each provision claims. Table 1. The Provisions related to Claims from The Construction Contract (1999) No. Sub-Clause Claimed By Claim For Employer Contractor Cost Time [Delayed Drawings or Instructions] [Right to Access to the Site] [Setting Out] [Unforeseeable Physical - Conditions] [Electricity, Water and Gas] [Employer s Equipment and - - Free-Issue Material] [Fossils] [Testing] [Rejection] [Remedial Work] [Extension of Time for Completion] [Delays Caused by Authorities] [Rate of Progress] [Delay Damages] [Consequences of Suspension] [Failure to Pass Tests on Completion] [Taking Over of Parts of Works] [Interference with Tests on - Completion] Table 1. The Provisions related to Claims from The Construction Contract (1999) (Cont.) No. Sub-Clause Claimed By Claim For Employer Contractor Cost Time [Extension of Defects Notification - - Period] [Failure to Remedy Defects] [Contractor to Search] [Omissions] [Right to Vary] -

5 Strategic data for emplyer s construction claims [Value Engineering] [Adjustments for Changes in Legislation] [Delayed Payment] [Contractor s Entitlement to - Suspend Work] [Indemnities] [Consequences of Employer s - Risks] [General Requirements for - Insurances] [Insurance for Works and - - Contractor s Equipment] [Consequences of Force Majeure] - Employers and Contractors Cost components There were seventeen cost components proposed by Adrian in However, six cost components collected from the contract provisions of The Conditions of Contract Contract for Building and Engineering Works Designed by the Employer [The Construction Contract (1999)] were added in order to improve the analysis. The relations between the contractors claim related provisions from [The Construction Contract (1999)] and the contractors claim cost components are the result of subjective analyses by the authors, taking account of their availabilities in each provision. The ranks of the cost components which have the highest frequencies among the contractual claims and the contract provisions which have the highest number of the related cost components, for both contractors and employers claims, can be analyzed by assigning the values to the cost component and contract provision matrices. The cost components which are seldom or never found in the claim specified in the related subclause were assigned 0 value while the cost components which are sometimes and always found in the claim related to such sub-clause were assigned 1 value and 2 value respectively. The values were then summed in both row direction and column direction to find the rank of the cost components and the rank of the contract provisions, respectively. The analysis shows the cost components with the highest frequencies among the contractors contractual claims and the contract provisions with the highest number of the related contractors claim cost components in Table 2 and Table 3 respectively. These cost components and contract provisions are found in several contractual claims and should be given special attention. Table 2. Rank of Contractors Claim Cost Components No. Cost Component Score 1. 1) Equipment Rental Cost 2) Cost for Owned Equipment Used ) Additional Material Unit Price 2) Additional Subcontractor Cost 34 34

6 552 Strategic data for emplyer s construction claims 3) Variable Job Overhead Cost 4) Profit 3. 1) Additional Direct Labor Hours Due to Lost Productivity 2) Increased Labor Rate 3) Interest or Finance Costs Table 3. Rank of Contract Provisions Related to the Contractors Claims No. Contract Provision Score 1. 1) 19.4[Consequences of Force Majeure] ) 7.4 [Testing] 30 2) 10.3[Interference with Tests on Completion] 3. 1) 1.9 [Delayed Drawings or Instructions] 2) 4.7 [Setting Out] 3) 4.24[Fossils] 4) 8.4 [Extension of Time for Completion] 5) 8.5 [Delays Caused by Authorities] 6) 8.9 [Consequences of Suspension] 7) 10.2[Taking Over of Parts of the Works] 8) 13.3[Variation Procedure] 9) 13.7[Adjustment for Changes in Legislation] 10)16.1[Contractor s Entitlement to Suspend Work] 11)17.4[Consequences of Employer s Risks] Note that almost all high-rank contract provisions are related to delay claims, scope-ofwork claims and acceleration claims. In addition, sub-clause 4.7[Setting Out] and 4.24[Fossils] are related to the changing-site-condition claims. On the other hand, the cost components of the employers claims were identified by using the contractors cost components as a framework. But only fifteen components were collected from the employers cost components. After being added seven cost components acquired from analyzing [The Construction Contract (1999)], there are twenty-two cost components used in substantiating and pricing the employers claims. After performing the same analysis of the contractor s claims, Table 4 and Table 5 respectively show the three employers claim cost components which are frequently found and the three contract provisions with the highest relationship with the employer s contractual claims. It should be noted that the important employers claim cost components are related to the overhead cost. These cost components and claim-related contract provisions should be given special attention. 30 Table 4. Rank of Employers Claim Cost Components No. Cost Component Score 1. 1) Variable Job Overhead Costs ) Additional Employer s Personnel Hours ) Variable Company Overhead Costs 2) Fixed Company Overhead Costs 8

