Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey
|
|
|
- Dwayne McDaniel
- 9 years ago
- Views:
Transcription
1 Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project participants to be one of the most disruptive and unpleasant events of a project. It is commonly recognized that the number of construction claims and disputes has been increasing and has become a burden to the construction industry. Avoiding claims and disputes requires the understanding of the causes of such claims. The purpose of this research is to quantitatively identify the causes of contractor claims in Egypt and suggesting methods of avoiding them. To achieve this objective, a literature review was conducted to identify the causes of claims in international literature, and a list of claim causes was synthesized. A questionnaire survey quantitatively evaluated the modified claim causes and investigated methods of avoiding / reducing them. The top reason for claims was found to be variations initiated by consultant / owner. Furthermore, suggestions to avoid claims include: using an appropriate and balanced contract; giving special consideration for contract clauses dealing with variations, disputes, inspections, approvals, payments and delays; and allowance for reasonable time for completion of design. Keywords: Claims Avoidance; Construction; Questionnaire Survey; Egypt; Variations. Introduction Claims are considered one of the most important items that could cause a harmful effect in organizations and in the construction industry. Claims can be frequent in large projects and can cause budgetary difficulties to employers. They may cause financial difficulties, restriction of cash flow, and loss of liquidity to contractors. Claims in construction contracts may be defined as a request or application for something or notification of presumed entitlement to which the contractor considers, believes or contends (Revay 1990). The number of construction claims has been increasing and are in general a time consuming and costly element in construction projects. The increasing number of international companies contemplating construction projects in Egypt, in addition to the significant problems with regards to claims propagation and management, have given relevance to the studying of causes, management and efficiency of construction claims (Basha el al. 2007; Hassanein and El Nemr 2008). Adversarial approaches to public and private sectors of the construction industry in Egypt generate a substantial increase in the use of litigation and arbitration for the settlement of disputes (Marzouk, El-Mesteckawi, and El-Said 2011). Furthermore, claims recovery policy can have a considerable effect on bid profit reduction in Egypt (Mohamed, Khoury and Hafez 2010). Accordingly, the study of construction claims and their causes in Egypt are quite relevant to construction firms Associate Professor, Construction and Building Engineering Department, College of Engineering and Technology, Arab Academy for Science and Technology and Maritime Transport, Alexandria, Egypt. E- mail: [email protected]; [email protected]. Head of Construction and Building Engineering Department, College of Engineering and Technology, Arab Academy for Science and Technology and Maritime Transport, Cairo, Egypt. [email protected]. Projects Director, Egypt for Management & Engineering Development Company, Cairo, Egypt. 75
2 and developers working in the Egyptian market. Egyptian organizations should equip themselves to deal with claims efficiently, expeditiously and minimize the cost in terms of both money and staff resources. International literatures have researched the causes of claims and have proposed recommendations for avoiding them (Ip 2002). However, the Egyptian culture and nature of its construction industry has different characteristics, and therefore these causes might not be applicable. Avoiding claims need firstly, to define the causes of claims in the context of the Egyptian construction industry then suggest methods of avoiding them. Accordingly, the objective of this paper is to identify the major causes of claims produced by contractors towards owners in the Egyptian construction industry, and to quantitatively asses the relative importance of these causes from the different points of view of owners, consultants, and contractor. The paper is also to browse the participant's propositions, on how to avoid causes of claims. The paper contains four further sections. First, the causes of claims in literature are then discussed, where a list of claim causes is reviewed. Second the administration of a questionnaire survey is discussed. Third the results of a questionnaire survey are reported to quantitatively rank the causes of claims and browse participant s suggestions as how to avoid them. Finally, a conclusion, recommendations and further work are discussed. Causes of Claims in Literature A plethora of authors have researched claims in international literature and analyzed their causes (Al-Momani 2000; Adrian 1993; Diekmann and Nelson 1985; Jergeas et al. 1994; Kumaraswamy and Yogeswaran 1998; Mcmullan 2003; and Semple et al.; 1994). As a result of the special nature of the Egyptian market in terms of the project parties attitudes and the cultural, political and business environment, causes of claims may differ from other countries worldwide. A synthesis of the causes of claims in international literature has been presented in Abd El-Razek, Bassioni and Abd El-Salam (2007) and modified according to the Egyptian construction industry using semi-structured interviews with 10 experts. The results were in line with the findings of Awad (2005). Table 1 shows the modified causes of claims as per Egyptian construction. Table 1: Modified Causes of Claims as Per Egyptian Construction No. Causes of claims 1 Delays in payments to contractors and resulting cash problems during construction 2 Inferior quality of design, drawings and / or specifications 3 The contract documents have errors, defects and omissions 4 Delays of approval of shop drawings, instructions and decision making 5 Restricted access 6 Faulty and / or late Owner-supplied equipment and material 7 Unbalanced bidding, underestimation and incompetence of contractors 8 Stakeholders involved in the project 9 Relatively low profitability of the construction industry 10 Variations initiated by the owner/consultant (additive/deductive) 11 Acceleration and stop-and-go operations 12 Insufficient time for bid preparation and inadequate investigation before bidding 13 Changed conditions 14 Increase of complexity and scale of building process 15 Delay of Owner representative/ consultant in inspection work 16 Unexpected changes in exchange, interest, and inflation rate 17 Unexpected change in materials prices 76
