BACKGROUND REPORT for the Peoria-Smith Station Area Plan

Size: px
Start display at page:

Download "BACKGROUND REPORT for the Peoria-Smith Station Area Plan"

Transcription

1 BACKGROUND REPORT for the Peoria-Smith Station Area Plan Peoria-Smith station I-225 Corridor City of Aurora October, 2009

2 Acknowledgements Mayor Mayor Ed Tauer City of Aurora Planning Department Robert Watkins, Director John Fernandez, Comprehensive Planning Manager Loretta Daniel, Principal Planner Huiliang Liu, Principal Planner Ed Armold, Principal Planner Public Works Dick Havercamp, Manager of Traffic Services Rick Hunter, Project Engineer Chris Carnahan, Operations Manager Parks and Recreation Jay Pierce, Principal Planner Curt Bish, Principal Planner RTD FasTracks Team Larry Warner, I-225 LRT Corridor Project Manager Bill Sirois, Manager of Transit Oriented Development Michael Baker Corp. Dwight Schock, Vice President Pete Hankovsky, Consultant Deputy Project Manager Consultant Team Crandall Arambula PC, Prime Consultant George Crandall, Principal Don Arambula, Principal Erin Carter, Associate/Project Coordinator Julia Reed, Urban Designer ArLand Land Use Economics Arleen Taniwaki, Principal and Manager Navjoy Consulting, Traffic/Transportation Planning Navin Nageli, Principal Karl Packer, Associate Vice-President Hartwig & Associates, Infrastructure Analysis/Cost Estimates Danielle Smith, Civil Engineer

3

4 Table of Contents Introduction Overview and Existing Conditions... 2 Public Involvement... 4 Vision and Objectives... 5 Fundamental Concept... 6 Build-Out Concept... 8 Land Use Land Use Public Space Circulation Pedestrian and Bicycle Circulation Automobile and Bus Circulation New and Enhanced Streets Street Categories Implementation Strategy Overview RTD Opening Day Projects RTD Phase 2 Projects Catalyst Projects Private Development Projects Design Standards Appendix Traffic Analysis...To Be Added Cost Estimates...To Be Added

5

6 Table of Figures Figure 1. Existing Conditions Diagram... 3 Figure 2. Community Workshop Figure 3. Community Workshop Figure 4. TOD Character Diagram... 5 Figure 5. Fundamental Concept Diagram... 7 Figure 6. Development Table... 8 Figure 7. Build-Out Concept Diagram... 9 Figure 8. Station Areas - View North Figure 9. Station Areas - View South Figure 10. Land Use Diagram Figure 11. Park Blocks Photograph Figure 12. Public Spaces Table Figure 13. Public Spaces Diagram Figure 14. Pedestrian and Bicycle Circulation Diagram Figure 15. Proposed Smith Road Auto & Truck Routes Figure 16. Automobile and Bus Circulation Diagram Figure 17. New and Enhanced Streets Diagram Figure 18. Street Categories Diagram Figure 19. Proposed Nome Street Types Figure 20. Proposed Nome Park Block Street Section Figure 21. Proposed Nome Retail Street Section Figure 22. Proposed Nome Commercial/Office Street Section Figure 23. Existing 33rd Avenue Section Figure 24. Proposed 33rd Avenue Section Figure 25. Existing Moline Street Section Figure 26. Proposed Moline Street Section Figure 27. Proposed Neighborhood Street Section Figure 28. Proposed Neighborhood Park Street Section Figure 29. Build-Out Concept Diagram Figure 30. Proposed Opening Day Projects Diagram Figure 31. Proposed RTD Phase 2 Projects Diagram Figure 32. Catalyst Projects Diagram Figure 33. Private Development Projects Diagram Figure 34. Ground-Floor Retail and Commercial Examples Figure 35. Ground-Floor Uses Diagram Figure 36. Buildings Built to Property Line Photographs Figure 37. Required Build-To Lines Diagram Figure 38. Street Edge Activated by Use Figure 39. Street Edge Activated by Doorways and Windows Figure 40. Required Active Edges Diagram Figure 41. Above Grade Residential Parking Figure 42. Above Grade Office Parking Figure 43. Building Heights Diagram... 53

7

8 Introduction

9 Overview and Existing Conditions The Smith-Peoria Station Area Plan is part of an ambitious transit-oriented development (TOD) planning process undertaken by the City of Aurora, Colorado, in partnership with the Regional Transportation District (RTD). The Smith-Peoria Station will be located near the Peoria Street and I-70 junction, a vehicular gateway to the City of Aurora and the Fitzsimons Medical Complex the City of Aurora s primary employment center. This location makes the Smith-Peoria station area regionally accessible and highly visible. The Smith-Peoria Station provides regional access to both the Interstate 225 (I-225) light rail and the East Corridor commuter rail. The I-225 light rail corridor will provide service south, through the City of Aurora, to the Southeast light rail corridor. The East Corridor commuter rail will provide east-west service to the Denver International Airport and downtown Denver. The Smith-Peoria Station will also provide park-n-ride facilities and bus transfers. Plan Purpose The Smith-Peoria Station Area Plan provides transit-oriented development that is integrated with the regionally accessible commuter and light rail station and bus transfer and park-nride facilities. The Smith-Peoria Station Area Plan serves as a tool to proactively plan for development rather than reactively respond to development pressures. This Plan is not intended to mandate redevelopment for property owners who do not wish to redevelop. Rather it provides a framework for future development, should existing property owners choose to redevelop, sell or relocate. Concurrent Planning The Smith-Peoria Station Area Plan was developed concurrently with the following: Smith-Peoria Station Environmental Evaluation (EE) RTD s analysis of alternative trackway alignments, transit platforms, and park-n-ride and bus facilities. The Smith-Peoria Station Area Plan reflects RTD s preferred EE options Strategic Parking Plan and Program Study The City of Aurora s projected commuter parking demand associated with the addition of light rail transit. The Smith-Peoria Station Area Plan satisfies the projected demand for 930 parking spaces the high-end 2015 projection identified in the study as well as the projected parking demand established in the I-225 Environmental Evaluation Fitzsimons Area Wide Multi-Modal Transportation Study City of Aurora study of the transportation needs in the Fitzsimons area associated with new development and the cumulative impacts of development along the entire I-225 transportation corridor. The Smith-Peoria Station Area Plan informs the land use and circulation recommendations in this study Existing Conditions Existing Land Use Existing land uses within 1/2-mile of the Smith-Peoria Station are primarily industrial uses, including warehousing and manufacturing facilities, a concrete batch plant and the City of Aurora water treatment plant. There are also correctional and detention facilities including the Immigration and Naturalization Services (INS) and the Denver County Jail. Other uses along Peoria Street include a family health facility, a church, a fire station and various retail and commercial uses. The Smith-Peoria Station is located within one mile of Stapleton, the largest new urbanist project in the United States, which includes residential, commercial and office development in a suburban context. In the Smith-Peoria station area, there are 22 properties with high potential for transit-supportive redevelopment. These properties, identified on the Existing Conditions Diagram, are either vacant or under utilized and are located in the proximity of the planned light rail and commuter rail station. Existing Transportation The primary north-south vehicular route in the study area is Peoria Street and the primary east-west routes are, I-70, Smith Road, Baranmor Parkway and Fitzsimons Parkway. The Union Pacific (UP) freight rail alignment runs east-west through the study area. Vehicles traveling on Peoria Street are frequently delayed by freight trains crossing this at-grade intersection. Delays are likely to increase with the addition of the East Corridor commuter rail. Sand Creek Regional Greenway Trail, a 14-mile pedestrian and bicycle multiuse trail, connects to the High Line Canal, Tollgate Creek and the Platte River Greenway in Commerce City. Smith Road provides continuous eastwest automobile and truck access from Highway E-470 to Colorado Boulevard. The planned Smith-Peoria Station will impact Smith Road between Moline and Peoria streets. A proposed realignment of Smith Road is described in the circulation section of this document. Planned Projects The study area includes the following planned projects: Park-n-Ride and Bus Transfer RTD has identified vacant parcels (5) and (6) as potential locations for park-nride and bus transfer facilities Aurora Housing Authority Mixed-income multi-family housing planned on a 5-acre site INS Expansion of current detention facility to accommodate 1200 additional beds Baranmor Ditch Reconfiguration of stormwater drainage-way to feed into to Sand Creek 2 Smith-Peoria Station Area Plan DRAFT

10 QUARI ST. C ST. D ST. E ST. MOLINE ST. LIMA ST. 1/2 Mile Radius INTERSTATE 70 E. 40TH AVE. 1/4 Mile Radius Planned Light Rail Platform E. 39TH AVE. E. 37TH AVE. Planned Commuter Rail Platform Vehicle Delays E. 38TH AVE. EXISTING Denver County Jail LEGEND UP Freight Rail Alignment Automotive Services Warehouse Warehouse Vacant 5 Vacant 6 Vacant 7 Warehouse Light Rail Platform Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment Warehouse Warehouse Warehouse Oakland Business Park Layton Trucking Company Commercial Businesses Convenience Restaurants Cement Batch Plant Multiple Ownerships Warehouses City of Aurora Water City of Aurora Vacant Automotive Testing 22 U-Store Self-Storage E. 33RD AVE OAKLAND ST. 20 E. 30THAVE. 21 SAND CREEK REGIONAL TRAIL Stapleton INS S A N D C R E E K EXISTING Planned Baranmor Ditch Planned Aurora Housing Authority E. 31ST AVE. E. 3OTH AVE. Planned INS Expansion Sand Creek Regional Greenway Trail E. 33RD AVE. BARANMOR PKWY. Morris Heights Neighborhood FITZSIMONS PKWY. Figure 1: Existing Conditions Diagram (2006 Aerial Photograph) Introduction 3