7 Strategic data for emplyer s construction claims 553 Table 5. Rank of Contract Provisions Related to the Employers Claims No. Contract Provision Score 1. 1) 8.7[Delay Damages] ) 11.4[Failure to Remedy Defects] ) 7.6[Remedial Work] 18 Data Required in Employers and Contractors Claim Management Processes. 67 pieces of data are found to be necessary in managing the employers contractual claims, which can be divided, by their sources (data directly and indirectly acquired by the employer or the engineer) and their relationships to the construction process (data related to the employer and the engineer, contractor and the subcontractor, project, etc. respectively), into seven groups, as shown in Table 4. Data in the Data Directly Acquired by the Employer or the Engineer category are the data which the employer or the engineer produces or posssesses while the data in Data Indirectly Acquired by the Employer or the Engineer category are the data which are produced or possessed by other parties. It should be noted that the employer or the engineer can acquire all data related to the employer and the engineer themselves directly. Therefore the cell in the Data the Employer or the Engineer Acquire Indirectly Data Related to the Employer and the Engineer group was not filled. Table 6 shows that there are several data required by the employers in substantiating and pricing the claims specified in The Construction Contract (1999). Some data can be collected from either the employers or the engineers, as the employers representatives, while some data must be collected from the contractors or other external sources. The data which must be collected from the contractor but which there is no contract provision specifying the contractor s obligation to provide to the engineer must be substituted by other data more conveniently acquired by the engineer. Some data, such as the contract value, the name of the bidders, and the bid price of each contractor in the project bidding in the past are always overlooked although they are necessary in substantiating some cost components of the claim. The engineers or the employers should inspect their claim management system whether such necessary data are sufficiently collected. Table 6. Data Necessary for Managing the Claims by the Employer Data Directly Acquired by the Data Indirectly Acquired by the Employer or the Engineer Employer or the Engineer A. Data Related to A1. General Information - the Employer and 1) Actual Employer s Cash Flow 2) Employer s Cost in the Segmented the Engineer Cost Code 3) Employer's Cost of Capital 4) Original Employer s Cash Flow 5) Works Done by the Employer A2. Free-Supplied Material 1) Date of Employer s Free-Supplied Material Purchase 2) Employer s Free-Supplied Material Unit Price

8 554 Strategic data for emplyer s construction claims B. Data Related to the Contractor and the Subcontractor C. Data Related to the Project 3) Employer s Free-Supplied Material Sent to the Contractor 4) Employer s Free-Supplied Material Return to Employer A3. Equipment 1) Employer's Equipment Actual Hour 2) Employer's Equipment Hourly Ownership Cost 3) Employer's Equipment Hourly Operating Cost A4. Personnel 1) Employer s Personnel Rate 2) Employer s Personnel Hours 3) Employer s Personnel Hours of Increased Employer s Personnel Rate A5. Engineer 1) Date of Instructions Issued 2) Details of Instruction Issued 1) Works Done by Other Contractors 1) Contractor's Cost of Capital 2) Details of Works Done by the Subcontractor 3) Total Price of Contracts the Contractor Receive C1. General Information 1) Date that the Work can be Used as Intended 2) Productivity Records 3) Required Rate of Return of Project 4) Test Result C2. Cost 1) Adjusted Unit Cost Table 6. Data Necessary for Managing the Claims by the Employer (Cont.) Data Directly Acquired by the Employer or the Engineer C. Data Related to the Project (Cont.) 2) Normal Hourly Equipment Operating Cost 3) Normal Hourly Equipment Ownership Cost C3. Document 1) Date of Documents Received 2) Date of Documents Submitted 3) Details of Documents Received 4) Details of Documents Submitted C4. Site Condition 1) Climatic Condition 2) Site Condition 3) Site Condition of Neighborhood Sites C5. Defect and Delay 1) Cause of Deficiency in Works 2) Details of Deficiency in Works 3) Delay Duration Attributable to the Contractor 4) Problem of Use of Works 5) Reasons of Delays C6. Site Event 1) Date of Each Use of Works 4) Works Done by the Contractor 1) Cost Pattern of the Opportunity Profit Loss Project 2) Expected Climatic Condition 3) Normal Productivity 4) Normal Equipment Rental Cost 5) Normal Labor Rate 6) Normal Material Unit Price 7) Percent Overhead+Profit+Tax / Direct Cost Data Indirectly Acquired by the Employer or the Engineer

