AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate

Size: px
Start display at page:

Download "AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate"

Transcription

1 AGENDA ITEM C9 DATE: February 2, 2015 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles Carden, Chief Operating Officer South Pasco Transmission Main Condition Assessment Services with Pure Technologies U.S. Inc. - Approve SUMMARY: A desktop analysis of the pipelines in Tampa Bay Water s Pre-stressed Concrete Cylinder (PCCP) system was completed to prioritize pipelines for inspection based on relative condition and consequence of failure. Staff has negotiated a scope of services for condition assessment of the South Pasco Transmission Main with Pure Technologies U.S. Inc. RECOMMENDATION: Approve condition assessment services for the South Pasco Transmission Main with Pure Technologies U.S. Inc. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate DISCUSSION: A desktop analysis of the pipelines in Tampa Bay Water s Pre-stressed Concrete Cylinder (PCCP) system was completed by AECOM to prioritize pipelines for inspection based on relative condition and consequence of failure. The South-Central Hillsborough Regional Wellfield Transmission Main had the highest priority, and was the first piping to be inspected as part of this program in April The Cypress Creek Wellfield Collection Main condition assessment was completed in July The South Pasco Transmission Main was constructed as multiple sections between 1971 and 2004 and has a medium risk of failure based on potential condition and risk of failure as determined by the desktop analysis. This pipeline is critical to Tampa Bay Water s system because it provides regional supply to Hillsborough County s Fawn Ridge and Lake Park delivery locations and to St. Petersburg s Cosme Water Treatment Plant and is the pipeline that conveys the South Pasco Wellfield supply through the regional system. Due to the length of this pipeline, staff intends to perform the assessment over two budget years. During FY miles of the Transmission Main will be assessed. There is currently only one vendor, Pure Technologies U.S. Inc. that provides condition assessment services for PCCP while keeping the line in service. Tampa Bay Water is using the terms, conditions and unit rates of the $5.8 million dollar Miami-Dade Contract BW9537-0/16 for pipeline condition assessment that was awarded February 15, 2012 and expires February 28, This is the same procedure used previously to assess the South- Central Hillsborough Regional and Cypress Creek Wellfield Collection mains. These attached scope of services will include a detailed plan for the assessment, insertion and extraction of the devices in the pipe, a detailed report of the damage and leaks found, a

2 Matt Jordan February 2, 2015 Page 2 prediction of the rate of future damage and failure, and a recommendation for the repair priority of any damaged or leaking pipe sections. The results of the condition assessment may lead to repair of the areas of poor condition. Recommended repairs will be included in a future renewal and replacement project for portions of the South Pasco Transmission Main. BACKGROUND: Buried pipelines comprise approximately 80% of Tampa Bay water s total agency assets. These pipes vary in age and material. Tampa Bay Water and many other Municipalities have had failures of Pre-stressed Concrete Cylinder Pipe (PCCP). PCCP is constructed with a steel cylinder wrapped with pre-stressed wires, which is coated and lined with cement. Failure of PCCP can occur due to corrosion of the pre-stressed wires, caused by low-grade materials of construction, or damage during original transport and installation. For example, the 20 mile long Cypress Creek Transmission Main was replaced in its entirety due to multiple pipeline failures and its critical position in the system. It would be extremely costly to replace all of the remaining 62 miles of PCCP in our system. Advanced condition assessment technologies have been developed over the years to help utilities identify where pipe future failures are more likely to occur. This will allow staff to target pipe section for repair or replacement rather than a more expensive replacement of the entire pipeline. Attachment

3 Suzannah Folsom, P.E. January 29, 2015 Tampa Bay Water 2575 Enterprise Road Clearwater, FL Dear Ms. Folsom: Pure Technologies U.S. Inc. (Pure) is pleased to offer our services to Tampa Bay Water (TBW) for pipeline assessment. We understand that TBW would like to assess the condition of the South Pasco Transmission Main (pipeline). The pipeline is constructed of prestressed concrete cylinder pipe (PCCP) and was installed in stages between 1961 and According to the plans provided by TBW, the pipeline to be assessed consists of the following diameters and lengths: South Pasco o 42-inch 30,500 linear feet or 5.78 linear miles (Note: 1.18 miles of this section is a Steel pipeline and only SmartBall will be analyzed). The total distances listed above are according to a preliminary review of the pipeline asbuilt plans. Accessibility to the pipelines will be confirmed following a field visit and the total distance of assessment will be confirmed after the analysis of the collected data. The pipeline will be inspected in one mobilization and are tentatively scheduled to occur after March 1, A detailed project plan will be provided to TBW upon acceptance of this scope of work. In the interim, the preliminary plan for South Pasco will be to insert the equipment through the access manhole at Station on the 42-inch main (C-42 drawings). Extraction is suggested at an access manhole located at 36-inch main at approximately Station (C-35 drawings). Details for the insertion and extraction shall be coordinated with TBW but if feasible, should include a temporary shut down and depressurization by TBW. 1 P a g e