11 Public Involvement The Smith-Peoria Station Area Plan was created in response to the public s vision for future growth and is based on information gathered through an extensive community involvement process that included several stakeholder meetings and three community workshops. Community Workshops Three community workshops for the Smith-Peoria Station were held at North Middle School, Montview Boulevard, Aurora, CO. Community Workshop 1 April 3, 2008 Participants provided input that was incorporated into the Plan s objectives, described on the following page. Community Workshop 2 July 23, 2008 Participants provided comments on land use and circulation alternatives and selected their preferred alternative. Figure 2. Community Workshop #1 Station Discussion Group Community Workshop 3 November 5, 2008 Participants provided comments on the refined preferred land use and circulation alternative. During each workshop, community input was documented using individual response sheet questionnaires. A summary record of public input received was produced for each of the three workshops. Prior to each public workshop, additional stakeholder meetings were conducted with property owners, residents, City staff, and RTD staff. Figure 3. Community Workshop #2 Station Discussion Group 4 Smith-Peoria Station Area Plan DRAFT

12 Vision and Objectives Station Area Vision Each of the nine stations on the I-225 light rail corridor are envisioned to have unique characteristics that complement the other stations to define the overall character of the corridor. Smith-Peoria Station Area Vision TOD Character Employment center Transportation Functions Commuter rail, light rail and bus transfer station Park-n-ride facility Quebec St Havana St. East Light Rail Corridor Peoria St. Montview Blvd. Colfax Ave. Peoria St. Smith-Peoria Chambers Rd. Montview Fitzsimons-Colfax 13th Avenue Primary Land Uses Employment with some housing Plan Objectives Objectives for the Smith-Peoria Station Area Plan were derived from public input gathered during Community Workshop 1. The Plan s objectives are to: Improve multi-modal connectivity and access to/from the station Locate the station platform west of Peoria Street Address auto traffic impacts on adjacent streets Respect and protect existing neighborhoods Provide a mix of uses to serve the neighborhood Create a safe pedestrian environment at the station The station area vision and plan objectives were used to guide the planning process and evaluate design alternatives throughout the project. Leetsdale Dr. Legend Light Rail Station Light Rail Alignment Commuter Rail Alignment Employment Center Residential Neighborhood Employment and Residential Downtown 6th Ave. Alameda Ave. Mississippi Ave. I-225 Light Rail Corridor Jewell Ave. Iliff Ave. Yale Ave. Nine Mile Abilene Florida Iliff Metro Center Figure 4. TOD Character Diagram Introduction 5

13 Fundamental Concept The Smith-Peoria Station Area supports the planned light rail and commuter rail stations by providing bus transfer and park-n-ride facilities in a transit-oriented office district that includes supporting retail, commercial and housing uses. The Fundamental Concept Diagram illustrates the key concepts of the Smith-Peoria Station Area Plan. These concepts, listed below, respond to the community s vision and objectives. Primary Station Access Street 30th Avenue and Nome Street serve as the primary pedestrian, bicycle and auto route through the station area, connecting the existing Morris Heights neighborhood to the Smith-Peoria Station and the transitsupportive commercial development on Nome Street Truck Route Smith Road, Moline Street and 33rd Avenue serve as the primary truck route through the station area. This route bypasses Nome Street allowing trucks to move efficiently through the station area, reducing conflicts with pedestrian, bicycle and vehicular traffic Transit Supportive Retail Retail uses proposed along Nome Street north of Station Avenue generate activity near the commuter and light rail platforms and provide goods and services for area residents, employees, and transit riders Transit-Supportive Office Mediumand high-density office development located Office development located adjacent to commuter and light rail stations supports higher levels of potential ridership by encouraging employees to commute by transit. Regional Greenway Extension A series of public green spaces between the existing Sand Creek Regional Greenway and Station Avenue extend the open space into the station area. The greenway extension serves as an organizing amenity for adjacent office and housing development Station Parking and Bus Transfers Planned RTD park-n-ride and bus transfer facilities will encourage transit ridership by providing convenient commuter parking and bus connections to local and regional destinations. These facilities have been located to provide direct access to the station while maximizing transit-oriented development potential adjacent to the station. 6 Smith-Peoria Station Area Plan DRAFT

14 MOLINE ST. Interstate 70 Primary Station Access Street Truck Route To Union Station To Stapleton Transit Supportive Retail Planned Commuter Rail Alignment Planned Light Rail and Commuter Rail Station RTD STATION AVE. Planned Light Rail Alignment Grade Separated Rail Crossing Station Parking and Bus Transfers To Denver Intl. Airport Transit Supportive Office Regional Greenway Extension 33RD AVE. Sand Creek Greenway 30th Avenue 30TH AVE.. Existing Morris Heights Neighborhood To Montview Light Rail Station Figure 5. Fundamental Concept Diagram Introduction 7

15 Build-Out Concept The build-out concept illustrates a realistic vision of the desired form and density of the station area once all identified parcels are fully developed. The Build-Out Concept Diagram is an essential tool for identifying and creating policy and regulatory updates that define permitted density, parking requirements, and building heights in the station area. Within a gross area of acres, 68.8 acres of development and redevelopment are proposed. The remaining 32.6 acres include new streets, sidewalks, RTD trackway and the RTD bus transfer area. No transit-oriented redevelopment is anticipated for existing parcels which are indicated in light gray on the build-out diagram. As these parcels redevelop over time, transit-supportive infill is encouraged. The build-out diagram identifies areas A, B and C. Each of these development areas include public and private projects that are likely to redevelop within a similar time frame. The development table below indicates each area s development potential. A potential 1,000 space surface parkn-ride lot has been identified north of the Union Pacific (UP) rail line within the City and County of Denver. This lot is identified for future expansion purposes only and would require the review and approval of the City and County of Denver and the property owner(s). Development Area A: Gross Area 22.9 (indicated by blue outline on the Build-Out Concept Diagram) Land Use Site Area (Acres) Retail 5.3 Station Plaza ,700 SF (ground fl oor) RTD Structured Parking 3.5 1,200 SP 302,400 SF RTD Surface Parking SP 487,100 SF Stormwater Detention 1.7 Development Area 18.7 Acres*** Net Density (Dwelling Units per Acre) Dwelling Units (DU) or Parking Spaces (SP) Total Area by Use (Square Feet) Development Area B: Gross Area 31.8 (indicated by red outline on the Build-Out Concept Diagram) Site Area Net Density Land Use Total Area by Use (Acres) (Dwelling Units per Acre) Dwelling Units (DU) (Square Feet) Office ,680,000 SF Commercial * 36,000 SF (ground fl oor) Public Space 2.2 Development Area 21.2 Acres*** Development Area C: Gross Area 46.7 (indicated by black outline on the Build-Out Concept Diagram) Land Use Site Area Net Density (Acres) (Dwelling Units per Acre) Dwelling Units (DU) Total Area by Use (Square Feet) Office ,000 SF Housing ,700 ** 1,829,330 SF Public Space 3.9 Development Area 28.9 Acres*** 68.8 Acres*** TOTAL DEVELOPMENT AREA Figure 6. Smith-Peoria Station Development Table (by area) * The acreage of ground-fl oor commercial uses that are located within offi ce blocks has been included in the offi ce site area. ** Housing estimates assume a 1,000 SF dwelling unit size. *** Acreage excludes streets, sidewalks, RTD trackway and the RTD bus transfer area. 8 Smith-Peoria Station Area Plan DRAFT

16 A ST. B ST. C ST. D ST. E ST. LIMA ST. E. 39TH AVE. E. 37TH AVE. 1/4 Mile Radius Potential Potential 1,000 Space Park-n-Ride Possible Overpass/Underpass MOLINE ST. Area A LEGEND Light Rail Platform E. 33RD AVE. OAKLAND ST. INS Area B BARANMOR PKWY. 1/2 Mile Radius Area C RTD Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment RTD Park-n-Ride E. 30THAVE. QUARI ST. E. 31ST AVE. E. 3OTH AVE. Retail Mixed Use Office (Retail/Com./Office/Housing) Mixed-Use Housing (Retail/Com./Housing/Office) RTD Structured Parking Surface Parking Station Plaza Stormwater Detention Planned Public Space Existing Public Space Existing Building Existing Parcel S A N D C R E E K Build-Out Summary Development Area: 67.7 Acres Retail...51,700 SF Commercial...36,000 SF Office...2,200,000 SF Housing...1,700 Dwelling Units RTD Park-n-Ride...1,980 Spaces Proposed Public Space Acres Note: Build-out Summary totals have been rounded FITZSIMONS PKWY. Figure 7. Build-Out Concept Diagram Introduction 9

17 The build-out illustratives demonstrate the land uses, transportation improvements and conceptual massing that may be achieved through implementation of the Smith-Peoria Station Area Plan. LEGEND: RTD Light Rail Station RTD Park-n-Ride Light Rail Alignment Retail Mixed-Use Office (Office/Commercial) Mixed-Use Housing (Retail/Commercial/Housing/Office) RTD Structured Parking Surface Parking Private Greenspace Proposed Public Space Enhanced Public Space Existing Public Space Existing Building Existing Parcel BARANMOR PKWY. 30TH AVE. Figure 8. Smith-Peoria Station Area View North 10 Smith-Peoria Station Area Plan DRAFT

18 30TH AVE. BARANMOR PKWY. MOLINE ST. 33RD. Figure 9. Smith-Peoria Station Area View South Introduction 11