3 Questionnaire Survey The objective of the questionnaire survey is to measure the importance of each claim cause from the different points of view of project parties (contractor, owner and consultant). The objective is also to collect participants responses on how to avoid the causes of claims. The degree of importance can be estimated through knowing the probability of occurrence of the cause and power of cause to deliver a claim. Multiplying the probability of occurrence by power of the cause can indicate the degree of importance. Questionnaire Design Questionnaire design is a long process that demands careful attention. A questionnaire is a powerful evaluation tool and should not be taken lightly. A questionnaire was designed in this research according to the modified list of causes. The questionnaire consists of four parts, as follows: Part One Contains the respondent s personal information, position, and work information. Part Two Contains sections for causes related to owner/consultant, contractor, and external conditions. In each section the respondent is asked to evaluate each cause of claims according to the probability of occurrence and power to produce a claim on a Likert scale in responses of: never; rarely; normally; frequently; and always, for probability of occurrence and responses of: none; weak; normally; strong; and very strong, for power to produce a claim. Part Three Respondents are asked to arrange causes of claims according to their importance from their points of view, and sought feedback on how to avoid such causes. Part Four Respondents are asked to explain a case of a claim that the respondent would like to share or review. Pilot Survey Before distributing the questionnaire, a pilot survey was conducted where the questionnaire was discussed with experts. Four experts reviewed the questionnaire for clarity, ambiguity and practicality. Experts feedback was that participants may face some difficulty when filling this questionnaire. Also the researcher would face difficulty in finding participants capable of filling out this questionnaire. It was decided among the research team to conduct the survey through personal administration of the questionnaire, in order to overcome the aforementioned problems, which actually proved to be effective in overcoming them. Sampling Approach The questionnaire was distributed to a non-random sample of 300 participants representing the different specializations of contractors, consultants and owners working in different positions (head office and site). The choice of participants was achieved through the Snow Balling sampling technique. The questionnaire was personally handed over to 77
4 respondents, and the interviewer was available to answer questions about questionnaire and to ensure that the questionnaire is rightly administered. This mode of follow up communication led to the completion of 63 questionnaires, and a 20% response rate (10 owners, 15 consultants, and 38 contractors). The rate of response was due to the difficulties faced in gathering responses. The sample constituted of 60% contractors, 25% consultants and 15% owners. The sample could also be classified by 65% public companies and 35% private companies. The scope of the research included different size public and private companies. The task of finding the appropriate person to fill the questionnaire was difficult, as different titles / positions handle claims in companies. For a head office of the organizations, firstly, the contracts department manager or claims department manager was sought. If that was inexistent the technical office manager or the engineer that transacts with that subject was sought. For sites the project manager was sought, and if it was difficult to meet, the technical office engineer was sought. In order to calculate the standard error in the responses of the questionnaire according to Easterby-Smith et al. (2002): Sample size = 2500/E2 If the sample size is 63, then 63 = 2500/E2 E2 = Standard Error (E) = 6.29 % Although the value of the standard error is above 0.05, it can yet be considered acceptable as it is still below Results and Data Analysis To determine the ranking of different causes according to importance from the point of view of contractors, consultants and owners, the researchers used the following equation: Importance index for cause of claim = Severity index of probability of occurrence * Severity index of power of this cause to produce claim. In order the calculate the severity index, first, the data collected from the survey was distributed in tables to obtain frequencies for every response for every cause, in the probability of occurrence and the power of causes to produce claims. Secondly, the severity index is calculated, and finally the causes are ranked according to their importance indices. The formula for calculating the severity index is as follows (Dominowski 1980): a i = Constant expressing the weight given to i. x i = variable expressing the frequencies. i = 0, 1,2,3,4 a 0 = 0, in case of a response of never for probability of occurrence, and never for power a 1 = 1, in case of response of rarely for probability of occurrence, and weak for power 78
