Risk Workshop Overview. MOX Safety Fuels the Future
|
|
|
- Georgiana Shaw
- 10 years ago
- Views:
Transcription
1 Risk Workshop Overview
2 RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification 3. TPRA 4. Risk Item Identification and Management Process Risk Registry Quantification Contingency Risk Identification Handling Closure 2
3 MFFF Risk Program Three Related Programs 1. Estimate and Schedule Uncertainty Analysis - documents the project planners and estimators degree of uncertainty with the estimate and schedule. This report also establishes a recommendation for Management Reserve at the 85% confidence level for the MOX Project Manager to mitigate cost and schedule issues during project execution that could not be precisely defined during the planning and estimated phase. 2. Technical and Programmatic Risk Analysis - evaluates potential project risks (both cost and schedule), factoring in the likelihood and consequence of each potential risk event, and suggests a contingency budget at the 85% confidence level. 3. Risk Management - manages identified Risk Events throughout the project lifecycle so that there is a minimal and acceptable impact on the cost, schedule, construction, engineering, and operational performance. 3
4 Management Reserve and T&PRA Contingency DCS Management Reserve for Estimate/Schedule Uncertainty Impacts due to Uncertainties in Estimating/Scheduling Defined Work Scope DOE Contingency Allowance for Technical & Programmatic Risk Analysis (T&PRA) Impacts due to Potential Discrete Risk Events Evaluation of uncertain issues effect on Integrated Project Schedule (IPS) & Option 1 Contract Budget Base (CBB) Estimate Evaluation of discrete risk events to determine individual Cost and Schedule Impact Monte Carlo analysis of cumulative Cost Impact to CBB Monte Carlo analysis of cumulative Schedule Impact to IPS Monte Carlo analysis of cumulative Cost impact to Total Project Costs (TPC) Monte Carlo analysis of cumulative Schedule Impact to IPS Uncertainty Impacts added to CBB Estimate and IPS to achieve 85% LOC in CBB/IPS Recommendation to DOE on T&PRA Contingency Allowance to achieve 85% LOC in TPC / IPS 4
5 Estimate and Schedule Uncertainty Analysis Control Accounts Created for WBS - Element Definitions -BOEs Uncertainty Categories Assigned - Justification Forms with BOEs - Standard Ranges Monte Carlo Cost Simulation - Converge at 85% Confidence - Record Cost Uncertainty Monte Carlo Simulation on Schedule Durations - Converge at 85% - Convert Duration Uncertainty to Hotel Load. Sum Cost Uncertainty and Hotel Load - Sum equals MR Recommendation Sum of Cost Uncertainty and Duration Uncertainty establishes MR Document Control Accounts Monte Carlo simulation of Triangulated Durations ESUA Process Basis for Cost Estimate Establish Uncertainty Category Monte Carlo Simulation of Triangulated Cost 5
6 Document Control Accounts Control Account Managers create the Element Definitions for the Control Account s Scope of Work. Control Accounts may be further detailed to Work Packages if detail is required to clarify levels of uncertainty. 6
7 Basis for Cost Estimate The Estimate of Cost and Duration is based on Historical Data, Documented Experience, Parametric Calculations, or Vendor Quotes. Estimates must be well documented with assumptions to support validations. Basis-of-Estimates are attached to the Element Definitions of Scope and are part of the controlled Baseline. 7
8 Establish Uncertainty Category Control Account Managers are responsible for establishing the Uncertainty Category for each Control Account or Work Package. Each Control Account is identified as a Definitive (D), Budget (B) or Conceptual (C) estimate. In some cases the uncertainty category may be assigned an X classification to allow the CAM to expand the range based on Vendor or supplier data. 8
9 Monte Carlo Simulation of Triangulated Cost The Uncertainty Data from the Control Account ESUA Forms is analyzed in a Monte Carlo Simulation. Each Estimate categorized for its uncertainty is represented by a triangulated range and calculated to an 85% Confidence level. Uncertainty ranges input to the Simulation software are (D) Definitive -5% to + 15% (B) Budget -15% to + 30% (C) Conceptual -30% to + 50% (X) User Defined (Range based on Vendor Quotes) 9
10 Monte Carlo simulation of Triangulated Durations The Schedule Monte Carlo analysis is loaded in PertMaster from the ESUA database. The uncertainties and the associated consequences are logically tied to the baseline activities creating a PertMaster modified model of the Project Schedule. The schedule slip is used to calculate the proposed MR for Schedule ESUA 10
11 Sum of Cost Uncertainty and Duration Uncertainty establishes MR To establish the overall recommendation for MR value, Monte Carlo Cost Value and the PertMaster Monte Carlo 85 % Level of Confidence Schedule Value are summed. 11
12 TPRA Analysis using the PertMaster RISK MANAGEMENT PROCESS Schedule Review - Risk Ready State - Review for logic & errors Risk Identification - Estimate Uncertainty - Risk Events: Risk Register Develop Preliminary Risk Model - Enter Estimate Uncertainty - Map Risks to Activities Preliminary Analysis & Review - Impacted Risk Plan - Monte Carlo simulation Final Model & Report - Risk Event plan - Response planning Risk Reporting Risk Response Schedule Review Risk Management Process Risk Risk Identification Assessment Based on: PMBOK Chapter 11