19

20 Land Use

21 Land Use The proposed land use concept provides transit-supportive office and housing uses that capitalize on the area s regional accessibility and support the planned commuter and light rail station. The recommended land uses are consistent with the Plan s fundamental concept, the community s objectives, and planned projects. The mixed-use designation on the Land Use Diagram indicates that a vertical mix of uses is permitted. Private parking should be located on all residential and office sites. Where surface lots are not indicated on the diagram, above- or below grade parking should be provided. Mixed-Use Office Proposed office uses near the Smith- Peoria Station will support commuter rail and light rail by providing a base of users who ride transit for commuting purposes. The office uses are located: Adjacent to desirable amenities, including two proposed public spaces Along transportation corridors that provide good drive-by visibility and regional access Peoria Street and Smith Road On parcels sized to accommodate Class A office building footprints On parcels sized to accommodate adequate on-site parking that meets accepted real estate market requirements Mixed-Use Housing The proposed housing uses will provide a base of residents near the Smith-Peoria Station who will support transit-ridership by using commuter and light rail transit as an alternative to driving. The housing uses will establish a desirable neighborhood that: Provides mixed-income and market rate housing options, including rental and owned units Provides a mix of housing types including condominiums, apartments and townhouses Is located adjacent to desirable residential amenities, including proposed parks, the existing Sand Creek Regional Greenway Trail, and the planned commuter rail and light rail stations Incudes concealed on-site parking that meets accepted real estate market requirements Incompatible uses exist in areas where mixed-use housing is proposed. These uses include the Immigration and Naturalization Services (INS) detention facility, a concrete batch plant and a City of Aurora water treatment plant. While these uses may redevelop in the long term, the following strategies should be taken to lessen the shortterm impacts: Provide landscape screening Establish building setbacks Orient buildings away from undesirable uses Retail Retail uses in the station area are proposed along an extension of Nome Street, southwest of the Smith-Peoria Station. Retail uses will generate activity near the commuter and light rail station and provide goods and services for area residents, employees and transit riders. Retail in this location will benefit from the drive-by visibility and regional accessibility created by the realignment of Smith Road to Nome Street. Retail uses should be limited to businesses that engage in the sale of merchandise or that are restaurants. These uses will activate the station by providing up to 18 hours of daily activity and eyes on the station The Implementation Strategy in this document provides further detail on the recommended ground-floor retail uses and proposes locations for groundfloor commercial uses as well. RTD Structured Parking An RTD park-n-ride structure for commuter rail and light rail transit patrons will be built south of Smith Road and west of Peoria Street. The parking structure will provide up to 1,200 spaces on three levels accommodating some of RTD s projected need for 1,900 parking spaces by RTD Surface Parking An RTD surface park-n-ride lot is planned for commuter rail and light rail transit patrons. The lot location is planned for the area south of Smith Road, on the east side of the Nome Street extension. The surface parking lots can provide up to 780 spaces accommodating RTD s projected need for 1,900 parking spaces by A potential surface park-n-ride lot has been identified north of the Union Pacific (UP) rail line within the City and County of Denver. While not part of the Smith-Peoria Station Area Plan, a park-n-ride in this location could serve transit riders commuting from areas north of the UP and help commuters avoid the delays caused by freight rail trains crossing Peoria Street. This lot is identified for future expansion purposes only and would require the review and approval of the City and County of Denver and the property owner(s). Stormwater Detention Stormwater detention basins are a planned element of RTD s park-n-ride facilities. These areas are intended to function as flood control facilities, collecting stormwater runoff from surrounding development and parking lots. These detention areas should be designed as attractive, vegetated areas. A planned detention basin is located between Moline and Nome streets. Public spaces are described in detail on the following page. 14 Smith-Peoria Station Area Plan DRAFT

22 A ST. B ST. C ST. D ST. E ST. LIMA ST. E. 39TH AVE. 1/4 Mile Radius Potential E. 37TH AVE. Possible Overpass/Underpass MOLINE ST. STATION AVE. LEGEND Concrete Batch Plant City of Aurora Water Treatment Light Rail Platform Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment UP Freight Rail Alignment E. 33RD AVE. OAKLAND ST. Planned INS Detention Facility Existing INS E. 30THAVE. BARANMOR PKWY. Aurora Housing Authority QUARI ST. 1/2 Mile Radius E. 31ST AVE. E. 3OTH AVE. RTD RTD Park-n-Ride Mixed Use Office (Retail/Com./Office/Housing) Mixed-Use Housing (Retail/Com./Housing/Office) Retail RTD Structured Parking RTD Surface Parking S A N D C R E E K Stormwater Detention Planned Public Space Existing Public Space Existing Building Existing Parcel FITZSIMONS PKWY. Figure 10. Land Use Diagram Land Use 15

23 Public Space Public spaces in the Smith-Peoria Station area provide locations for passive recreation and serve as visual amenities for nearby office and housing development. The Public Spaces Diagram on the following page identifies key locations for proposed public spaces including: Station Plaza An attractive passthrough area for transit patrons that includes trees, planting beds, and benches Moline Park A green amenity with opportunities for informal, passive recreation that will attract highdensity office uses Pedestrian Greenway A pedestrian and bicycle pass-through that provides shared green space for adjacent housing Nome Greenway A linear organizing feature for the station area that serves as an off-street pedestrian and bicycle connection between the existing Morris Heights neighborhood, the proposed Nome retail uses, the Smith-Peoria Station, and Station Park Station Park A public space located south of the proposed park-n-ride facilities, Station Park will serve as a window to the station platform for office uses to the south Baranmor Park An informal, neighborhood park that will serve as an amenity for adjacent high-density housing uses The proposed and enhanced public spaces will: Serve as focal points for new development Support high-density office development and viable market-rate housing Be publicly accessible at all hours Figure 11. Pedestrian Greenway, Portland, Oregon The Public Spaces Table below indicates a total of 7.2 acres of proposed public space within the Smith-Peoria station area. Public Spaces Location Proposed Area (Acres) Station Plaza 1.1 Moline Park Pedestrian Greenway Nome Greenway Station Park Baranmor Park TOTAL PROPOSED PUBLIC SPACE Acres Figure 12. Public Spaces Table 16 Smith-Peoria Station Area Plan DRAFT

24 A ST. B B ST. ST. C ST. D ST. E ST. LIMA ST. E. 39TH AVE. E. 37TH AVE. 1/4 Mile Radius Potential Station Plaza (1.1 Acres) SMITH RD. MOLINE ST. Moline Park (1.0 Acres) Pedestrian Greenway (1.0 Acres) STATION AVE. E. 33RD AVE. OAKLAND ST. INS Station Park (1.2 Acres) Baranmor Park (1.1 Acres) BARANMOR PKWY. BARANMOR PKWY. 1/2 Mile Radius Nome Park Blocks (1.8 Acres) E. 30TH AVE. QUARI ST. E. 31ST AVE. E. 3OTH AVE. LEGEND Light Rail Platform Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment RTD RTD Park-n-Ride S A N D C R E E K Redevelopment Parcel Planned Public Space Existing Public Space Floor Commercial Existing Building Existing Parcel FITZSIMONS PKWY. Figure 13. Public Spaces Diagram Land Use 17

25

26 Circulation

27 Pedestrian and Bicycle Circulation The pedestrian and bicycle circulation system provides safe, direct, convenient and attractive pedestrian and bicycle connections between the Smith-Peoria Station, the existing Morris Heights neighborhood and the Sand Creek Regional Trail, and other key regional destinations. The Pedestrian and Bicycle Circulation Diagram incorporates the existing and planned bicycle routes identified by the Northwest Aurora Bicycle and Pedestrian Master Plan. In order to provide a regional station access system, pedestrian and bicycle routes are identified for the entire station area. Routes within the City and County of Denver would require the review and approval from the local agencies prior to implementation. Pedestrian Circulation Recommended on- and off-street pedestrian routes in the Smith-Peoria station area promote transit use by providing walkable connections between the existing Morris Heights neighborhood, the planned Smith- Peoria Station and proposed office and housing development. Pedestrian routes within the station area should comply with City of Aurora Urban Street Standards and include the following elements: Wide sidewalks Street trees Special paving Special lighting Bicycle Circulation The recommended bicycle network in the Smith-Peoria station area will serve as an amenity for development and contribute to a significant reduction in vehicle miles traveled by providing an alternate mode of transportation within the station area. This network is a combination of on- and off-street bicycle routes that provide connections between existing and proposed neighborhoods and key destinations, including the Stapleton development, Park Lane Elementary School, proposed public space amenities and the Fitzsimons Medical Complex (Aurora s primary employment center). This network At a minimum, bicycle routes should comply with City of Aurora Urban Street Standards and may include the following design elements: Bicycle route signs Adequate space for cyclists within bike lanes or on off-street bikeways Cyclist-activated, motion-detecting crossing signals and special surfaces such as painted lanes, striping and bike box treatments at major intersections Storage lockers and covered racks conveniently located at the station Protected Bike Paths Protected bike paths provide comfortable dedicated routes separated from vehicular traffic by a raised curb and planting zone for riders of all ages and abilities. The designated bike route should also be differentiated from the sidewalk through use of striping, signage and paving materials. A protected bike path is recommended on the west side of Nome Street and the south side of 30th Avenue west of Peoria Street. The protected bike path provides access to the Smith- Peoria Station from the existing Morris Heights neighborhood and from proposed housing development south of 33rd Avenue. Bicycle Lanes On-street bicycle lanes dedicated lanes located within the roadway provide commuter bicyclists with on-street routes to key destinations and connections to off-street bicycle systems. The following north-south streets should include bicycle lanes: Peoria Street Moline Street Nome Street north of 37th Avenue The following east-west streets should include bicycle lanes: E. 40th Avenue (west of Peoria Street) Smith Road (west of Nome Street) E. 33rd Avenue Baranmor Parkway E. 30th Avenue (east of Peoria Street) Multi-Use Paths The existing Sand Creek multi-use path, located along the south bank of Sand Creek, serves as an off-street route for walkers, joggers, and recreational and commuter bicyclists. This route includes a combined pedestrian and bicycle path that connects east to the High Line Canal and Tollgate Creek trails and west to the Platte River Greenway trail in Commerce City. Multi-Use Underpass A multi-use underpass is proposed to connect pedestrians and bicyclists from the Nome Street extension to the existing Nome Street north of 37th Avenue. This underpass will provide a safe, convenient alternative to the Peoria Street route, which has over 30,000 vehicle trips per day and regular delays at the Peoria Street/ Union Pacific rail intersection. 20 Smith-Peoria Station Area Plan DRAFT