5 a 2 = 2, in case of response of normally for probability of occurrence, and normally for power a 3 = 3, in case of response of frequently for probability of occurrence, and strong for power a 4 = 4, in case of response of always for probability of occurrence, and very strong for power The ranking of causes of claims according to the results of each project party is shown in Figure 1. It can be seen from the figure that the top cause of claims is variations initiated by the employer / engineer. Other important causes in their rank order are: unexpected changes in materials prices ; unexpected bidding, underestimation and incompetence of contractors ; contract documents having errors, defects, omissions, and poor management ; and delays in payments to contractors and resulting cash problems during construction. The least important reason causing claims was restricted access. Other low important reasons were, in reverse ranking order: increase of complexity and scale of building process ; delay of owner representative / consultant in inspection of work ; changed conditions ; and faulty and / or late owner-supplied equipment and material. Intermediate ranking causes have been omitted in the figure for illustrative purposes. Figure 1. Highest and Lowest Overall Ranking Causes of Claims 79
6 Differences in Project Party s Responses To quantitatively assess the differences among parties, the Spearman's correlation coefficient was applied to the ranking of contractors and consultants, contractor with owner and consultant with owner. By applying the equation between contractor and consultant, the correlation coefficient obtained was equal to , which can be considered a medium to strong correlation. The correlation coefficient between contractor and owner was 0.7, which can be considered as a medium to strong correlation. The correlation coefficient between consultant and owner was equal to , which can be considered as a strong correlation. The stronger correlation between the consultant and owner can be explained by consultant and owner being jointly responsible for some of the causes and the consultant working on behalf of the owner in projects. This can be seen in Table 2, where the responses of the consultant and owner being much closer to one another for the causes of delays of approval of shop drawings, instructions and decision making, delay of owner representative / consultant in inspection work, and unbalanced bidding, underestimation and incompetence of contractors. Table 2: Ranking of Causes according to their Importance from Contractor, Consultant and Owner Rank No. Causes of claims Ranking contractor consultant owner 1 7 Variations initiated by the employer/engineer (additive/deductive) Unexpected change in materials prices Unbalanced bidding, underestimation and incompetence of contractors Contract documents have errors, defects, omissions, and poor management Delays in payments to contractors and resulting cash problems during construction Relatively low profitability of the construction industry Unexpected changes in exchange, interest, and inflation rate Inferior quality of design, drawings and / or specifications Acceleration and stop-and-go operations Stakeholders involved in the project Delays of approval of shop drawings, instructions and decision making Insufficient time for bid preparation and inadequate investigation before bidding Faulty and / or late owner-supplied equipment and material Changed conditions Delay of owner representative/ consultant in inspection of work Increase of complexity and scale of building process Restricted access
7 The most important cause of claims variations initiated by the employer / engineer received unanimous top ranking from all parties, which shows how important this cause is and the effect it might have in decreasing the number of claims in the industry. The opinions of all three parties were close for the four least ranked causes, such as in insufficient time for bid preparation and inadequate investigation before bidding, restricted access, changed conditions, and increased complexity and scale of building process. The ranking of the cause delays in payments to contractors and resulting cash problems during construction in the owner s point of view (11th) is much lower than that of the contractor and consultant (2nd and 4th, respectively). This is probably due to the owner being responsible for such payments. Avoiding Construction Claims Part three of questionnaire asked the participants to give suggestions for how to avoid claims. As a result of these responses and of discussions within the personal administration of the survey, a number of suggestions have been compiled. In general, avoidance of claims needs real desire and complete coordination between parties. A policy of claims avoidance should be adopted by all concerned with the project. This policy should apply like quality assurance from the day the owner takes the decision to build until the final account is agreed. The compiled suggestions of participants to avoid causes of claims are as follows: Special consideration should be given to an appropriate contract type with a wellbalanced contract. Special consideration for contract clauses dealing with variations / extras, disputes, inspections, approvals, payments, and delays. Owner must allow reasonable time for design team to produce clear and complete drawings and specifications. Reasonable investigation is required from the owner in choosing consultants. Provision of a proper mechanism for processing and evaluating variations. Use of critical path scheduling, cost control, and productivity analysis to monitor progress and detect any changes in schedule, cost and productivity. Enforcing liquidated damage clauses and offering incentives for early completion. Developing human resources in the construction industry, through proper training. This calls for providing incentives such as offering a tax deduction on money spent on training. Also developing human resources applies to construction engineers who lack adequate managerial skills. There is an urgent need for offering training courses in scheduling, time and cost control, information systems, contracting, quantity survey and management of human resources. Contracts should mention the maximum or anticipated time for owner / consultant replies to contractor requests. 81