9 Strategic data for emplyer s construction claims 555 2) Date of Special Events Occurred 3) Details of Special Events Occurred 4) Purpose of Each Use of Works D. Miscellaneous 1) Estimated Payment to Other Contractors 2) Original Value of Works 3) Payment Amount 4) Payment Date 5) Payment Purpose 6) Payment to Whom 7) Bid Price of Each Contractor 1) Date of Law and Regulation Changed 2) Details of Law and Regulation Changed 3) Law or Regulation 4) Bid Price of Each Contractor in Past Bidding Project 5) Expert s Opinion : Engineering 6) Expert s Opinion : Law 7) Expected Interest Rate of Central Bank at Profit Loss Project Duration 8) Interest Rate of Central Bank CONCLUSION This paper presents the claim-related provisions of The Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer or The Construction Contract (1999), the contractors and the employers cost components, the ranks of the important cost components and the claim-related contract provisions, and the data necessary for the employers in managing their construction claims. There are thirtytwo provisions of The Construction Contract (1999) which are related to the construction claims. They have relationship to some components of twenty-three contractors claim cost components or twenty-two employers cost components in different ways. The most important cost components and claim-related contract provisions, both for employers and contractors claims, were also presented. Finally, there are 67 pieces of data required in substantiating and pricing the claims by the employers, which can be divided into seven groups. The strategic data acquired from this research, especially that are necessary for substantiating and pricing high ranked contractual claims and their related cost components, should be paid high level of attention in order to enhance the effectiveness in the employers claim management process and to reduce the project time and cost. References Adrian, J J (1988) Construction Claims : A Quantitative Approach, New Jersey, Prentice- Hall. Arditi, D and Patel, B K (1989) Expert System for Claim Management in Construction Project. Project Management, Vol. 7 No. 3, pp Booen, P L (2004) Claims & Adjustments of the Contract. FIDIC Global Conditions of Contract Seminar (January 2001), Bowcock, J (2004) The Four New FIDIC Forms of Contract - Introduction. FIDIC New Contract Launch Seminar Series (Sep.-Dec.1998), Callahan, J T (1998) Managing Transit Construction Contract Claims. Synthesis of Transit Practice 28, Washington, National Academic Press. Federation Internationale des Ingenieurs-Conseils (1999) Conditions of Contract for Construction, First Edition, Lausanne, FIDIC. Khanchitvorakul, S (2000) Development of Construction Claim Supporting System, Master Thesis Department of Civil Engineering King Mongkut University of Technology Thonburi [KMUTT].

10 556 Strategic data for emplyer s construction claims Levin, P (1998) Construction Contract Claims, Changes & Dispute Resolution, Second Edition, Boston, ASCE Press. McDonald, P R (1984) Construction Claims Costing for Owners and Contractors. Construction Management and Economics, Vol. 2, pp Pogorilich (1992) The Daily Report as a Job Management Tool. Cost Engineering, Vol. 34, No. 2, pp Scott, S and Assadi, S (1999) A survey of the site records kept by construction supervisors. Construction Management and Economics, Vol. 17, pp Semple, C, Hartman, F T, and Jergeas, G (1994) Construction Claims and Disputes : Clauses and Cost/ Time Overruns. ASCE Journal of Construction Engineering and Management, Vol. 120, No. 4, pp Surawongsin, P (2002) The Implementation of Construction Claims Management in the Thai Construction Industry, Master Thesis School of Civil Engineering Asian Institute of Technology[AIT].

Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey

Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project

More information

Conditions of Contract for CONSTRUCTION

Conditions of Contract for CONSTRUCTION Conditions of Contract for CONSTRUCTION FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER Multilateral Development Bank Harmonised Edition June 2010 General Conditions This publication is exclusive

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK

CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK SUMMARY The FIDIC Conditions are used extensively on international

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004) Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament

More information

Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals

Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Journal of Construction in Developing Countries, Vol. 16(1), 41 67, 2011 Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Visuth Chovichien

More information

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill FIDIC users guide A practical guide to the 1999 Red and Yellow Books Brian W. Totterdill Published by Thomas Telford Publishing, Thomas Telford Ltd, 1 Heron Quay, London E14 4JD. URL: www.thomastelford.com

More information

Standard conditions of purchase

Standard conditions of purchase Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out

More information

CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS

CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS 1 (1) CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS ANETTE KAVALEFF [OY KAVALEFF CONSULTING AB] KATJA KOSKELAINEN MARJAANA KOUSA [RASTOR OY] 1. ABSTRACT Changes during a project are more of a rule