28 LIMA ST. MOLINE ST. QUARI ST. B ST. A ST. B ST. C ST. D ST. E ST. To Montbello Neighborhood INTERSTATE 70 1/2 Mile Radius E. 40TH AVE. E. 39TH AVE. 1/4 Mile Radius Potential E. 38TH AVE. E. 37TH AVE. Possible Overpass/Underpass To Stapleton STATION AVE. E. 33RD AVE. E. 33RD AVE. BARANMOR PKWY. To East Morris Heights Neighborhood OAKLAND ST. INS West Morris Heights Neighborhood LEGEND Light Rail Platform E. 3OTH AVE. E. 31ST AVE. To Park Lane Elementary School Commuter Rail Platform RTD Light Rail Alignment Commuter Rail Alignment RTD Park-n-Ride Pedestrian Circulation To Stapleton Sand Creek Open Space S A N D C R E E K Protected Bicycle Path Bicycle Lanes Multi-use Path Multi-use Underpass Redevelopment Parcel Planned Public Space Existing Public Space Stapleton FITZSIMONS PKWY. To Fitzsimons Medical Complex Existing Building Existing Parcel Figure 14. Pedestrian and Bicycle Circulation Diagram Circulation 21

29 Automobile, Truck and Bus Circulation The proposed auto, truck and bus circulation routes support transitoriented development by directing heavy traffic away from neighborhood streets and promote light rail and commuter rail ridership by providing access to the station s bus transfer and park-n-ride facilities. The Automobile and Bus Circulation Diagram identifies the primary auto and bus routes in the Smith-Peoria station area. Automobile and Truck Circulation The proposed automobile routes direct through-traffic to and from the Smith- Peoria Station to major auto corridors including Peoria Street, Smith Road and I-70. Local traffic is allowed to disperse on neighborhood streets. Due to the location of the planned light rail platforms and the tail-track that is necessary for train maneuvering at the end of the line, RTD will be removing Smith Road between Moline and Peoria streets. To ensure the integrity of transitoriented development in the station area, the following auto and truck routes are proposed: Proposed Auto Route Realign Smith Road to connect to Nome Street. The redirection of auto traffic from Smith Road to Nome Street to 33rd Avenue will provide the drive-by traffic that is essential for the success of retail and commercial development proposed along Nome Street Proposed Truck Route Moline Street and 33rd Avenue are proposed as a truck route in order to ensure that Nome Street can be designed as a narrow, pedestrian friendly street Currently, vehicles traveling on Peoria Street may be delayed at the at-grade UP freight train crossing located north of Smith Road. More frequent delays may occur with commuter trains passing through this intersection. To improve vehicle circulation and prevent train-related delays, an overpass or underpass is proposed on Peoria street over the UP freight rail and planned commuter rail lines. Bus Circulation The Smith-Peoria Station is intended to serve as a bus-to-rail transfer station. To service to Smith-Peoria station area and provide access to the station, new bus routes must be added and the existing route 121 must be re-routed as indicated on the diagram. The Smith-Peoria study area is currently served by route 121 and route PTHE. Proposed bus routes and existing route modifications include: Addition of bus service on E. 33rd Avenue and Nome Street to Smith Road, servicing the Smith-Peoria Station and Stapleton neighborhood Potential realignment of route 121 from Peoria Street to Baranmor Parkway and Smith Road in the event that an overpass or underpass is constructed on Peoria Street at the UP rail creating a grade separation from Smith Road Smith Road Removal Proposed Smith Road Realignment Proposed Truck Route MOLINE ST. Planned Light Rail Tail-Track Planned Light Rail Platforms Existing Smith Road Alignment Proposed Auto Route 33RD AVE. Figure 15. Proposed Smith Road Auto and Truck Routes 22 Smith-Peoria Station Area Plan DRAFT

30 QUARI ST. A ST. B B ST. ST. C ST. D ST. E ST. MOLINE ST. LIMA ST. INTERSTATE 70 1/2 Mile Radius E. 40TH AVE. To Montbello Neighborhood 1/4 Mile Radius Potential 121 E. 39TH AVE. E. 38TH AVE. E. 37TH AVE. Possible Overpass/Underpass To Stapleton STATION AVE. To East Morris Heights Neighborhood E. 33RD AVE. PTHE BARANMOR PKWY. 121 PTHE E. 33RD AVE. OAKLAND ST. LEGEND Light Rail Platform Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment UP Freight Rail Alignment RTD RTD Park-n-Ride Auto Circulation Truck Route Bus Circulation (Existing) Bus Circulation (Potential Realignment) Bus Circulation (Proposed) Bus Routes INS S A N D C R E E K E. 31ST AVE. E. 30TH AVE. To Fitzsimons Medical Complex FITZSIMONS PKWY. West Morris Heights Neighborhood 121 To East Morris Heights Neighborhood Redevelopment Parcel Planned Public Space Existing Public Space Existing Building Existing Parcel Figure 16. Automobile and Bus Circulation Diagram Circulation 23

31 New and Enhanced Streets New and enhanced streets, sidewalks and intersections help to create a comprehensive street grid that will provide convenient multi-modal access to proposed development in the Smith-Peoria station area, while strengthening and relieving pressure on the existing roadway network. The grid established by the new and enhanced streets generally follows existing property lines and establishes block sizes that foster urban-style redevelopment rather than suburban super-blocks. General Guidelines New streets should comply with the City of Aurora Urban Street Standards and should: Be dedicated public streets Meet ADA specifications The following recommendations will help to ensure high-quality streets in the Smith-Peoria study area. Sustainability Green street design principles, such as stormwater infiltration and permeable surface treatments, are encouraged for all street types. Street Design The design recommendations detailed on the following pages are informed by preliminary traffic analysis and are based on existing average daily trips (ADT) and projected ADT for the study area. Streets are designed to meet City standards and level-of-service needs. New and Enhanced Streets New and enhanced streets will: Ensure that the mobility of existing arterial streets is not degraded Minimize auto traffic impacts on existing neighborhoods Provide direct and convenient access to the future light rail and commuter rail station for all transportation modes Provide adequate right-of-way and traffic control devices for proposed bicycle routes as described in the City of Aurora s Bicycle Facility Design Guidelines New Pedestrian/Bike Underpass The proposed pedestrian and bike underpass will: Provide a safe and direct north-south station connection as an alternative to Peoria Street for transit riders commuting from the north on foot or by bike Provide direct access between the station and potential RTD park-nride lot in the City and County of Denver Enhanced Intersections Enhanced intersection treatments, including crosswalks, landscaping and curb extensions, are recommended at the following locations: Peoria Street and 30th Avenue Peoria Street and 33rd Avenue Proposed Traffic Signals New traffic signals may be warranted to improve safety and access at the following intersections: 33rd Avenue and Nome Street 30th Avenue and Nome Street Smith Road and Moline Street 24 Smith-Peoria Station Area Plan DRAFT

32 A ST. B ST. LIMA ST. OAKLAND ST. C ST. D ST. E ST. E. 39TH AVE. 1/4 Mile Radius Potential E. 37TH AVE. Possible Overpass/Underpass MOLINE ST. STATION AVE. E. 33RD AVE. BARANMOR PKWY. 1/2 Mile Radius INS LEGEND Light Rail Platform Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment RTD RTD Park-n-Ride New Street/Sidewalk New Pedestrian/Bike Underpass Enhanced Street/Sidewalk Enhanced Intersection New Traffic Signal Redevelopment Parcel Planned Public Space Existing Public Space Existing Building Existing Parcel E. 3OTH AVE. S A N D C R E E K QUARI ST. E. 31ST AVE. E. 3OTH AVE. FITZSIMONS PKWY. Figure 17. New and Enhanced Streets Diagram Circulation 25