8 Conclusion and Recommendations The number of construction claims has been increasing and has become a time-consuming and costly element in construction projects in Egyptian. There is no guarantee that claims can be avoided entirely. However, avoiding claims and disputes requires the understanding for causes of claims, and thus this research aimed to identify these causes and possible methods of avoiding claims. A questionnaire survey was used to quantitatively evaluate the causes of claims from literature. The questionnaire was designed and reviewed for clarity, ambiguity and practicality. There was agreement among all parties on choosing "variations initiated by the employer/engineer (additive/deductive)" to be the most important cause of claims in Egypt. Other important causes in their rank order are: unexpected changes in materials prices ; unexpected bidding, underestimation and incompetence of contractors ; contract documents having errors, defects, omissions, and poor management ; and delays in payments to contractors and resulting cash problems during construction. The least important reason causing claims was restricted access. Other low important reasons were, in reverse ranking order: increase of complexity and scale of building process ; delay of owner representative / consultant in inspection of work ; changed conditions ; and faulty and / or late owner-supplied equipment and material. A medium to strong correlation existed between the opinions of the contractor and owner and between the contractor and consultant, whereas, a strong correlation existed between the consultant and owner. This can be explained by the joint responsibility between the consultant and owner towards some of the causes or by the consultant working on behalf of the owner. The recommendations to industry to avoid or at least reduce claims in Egyptian construction are: using well balanced contracts, in terms of the contractor / consultant / and owner rights and responsibilities, such as FIDIC contracts; giving special consideration to contract clauses especially those related to times of owner/consultant replies, approvals, variations, inspections and payments; owner to choose appropriate tendering and awarding methods, as well as appropriate contract types; good choice of experienced consultants, especially in construction management; owner to allow reasonable time for design team to produce clear and complete drawings and specifications; provision of a proper mechanism for processing and evaluating variations and claims in the contract; use of proper project management and control techniques; enforcement of liquidated damage clauses and offering incentives for early completion; presence of a maximum or anticipated time for owner / consultant to reply to contractor request; and all parties to develop their human resources capabilities, especially in the areas of construction and general management skills. It should be noted that many of these recommendations apply to activities happening in the procurement phase and so, more care should be given to this phase of the project. In 82
9 general, it can be said that the owner's choice of contract, procurement strategy, consultants, and contractor sets the tone for claims. Furthermore, a policy of claims avoidance should be adopted by all parties concerned and should be applied in a manner similar to quality assurance from the day the owner takes the decision to build until the final account is agreed. This research opens the door to possible future research. Examples are investigating the causes of change / variation orders, investigating the causes of claims in other Arabic, African, Asian and developing countries, comparing the causes in different countries in light of their surrounding environment. Furthermore, the processes and procedure used in international contracts, such as FIDIC contracts can be investigated as to their application in Egypt, and the effect this might have on claims. Finally, each of the claim causes and suggestions for reducing claims can be researched so as to quantify their effect. References Abd El-Razek, M. E., Bassioni, H. A. and Abd El-Salam, W. A., Investigation into the cuases of claims in Egyptian Building Construction. Proceedings of the 23 rd Annual Conference of the Association of Researchers in Construction ARCOM, September 3 rd 5 th, University of Ulster, Belfast. Al-Moumani HA., Construction delay: a quantitative analysis. International Journal of project Management, 18, 51-9 Awad, A., Measuring the Efficiency of Construction Claim Administration in Construction Companies in Egypt. Master Thesis, Faculty of Engineering, Zagazig University. Basha, I. M., Askar, M. M., Amer, M. I., and Saleb, A. L., Measuring the efficiency of construction claim administration in construction companies in Egypt. Housing and Building Research Center HBRC Journal, 3 (1), Diekmann, J. E. and Giraed, M. J., Are Contract Disputes Predictable. Journal of Construction Engineering and Management, 121 (4), Dominowski, R., Research Methods. Prentice Hall, Englewood Cliffs, New Jersey, USA. Easterby-Smith, M., Thorpe, R. and Lowe, A., Management Research: An Introduction. Sage Publications, London, UK. Hassanein, A. A. G., and El Nemr, W., Claims management in the Egyptian industrial construction sector: A contractor s perspective. Engineering, Construction, and Architectural Management, 15(3), Ip, S. S., An overview of construction claims: How they arise and how to avoid them. Loreman Seminar for Construction Contracting for Public Entities in British Columbia, Canada, October 31, Jergeas, G. F. and Hartman, F. T., Contactors' Construction-Claims Avoidance. Journal of Construction Engineering and Management, 120 (3), Kumaraswamy, M. M. and Yogeswaran, K., Significant sources of construction claims. International Construction Law Review, 15 (1), Marzouk, M., El-Mesteckawi, L. and El-Said, M., Dispute resolution aided tool for construction projects in Egypt. Journal of Civil Engineering and Management, 17 (1), McMullan, j., Trends in construction contract disputes. Electronic Construction Law J., [online] 83
10 Mohamed, K. A., Khoury, S. S., and Hafez, S. M.,, Contractor s decision for bid profit reduction within opportunistic bidding behavior of claims recovery. International Journal of Project Management, 29 (1), Revay, S.G., "Claim Seminar." Special seminar prepared for Macmillan Bloedel Limited, Revay and Associates Ltd., Vancouver, british Columbia. Semple, C. et al., Construction Claims and Disputes: Causes and Cost/Time Overruns. Journal of Construction Engineering and Management, 120 (4),
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS
STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand.