More information

ARTWORK COMMISSION AGREEMENT

ARTWORK COMMISSION AGREEMENT ARTWORK COMMISSION AGREEMENT THIS AGREEMENT is made the day of in the year BETWEEN the Minister for Works of Level 6, 16 Parkland Road, Osborne Park, WA 6017 being the body corporate created under Section

More information

7.4.1 Be required to make exhaustive or continuous on-site reviews;

7.4.1 Be required to make exhaustive or continuous on-site reviews; SUPPLEMENTARY CONDITIONS TO THE CANADIAN STANDARD FORM OF CONTRACT FOR ARCHITECTURAL SERVICES DOCUMENT SIX 2006 EDITION RAIC 6 2006 FRASER HEALTH PROJECTS The following Supplementary Conditions are specific

More information

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October

More information

ROADMAP TO A SUCCESSFUL TERMINATION FOR DEFAULT

ROADMAP TO A SUCCESSFUL TERMINATION FOR DEFAULT ROADMAP TO A SUCCESSFUL TERMINATION FOR DEFAULT By: Frank E. Riggs, Jr. frank.riggs@troutmansanders.com 404.885.3353 One of the most difficult, and potentially costly, decisions facing a project owner

More information

Construction Change Orders

Construction Change Orders Construction Change Orders Michael E. Purdy Contracts Manager University of Washington (206) 221-4235 mpurdy@u.washington.edu 1 Agenda Tools to Prevent Change Orders 4 Elements of Change Orders Authorization

More information

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni The FIDIC Form of Contract The Fourth Edition of the Red Book 2nd Edition Nael G. Bunni BSc, MSc, PhD, CEng, FIEI, FICE, FIStruct, FCIArb, FInstD, MconsEI b Blackwell Science Contents List of Figures List

More information

Project Management Procedures

Project Management Procedures 1201 Main Street, Suite 1600 Columbia, South Carolina 29201 Project Management Procedures Start Up The grant becomes effective upon return of one copy of the grant award executed by the Chief Executive

More information

CONSTRUCTION CLAIMS AND DISPUTES: CAUSES AND COST/TIME OVERRUNS

CONSTRUCTION CLAIMS AND DISPUTES: CAUSES AND COST/TIME OVERRUNS CONSTCTION CAIMS AND DISPTES: CASES AND COST/TIME OVENS By Cheryl Semple, ~ Francis T. Hartman, 2 and George Jergeas 3 AnsrACT: Avoiding construction claims and disputes requires understanding of the contractual

More information

AIA Document A312 - Electronic Format. Performance Bond

AIA Document A312 - Electronic Format. Performance Bond AIA Document A312 - Electronic Format Performance Bond THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...

More information

Contractor s Claims Under The FIDIC Contracts For Major Works

Contractor s Claims Under The FIDIC Contracts For Major Works March 17, 2005 [This paper is to be published in the Construction Law Journal, London, in 2005]] International Construction Contracts and Dispute Resolution Co-Hosted by ICC and FIDIC In partnership with

More information

LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements

LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements Alan R. Merkle Stoel Rives LLP 600 University Street, Suite 3600 Seattle, WA 98101-4109

More information

SCHEDULE 5 INSURANCE TABLE OF CONTENTS 1. INSURANCE REQUIREMENTS... 1

SCHEDULE 5 INSURANCE TABLE OF CONTENTS 1. INSURANCE REQUIREMENTS... 1 SCHEDULE 5 INSURANCE TABLE OF CONTENTS 1. INSURANCE REQUIREMENTS... 1 1.1 Project Specific Construction Period Insurance... 1 1.2 Additional Construction Period Insurance... 1 1.3 Operating Period Insurance

More information

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE

More information

Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department

Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department Current Position PKR CONSULTING, INC. Founder and Chief Executive Officer, 2004 Present Provides construction consulting, dispute resolution and expert witness services to owners, contractors, subcontractors,

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table

More information

INDEX. bonded contract, 289 insureds, 243. misrepresentation, 291 obtaining, 242

INDEX. bonded contract, 289 insureds, 243. misrepresentation, 291 obtaining, 242 INDEX B non-conforming tender, 284 boiler and machinery insurance, performance bond 241 default by the obligee, 288 coverage, 243 failure to notify, 289 definition of the accident, 245 material variation

More information

COLOCATION SERVICE SCHEDULE

COLOCATION SERVICE SCHEDULE COLOCATION SERVICE SCHEDULE 1. DEFINITIONS AND INTERPRETATION 1.1 Definitions Capitalised terms in this Service Schedule not otherwise defined here have the meaning given in the Standard Terms and Conditions:

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts 11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Risk Allocation in Construction Contracts Risks 2 In the absence of a contract, all risks are the owner's Contracting is

More information

Measured development Construction and Engineering Training Supplement Guide

Measured development Construction and Engineering Training Supplement Guide Construction and Engineering Training Supplement Guide Welcome Eversheds is the law firm behind some of the world s most ambitious construction and engineering projects. We have one of the biggest teams

More information

1. Interpretation 1.1. In these conditions the Company means Original Cine Pty Ltd (trading as The Visionhouse) and its successors and assigns of 195 Rouse Street, Port Melbourne, Victoria, Australia 3207.