33 Street Categories Street categories recommended in the Smith-Peoria study area accommodate the area s multi-modal circulation needs and meet City of Aurora Public Works level-of-service requirements. The recommended street categories are designed and located to support proposed new land uses. The Street Categories Diagram identifies all new and enhanced streets in the Smith-Peoria study area and categorizes them as follows: Signature Streets Neighborhood Streets Neighborhood Park Streets Truck Emphasis Street Detailed cross-sections illustrating the proposed street designs are located on the following pages. Signature Streets The signature streets: Establish the station area as a distinctive and memorable place Provide direct and convenient station access for all modes of transportation from adjacent neighborhood streets and major vehicle corridors Accommodate moderate vehicletraffic volumes while maintaining safety and function for all transportation modes Ensure essential drive-by visibility for ground-floor retail and commercial uses on 13th Avenue and Station Street Signature streets may include design elements such as: Special paving Benches, bicycle racks, and other street furniture Ornamental street lights Special landscaping The signature streets described on pages of this document are: 30th Avenue Nome Street 33rd Avenue Neighborhood Streets The majority of new streets in the 13th Avenue station area are Neighborhood Streets. These neighborhood streets generally accommodate low traffic volumes, provide on-street parking to complement the adjacent residential land uses and have sidewalk widths that support walking as a primary means of station area transportation. These streets can be places for informal public interaction and environmental enhancement. A detailed description and cross-section of a Neighborhood Street is provided on page 32 of this document. Neighborhood Park Streets Where neighborhood streets are adjacent to proposed public spaces special conditions apply. In these locations, neighborhood park streets are proposed. On these streets, parking is not recommended adjacent to the public space in order to: Provide sight lines from adjacent land uses to the public spaces Perceptually expand the public spaces to the surrounding buildings and link the streets to the public space A detailed description and cross-section of a Neighborhood Park Street is provided on page 32 of this document. Truck Emphasis Street To facilitate truck mobility in the station area without compromising the intimate character of Nome Street, a Truck Emphasis Street is proposed on Moline Street between Smith Road and 33rd Avenue. A detailed description and cross-section of Moline Street is provided on page 33 of this document. 26 Smith-Peoria Station Area Plan DRAFT

34 A ST. B ST. LIMA ST. OAKLAND ST. C ST. D ST. E ST. E. 39TH AVE. 1/4 Mile Radius Potential E. 37TH AVE. Possible Overpass/Underpass MOLINE ST. STATION AVE. E. 33RD AVE. BARANMOR PKWY. 1/2 Mile Radius INS LEGEND Light Rail Platform Commuter Rail Platform Light Rail Alignment Commuter Rail Alignment RTD RTD Park-n-Ride Neighborhood Signature Street Neighborhood Street Neighborhood Park Street Truck Emphasis Street Redevelopment Parcel Planned Public Space Existing Public Space Existing Building Existing Parcel E. 3OTH AVE. S A N D C R E E K QUARI ST. E. 31ST AVE. E. 3OTH AVE. FITZSIMONS PKWY. Figure 18. Street Categories Diagram Circulation 27

35 Signature Streets: Nome Street (South of 33rd Avenue) At build-out, Nome Street will serve as the primary north-south connection through the station area. In response to the various land uses proposed along Nome Street, there are three street cross-sections proposed between 30th Avenue and Smith Road, as shown on the diagram to the right. SMITH RD Proposed Nome Retail Street. STATION AVE. The existing portion of Nome Street, located between 33rd and 30th avenues, should be improved as a park block street that supports automobile, bicycle and pedestrian circulation. The cross-section below illustrates the proposed improvements. At a minimum, Nome Street should include the following elements: One 14-ft. sidewalk with pedestrian through zones, curbs, and curb-side landscaped areas (east side of Nome Street) 7-ft. curb-side parallel parking lane (east side of Nome Street) Two 11-ft. travel lanes 7-ft. curb-side landscape zone (west side of Nome Street) 10-ft. protected bike path 5-ft. landscape buffer between bike and pedestrian zones 8-ft. sidewalk Proposed Nome Commercial/Office Street 33RD AVE. Proposed Nome Park Block Street Figure 19. Proposed Nome Street Types Parking is prohibited where adjacent to public spaces. Proposed Nome Street > Proposed B Street N Figure 20. Proposed Nome Park Block Street Cross-Section (South of 33rd Avenue) 28 Smith-Peoria Station Area Plan DRAFT

36 Signature Streets: Nome Street Extension (33rd Avenue to Smith Road) The extension of Nome Street from 33rd Avenue to Smith Road will serve as a link in the Smith Road/Nome Street/30th Avenue roadway system and will provide continuous multi-modal circulation through the station area. There are two proposed street crosssections for the Nome Street extension between 33rd Avenue and Smith Road: Retail Street where adjacent to ground-floor retail uses between Smith Road and Station Avenue Commercial/Office Street where adjacent to ground-floor commercial or office uses between Station Avenue and 33rd Avenue Retail Street The proximity of Nome Street to the Smith-Peoria Station creates an opportunity for transit-supportive retail uses between Smith Road and Station Avenue. To support these retail uses, the following minimum elements are proposed within the 68 ft. right-of-way: Two 16-ft. sidewalks, including a 1.5-ft. building edge zone, 7-ft. furnishing zone, 6-ft. throughway and a 1.5-ft frontage zone Two 7-ft. curb-side parallel parking lanes Two 11-ft. travel lanes Commercial/Office Street A protected bike path is proposed on Nome Street where adjacent to ground-floor commercial or office uses. The following minimum elements are proposed within the 73-ft. right-of-way (described east to west): One 14-ft. sidewalk with pedestrian through zone, curb, and curb-side landscaped area One 7-ft. curb-side parallel parking lane Two 11-ft. travel lanes 7-ft. curb-side landscape zone 10-ft. protected bike path 5-ft. landscape buffer between bike and pedestrian zones 8-ft. sidewalk Retail Office Comm. Retail > Figure 21. Proposed Nome Retail Street Cross Section Office Comm. Figure 22. Proposed Nome Commercial/Office Street Cross-Section N > N Circulation 29

37 Signature Streets: 33rd Avenue 33rd Avenue will serve as an east-west connection between Peoria and Moline streets. It will support bus, truck, auto, bicycle and pedestrian circulation. To accommodate these modes of transportation, sidewalks have been widened and on-street parking lanes have been exchanged for on-street bike lanes. The 33rd Avenue cross-section to the right illustrate a view looking east from Peoria Street. The existing 35-ft. curb-to-curb dimension has been maintained. The proposed 67-ft. cross-section can be accommodated by expansion of the existing right-of-way or the creation of an easement. Design elements of the proposed 33rd Avenue Signature Street include: Two 16-ft. sidewalks, including a 1.5-ft. building edge zone, 7-ft. furnishing zone, 6-ft. throughway and a 1.5-ft frontage zone Two 7-ft. on-street bicycle lanes Two 10-ft 6-in. travel lanes 30 Smith-Peoria Station Area Plan DRAFT

38 N> Figure 23. Existing 33rd Avenue Cross-Section N> Figure 24. Proposed 33rd Avenue Cross-Section Circulation 31

39 Truck Emphasis Street: Moline Street Moline Street will serve as a northsouth truck and bicycle connection between Smith Road and 33rd Avenue. To accommodate these modes, on-street parking lanes has been exchanged for on-street bike lanes and lane widths have been widened. The proposed 64-ft. cross-section can be accommodated by expansion of the existing right-of-way or the creation of an easement. Design elements include: Two 14-ft. sidewalks with pedestrian through zones, curbs, and curb-side landscaped areas Two 7-ft. on-street bicycle lanes Two 11-ft. travel lanes N> Figure 25. Existing Moline Street Cross-Section Edge Uses Vary Figure 26. Proposed Moline Street Cross-Section 32 Smith-Peoria Station Area Plan DRAFT

40 Neighborhood Streets The proposed neighborhood street cross-section includes a 62-ft. right-ofway, measured from building edge to building edge. Design elements include: Two 14-ft. sidewalks with pedestrian through zones, curbs, and curb-side landscaped areas Two 7-ft. curb-side parallel parking lanes Two 10-ft. travel lanes Figure 27. Proposed Neighborhood Street Cross-Section Neighborhood Park Streets Edge Uses Vary The proposed neighborhood park street cross-section includes a 55-ft. right-ofway, measured from building edge to back-of-sidewalk on the park side of the street. Design elements include: Two 14-ft. sidewalks with pedestrian through zones, curbs, and curb-side landscaped areas One 7-ft. curb-side parallel parking lane on the building side of the street Two 10-ft. travel lanes Note: The edge condition on the opposite side of the street from the public space varies (i.e. building, public space, parking lot) Figure 28. Proposed Neighborhood Park Street Cross-Section Circulation 33

Lincoln Downtown Master Plan Update

Lincoln Downtown Master Plan Update Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating

More information

Downtown Tampa Transportation Vision

Downtown Tampa Transportation Vision Downtown Tampa Transportation Vision Executive Summary August 1, 2006 Hillsborough County Metropolitan Planning Organization County Center, 18 th Floor Tampa, Florida 33602 813-272-5940 www.hillsboroughmpo.org

More information

peoria station Existing Conditions Report catalytic project Final 07.20.2014 4969 Broadway Boulder, CO 80304 303-440-9200 www.migcom.

peoria station Existing Conditions Report catalytic project Final 07.20.2014 4969 Broadway Boulder, CO 80304 303-440-9200 www.migcom. DENVER REGIONAL COUNCIL OF GOVERNMENTS peoria station catalytic project Final 07.20.2014 4969 Broadway Boulder, CO 80304 303-440-9200 www.migcom.com In association with: Fox Tuttle Transportation Group

More information

Walkable Communities Florida Department of Transportation State Safety Office Pedestrian and Bicycle Program April 1995 www.dot.state.fl.us/safety Twelve Steps for an Effective Program Page 1 Twelve Steps

More information

Topic 2 11/28/2012 Blocks & Street Network

Topic 2 11/28/2012 Blocks & Street Network TOPIC 2 Blocks & Street Network Implementation Note: 1. Some recommendations are summarized in the tables herein. For complete recommendation language, please see the. 2. Recommendations referenced in

More information

DESIGN ASSISTANCE APPLICATION

DESIGN ASSISTANCE APPLICATION DESIGN ASSISTANCE APPLICATION for FY 2016 NEW RIVER MULTI USE PATH: PINNACLE PEAK ROAD TO HAPPY VALLEY ROAD CITY OF PEORIA APPLICATIONS ARE DUE VIA ONLINE SUBMITTAL BY 10:00 AM ON MONDAY, JUNE 29, 2015

More information

VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY

VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY 3 VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY The overall planning strategy for the Bank Street CDP is to ensure that future development is undertaken in a coordinated and planned approach, supported

More information

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010)

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Summary Description Proposed Project: Electrified Commuter Rail 30.2 Miles, 13 Stations Total

More information

Schenk-Atwood Neighborhood Business District Master Plan

Schenk-Atwood Neighborhood Business District Master Plan Schenk-Atwood Neighborhood Business District Master Plan Prepared for the Schenk-Atwood Revitalization Association (SARA) and the City of Madison SCHREIBER/ANDERSON ASSOCIATES, INC. BEST Real Estate Group,

More information

For more information, visit: rethinkingstreets.com

For more information, visit: rethinkingstreets.com For more information, visit: rethinkingstreets.com 37 Arterial Rehab Busy, multi-lane streets, often referred to as arterials, crisscross the landscape of our cities and suburbs. Alongside these wide thoroughfares,

More information

Introduction to Station Area Planning The Charlotte Story

Introduction to Station Area Planning The Charlotte Story Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History

More information

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two.