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT M. Salama 1, H. Abd El Aziz 2, H. El Sawah 3 and A. El Samadony 3 1School of Built Environment, Heriot Watt University,
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
Who pays the Money for the Time?
Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency
A Study On Factors Influencing Construction Contract Claim Management
A Study On Factors Influencing Construction Contract Claim Management K.Sundhar #1, N.Nandhini #2 #1 PG Student (M.E Construction Engineering and Management), #2 Assistant Professor ( Department of civil
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: [email protected] 2 Asso.
Analytical Model for Analyzing Construction Claims and Opportunistic Bidding
Analytical Model for Analyzing Construction Claims and Opportunistic Bidding S. Ping Ho, A.M.ASCE, 1 and Liang Y. Liu, M.ASCE 2 Abstract: Construction claims are considered by many project participants
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
Samantha Ip Clark Wilson LLP tel. 604.643.3172 [email protected] D/RJR/682791.1
by Samantha Ip Clark Wilson LLP tel. 604.643.3172 [email protected] D/RJR/682791.1 TABLE OF CONTENTS A. INTRODUCTION...1 B. GENERAL INFORMATION ON THE TYPES OF LIABILITY INSURANCE...1 1. GENERAL LIABILITY
Construction Claims in
Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
Capital Projects. Providing assurance over effective delivery of projects
Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects
Construction Bonds. Vanessa S. Werden 604.408.2033 [email protected]
Construction Bonds Vanessa S. Werden 604.408.2033 [email protected] What is a bond? A bond is a special form of contract whereby one party guarantees the performance by another party of certain obligations. A
Factors Affecting the Completion of Post Graduate Degrees using Distance Mode T. S. V. De Zoysa, The Open University of Sri Lanka [email protected].
Factors Affecting the Completion of Post Graduate Degrees using Distance Mode T. S. V. De Zoysa, The Open University of Sri Lanka [email protected] The Open University of Sri Lanka has been conducting Post
Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals
Journal of Construction in Developing Countries, Vol. 16(1), 41 67, 2011 Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Visuth Chovichien
Project manager services
Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism
The New Standard Construction Contracts: NZS3910, 3916 and 3917
The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of
Influence of Tactical Factors on ERP Projects Success
2011 3rd International Conference on Advanced Management Science IPEDR vol.19 (2011) (2011) IACSIT Press, Singapore Influence of Tactical Factors on ERP Projects Success Shahin Dezdar + Institute for International
15-213. Procurement practices of school districts and charter schools; definitions
ARIZONA AUTHORITY 15-213. Procurement practices of school districts and charter schools; definitions A. The state board of education shall adopt rules prescribing procurement practices for all school districts
Procurement Strategy and Contract Selection
GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works
Procurement guidance Managing and monitoring suppliers performance
Procurement guidance Managing and monitoring suppliers performance Procurement guidance: Managing and monitoring suppliers performance Page 2 of 16 Table of contents Table of contents... 2 Purpose of the
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer
THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE
NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS
NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS THE AUSTRALIAN INSTITUTE OF QUANTITY SURVEYORS THE AUSTRALIAN INSTITUTE OF QUANTITY SURVEYORS NATIONAL COMPETENCY STANDARDS
Document Management Systems in Small and Medium Size Construction Companies in Jordan
Document Management Systems in Small and Medium Size Construction Companies in Jordan Abstract Hesham Ahmad 1, Maha Ayoush 2 and Subhi Bazlamit 3 Document management systems (DMS) are now becoming more