More information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document

More information

REQUEST FOR QUOTE NUMBER: 10RD75957YB WILL BE RECEIVED UNTIL 11/5/2010 at 2:00 p.m.

REQUEST FOR QUOTE NUMBER: 10RD75957YB WILL BE RECEIVED UNTIL 11/5/2010 at 2:00 p.m. DEPARTMENT OF PURCHASING & CONTRACT COMPLIANCE Winner 2000-2009 Achievement of Excellence in Procurement Award National Purchasing Institute Cecil S. Moore, Director REQUEST FOR QUOTE NUMBER: 10RD75957YB

More information

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman

More information

Contract Administration

Contract Administration Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306

More information

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES General Terms of Public Procurement in service contracts November 2009 Contents Introduction........................................................................................................................................3

More information

Australian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1)

Australian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1) AS 4300 1995 (Incorporating Amendment No. 1) Australian Standard General conditions of contract for design and construct This Australian Standard was prepared by Committee OB/3, General Conditions of Contract.

More information

Defects liability period an introduction

Defects liability period an introduction Investing in Infrastructure International Best Legal Practice in Project and Construction Agreements January 2016 Damian McNair Partner, Legal M: +61 421 899 231 E: damian.mcnair@au.pwc.com Defects liability

More information

DOCUMENT. General Purchase Conditions

DOCUMENT. General Purchase Conditions 1. Scope 1.1 These general purchase conditions (hereinafter the GPC ) shall apply to all kinds of materials, articles, products and services related to them, (hereinafter Products ), offered, sold or supplied

More information

COLOCATION SERVICE SCHEDULE

COLOCATION SERVICE SCHEDULE COLOCATION SERVICE SCHEDULE 1. DEFINITIONS AND INTERPRETATION 1.1 Definitions Capitalised terms in this Service Schedule not otherwise defined here have the meaning given in the Master Services Agreement:

More information

International Accounting Standard 11 Construction Contracts

International Accounting Standard 11 Construction Contracts International Accounting Standard 11 Construction Contracts Objective The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts.

More information

Who pays the Money for the Time?

Who pays the Money for the Time? Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency

More information

Translation from German. GENERAL TERMS AND CONDITIONS of mangoart GmbH Bräuergasse 11, 4470 Enns, Austria +43 7223 / 912 78, office@mangoart.

Translation from German. GENERAL TERMS AND CONDITIONS of mangoart GmbH Bräuergasse 11, 4470 Enns, Austria +43 7223 / 912 78, office@mangoart. Translation from German GENERAL TERMS AND CONDITIONS of mangoart GmbH Bräuergasse 11, 4470 Enns, Austria +43 7223 / 912 78, office@mangoart.at 1. Applicability; Conclusion of contract 1.1 mangoart GmbH

More information

Accounting System Requirements

Accounting System Requirements Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Nominated Subcontractors on International Projects: Approaches to Risk Allocation Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.

More information

Characteristics of the Participants

Characteristics of the Participants 3 Financial Analysis for Replacement of Construction Equipment in Saudi Arabia Ali A. Shash (Center for Engineering Research, Research Institute, King Fahd University of Petroleum & Minerals, Saudi Arabia)

More information

PRIME CONSULTANT SERVICES

PRIME CONSULTANT SERVICES GUIDELINES FOR Professional Engineers providing PRIME CONSULTANT SERVICES 1.0 INTRODUCTION 1.1 PURPOSE OF GUIDELINES The "Guidelines for Professional Engineers providing Prime Consultant Services" have

More information

CLSA SECURITIES (THAILAND) LIMITED - FUTURES/OPTIONS TRADING SERVICES ANNEX

CLSA SECURITIES (THAILAND) LIMITED - FUTURES/OPTIONS TRADING SERVICES ANNEX CLSA SECURITIES (THAILAND) LIMITED - FUTURES/OPTIONS TRADING SERVICES ANNEX 1. Definitions and Interpretation 1.1 Subject to Clauses 1.2 and 1.3 below, in this CLSA Securities (Thailand) Limited Futures/Options

More information

Invitation to Tender

Invitation to Tender Invitation to Tender Provision of Training in Technology Transfer and Related Areas for The Southern Africa Innovation Support Programme 1. Drawing up the tender The tender must be submitted in writing

More information

Construction Contracts

Construction Contracts STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.