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two. Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts Design and Development Guidelines Request for Qualifications and Expressions of Interest with Preliminary Development Plans Part

More information

Los Angeles Union Station, CA Sustainable Neighborhood Assessment. April 22-23, 2014

Los Angeles Union Station, CA Sustainable Neighborhood Assessment. April 22-23, 2014 Los Angeles Union Station, CA Sustainable Neighborhood Assessment April 22-23, 2014 Sustainable Neighborhood Assessment Through the Sustainable Neighborhood Assessment Tool developed by Global future development

More information

What we build today will create Denver s tomorrow. Signature development projects will strengthen our economy, create jobs and improve neighborhoods.

What we build today will create Denver s tomorrow. Signature development projects will strengthen our economy, create jobs and improve neighborhoods. Mayor Hancock s Vision for Building a World-Class City What we build today will create Denver s tomorrow. Signature development projects will strengthen our economy, create jobs and improve neighborhoods.

More information

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project. Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation

More information

Light Rail Transit in Phoenix

Light Rail Transit in Phoenix 4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February

More information

Comprehensive Plan Policies that support Infill and Mixed Use

Comprehensive Plan Policies that support Infill and Mixed Use Comprehensive Plan Policies that support Infill and Mixed Use Introduction A comprehensive plan provides a broad vision for the future growth of a community. It is often formulated using community visioning

More information

Florida Avenue Multimodal Transportation Study. June 19, 2013

Florida Avenue Multimodal Transportation Study. June 19, 2013 Florida Avenue Multimodal Transportation Study June 19, 2013 Today s Agenda Team & project introduction Project Timeline What you said Tools we use Mapped data and what clues it can provide Highlights

More information

Nine Mile Station Urban Renewal Plan

Nine Mile Station Urban Renewal Plan Nine Mile Station Urban Renewal Plan Aurora, Colorado April 2014 Prepared for: Aurora Urban Renewal Authority Aurora, Colorado City Council Nine Mile Station Urban Renewal Plan Draft date: 3-31-2014 Aurora,

More information

REGIONAL NON-MOTORIZED TRANSPORTATION NETWORK

REGIONAL NON-MOTORIZED TRANSPORTATION NETWORK Chapter 10 Bicycle and Pedestrian SAFETEA-LU legislation requires that non-motorized users be considered in the LRTP. The legislation allows for bicycle and pedestrian safety to be incorporated into the

More information

Goals & Objectives. Chapter 9. Transportation

Goals & Objectives. Chapter 9. Transportation Goals & Objectives Chapter 9 Transportation Transportation MISSION STATEMENT: TO PROVIDE A TRANSPORTATION NETWORK CAPABLE OF MOVING PEOPLE AND GOODS EFFICIENTLY AND SAFELY. T he transportation system

More information

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan Transportation Authority (Metro) 2009 Transportation Improvement Program Call for Projects APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan

More information

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates SANTA MONICA TRAVEL DEMAND FORECASTING MODEL TRIP GENERATION RATES SUBMITTED BY: 201 Santa Monica Blvd., Suite 500 Santa Monica,

More information

Attachment B Policy Audit Template

Attachment B Policy Audit Template Attachment B Policy Audit Template 5 6 7 8 9 0 Provide A Variety of Transportation Choices Provide A Variety of Transportation Choices Provide A Variety of Transportation Choices Encourage transit-oriented

More information

Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections

Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections Phil Erickson Community Design + Architecture Mike Johnson HDR Engineering CTF Charrette Approach

More information

HARRIS TEETER AT LADY S ISLAND CITY OF BEAUFORT DRB CONCEPTUAL PROJECT NARRATIVE Submittal Date: September 2, 2015 Meeting Date: September 10, 2015

HARRIS TEETER AT LADY S ISLAND CITY OF BEAUFORT DRB CONCEPTUAL PROJECT NARRATIVE Submittal Date: September 2, 2015 Meeting Date: September 10, 2015 HARRIS TEETER AT LADY S ISLAND CITY OF BEAUFORT DRB CONCEPTUAL PROJECT NARRATIVE Submittal Date: September 2, 2015 Meeting Date: September 10, 2015 PROPOSED REDEVELOPMENT The project consists of demolishing

More information

Downtown South Salt Lake Redevelopment City of South Salt Lake

Downtown South Salt Lake Redevelopment City of South Salt Lake Project Information LOCAL PLANNING RESOURCE PROGRAM 2015 Downtown South Salt Lake Redevelopment City of South Salt Lake Overview of Objectives: Building a downtown city center could be the most significant

More information

30 Years of Smart Growth

30 Years of Smart Growth 30 Years of Smart Growth Arlington County s Experience with Transit Oriented Development in the Rosslyn-Ballston Metro Corridor A Presentation by the Arlington County Department of Community Planning,

More information

APPENDIX F:TRIPLE BOTTOM LINE ANALYSIS

APPENDIX F:TRIPLE BOTTOM LINE ANALYSIS APPENDIX F:TRIPLE BOTTOM LINE ANALYSIS Triple Bottom Line Analysis Map (TBLAM) Project or Decision: College Ave Corridor for FC Moves long range transportation plan for College Ave., for redevelopment

More information

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014 North Avenue Corridor Study Advisory Committee Meeting #5 June 11, 2014 Agenda Welcome and introductions Concept refinement and evaluation: Public meeting and web survey General cross-section concepts

More information

Guiding Principles. McCauley Area Focused Urban Design Plan. 1 Connect: Chinatown and Little Italy with downtown and surrounding areas

Guiding Principles. McCauley Area Focused Urban Design Plan. 1 Connect: Chinatown and Little Italy with downtown and surrounding areas McCauley Area Guiding Principles 1 Connect: Chinatown and Little Italy with downtown and surrounding areas 2 Strengthen: Cultural character in Chinatown and Little Italy 3 Develop: Strong East West pedestrian

More information

Review Public Input Report Jenn Toothaker. Approval of Meeting Summaries: May 21, May 23, May 30, & June 20, 2013 Meetings

Review Public Input Report Jenn Toothaker. Approval of Meeting Summaries: May 21, May 23, May 30, & June 20, 2013 Meetings Call to the Audience Guidelines 2 Call to the Audience opportunities Must fill out participant card Participants called in the order cards are received 3 minutes allowed per participant CTF Facilitator

More information

Michael B. Hancock Mayor. October 31, 2014

Michael B. Hancock Mayor. October 31, 2014 Michael B. Hancock Mayor City and County of Denver OFFICE OF THE MAYOR CITY AND COUNTY BUILDING DENVER, CO 80202-5390 TELEPHONE: (720) 865-9090 FAX: (720) 865-8787 TTY/ TTD: (720) 865-9010 October 31,

More information

COUNTY OF ALBEMARLE PLANNING STAFF REPORT SUMMARY. Staff: Claudette Grant

COUNTY OF ALBEMARLE PLANNING STAFF REPORT SUMMARY. Staff: Claudette Grant COUNTY OF ALBEMARLE PLANNING STAFF REPORT SUMMARY Project Name: ZMA 2013-00004 Hollymead Town Center Block VI Planning Commission Public Hearing: July 29, 2014 Staff: Claudette Grant Board of Supervisors

More information

BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE

BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE February 23, 2006 PROJECT INTRODUCTION Project Area 230 acres $50 million estimated market value (approximately) 50 acres parkland 100 residences (estimated)

More information

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Executive Summary. Transportation Needs CHAPTER. Existing Conditions CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in

More information

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Transportation & Mobility projects that meet the following criteria: enhances regional mobility; supports public transit;

More information

1. Land Use. Chapter 1: Land Use 1-1 Adopted 10/2/09 Amended 3/22/11, 8/16/11

1. Land Use. Chapter 1: Land Use 1-1 Adopted 10/2/09 Amended 3/22/11, 8/16/11 1. Land Use Minneapolis will develop and maintain a land use pattern that strengthens the vitality, quality and urban character of its downtown core, commercial corridors, industrial areas, and neighborhoods

More information

REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE 2015-0183 TO PLANNED UNIT DEVELOPMENT APRIL 9, 2015

REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE 2015-0183 TO PLANNED UNIT DEVELOPMENT APRIL 9, 2015 AWH REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE 2015-0183 TO PLANNED UNIT DEVELOPMENT APRIL 9, 2015 The Planning and Development Department hereby forwards