TRAINING NEEDS IN CONSTRUCTION PROJECT MANAGEMENT IN PORTUGAL
INTERNATIONAL CONGRESS ON PROJECT ENGINEERING VALENCIA, September 13-15, 2006 TRAINING NEEDS IN CONSTRUCTION PROJECT MANAGEMENT IN PORTUGAL J. C. Teixeira (s), B. R. Pires Abstract Training in construction
HACC Central Pennsylvania s Community College Harrisburg, PA. Request for Proposal RFP13-08. For. Integrated Marketing Communications Services
HACC Central Pennsylvania s Community College Harrisburg, PA Request for Proposal RFP13-08 For Integrated Marketing Communications Services Issued: Feb. 22, 2013 Deadline for Questions: Response to Questions:
7.4.1 Be required to make exhaustive or continuous on-site reviews;
SUPPLEMENTARY CONDITIONS TO THE CANADIAN STANDARD FORM OF CONTRACT FOR ARCHITECTURAL SERVICES DOCUMENT SIX 2006 EDITION RAIC 6 2006 FRASER HEALTH PROJECTS The following Supplementary Conditions are specific
Evaluating the effects of communication in construction project delivery in Nigeria
Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5): pp 048-054, June, 2014. Copyright 2014 Spring Journals Full Length Research Paper Evaluating the effects of communication
INDEX. bonded contract, 289 insureds, 243. misrepresentation, 291 obtaining, 242
INDEX B non-conforming tender, 284 boiler and machinery insurance, performance bond 241 default by the obligee, 288 coverage, 243 failure to notify, 289 definition of the accident, 245 material variation
Case Study: Ten Document Needs for Schedule Litigation Support
Case Study: Ten Document Needs for Schedule Litigation Support Tulio Sulbaran, Ph.D 1 Abstract - This paper will present record keeping documentation of the construction schedule with regard to litigation.
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, Claims & Counterclaims
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, 469 (ECCM Workshops 3, 4 & 5) Certified Program التقنيات العملية في إعداد الجدول الزمني والمالي اإلدارة الموقعية
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication
King Fahd University of Petroleum and Minerals
King Fahd University of Petroleum and Minerals Department of Construction Engineering and Management CEM 515 Project Quality Management Term Paper Procurement Quality Management In Construction Project
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
DETERMINANTS OF PROJECT MANAGEMENT SUCCESS
DETERMINANTS OF PROJECT MANAGEMENT SUCCESS Gary Walker, Dr Shamil Naoum and Professor Rod Howes South Bank University, School of Construction, London. SW8 2JZ One of the features of the construction industry
Engy Mohamed Abou Sreea khalil Elsayd C.V
First- Personal Data Date of Birth: 01/12/1978 Place of Birth: Cairo Marital Status: Married Position: Associate professor Engy Mohamed Abou Sreea khalil Elsayd C.V Affiliation: Faculty of Mass Communication
IMPACT OF EFFECTIVE ORGANIZATIONAL CHARACTERISTICS ON ADOPTION OF CUSTOMER RELATIONSHIP MANAGEMENT IN MELLI BANK BRANCHES IN KHUZESTAN PROVINCE-IRAN
IMPACT OF EFFECTIVE ORGANIZATIONAL CHARACTERISTICS ON ADOPTION OF CUSTOMER RELATIONSHIP MANAGEMENT IN MELLI BANK BRANCHES IN KHUZESTAN PROVINCE-IRAN Mohammad Ali Enayati Shiraz 1, Elham Ramezani 2 1 Department
EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT
EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT Shreyash Raut 1, S S Pimplikar 2, Karan Sawant 3 1 Research Graduate ME Civil Construction & Management, Civil Engineering,
Information Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1
CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 PART 3G Contracts Standing Orders 2015/16 Definitions Aggregation is the combining together of the total contract value from separate contracts
CHAPTER I INTRODUCTION
CHAPTER I INTRODUCTION 1.1 Introduction Construction accidents are the third most likely cause of work-related injury, after mining and agriculture. For every 100,000 workers in the construction industry,
Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department
Current Position PKR CONSULTING, INC. Founder and Chief Executive Officer, 2004 Present Provides construction consulting, dispute resolution and expert witness services to owners, contractors, subcontractors,
Assessment of Critical Success Factors for Construction Projects in Pakistan
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
Policies and Procedures for CONTRACTOR PERFORMANCE EVALUATION
SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION Policies and Procedures for CONTRACTOR PERFORMANCE EVALUATION Rev. November 1, 2013 This document is a working document that may be updated as necessary to meet
CHAPTER 11 APPEALS AND DISPUTES
CHAPTER 11 APPEALS AND DISPUTES In this Chapter look for... 11. General 11.1 Deleted 11.2 Administrative Appeals 11.3 Disputes 11.4 Alternative Dispute Resolution (ADR) 11. General. The Virginia Public
Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer
Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland
CONSTRUCTION CLAIMS AND DISPUTES: CAUSES AND COST/TIME OVERRUNS
CONSTCTION CAIMS AND DISPTES: CASES AND COST/TIME OVENS By Cheryl Semple, ~ Francis T. Hartman, 2 and George Jergeas 3 AnsrACT: Avoiding construction claims and disputes requires understanding of the contractual
Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia
Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia Anisur Rahman 1 and Muhammad T. Attar 2 1,2 Griffith School of Engineering, Griffith University, Gold Coast Campus, QLD
MODELING OF RISK ASSESSMENT FOR INTEGRATED PROJECT MANAGEMENT SYSTEM IN CONSTRUCTION
MODELING OF RISK ASSESSMENT FOR INTEGRATED PROJECT MANAGEMENT SYSTEM IN CONSTRUCTION Amiruddin Ismail 1, Abbas M. Abd 1 and Zamri Bin Chik 1 1 Civil and Structural Engineering Department, Faculty of Engineering,
NOTE: SERVICE AGREEMENTS WILL BE DRAFTED BY RISK SERVICES SERVICE AGREEMENT
NOTE: SERVICE AGREEMENTS WILL BE DRAFTED BY RISK SERVICES SERVICE AGREEMENT Between: And: XXXXXX (the Contractor") Langara College 100 West 49 th Avenue Vancouver, BC V5Y 2Z6 (the College") The College
Information Technology Project Oversight Framework
State of California California Technology Agency Information Technology Project Oversight Framework SIMM Section 45 Revised April 2011 This Page Intentionally Left Blank California Technology Agency Table
FINANCE AND ACCOUNTING OUTSOURCING AN EXPLORATORY STUDY OF SERVICE PROVIDERS AND THEIR CLIENTS IN AUSTRALIA AND NEW ZEALAND.
FINANCE AND ACCOUNTING OUTSOURCING AN EXPLORATORY STUDY OF SERVICE PROVIDERS AND THEIR CLIENTS IN AUSTRALIA AND NEW ZEALAND. Graham Ray, Accounting Lecturer, School of Commerce and Management, Southern
Guidance Notes for the NEC Engineering and Construction Contract
The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
Construction Project Management in China and Its Development Prospect
CIB TG 23 International Conference, October 2003, Hong Kong Page 1 of 8 Construction Project Management in China and Its Development Prospect Bosen He Email: [email protected] Management School, Tianjin
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49)
CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49) BONDS AND GUARANTEES In difficult economic times, procuring security for performance of obligations will be a significant concern for many parties
Construction Cost Management
Construction Cost Management In the last decade, following the Latham and Egan reports, there have been many significant changes in the role of the construction cost manager. Keith Potts examines the key
Fatemeh Akbari* Master of Industrial Engineering Islamic Azad University, Zahedan Brench, Iran
To Design and to Present a Tool to Prevent Extra Expense Incurring in School Reconstruction Projects (A case study: Reconstruction Department affiliated to School Equipment and Development Unit in Sistan
IN THE SUPREME COURT OF BRITISH COLUMBIA DOROTHY YOUNG SHELL CANADA LIMITED. Brought under the Class Proceedings Act, R.S.B.C. 1996, c.