4 This project will deliver to TBW the following: 1. The number of broken prestressing wire wraps in each inspected pipe section as well as any leaks found. 2. A performance curve for each pipe design class/soil depth combination for each pipe design with broken pre-stressing wires calculated using a 3-D non-linear finite element analysis 3. A structural engineering analysis detailing the repair priority for each pipe section with broken prestressing wire wraps. This report will provide TBW: A. Categorization of the structural damage found, allowing TBW to prioritize its rehabilitation program and allocate funds accordingly in an emergency and/or an annual basis. B. Information needed to extend the useful life of their pipelines using the information as a starting point for a root cause analysis if the pipeline is deteriorating. 2 P a g e

5 Cost Estimate Pure will deliver the electromagnetic inspection on the PipeDiver platform; leak detection will be performed on the SmartBall platform. TBW will be contracting Pure through an agreement Pure currently has with the Miami-Dade Water and Sewer Department (WASD). The terms and conditions associated with the assessment for TBW are based on the contract approved for WASD by the Miami-Dade County Department of Procurement Management (Master Agreement BW ). The cost for this project is referenced in Appendix B of this Master Agreement and is detailed in the table below. Service Quantity Unit Cost Total Cost PipeDiver/Smartball Mobilization & Planning 1 $85, $85, Inspection/Analysis/Reporting: 4.60 miles $69, $321, South Pasco SmartBall only 6,230 linear $4.00 $24, feet Total $431, TBW and Pure s responsibilities are detailed in the Master Agreement, Appendix A. We look forward to providing these specialized services. If you have any questions or concerns, please do not hesitate to contact me. Regards, Mike Garaci [email protected] 3 P a g e

Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel

Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel OAWWA 73 rd Annual Conference Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel By Jason DeLaet, P.E. Supervising Engineer Greater Cincinnati Water Works & Michael J. Livermore

More information

WSSC Ad-Hoc Committee on Large Diameter Water Mains. August 2, 2013

WSSC Ad-Hoc Committee on Large Diameter Water Mains. August 2, 2013 WSSC Ad-Hoc Committee on Large Diameter Water Mains August 2, 2013 Purpose: To Gain an Understanding of WSSC s Current Approach to PCCP Inspections, Monitoring and Repair/Replacement 2 PCCP Management

More information

Meeting the Challenge of Pipeline Emergency Repair

Meeting the Challenge of Pipeline Emergency Repair Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider

More information

Force Main Condition Assessment: New Technologies & Case Studies

Force Main Condition Assessment: New Technologies & Case Studies Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the

More information

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick

More information

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Luis Aguiar Miami-Dade Water & Sewer Department Anna Pridmore, PhD Structural Technologies PROJECT BACKGROUND Miami-Dade Water & Sewer Department

More information

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Measuring the Condition of Prestressed Concrete Cylinder Pipe Measuring the Condition of Prestressed Concrete Cylinder Pipe John Marshall, P.E.I, I J.W. Marshall and Associates, and Paul S. Fisk, President NDT Corporation Introduction Prestressed Concrete Cylinder

More information

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University

More information

Chesapeake Section AWWA Symposium

Chesapeake Section AWWA Symposium PRESTRESSED CONCRETE CYLINDER PIPE (PCCP) Chesapeake Section AWWA Symposium HANSON PRESSURE PIPE Steve Smith January 16,2014 Interpace Projects with Problems INTERPACE 45 MILLION FEET 11,500 PROJECTS Slide

More information

Prestressed Concrete Pipe Fitness for Service and Repair

Prestressed Concrete Pipe Fitness for Service and Repair Prestressed Concrete Pipe Fitness for Service and Repair Rasko Ojdrovic [email protected] 781-907-9231 IAEA - EPRI 15 October 2014 www.sgh.com SGH Pipeline Experience More than 25 years of research, analysis,