More information

Downtown Core Sub-district

Downtown Core Sub-district 3-10 Land Use Downtown Core Sub-district District development will be most intense and most urban in character in the Downtown Core. The objective is to establish this area as a citywide and regional retail

More information

Narrative Response/Attachment 1 (WisDOT 2014-2018 TAP- Second Round Application ID-SWBP22)

Narrative Response/Attachment 1 (WisDOT 2014-2018 TAP- Second Round Application ID-SWBP22) Narrative Response/Attachment 1 (WisDOT 2014-2018 TAP- Second Round Application ID-SWBP22) 2. For Bicycle and Pedestrian Projects: Clearly indicate the location, length, width, surface materials, and any

More information

FILE NO.: Z-6915-C. Gamble Road Short-form PCD and Land Alteration Variance Request

FILE NO.: Z-6915-C. Gamble Road Short-form PCD and Land Alteration Variance Request FILE NO.: Z-6915-C NAME: Gamble Road Short-form PCD and Land Alteration Variance Request LOCATION: Located on the Northwest corner of Chenal Parkway and Gamble Road DEVELOPER: Davis Properties P.O. Box

More information

Motorcycle & Pedestrian Master Plans in Indianapolis, Indiana

Motorcycle & Pedestrian Master Plans in Indianapolis, Indiana PROJECT PURPOSE The Warsaw + Winona Lake Bicycle and Pedestrian Master Plan establishes a comprehensive framework for a connected bicycle and pedestrian system that will be used for both recreation and

More information

CITY COUNCIL / PLANNING COMMISSION JOINT STUDY SESSION AGENDA REPORT

CITY COUNCIL / PLANNING COMMISSION JOINT STUDY SESSION AGENDA REPORT CITY COUNCIL / PLANNING COMMISSION JOINT STUDY SESSION AGENDA REPORT MEETING DATE: SEPTEMBER 8, 2015 ITEM NUMBER: 1 SUBJECT: PROPOSED GENERAL PLAN LAND USE ALTERNATIVE FOR THE YEAR 2015-2025 GENERAL PLAN

More information

Restoration. a brief look at

Restoration. a brief look at Copyright 2009 Canin Associates, Inc. All rights reserved. No part of this publication may be reproduced or transmitted by any means without written permission from Canin Associates, Inc. a brief look

More information

Corridor Goals and Objectives

Corridor Goals and Objectives Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty

More information

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES How to Get Started ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES Design Elements Selecting appropriate design treatments for school neighborhoods creates environments that address the needs of all

More information

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile

More information

GIS Analysis of Population and Employment Centers in Metro Denver Served by RTD s FasTracks

GIS Analysis of Population and Employment Centers in Metro Denver Served by RTD s FasTracks APA Transportation Planning Division 2011 Student Paper Competition GIS Analysis of Population and Employment Centers in Metro Denver Served by RTD s FasTracks Patrick Picard 2208 E. 17 th Ave., Apt. #4

More information

28.0 Development Permit Area #2 (Neighbourhood District)

28.0 Development Permit Area #2 (Neighbourhood District) 28.0 Development Permit Area #2 (Neighbourhood District) Goals and Objectives To provide a guide for infill and new development in the Neighbourhood District. To outline the nature, form and character

More information

SCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA

SCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA SCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA PROJECT OVERVIEW OVERVIEW The FCCD+R, in coordination with the FDOT District 7, are to facilitate numerous meetings

More information

Rapid City Downtown Area Master Plan. Draft Plan Concepts April 2016

Rapid City Downtown Area Master Plan. Draft Plan Concepts April 2016 Rapid City Downtown Area Master Plan Draft Plan Concepts April 2016 CALL TO ACTION! A Thriving Downtown = Regional Economic Prosperity Rapid City is competing nationally for a limited supply of young skilled

More information

Near West Side Comprehensive Plan Executive Summary (Revised) April 2004 City of Milwaukee DCD

Near West Side Comprehensive Plan Executive Summary (Revised) April 2004 City of Milwaukee DCD Near West Side Comprehensive Plan Executive Summary (Revised) April 2004 City of Milwaukee DCD Boundaries The Near West Side Comprehensive Plan covers a broad area immediately west of Milwaukee s downtown.

More information

Tier 1 Strategies. WV Route 14 Corridor Management Plan

Tier 1 Strategies. WV Route 14 Corridor Management Plan 1.1 1.2 1.3 1.4 Signal timing optimization system improvements. Improve geometry traffic control at high crash intersections. Construct intersection capacity improvement projects. Widen longer sections

More information

The Transect Zones

The Transect Zones T1 TABLE 1. TRANSECT ZONE DESCRIPTIONS TABLE 1: Transect Zone Descriptions. The following are general descriptions of the character of each Transect Zone. They may be interpreted as a constituent part

More information

Northern Nevada Water Planning Commission

Northern Nevada Water Planning Commission 12-07-11: NNWPC Agenda Item 6 Northern Nevada Water Planning Commission DATE: November 29, 2011 STAFF REPORT TO: FROM: SUBJECT: Chairman and Members, Northern Nevada Water Planning Commission Jim Smitherman,

More information

OVERVIEW PROJECT SUMMARY

OVERVIEW PROJECT SUMMARY OVERVIEW Cesar Chavez showcases how to successfully redesign a primary arterial route into a neighborhood destination, improving modal share, water sensitive design, biodiversity and safety whilst maintaining

More information

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs KENTUCKY TRANSPORTATION CABINET Department of Rural and Municipal Aid Office of Local Programs Office of Local Programs Transportation Enhancements Safe Routes to School Congestion Mitigation and Air Quality

More information

PLANNING DIVISION STAFF REPORT February 23, 2015. Summary. Background Information PREPARED FOR THE PLAN COMMISSION. Legistar File ID # 36810

PLANNING DIVISION STAFF REPORT February 23, 2015. Summary. Background Information PREPARED FOR THE PLAN COMMISSION. Legistar File ID # 36810 PLANNING DIVISION STAFF REPORT PREPARED FOR THE PLAN COMMISSION Project Address: Application Type: Legistar File ID # 36810 Prepared By: Summary Conditional Use Timothy M. Parks, Planning Division Report

More information

S-11: Tacoma Link Extension to Tacoma Community College

S-11: Tacoma Link Extension to Tacoma Community College Project Number S-11 Subarea Pierce Primary Mode Light Rail Facility Type Corridor Length 3.65 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT

More information

Citizen Advisory Group Meeting #1 December 8, 2011 6:00 p.m.

Citizen Advisory Group Meeting #1 December 8, 2011 6:00 p.m. Citizen Advisory Group Meeting #1 December 8, 2011 6:00 p.m. Meeting Agenda 1. Background Information 2. Policy Framework 3. Plan Development Process 4. Public Input Results 5. Vision Statement 6. Group

More information

STOP CONSOLIDATION TRANSIT STRATEGIES

STOP CONSOLIDATION TRANSIT STRATEGIES TRANSIT STRATEGIES STOP CONSOLIDATION Transit stops are the places where people access transit service, and greatly impact many elements of passengers transit experiences. They are typically thought of

More information

Opal Service District Plan

Opal Service District Plan 8 The Opal Service District includes a variety of planned land uses including commercial, mixed-use, flex office, industrial, and hospitality. This Plan seeks to simplify the land use categories to allow

More information

Pedestrian & Bicycle Plan

Pedestrian & Bicycle Plan RAMSEY COMMUNITIES COUNTYWIDE Pedestrian & Bicycle Plan PRIMER: LEGAL FRAMEWORK PRIMER: LEGAL FRAMEWORK Walking and Biking for All e 2 CHAPTER 2: Walking and Biking for All This page intentionally left

More information

Comprehensive Plan Update

Comprehensive Plan Update Comprehensive Plan Update Today s Agenda 1. Welcome and Presentation 2. Reality Check-Lite Exercise 3. Greenway Mapping Exercise 4. Priority Thought Wall Exercise 5. Next Steps Recap of Feb. Public Meetings

More information

INTRODUCTION TO ZONING DISTRICT REGULATIONS

INTRODUCTION TO ZONING DISTRICT REGULATIONS INTRODUCTION TO ZONING DISTRICT REGULATIONS Classification of Zoning Districts Zoning districts in Dorchester County are categorized as Suburban Urban, Suburban Transition, or Rural. These districts are

More information

Presentation to Community Task Force July 9, 2007

Presentation to Community Task Force July 9, 2007 Alternative Evaluation Results Presentation to Community Task Force July 9, 2007 Outline of Presentation Overview of alternative evaluation Alternative evaluation methodology Process and assumptions General

More information

Marshall V. Davidson Jr. Richard N. Gill

Marshall V. Davidson Jr. Richard N. Gill Marshall V. Davidson Jr. Richard N. Gill 512-225-2481 210-581-7720 TOTAL ACREAGE: 762.203 KMDS SITES: D E F INFRASTRUCTURE I J K L O U P Q R lum Creek offers over 700 acres of commercial real estate for

More information

Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013

Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013 Near Westside Neighborhood and University Avenue Corridor Transportation Study Public Workshop #2 September 12 and 23, 2013 Presentation Outline: Brief Review of Study Scope, Background, and Current Conditions

More information

Developing Street Standards That Allow Flexibility

Developing Street Standards That Allow Flexibility Developing Street Standards That Allow Flexibility ABSTRACT GWEN OWENS City of Sacramento 927 10th Street Sacramento, CA 95814 gowens@sacto.org The City of Sacramento, California, recently updated its