More information

Smart Meters Programme Schedule 9.1. (TUPE) (CSP South version)

Smart Meters Programme Schedule 9.1. (TUPE) (CSP South version) Smart Meters Programme Schedule 9.1 (TUPE) (CSP South version) Schedule 9.1 (TUPE) (CSP South version) Amendment History Version Date Status v.1 Signature Date Execution copy SCHEDULE 9.1 TUPE 1. PURPOSE

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

Terms and Conditions For Mobile Phone Service. Pre-Paid Type. Between The Service Provider And Subscribers

Terms and Conditions For Mobile Phone Service. Pre-Paid Type. Between The Service Provider And Subscribers Terms and Conditions For Mobile Phone Service Pre-Paid Type Between The Service Provider And Subscribers 1. General 1.1 This Terms and Conditions for Mobile Phone Service ( Terms and Conditions ) is binding

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

PITTSBURG UNIFIED SCHOOL DISTRICT

PITTSBURG UNIFIED SCHOOL DISTRICT PITTSBURG UNIFIED SCHOOL DISTRICT New Construction and Modernization Projects PRE-QUALIFICATION PROGRAM QUESTIONNAIRE FOR PROJECTS $20 MILLION AND OVER TABLE OF CONTENTS PAGE NO. GENERAL INFORMATION.......i

More information

CHAPTER 23. Contract Management and Administration

CHAPTER 23. Contract Management and Administration Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...

More information

Module 3 Licensed Software TABLE OF CONTENTS. Version 3.0

Module 3 Licensed Software TABLE OF CONTENTS. Version 3.0 1 Module 3 Licensed Software Version 3.0 TABLE OF CONTENTS 1. AGREED TERMS AND INTERPRETATION... 2 2. LICENCE TERMS... 3 3. SUPPLY OF... 8 4. UPDATES AND NEW RELEASES... 9 5. OPEN SOURCE SOFTWARE... 10

More information

10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest

10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest Requirements Procurement under the New Requirements 1 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between

More information

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES Names of Parties 1. (Company Name) of (Company Address) ( Consultancy ). 2. Redline Group Ltd of 26-34 Liverpool Road, Luton. Beds LU1

More information

A Study On Factors Influencing Construction Contract Claim Management

A Study On Factors Influencing Construction Contract Claim Management A Study On Factors Influencing Construction Contract Claim Management K.Sundhar #1, N.Nandhini #2 #1 PG Student (M.E Construction Engineering and Management), #2 Assistant Professor ( Department of civil

More information

New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions

New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions ACRS Lic No. A021974 Lic No. 192237C New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions *Definitions are in clause 19 1. FORMATION OF AGREEMENT 1.1 Acceptance of Quotation The Customer must accept

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi)

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) Version 1.0 9 June 2015 HISTORY OF CHANGES Version Publication date Changes 1.0 09.06.2015 Initial version 1 EUROPEAN COMMISSION

More information

Causes, Effects and Minimization of Delays in Construction Projects

Causes, Effects and Minimization of Delays in Construction Projects Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi

More information

Insert Name of Project Here Reference Version. Insert Title of Works Here. United Nations Office for Project Services ( UNOPS ) -and-

Insert Name of Project Here Reference Version. Insert Title of Works Here. United Nations Office for Project Services ( UNOPS ) -and- Insert Name of Project Here Reference Version Insert Title of Works Here United Nations Office for Project Services ( UNOPS ) -and- Name of Contractor Lump Sum Construction Contract Contract No.: Insert

More information

AGREEMENT BETWEEN THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO and PROJECT ARCHITECT for A PROJECT OF LIMITED SIZE OR SCOPE

AGREEMENT BETWEEN THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO and PROJECT ARCHITECT for A PROJECT OF LIMITED SIZE OR SCOPE AGREEMENT BETWEEN THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO and PROJECT ARCHITECT for A PROJECT OF LIMITED SIZE OR SCOPE This Agreement is made as of, 20 (the Effective Date ), by and

More information

NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS

NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS NAS 13 NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS CONTENTS Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT

More information

PhoneWatch Install, Monitoring & Service Terms and Conditions

PhoneWatch Install, Monitoring & Service Terms and Conditions Please read these terms and conditions set out below and note, in particular, the important conditions relating to Our Contract with You (clause 2), Duration of Contract (clause 3), Ownership of the Alarm

More information

Local Government Guide to Procurement with Federal Grant Funding

Local Government Guide to Procurement with Federal Grant Funding I. INTRODUCTION A. The Grants Management Common Rule (GMCR): What is it? The GMCR is a set of regulations (including procurement regulations) that applies to all entities that receive federal grant money.