More information

Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions

Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions Seth Anderson, GISP Management Consultant Celine Hyer, P.E. Associate Vice President Presentation Topics The Infrastructure

More information

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade

More information

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to

More information

SECTION 3 SANITARY SEWER DESIGN

SECTION 3 SANITARY SEWER DESIGN SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary

More information

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902 External Wrapping of Steel Riser Pipe Case Study HJ3 CS200902 Introduction Refineries process a wide variety of petroleum products. As part of the process, they rely on cooling towers, which recycle water

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY

DEPARTMENT OF ENVIRONMENTAL QUALITY PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized

More information

Sanitary Sewer Master Plan

Sanitary Sewer Master Plan , Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY

More information

Pipeline Asset Management: From Assessment to Prioritized Projects List

Pipeline Asset Management: From Assessment to Prioritized Projects List PROGRAM MANAGEMENT INEERING Pipeline Asset Management: From Assessment to Prioritized Projects List TAWWA / WEAT Summer Seminar July 28, 2011 PLANN NING ENG Andrew Hunt, PE Asset Management Project Manager

More information

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets *Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; [email protected] Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes

More information

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN

More information

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C.

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C. McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C. 111 Wheatfield Drive, Suite 1 Milford, Pennsylvania 18337 (570) 296-2765 fax: (570) 296-2767 e-mail: [email protected] RICHARD D. McGOEY, P.E. (NY &

More information

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R CCTV PIPE INSPECTION AND EVALUATION For RUNWAY 17L-35R At ST. PETERSBURG CLEARWATER INTERNATIONAL AIRPORT February 2011 CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R ST. PETERSBURG CLEARWATER INTERNATIONAL

More information

WEKO-SEAL Internal Joint Sealing WEKO-SEAL. internal pipe-joint sealing

WEKO-SEAL Internal Joint Sealing WEKO-SEAL. internal pipe-joint sealing WEKO-SEAL Internal Joint Sealing WEKO-SEAL internal pipe-joint sealing We know seals inside and out. Retaining Band Test Valve WEKO-SEAL WEKO-SEAL is the leading trenchless system for internally and economically

More information

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

City of Bakersfield Public Works Department Sewer System Management Plan December 2014 City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals

More information

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana

More information

Contracting Opportunities Vendor Day May 17, 2011

Contracting Opportunities Vendor Day May 17, 2011 Customer Care Team Contracting Opportunities Vendor Day May 17, 2011 Customer Care Team: What We Do Team Office customer advocacy and contracting Customer Relations Group call centers, claims, special

More information

Funding the Vision: Investing in Safe, Reliable Service

Funding the Vision: Investing in Safe, Reliable Service Funding the Vision: Investing in Safe, Reliable Service KUB Financial Plan Executive Summary Fiscal Year 2015 Table of Contents Funding The Vision: Investing in Safe, Reliable Service 1 KUB Proposed Fiscal

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM

SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM Page 1 of 9 SUMMARY OF DISTRIBUTION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Distribution Integrity Management Program ( DIMP ) activities are focused on obtaining and evaluating information

More information

Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems.

Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems. Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems. Aging pipeline infrastructure and industry s inability to evaluate and inspect has left many engineers and plant managers

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES

ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES Jose L. Villalobos, P.E. 1 and Carl Perry 2 Abstract: This paper presents strategies for the control of external corrosion on municipal

More information

Rehabilitation or Replacement? That Is The Question

Rehabilitation or Replacement? That Is The Question Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections

More information

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)

More information

Township of Enniskillen. Asset Management Plan

Township of Enniskillen. Asset Management Plan Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing

More information

RESPONSIBLE DEPARTMENT: ADDITIONAL DIRECTOR (S): ASSISTANT CITY MANAGER: JIM CALLAWAY

RESPONSIBLE DEPARTMENT: ADDITIONAL DIRECTOR (S): ASSISTANT CITY MANAGER: JIM CALLAWAY CITY COUNCIL AGENDA REQUEST AGENDA OF: 07-01-14 AGENDA REQUEST NO: IV-D INITIATED BY: GREG NICHOLS PROJECT MANAGER RESPONSIBLE DEPARTMENT: ENGINEERING PRESENTED BY: TIMOTHY JAHN, P.E. SENIOR ENGINEER DIRECTOR:

More information

COLLECTION SYSTEM SETTLEMENT AGREEMENT

COLLECTION SYSTEM SETTLEMENT AGREEMENT COLLECTION SYSTEM SETTLEMENT AGREEMENT Wastewater Collection System Rehabilitation and Replacement Report and Plan A deliverable of the Settlement Agreement and Final Order between the city of Los Angeles

More information

North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show. Orlando, Florida April 13-17, 2014

North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show. Orlando, Florida April 13-17, 2014 North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Miami Thrice; Lanzo, HJ3, and Carbon Fiber combine to preempt Catastrophic Line Breaks

More information

RESTRICTING GROUNDWATER WITHDRAWALS TO PROTECT WATER RESOURCES: ECONOMIC IMPACT ASSESSMENT

RESTRICTING GROUNDWATER WITHDRAWALS TO PROTECT WATER RESOURCES: ECONOMIC IMPACT ASSESSMENT CHAPTER 14 RESTRICTING GROUNDWATER WITHDRAWALS TO PROTECT WATER RESOURCES: ECONOMIC IMPACT ASSESSMENT Grace Johns and Lisa A. McDonald Economic analysis methods have been used in Florida to identify positive

More information

Bridges & Culverts Condition by Quantity

Bridges & Culverts Condition by Quantity 3.4.3 What condition is it in? Approximately 93% of the municipality s bridge structures are in good to excellent condition, with the remaining 7% in fair condition. As a result, the municipality received

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT

TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT I / 7 Natural Gas Transport. General principle The most efficient and effective method of natural gas distribution from the place of production to the

More information

Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands

Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands Waste Management Infrastructure Rehabilitation in the U.S. Virgin Islands The United States Virgin Islands is a group of islands in the Caribbean that are an insular area of the United States. The islands

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR ABSTRACT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 Virginia

More information

Emerging Technologies in Wastewater Collection Systems

Emerging Technologies in Wastewater Collection Systems Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation

More information

Using Risk-Based GIS Modeling Software to Optimize Sewer Renewal Planning

Using Risk-Based GIS Modeling Software to Optimize Sewer Renewal Planning Close Using Risk-Based GIS Modeling Software to Optimize Sewer Renewal Planning By Paul F. Boulos Rapid population growth and the deterioration of aging infrastructures are overtaxing sewer systems worldwide.

More information

At the end of today s seminar you should be better. Recognize the causes of Sewer Lateral backup. Identify techniques to protect your home from

At the end of today s seminar you should be better. Recognize the causes of Sewer Lateral backup. Identify techniques to protect your home from Preventing Sewer Backups Presented by IAPMO Today s Objectives At the end of today s seminar you should be better able to: Recognize the causes of Sewer Lateral backup Identify techniques to protect tyour

More information

SANITARY SEWER SYSTEM ASSESSMENT

SANITARY SEWER SYSTEM ASSESSMENT SANITARY SEWER SYSTEM ASSESSMENT What is this tool? The Sanitary Sewer System Assessment is a form that helps your utility identify and document all of the components in your utility s sanitary sewer system.

More information

NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without

More information

Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida

Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida GWPC September 27, 2015 Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida Virginia Walsh, PhD, P.G. Miami-Dade Water and Sewer Department Ed Rectenwald, P.G. MWH

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 1/12/2007 1 Briefing Purpose Provide update on Wastewater Collection Activities

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort June 25, 2012 Thomas Gossiaux, PE (AECOM) Matt Raysin, PE (GCDC-WWS) Dave Barnas, PE (AECOM) Ed Tharp, PE (AECOM) Summary

More information

HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS

HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS Shiwei William Guan, Ph.D. Vice President, R&D and International Business Madison Chemical Industries Inc. 490

More information

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM Stadium Reconstruction EIR Appendices \ AECOM Technical Services, Inc 401 West A Street Suite 1200 San Diego, CA 92101 www.aecom.com 619-610-7600 tel 619-610-7601

More information

City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS

City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS Page No. 1.0 INTRODUCTION...2 2.0 PIPE MATERIAL CONSIDERATIONS...3 2.1 RCP...

More information

Water Main Lining A Sustainable Alternative to Open Cut Replacement

Water Main Lining A Sustainable Alternative to Open Cut Replacement Water Main Lining A Sustainable Alternative to Open Cut Replacement Sean O Dell, PE Baxter & Woodman, Inc. B&W Client Seminar, Crystal Lake May 1, 2014 Agenda Why, What, When, Where, Who, How Reduction

More information

Design Criteria & Service Goals

Design Criteria & Service Goals 4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on

More information

Best Practices Manual for Prestressed Concrete Pipe Condition Assessment: What Works? What Doesn t? What s Next?

