1 CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities. This template may not contain all applicable requirements for all construction sites. Please refer to the Department s Generic Permit for Stormwater Discharge from Large and Small Construction Activities, DEP Document (4)(a) to verify that you are meeting all permit requirements. Part V of the above referenced generic permit specifically lists requirements of the Stormwater Pollution Prevention Plan. The SWPPP shall be completed prior to the submittal of the Notice of Intent (NOI) to be covered under the Department s Generic Permit for Stormwater Discharge from Large and Small Construction Activities. The SWPPP shall be amended whenever there is a change in design, construction, operation, or maintenance, which has a significant effect on the potential for discharge of pollutants to surface waters of the state or a Municipal Separate Storm Sewer System (MS4). The SWPPP also shall be amended if it proves to be ineffective in significantly reducing pollutants from sources identified in Part V.D.1. of the permit. The SWPPP also shall be amended to indicate any new contractor and/or subcontractor that will implement any measure of the SWPPP. All amendments shall be signed, dated, and kept as attachments to the original SWPPP. 1
2 Stormwater Pollution Prevention Plan "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." Name (Operator and/or Responsible Authority) Date Project Name and location information: A site map must be developed and must contain, at a minimum, the following information: 1. Drainage patterns, 2. Approximate slopes after major grading activities, 3. Areas of soil disturbance, 4. Outline all areas that are not to be disturbed, 5. Location of all major structural and non-structural controls, 6. The location of expected stabilization practices, 7. Wetlands and surface waters, and 8. Locations where stormwater may discharge to a surface water or MS4. 2
3 Site Description Describe the nature of the construction activity: Describe the intended sequence of major soil disturbing activities: Total area of the site: Total area of the site to be disturbed: Existing data describing the soil or quality of any stormwater discharge from the site: Acres Acres Estimate the drainage area size for each discharge point: Latitude and longitude of each discharge point and identify the receiving water or MS4 for each discharge point: 3
4 Give a detailed description of all controls, Best Management Practices (BMPs) and measures that will be implemented at the construction site for each activity identified in the intended sequence of major soil disturbing activities section. Provide time frames in which the controls will be implemented. NOTE: All controls shall be consistent with performance standards for erosion and sediment control and stormwater treatment set forth in s , F.A.C., the applicable Stormwater or Environmental Resource Permitting requirements of the Department or a Water Management District, and the guidelines contained in the Florida Development Manual: A Guide to Sound Land and Water Management (DEP, 1988) and any subsequent amendments. Describe all temporary and permanent stabilization practices. Stabilization practices include temporary seeding, mulching, permanent seeding, geotextiles, sod stabilization, vegetative buffer strips, protection of trees, vegetative preservations, etc. Describe all structural controls to be implemented to divert stormwater flow from exposed soils and structural practices to store flows, retain sediment on-site or in any other way limit stormwater runoff. These controls include silt fences, earth dikes, diversions, swales, sediment traps, check dams, subsurface drains, pipe slope drains, level spreaders, storm drain inlet protection, rock outlet protection, reinforced soil retaining systems, gabions, coagulating agents and temporary or permanent sediment basins. 4
5 Describe all sediment basins to be implemented for areas that will disturb 10 or more acres at one time. The sediment basins (or an equivalent alternative) should be able to provide 3,600 cubic feet of storage for each acre drained. Temporary sediment basins (or an equivalent alternative) are recommended for drainage areas under 10 acres. Describe all permanent stormwater management controls such as, but not limited to, detention or retention systems or vegetated swales that will be installed during the construction process. Describe in detail controls for the following potential pollutants Waste disposal, this may include construction debris, chemicals, litter, and sanitary wastes: Offsite vehicle tracking from construction entrances/exits: 5
6 The proper application rates of all fertilizers, herbicides and pesticides used at the construction site: The storage, application, generation and migration of all toxic substances: Other: Provide a detailed description of the maintenance plan for all structural and non-structural controls to assure that they remain in good and effective operating condition. 6