More information

Construction Claims Services. Helping you prevent, analyze and resolve construction disputes.

Construction Claims Services. Helping you prevent, analyze and resolve construction disputes. Construction Claims Services Helping you prevent, analyze and resolve construction disputes. helping clients manage construction disputes Construction projects face continual challenges that arise from

More information

Construction Contracts

Construction Contracts 65 Accounting Standard (AS) 7 Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT COSTS 15-20

More information

TERMS AND CONDITIONS FOR PAYMENT CARDS SERVICING

TERMS AND CONDITIONS FOR PAYMENT CARDS SERVICING TERMS AND CONDITIONS FOR PAYMENT CARDS SERVICING 1. TERMS AND DEFINITIONS 1.1. Authorisation is a query to check Card validity and availability of corresponding funds on the Card s account. 1.2. Card means

More information

PAYMENT IN FULL? contractors over how much money is due for a particular contract. A roofing contractor may

PAYMENT IN FULL? contractors over how much money is due for a particular contract. A roofing contractor may PAYMENT IN FULL? What should roofing contractors do if they receive a check for less than the full amount, but the check contains language indicating it is final payment? INTRODUCTION Roofing contractors

More information

Responsibilities of Engineering Surveyors under ISO 9000 in Hong Kong Construction Industry

Responsibilities of Engineering Surveyors under ISO 9000 in Hong Kong Construction Industry Responsibilities of Engineering Surveyors under ISO 9000 in Hong Kong Construction Industry Steve Y. W. Lam and Conrad H. W. Tang Department of Land Surveying & Geo-Informatics Hong Kong Polytechnic University,

More information

JRI S STANDARD TERMS OF PURCHASE. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.

JRI S STANDARD TERMS OF PURCHASE. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. JRI S STANDARD TERMS OF PURCHASE 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day (other than a Saturday, Sunday or public holiday) when banks

More information

KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms.

KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms. KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms. Page 1 of 14 OWNER CHECKLIST (To be completed by the owner prior to signing

More information

COLLECTIVE INVESTMENT LAW DIFC LAW No. 2 of 2010

COLLECTIVE INVESTMENT LAW DIFC LAW No. 2 of 2010 ---------------------------------------------------------------------------------------------- COLLECTIVE INVESTMENT LAW DIFC LAW No. 2 of 2010 ----------------------------------------------------------------------------------------------

More information

ACCOUNTING FOR CONSTRUCTION IN PROGRESS

ACCOUNTING FOR CONSTRUCTION IN PROGRESS ATTACHMENT X GOVERNMENT REGULATION OF THE REPUBLIC OF INDONESIA NUMBER YEAR 00 DATE JUNE 00 GOVERNMENT ACCOUNTING STANDARDS STATEMENT NO.0 ACCOUNTING FOR CONSTRUCTION IN PROGRESS TABLE OF CONTENTS Paragraph

More information

CHAPTER 2 CONTRACT STRATEGY

CHAPTER 2 CONTRACT STRATEGY CHAPTER 2 CONTRACT STRATEGY At the early stage of a project and once a project manager is selected, the main issue that faces the owner is to decide on the contract strategy that best suits the project

More information

Terms & Conditions Verder B.V. (02031806) Filed at the Chamber of Commerce on 29-01-2015

Terms & Conditions Verder B.V. (02031806) Filed at the Chamber of Commerce on 29-01-2015 Terms & Conditions Verder B.V. (02031806) Filed at the Chamber of Commerce on 29-01-2015 1. General 1.1 These terms and conditions use the following terms and definitions: Product: items, as well as services

More information

Guidance Notes for the NEC Engineering and Construction Contract

Guidance Notes for the NEC Engineering and Construction Contract The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors

More information

TEXTURA AUSTRALASIA PTY LTD ACN 160 777 088 ( Textura ) CONSTRUCTION PAYMENT MANAGEMENT SYSTEM TERMS AND CONDITIONS OF USE

TEXTURA AUSTRALASIA PTY LTD ACN 160 777 088 ( Textura ) CONSTRUCTION PAYMENT MANAGEMENT SYSTEM TERMS AND CONDITIONS OF USE TEXTURA AUSTRALASIA PTY LTD ACN 160 777 088 ( Textura ) CONSTRUCTION PAYMENT MANAGEMENT SYSTEM TERMS AND CONDITIONS OF USE Welcome to the Textura Construction Payment Management ( CPM ) System. By clicking

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES

MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES THIS AGREEMENT is made and entered into this day of, 2007, by and between the University of Washington ( Owner ) and, ( Project

More information

General Procurement Terms and Conditions of SMEPRO INTERNATIONAL B.V.