Best Practices Manual for Prestressed Concrete Pipe Condition Assessment: What Works? What Doesn t? What s Next? Best Practices Manual for Prestressed Concrete Pipe Condition Assessment: What Works? What Doesn t? What s Next? Subject Area: Infrastructure Best Practices Manual for Prestressed Concrete Pipe Condition

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

SOCALGAS APROACH TO PIPELINE INTEGRITY

SOCALGAS APROACH TO PIPELINE INTEGRITY SUMMER 2011 SOCALGAS APROACH TO PIPELINE INTEGRITY Southern California Gas Company (SoCalGas ) is committed to providing clean, safe and reliable natural gas to its customers and takes important steps

More information

49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards

49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards 49 CFR 192 Transportation of Natural and Other Gas By Pipeline: Minimum Federal Safety Standards THIS DOCUMENT CONTAINS ONLY THE SECTIONS NEEDED FOR THE API 1169 ICP EXAMS Subpart G General Construction

More information

City Code citations from various small, medium and large cities on ownership of sewer service connections:

City Code citations from various small, medium and large cities on ownership of sewer service connections: From: Kody Van Dyk Sent: Wednesday, October 29, 2014 2:09 PM To: Carrie Logan; Scot Campbell Cc: Maree Peck; Bruce Robertson; Shannon Syth Subject: Sewer Service Repair/Replacement A Sandpoint property

More information

Dry Weather Flow from Footing Drains and Service Connections

Dry Weather Flow from Footing Drains and Service Connections Wastewater Master Plan DWSD Project No. CS-1314 Dry Weather Flow from Footing Drains and Service Connections Technical Memorandum Original Date: May 2, 2002 Revision Date: September 2003 Author: CDM Table

More information

Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective

Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Building the Foundation for an Effective Asset Management Program Scott D. Kelly, P.E. Assistant City Administrator

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

ASSET MANAGEMENT PLAN Published January 2009

ASSET MANAGEMENT PLAN Published January 2009 San Diego County Water Authority 2 0 1 1 ASSET MANAGEMENT PLAN Published January 2009 4677 Overland Avenue San Diego, CA 92123 858-522-6600 www.sdcwa.org This page intentionally left blank. Table of Contents

More information

MEMORANDUM. General: Foundation:

MEMORANDUM. General: Foundation: MEMORANDUM State of Alaska Department of Transportation and Public Facilities Central Region - Division of Construction and Operations Public Facilities Branch TO: Jennifer Murrel DATE: August 19, 2010

More information

CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN

CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN Adopted October 5, 2009 Table of Contents Chapter Description Page 1 Facility Descriptions... 3 1.1 Municipal Power Plant, 1001 Park

More information

Houston Asset Management In The Fast Lane: Final Report

Houston Asset Management In The Fast Lane: Final Report City of Houston Asset Management In The Fast Lane: Final Report Sandeep Aggarwal PE, Managing Engineer, City of Houston Yvonne W. Forrest, Senior Assistant Director, City of Houston Paul Schumi, Director,

More information

Let Us Give Utilities the Respect that they Deserve.

Let Us Give Utilities the Respect that they Deserve. Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous

More information

Bulletin. Gerard D. Perry, Director of Accounts. DATE: August 2014. Sewer Rate Relief Fund FY2015

Bulletin. Gerard D. Perry, Director of Accounts. DATE: August 2014. Sewer Rate Relief Fund FY2015 Massachusetts Department of Revenue Division of Local Services Amy A. Pitter, Commissioner Robert G. Nunes, Deputy Commissioner & Director of Municipal Affairs Bulletin TO: Mayors, City Managers, Selectmen,

More information

INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By

INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By ABSTRACT Migdalia Hernandez, City of Sanford P.O. Box

More information

The Original Carbon Fiber Reinforced Polymer System

The Original Carbon Fiber Reinforced Polymer System Infrastructure The Original Carbon Fiber Reinforced Polymer System Phone: 52.292.39 Toll Free: 866.38.269 Fax: 52.48.5274 282 E. Fort Lowell Rd. Tucson, AZ 8576 www.dowaksausa.com Test results are supported

More information

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

More information