7 Inspections: Describe the inspection and inspection documentation procedures, as required by Part V.D.4. of the permit. Inspections must occur at least once a week and within 24 hours of the end of a storm event that is 0.50 inches or greater (see attached form). Identify and describe all sources of non-stormwater discharges as allowed in Part IV.A.3. of the permit. Flows from fire fighting activities do not have to be listed or described. This SWPPP must clearly identify, for each measure identified within the SWPPP, the contractor(s) or subcontractor(s) that will implement each measure. All contractor(s) and subcontractor(s) identified in the SWPPP must sign the following certification: I certify under penalty of law that I understand, and shall comply with, the terms and conditions of the State of Florida Generic Permit for Stormwater Discharge from Large and Small Construction Activities and this Stormwater Pollution Prevention Plan prepared thereunder. Name Title Company Name, Address and Phone Number Date 7
8 Stormwater Pollution Prevention Plan Inspection Report Form Inspections must occur at least once a week and within 24 hours of the end of a storm event that is 0.50 inches or greater. Project Name: FDEP NPDES Stormwater Identification Number: FLR10 Location Rain data Type of control (see below) Date installed / modified Current Condition (see below) Corrective Action / Other Remarks Condition Code: G = Good M = Marginal, needs maintenance or replacement soon P = Poor, needs immediate maintenance or replacement C = Needs to be cleaned O = Other Control Type Codes 1. Silt Fence 10. Storm drain inlet protection 19. Reinforced soil retaining system 28. Tree protection 2. Earth dikes 11. Vegetative buffer strip 20. Gabion 29. Detention pond 3. Structural diversion 12. Vegetative preservation area 21. Sediment Basin 30. Retention pond 4. Swale 13. Retention Pond 22. Temporary seed / sod 31. Waste disposal / housekeeping 5. Sediment Trap 14. Construction entrance stabilization 23. Permanent seed / sod 32. Dam 6. Check dam 15. Perimeter ditch 24. Mulch 33. Sand Bag 7. Subsurface drain 16. Curb and gutter 25. Hay Bales 34. Other 8. Pipe slope drain 17. Paved road surface 26. Geotextile 9. Level spreaders 18. Rock outlet protection 27. Rip-rap Inspector Information: Name Qualification Date The above signature also shall certify that this facility is in compliance with the Stormwater Pollution Prevention Plan and the State of Florida Generic Permit for Stormwater Discharge from Large and Small Construction Activities if there are not any incidents of non-compliance identified above. * * * * * * "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." Name (Responsible Authority) Date
SAMPLE COPY. Stormwater Pollution Prevention Plan. A site map must be developed and must contain, at a minimum, the following information:
Stormwater Pollution Prevention Plan "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure
State of Florida. Department of Environmental Protection. Generic Permit. For. Stormwater Discharge from Large and Small Construction Activities
State of Florida Department of Environmental Protection Generic Permit For Stormwater Discharge from Large and Small Construction Activities February 2009 This permit is issued under the provisions of
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local
COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION
COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)
Activity Yes No N/A Notes
CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
SECTION A: LOCAL STORM WATER POLLUTION PREVENTION PLAN
INSTRUCTIONS FOR PREPARING THE LOCAL STORM WATER POLLUTION PREVENTION PLAN City of Hawthorne For sites between 1 and 5 acres As of March 10, 2003, EPA Phase II rules will supercede this document. The Local
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources
City of Beaumont, Texas Grading Permit Information
General Information City of Beaumont, Texas Grading Permit Information The permit application shall be signed by the property owner (or lessee) or his authorized representative and by the contractor (if
CONSTRUCTION PERMIT SUBMITTAL CHECKLIST
LAS VEGAS VALLEY STORMWATER QUALITY MANAGEMENT PROGRAM CONSTRUCTION PERMIT SUBMITTAL CHECKLIST (Applies to all Grading Site Development Building and Encroachment Permits and plans including Final Parcel
CHAPTER 2 CONSTRUCTION STORMWATER POLLUTION PREVENTION
CHAPTER 2 CONSTRUCTION STORMWATER POLLUTION PREVENTION CONTENTS 2.0 INTRODUCTION 2-1 2.1 MIMINUM REQUIREMENT #2 SWPP 2-1 ELEMENT 1: MARK CLEARING LIMITS 2-1 ELEMENT 2: ESTABLISH CONSTRUCTION ACCESS 2-2
STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY
STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY Project Name Permittee NOI # Start Time Inspector s Name(s) Green Card Certification # Inspector s Contact Information
STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY STORMWATER MANAGEMENT PLAN PREPARATION GUIDANCE. Revised 4/2011. Contact information
COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT Water Quality Control Division Stormwater Program STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY STORMWATER MANAGEMENT PLAN PREPARATION
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting
TCEQ TPDES CGP EPA NPDES GCP Inspection of Controls Report
TCEQ TPDES CGP EPA NPDES GCP Inspection of Controls Report Complete this form every seven days and after every rain event of 0.5" or greater and retain in your SWP3. General Information Name of Project:
Waste Handling & Disposal
Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended
Storm Water Management Requirements for Construction Projects Less than One Acre
Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to
BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ
BEST MANAGEMENT PRACTICES (BMPs)... What are They? CLEAN STREETS MEAN CLEAN STREAMS Inexpensive to implement and easy to use, BMPs help you to do your share to protect the environment. The term Best Management
Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.