General Procurement Terms and Conditions of SMEPRO INTERNATIONAL B.V. General Procurement Terms and Conditions of SMEPRO INTERNATIONAL B.V. Article 1 - Definitions In these General Procurement Terms and Conditions, the terms below have the following meaning: SMEPRO : The

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

Property, Stock and Business Agents Regulation 2014

Property, Stock and Business Agents Regulation 2014 New South Wales Property, Stock and Business Agents Regulation 2014 under the Property, Stock and Business Agents Act 2002 [If this Regulation is made, the following enacting formula will be included:]

More information

SMALL, SMALL DISADVANTAGED, AND WOMEN -OWNED SMALL BUSINESS MODEL SUBCONTRACTING PLAN OUTLINE* Identification Data. Contractor: Address:

SMALL, SMALL DISADVANTAGED, AND WOMEN -OWNED SMALL BUSINESS MODEL SUBCONTRACTING PLAN OUTLINE* Identification Data. Contractor: Address: SMALL, SMALL DISADVANTAGED, AND WOMEN -OWNED SMALL BUSINESS MODEL SUBCONTRACTING PLAN OUTLINE* Identification Data Contractor: Address: Solicitation or Contract Number: Item/Service: Total Amount of Contract

More information

General Terms and Conditions for Online Sales of TomTom Inc ( TomTom )

General Terms and Conditions for Online Sales of TomTom Inc ( TomTom ) General Terms and Conditions for Online Sales of TomTom Inc ( TomTom ) 1) Scope a) These Terms and Conditions shall apply to all purchase orders submitted or to be submitted by you for any item, service

More information

GENERAL TERMS FOR COST CONTROL

GENERAL TERMS FOR COST CONTROL GENERAL TERMS FOR COST CONTROL These conditions only apply to tenders and contracts which are subject to cost control. The Armed Forces of Norway Form 5055 (March 2008) 1 General Conditions These conditions

More information

General Terms of Public Procurement in Supply Contracts JYSE 2014 SUPPLIES

General Terms of Public Procurement in Supply Contracts JYSE 2014 SUPPLIES General Terms of Public Procurement in Supply Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Supply Contracts ()...8 1 Definitions...8

More information

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF ENVIRONMENTAL REMEDIATION

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF ENVIRONMENTAL REMEDIATION NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF ENVIRONMENTAL REMEDIATION TECHNICAL ASSISTANCE GRANTS STATE ASSISTANCE CONTRACT RECORD KEEPING AND PAYMENT GUIDE 1.0 ACCOUNTING SYSTEM

More information

24 CFR PART 85 85.36 Procurement. States. Procurement standards.

24 CFR PART 85 85.36 Procurement. States. Procurement standards. 85.36 Procurement. (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will

More information

Risks in International Consultancy Appointments: The FIDIC White Book

Risks in International Consultancy Appointments: The FIDIC White Book Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction

More information

DO NOT INCLUDE THIS COVER PAGE IN YOUR SPECIFICATIONS

DO NOT INCLUDE THIS COVER PAGE IN YOUR SPECIFICATIONS May 21, 2012 Recommended SUPPLEMENTARY CONDITIONS for Construction Management Contract for Services and Construction, CCDC 5B, 2010 - Stipulated Price Option (Appendix) CCDC 5B - Stipulated Price Option

More information

Standard conditions of electricity supply licence

Standard conditions of electricity supply licence Gas and Electricity Markets Authority ELECTRICITY ACT 1989 Standard conditions of electricity supply licence SECTION A: STANDARD CONDITIONS FOR ALL SUPPLIERS Standard conditions 1 to 6: General arrangements

More information

Project manager services

Project manager services Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism

More information

Document A312" 2010. of business) OWNER'S REPRESENTATIVE: (Architect, Engineer or other party:) 500 North Main Street Monroe, North Carolina 28112

Document A312 2010. of business) OWNER'S REPRESENTATIVE: (Architect, Engineer or other party:) 500 North Main Street Monroe, North Carolina 28112 Document A312" 2010 Payment Bond CONTRACTOR: (Name, legal status and address) OWNER: (Name, legal status and address) Union County 500 North Main Street Monroe, North Carolina 28112 CONSTRUCTION CONTRACT

More information