IN THE SUPREME COURT OF BRITISH COLUMBIA No. L021060 Vancouver Registry Between: And: DOROTHY YOUNG SHELL CANADA LIMITED Brought under the Class Proceedings Act, R.S.B.C. 1996, c. 50 Plaintiff Defendant
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Lina Warrad. Applied Science University, Amman, Jordan
Journal of Modern Accounting and Auditing, March 2015, Vol. 11, No. 3, 168-174 doi: 10.17265/1548-6583/2015.03.006 D DAVID PUBLISHING The Effect of Net Working Capital on Jordanian Industrial and Energy
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
PRIME CONSULTANT SERVICES
GUIDELINES FOR Professional Engineers providing PRIME CONSULTANT SERVICES 1.0 INTRODUCTION 1.1 PURPOSE OF GUIDELINES The "Guidelines for Professional Engineers providing Prime Consultant Services" have
Construction Change Orders
Construction Change Orders Michael E. Purdy Contracts Manager University of Washington (206) 221-4235 [email protected] 1 Agenda Tools to Prevent Change Orders 4 Elements of Change Orders Authorization
Home Building Protection Review Consultation Responses
Home Building Protection Review Consultation Responses November 2014 Contents 1 Introduction 1 2 Response overview 2 3 The insurance model 3 First resort model 4 Mandatory last resort fidelity fund 4 Voluntary
Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee
FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman
JOB SATISFACTION AND EMPLOYEES WORK PERFORMANCE: A CASE STUDY OF PEOPLE S BANK IN JAFFNA PENINSULA, SRI LANKA
JOB SATISFACTION AND EMPLOYEES WORK PERFORMANCE: A CASE STUDY OF PEOPLE S BANK IN JAFFNA PENINSULA, SRI LANKA Balasundaram NIMALATHASAN University of Jaffna, Sri Lanka Associate Professor PhD Valeriu BRABETE
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service
RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which
1 OF 7. there will be few "surprises" as the work progresses.
1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result
Bonding for Contractors. Barrie Construction Association September 17, 2015
Bonding for Contractors Barrie Construction Association September 17, 2015 1 Topics What do bonds do? How does a bond benefit you? How do you get a bond? What are the information requirements? What is
GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES
GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES GENERAL CONDITIONS OF CONTRACT FOR MINOR WORKS PAGE 1 BASE D ON WA LOCAL GOVERNMENT ASSOCIATION MODEL 2010 TABLE OF CONTENTS 1 INTERPRETATION 2 RISE
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector
The Role of Financial Analysis Ratio in Evaluating Performance. (Case Study: National Chlorine industry)
JUNE 213 The Role of Financial Analysis Ratio in Evaluating Performance (Case Study: National Chlorine industry) Abdel- Rahman kh. El- Dalabeeh Accounting Department, Faculty of Finance and Business Administration,
User Resistance Factors in Post ERP Implementation
User Resistance Factors in Post ERP Implementation Sayeed Haider Salih 1 e-mail: [email protected] Ab Razak Che Hussin 2 e-mail: [email protected] Halina Mohamed Dahlan 3 e-mail: [email protected] Author(s)
Risk Management in Construction Projects
Risk Management in Construction Projects Seyed Hossein Abedian Kalkhoran 1 Gholamali Liravi 2 Fereshte Rezagholi 3 1 Me Civil (C & M) Student, Mit College, University Of Pune, Pune, India, 1 Me Civil (C
National Commission for Academic Accreditation & Assessment
National Commission for Academic Accreditation & Assessment Standards for Quality Assurance and Accreditation of Higher Education Programs Evidence of Performance Judgments about quality based on general
June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers
John Keel, CPA State Auditor An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers Report No. 08-038 An Audit Report on The Department of Information
Australian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1)
AS 4300 1995 (Incorporating Amendment No. 1) Australian Standard General conditions of contract for design and construct This Australian Standard was prepared by Committee OB/3, General Conditions of Contract.
Explaining an architect s services. General information on the usual tasks undertaken by an architect
Explaining an architect s services General information on the usual tasks undertaken by an architect June 2008 What an architect may do for you Introduction The root cause of disputes and complaints against
Multi-Dimensional Success Factors of Agile Software Development Projects
Multi-Dimensional Success Factors of Agile Software Development Projects Nagy Ramadan Darwish Department of Computers and Information Sciences Institute of Statistical Studies and Research Cairo University
Contract Management. Brief 22. Public Procurement. September 2011
Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This
Master of business administration. construction industry concentration
Master of business administration construction industry concentration About the program Introduction The construction industry in Egypt is a major contributor to the Egyptian economy and one of its fastest
C.V - PERSONAL INFORMATION: \ P.B. 45744, Riyadh11522 Fax\0096612089030. - Scientific Degrees:
- PERSONAL INFORMATION: C.V \ P.B. 45744, Riyadh11522 Fax\0096612089030 [email protected] [email protected] http://faculty.ksu.edu.sa/i-homaidan - Scientific Degrees: - BA, College of social
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
ICAO Procurement Process Briefing
ICAO Procurement Process Briefing The following is a briefing in an effort to provide the reader with an insight into the ICAO Technical Co-operation Bureau s Procurement Process and role in relation to
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