4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it
MONTANA Water Quality & Storm Water Management Training Programs For Construction Activities
MONTANA Water Quality & Storm Water Management Training Programs For Construction Activities Program Delivery: Altitude Training Associates (ATA) Course # Title Length *Prerequisite BMP 101 Introduction
STORM WATER MANAGEMENT HANDBOOK FOR CONSTRUCTION ACTIVITIES
STORM WATER MANAGEMENT HANDBOOK FOR CONSTRUCTION ACTIVITIES Prepared by City of Houston Harris County Harris County Flood Control District 2006 Edition NOTICE TO USERS The Storm Water Management Handbook
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Appendix I: BMP Inspection Form CASQA SWPPP Template 91 January2011 BMP INSPECTION REPORT Date and Time of Inspection: Date Report Written: Inspection Type: (Circle one) Weekly Complete Parts I,II,III
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
Vehicle Tracking Pad
Stormwater Quality Best Management Practices Construction Sites s When to use: Where construction vehicles leave active construction areas onto surfaces where runoff is not checked by sediment controls
Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations
SWPPP for Park Operations 2 Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations Bordered by Lake Washington & Lake Sammamish, the City of Bellevue has more than 60 miles of streams,
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
WORKERS COMPENSATION REQUIREMENTS UNDER WORKERS COMPENSATION LAW 57
January 1, 2011 WORKERS COMPENSATION REQUIREMENTS UNDER WORKERS COMPENSATION LAW 57 To comply with coverage provisions of the Workers Compensation Law ( WCL ), businesses must: A) be legally exempt from
Storm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
Storm Drain Inlet Protection for Construction Sites (1060)
Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain
STATEMENT OF ACKNOWLEDGMENT
General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities, issued 8/21/13, effective 10/1/13 Stormwater Monitoring Report SITE INFORMATION Permittee: BNE Energy
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts Submitted to: Town of Sudbury December 2011 Table of Contents 1.0 Introduction... 1 1.1 Responsibility...
Storm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering
TABLE OF CONTENTS. Page 2 of 37 Ohio EPA Permit No.: OHC000004
Page 2 of 37 TABLE OF CONTENTS PART I. COVERAGE UNDER THIS PERMIT A. Permit Area B. Eligibility C. Requiring an individual permit or an alternative general permit D. Permit requirements when portions of
SE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION
SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 104-1 Description. Provide erosion control measures on the project and in areas outside the right-of-way where work is accomplished
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
Definition of Tower from the Bradley County Zoning Resolution
Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio
Construction Site Inspection. Inspecting to Keep You in Compliance
Construction Site Inspection Inspecting to Keep You in Compliance Inspection/Monitoring/Reporting Know if your plan is working Document corrective actions Ketchikan A Contractor that destroys their site
A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems.