More information

CITY COUNCIL PACKET MEMORANDUM

CITY COUNCIL PACKET MEMORANDUM CITY COUNCIL PACKET MEMORANDUM DOCUMENT: Final Plan and Final Plat SUBJECT: City Center Lenexa The Domain at City Center CONTACT PERSON: Beccy Yocham, Director of Community Development DATE: December 3,

More information

Supplemental Plan Check Corrections Sheet for Bicycle Parking Ordinance (Effective 3/13/2013)

Supplemental Plan Check Corrections Sheet for Bicycle Parking Ordinance (Effective 3/13/2013) Supplemental Plan Check Corrections Sheet for Bicycle Parking Ordinance (Effective 3/13/2013) Plan Check PCIS application number: - - Job Address Zone: P.C. Engineer (E-mail: firstname.lastname@lacity.org)

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total

More information

Chapter 9: Transportation

Chapter 9: Transportation Chapter 9: Transportation What is this chapter about? The goals and policies in this chapter convey the City s intent to: Create a coordinated, efficient, and more affordable multimodal transportation

More information

Indianapolis SDAT. Neighborhood Restoration

Indianapolis SDAT. Neighborhood Restoration Neighborhood Restoration Working Toward a Sustainable Future live * work * play October 30 th, 2009 Message Hear concerns Build consensus Provide Recommendations Transition from Fragmentation/disconnect

More information

CITY OF BRAMPTON STREET CORRIDOR MASTER PLAN

CITY OF BRAMPTON STREET CORRIDOR MASTER PLAN 1.0 INTRODUCTION... 1 1.1 Purpose of Document... 1 1.2 Master Plan Goal...1 1.3 Design Objectives... 2 1.4 Design Approach... 2 2.0 PROJECT SCOPE...2 2.1 City Context 2 2.2 Regional Context 2 3.0 DESIGN

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015)

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total Capital

More information

CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND)

CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND) Regional Transportation Plan 2035 28 CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND) The Cache Transportation Vision Plan shows roadway, bicycle, transit and pedestrian projects that attempt

More information

CITY OF NORMANDY PARK MANHATTAN VILLAGE REDEVELOPMENT AREA STRATEGY AND CONCEPTUAL MASTER PLAN

CITY OF NORMANDY PARK MANHATTAN VILLAGE REDEVELOPMENT AREA STRATEGY AND CONCEPTUAL MASTER PLAN CITY OF NORMANDY PARK MANHATTAN VILLAGE REDEVELOPMENT AREA STRATEGY AND CONCEPTUAL MASTER PLAN Project Purpose The City of Normandy Park is studying ways to help property owners in the Manhattan Village

More information

RESOLUTION NO. WHEREAS, the 2016-2017 City Budget Forecast estimates that housing

RESOLUTION NO. WHEREAS, the 2016-2017 City Budget Forecast estimates that housing RESOLUTION NO. WHEREAS, the 2016-2017 City Budget Forecast estimates that housing (21.6 percent) and transportation (14.9 percent) are the two largest expense categories for the typical Austin family;

More information

Examples of Transportation Plan Goals, Objectives and Performance Measures

Examples of Transportation Plan Goals, Objectives and Performance Measures Examples of Transportation Plan Goals, Objectives and Performance Measures The next step in the Long Range Transportation Plan (LRTP) process is to develop goals, objectives, and performance measures.

More information

Downtown Community Planning Council Meeting offebruary 18, 2015

Downtown Community Planning Council Meeting offebruary 18, 2015 - san diego Item #12 DATE ISSUED: ATTENTION: SUBJECT: February 13, 2015 Downtown Community Planning Council Meeting offebruary 18, 2015 Consideration of Support for Grant Applications for the San Diego

More information

N Street Protected Bikeway

N Street Protected Bikeway N Street Protected Bikeway The N Street Protected Bikeway project was identified in the 2005 City of Lincoln Downtown Master Plan and the 2012 Downtown Master Plan Update as the completion of the last

More information

Preliminary Plan Application and Checklist

Preliminary Plan Application and Checklist ALL APPLICATIONS ARE DUE AT 12:00 NOON ON THE FILING DATE Office Use Only PRELIMINARY / REVISED PRELIMINARY PLAN $300.00 Fee Paid: $ Date Paid: ALL FIELDS HIGHLIGHTED IN RED ARE REQUIRED FIELDS Case No.:

More information

South Waterfront Area Dave Unsworth

South Waterfront Area Dave Unsworth South Waterfront Area Dave Unsworth TriMet Capital Projects September 14, 2011 Presentation outline Background Partnering Agreements Project descriptions OHSU Portland Aerial Tram New Campus Portland Streetcar

More information

01/31/13 ACHIEVING THE VISION FOR RESTON. Reston Master Plan Special Study Task Force

01/31/13 ACHIEVING THE VISION FOR RESTON. Reston Master Plan Special Study Task Force ACHIEVING THE VISION FOR RESTON Reston Master Plan Special Study Task Force The Reston Master Plan Special Study Task Force was appointed by Hunter Mill District Supervisor Catherine Hudgins to review

More information

STAFF REPORT. December 20, 2004. North District Community Council. Director of Community Planning - North

STAFF REPORT. December 20, 2004. North District Community Council. Director of Community Planning - North STAFF REPORT December 20, 2004 To: From: Subject: North District Community Council Director of Community Planning - North Preliminary Report Respecting Revised Application OPA & Rezoning Application 01

More information

Midtown Corridor Alternatives Analysis Scope of Work. April 18, 2012

Midtown Corridor Alternatives Analysis Scope of Work. April 18, 2012 Midtown Corridor Alternatives Analysis Scope of Work April 18, 2012 Table of Contents PART 1: STUDY AREA MAPS... 1 Attachment A: Existing and Planned Transit Service... 2 Attachment B: Corridor Boardings

More information

APPENDIX B: THE PORTLAND METROPOLITAN REGION S CASE FOR ACTIVE TRANSPORTATION

APPENDIX B: THE PORTLAND METROPOLITAN REGION S CASE FOR ACTIVE TRANSPORTATION APPENDIX B: THE PORTLAND METROPOLITAN REGION S CASE FOR ACTIVE TRANSPORTATION Prepared by Alta Planning & Design May 2009 Call for Active transportation demonstration projects Metro invites partners to

More information

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24 Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge

More information

Draft Goals and Objectives Wadena Comprehensive Plan City of Wadena, Minnesota. Land Use Goals:

Draft Goals and Objectives Wadena Comprehensive Plan City of Wadena, Minnesota. Land Use Goals: Draft Goals and Objectives Wadena Comprehensive Plan City of Wadena, Minnesota Land Use Goals: 1. Growth in Wadena will be undertaken in such a manner as to create a full range of living, working, shopping,

More information

Cherokee County: Bells Ferry LCI Study & County Ordinance Audit. Prepared by Atlanta Regional Commission Staff 2006. Atlanta Regional Commission

Cherokee County: Bells Ferry LCI Study & County Ordinance Audit. Prepared by Atlanta Regional Commission Staff 2006. Atlanta Regional Commission Cherokee County: Bells Ferry LCI Study & County Ordinance Audit Prepared by Atlanta Regional Commission Staff 2006 Atlanta Regional Commission 1 Document Review and Recommendations Introduction The objective

More information

12 February 8, 2012 Public Hearing APPLICANT:

12 February 8, 2012 Public Hearing APPLICANT: 12 February 8, 2012 Public Hearing APPLICANT: PROPERTY OWNER: VIRGINIA BEACH ASSOCIATES, LC REQUEST: Conditional Change of Zoning (I-1 to Conditional A-36) STAFF PLANNER: Faith Christie ADDRESS / DESCRIPTION:

More information

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) To be considered for STP funding, a proposed project must

More information

Fast Track A Successful Redevelopment: The Palm Beach Outlets Story

Fast Track A Successful Redevelopment: The Palm Beach Outlets Story Fast Track A Successful Redevelopment: The Palm Beach Outlets Story SPEAKERS Rick Greene, AICP City of West Palm Beach Brian Seymour, Esq. Gunster Ken Tuma, PE UDKS Josh Long, AICP Gunster Grand Opening

More information

9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015

9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015 9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS April 24, 2015 Kunzman Associates, Inc. 9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS April 24, 2015 Prepared by: Bryan Crawford Carl Ballard,

More information

HOW WILL PROGRESS BE MONITORED? POLICY AREA. 1. Implement the 2040 Growth Concept and local adopted land use and transportation plans

HOW WILL PROGRESS BE MONITORED? POLICY AREA. 1. Implement the 2040 Growth Concept and local adopted land use and transportation plans PERFORMANCE MONITORING APPROACH OAR 660-044-0040(3)(e) directs Metro to identify performance measures and targets to monitor and guide implementation of the Climate Smart Strategy. The purpose of performance

More information

TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations. Part 2: Station Typology and Mode of Access Planning Tool

TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations. Part 2: Station Typology and Mode of Access Planning Tool TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations Part 2: Station Typology and Mode of Access Planning Tool Jamie Parks, AICP Kittelson & Associates, Inc. Acknowledgements

More information

I-90 ALLSTON INTERCHANGE PLACEMAKING STUDY Boston Redevelopment Authority

I-90 ALLSTON INTERCHANGE PLACEMAKING STUDY Boston Redevelopment Authority I-90 ALLSTON INTERCHANGE PLACEMAKING STUDY Boston Redevelopment Authority The Cecil Group Stantec Nelson/Nygaard Task Force Presentation December 17, 2015 I-90 Allston Interchange Placemaking Study Agenda

More information