19. STORMWATER MANAGEMENT A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems. The majority of the approximately ±500 acre Property
Low Impact Development Checklist
New Jersey Stormwater Best Management Practices Manual February 2004 A P P E N D I X A Low Impact Development Checklist A checklist for identifying nonstructural stormwater management strategies incorporated
Annual Standards and Specifications. Erosion and Sediment Control
Annual Standards and Specifications for Erosion and Sediment Control January 2012 Version: September 15, 2009 INTRODUCTION Virginia Commonwealth University (VCU), Annual Standards and Specifications for
Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides
Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides Chris Newman US EPA Region 5 Chicago, IL Compost-Based BMPs Compost-based
Stormwater/Wetland Pond Construction Inspection Checklist
: Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials
Standard Operating Procedures Storm Drain System Maintenance
s Storm Drain System Maintenance SECTIONS 1. Storm Drain System Inspections 2. Storm Drain System Cleaning 3. Storm Drain System Repairs 4. Proper Disposal of Material Storm Sewer System Cleaning Directive
CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE
1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,
APPLICATION PROCESS FOR LAND DISTURBING PERMIT
PREFACE: APPLICATION PROCESS FOR LAND DISTURBING PERMIT The property owner, developer and designated planners and engineers shall review the general development plans and detailed plans of the Local Issuing
Beseck Switching Station Inspection
Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV
Storm Drain Inlet Protection for Construction Sites (1060)
Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain
BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
SECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS
BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS Check here for Address or phone number change the fiscal year (July 1 June 30), and date(s) maintenance was performed. Under Inspection,
Vehicle Tracking Control (VTC)
Vehicle Tracking Control (VTC) SM-4 Description Vehicle tracking controls provide stabilized construction site access where vehicles exit the site onto paved public roads. An effective vehicle tracking
CHAPTER 10 POLLUTION PREVENTION PLAN
CHAPTER 10 10.1 INTRODUCTION Virginia Stormwater Management Program (VSMP) land-disturbing activities covered under the General Construction Permit (GCP) are required to develop a Stormwater Pollution
Developing Your Stormwater Pollution Prevention Plan A Guide for Construction Sites
Developing Your Stormwater Pollution Prevention Plan A Guide for Construction Sites Who? Construction site operators (generally, the person who has operational control over construction plans and/or the
CHAPTER 62-624 MUNICIPAL SEPARATE STORM SEWER SYSTEMS
CHAPTER 62-624 MUNICIPAL SEPARATE STORM SEWER SYSTEMS 62-624.100 Policy and Purpose. 62-624.200 Definitions. 62-624.300 General Provisions. 62-624.310 General Conditions, Individual Permits. 62-624.400
C. Storm Water Pollution Prevention Plan (SWPPP) Yes No Response / Comment. D. Good Site Management Housekeeping Yes No Response / Comment
CE 2063 (Rev. 12/11) Page 1 of 8 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: CONTRACTOR NAME AND ADDRESS: Submitted by (Print Name and Sign): ORACLE NUMBER: WDID NUMBER: PROJECT SITE RISK LEVEL: Risk
Good? Bad? Why? http://uncultured.com/2007/09/20/notre-dame-and-watering-sidewalks/ Training Module 4
Good? Bad? Why? http://uncultured.com/2007/09/20/notre-dame-and-watering-sidewalks/ Solution Sprinklers should be directed at lawn areas Spraying water on pavement increases runoff Look for more water-efficient
Erosion Control and Stormwater Quality Field Guide
Perimeter Perimeter Control Control Erosion Control and Stormwater Quality Field Guide [Type the abstract of the document here. The abstract is typically a short summary of the contents of the document.
Stormwater Best Management Practice (BMP) Selection and Implementation
Stormwater Best Management Practice (BMP) Selection and Implementation January, 2003 Midwest Research Institute Funding for this program was made possible through a Section 319 Nonpoint Source Management
Architectural Processing and Inspections for Home Mortgage Insurance
Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect
Florida Department of Environmental Protection
Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,
STORM WATER MANAGEMENT PLAN (SWMP)
ENVIRONMENTAL HEALTH, SAFETY & RISK MANAGEMENT OFFICE STORM WATER MANAGEMENT PLAN (SWMP) DEL MAR COLLEGE CO-PERMITEE (Previously TXS 000601) January 24, 2009 1.0 INTRODUCTION S TORM W ATER M ANAGEMENT
Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans
APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may
SeCTion 656 - TemPoRARy Soil erosion and WaTer pollution ConTrol sewpcp requirements
Appendix C SECTION 656 - TEMPORARY SOIL EROSION AND WATER POLLUTION CONTROL 656.1 Responsibility of the Contractor-Prepare and Follow Plan. The Contractor shall provide continuous and effective temporary
Integrated Pest Management, Erosion and Sedimentation Control, and Landscape Management Plan
Integrated Pest Management, Erosion and Sedimentation Control, and Landscape Management Plan Introduction Conventional site and landscape management can have adverse impacts on the surrounding environment
SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1
SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1 An application for approval of a soil erosion and sediment control plan in accordance with these regulations shall be
Preventing Storm Water Pollution: What We Can Do
Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Streets and Drainage Maintenance PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL
III. Relying on another Governmental Entity
I. Permittee Information Permittee Name Cowlitz County Contact Name Patrick Harbison Permittee Coverage Number WAR4-524 Phone Number 36-577-33 Mailing Address 16 13th Ave. S City State Zip + 4 Kelso WA
Temporary Batch Plants
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
STORMWATER BEST MANAGEMENT PRACTICES (BMPs) & CONVEYANCES OPERATION & MAINTENANCE AGREEMENT
Prepared by / Return to: West Pikeland Township 1645 Art School RD Chester Springs PA 19425 Being UPI # 34- - STORMWATER BEST MANAGEMENT PRACTICES (BMPs) & CONVEYANCES OPERATION & MAINTENANCE AGREEMENT
DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS
DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS The City of DeSoto s Department of Development Services is the point of contact for storm drainage related issues. The following are some frequently
Operation & Maintenance Document Templates
Appendix G Operation & Maintenance Document Templates The following templates are provided to assist project applicants in preparing stormwater treatment measure maintenance plans, which municipalities
Permeable Pavement Construction Guide
Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
Carlton Fields Memorandum
Carlton Fields Memorandum TO: FROM: RE: DAN WEEDE FRED RUSHING RIPARIAN BUFFER DATE: JULY 26, 2013 BACKGROUND Both the state of Georgia and the city of Atlanta 1 have certain guidelines that must be followed
STORMWATER MANAGEMENT CHECKLIST
STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative
Storm Drain Inlet Protection
Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description Applications Installation and Implementation Requirements Devices installed at storm drain inlets to detain and/or
SECTION 5. Sediment Control Measures
SECTION 5 Sediment Control Measures 60. STORM DRAIN INLET PROTECTION When Runoff from earth change activities will discharge to a catch basin or storm drain inlet. A newly constructed catch basin or storm
Laws Requiring Pollution Prevention Practices
Laws Requiring Pollution Prevention Practices Stormwater/urban runoff is being addressed as a result of the 1987 amendments to the Federal Clean Water Act [Section 402(p)], which established requirements
D R A F T. Best Management Practices Plan (Surface Water, Sediment & Erosion Control) West Carleton Environmental Centre. May 2014
Best Management Practices Plan (Surface Water, Sediment & Erosion Control) West Carleton Environmental Centre D R A F T Prepared for: Waste Management of Canada Corporation 2301 Carp Road Ottawa, Ontario
Concrete Waste Management
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
Outdoor Storage of Raw Materials SC-33
Objectives Cover Contain Educate Reduce/Minimize Description Raw materials, by-products, finished products, containers, and material storage areas exposed to rain and/or runoff can pollute stormwater.
Storm Drain Inlet Protection - IP
Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior
Stormwater Ponds. c ıty of a bı le ne st or m wat e r utı lıty dıv ısı on
CLEAN WATER FACT SHEET Stormwater Ponds c ıty of a bı le ne st or m wat e r utı lıty dıv ısı on Rapid growth in the City of Abil ene and consequent development, as well as construction of culverts, drains,
IAC 7/2/08 Agriculture and Land Stewardship[21] Ch 44, p.1
IAC 7/2/08 Agriculture and Land Stewardship[21] Ch 44, p.1 CHAPTER 44 ON-SITE CONTAINMENT OF PESTICIDES, FERTILIZERS AND SOIL CONDITIONERS [Prior to 7/27/88, see 21 Ch 9] PESTICIDES 21 44.1(206) Definitions.
City of San Diego Urban Runoff Management Program. Appendix XI. Minimum BMPs for Mobile Businesses
City of San Diego Urban Runoff Management Program This Page Left Intentionally Blank. Minimum Best Management Practices (BMPs) for Mobile Businesses No. BMP Title Description and Examples Justification
Spill Prevention, Control & Cleanup SC-11
Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Spills and leaks, if not properly controlled, can adversely impact the storm drain system and receiving waters. Due to
Standards Oversight Council (SOC) Supporting Technical Standards for Urban and Rural Soil and Water Conservation
Standards Oversight Council (SOC) Supporting Technical Standards for Urban and Rural Soil and Water Conservation 702 E. Johnson Street, Madison, Wisconsin 53703 (608) 441-2677 Fax (608) 441-2676 [email protected]