13 Schedule Review Schedule Check Checks for Schedule Best Practices Remember... Not Everything has to be Perfect Don t delete Problem Activities...Defeats the Purpose! Pre-Analysis Check Not all Schedule Issues will be identified by Schedule Check The Pre-Analysis Run will check Duration, Criticality and Relative Duration to Project 13
14 Risk Identification Estimate Uncertainties Identify Risky Areas of the Project Focus on the Critical Path and High Risk Activities. Decide if risk is based on Project Phase, Area of Work, Contractor. Document Assumptions, Corrective Actions, and Mitigations. Create a Risk Register Document Risk and Modify as Necessary. Identify Risk Item Owners and a Tracking/Reporting System. 14
15 Risk Assessment Developing a Risk Model requires an application of the data collected in the previous step run through a calculating tool. Estimate Schedule Uncertainty Applied from ESUA in PertMaster Import Schedule Data. Review Task Detail and Correct if Necessary. Establish Correlation between Activities or Groups of Activities. Update Risk Index For each Risk, Qualitatively Assess Probability, Schedule Impact, Cost Impact and Performance Impact. Map each Risk to specific tasks. Triangulate the Cost and Schedule Quantitative Impacts. 15
16 Risk Response Build the Impacted Plan Each Risk Item is added to the Model as a Task Run the Analysis View the Results Re-work the Plan Add Mitigation Plan from Risk Index to Model Re-run the plan Save the Pre- and Post-mitigation plans 16
17 Risk Reporting Schedule Comparison Options Dependent on Customer Deterministic Bar 85% Probabilistic S-Curves 17
18 Monte Carlo Simulation Monte Carlo Range forms an Envelope One Value each Iteration Random Simulation of Durations Iterations 1 10 Days 2 9 Days 3 14 Days 4 17 Days 5 10 Days 6 14 Days 7 21 Days 8 13 Days 9 3 Days 10 7 Days Days Days 13 etc Optimistic Likely Pessimistic 18
19 Monte Carlo Simulation 19
20 Risk Summary Estimate Uncertainty (ESUA) Based on a model of 3-Point Estimate Monte Carlo Simulation Risk Events (TPRA) Creates a Registry of Risk Items Assign Probability and Impact Values in a Matrix Risk Mitigation Action to reduce the impact of the Risk Establishes Contingency Estimate Uncertainty + Risk Event Mitigation = Total Risk Exposure 20
21 Identify Risk Brainstorming Sessions with SMEs Documenting Risk Items in Database Technical and Programmatic Risk Management Process Analyze Risk Evaluate Potential of Risk Occurrence Identify Impact Points in Schedule Identify Owners and Stakeholders Identify Analyze Qualify Risk (Low, Medium, High) Establish Probability of Occurrence Establish Cost and Schedule Impact Ranges Load Risk into Registry and Calculate Risk Score Quantify Risk Establish Potential Cost of Risk Impact (pre- Mitigation) Establish Potential Schedule Impact (premitigation) Monitor and Status Risk Management Process Qualify Decide Handling Strategy Accept Plan as part of PMB Avoid Plan action required an include in PMB Mitigate (Reduce) Decide when to take action and when to include action in PMB. Transfer Concurrence with new Owner Re-Quantify Impacts based on Handling Cost and Actions (post-mitigation) Handle Quantify Monitor and status Update Quarterly or if action occurs Use of Risk Item Change Form Quarterly Reporting from IRMC 21
22 Risk Item Management Process Risk Owner Risk Item Identified Submit Risk Form to Risk Manager Complete Qualification Quantify Risk Review and Update Registry Risk Manager Review Risk Form Add Risk to Risk Registry Link Risk to Schedule Review and Resolve Registry Updates Delete Closures Schedule Meeting with Risk Owner Schedule Meeting with Risk Owner Build Cost and Duration Profiles Export Risk Registry Generate and Export Registry Reports Re-build Profiles Integrated Risk Management Committee (IRMC) Review/Approve Proposed Adds and Closures 22
23 23
24 24
25 25
26 Risk Comparisons DOE Risks Characteristics Identified During Planning Phase and through Implementation May include Threats and Opportunities Impact must be qualified in premitigation. Handling strategies include avoidance, acceptance and mitigation. Typical Risk Matrix is 3X3 or 5X5 Risk Management is tied to Standard Guidelines. Non-DOE Risk Characteristics Identified during Early Project Initiation and Definition Phase and through implementation Only include Threats! Opportunities are BD responsibilities. If impact is considered low, no further action required. Treated as an Assumption. Any handling of the risk is for mitigation. Acceptance is considered paying to mitigate. Matrix may be 9X9 to include impacts on customers or public. Risk Programs are developed by the Project Steering Committee based on Project Complexity. 26
27 Non-DOE RISK Process Identify Potential Risks List/Add Risk to Log Is Risk High? Complete a Risk Form Add to Project Records and Status Monthly Mitigation Requires new Project Monitor and Review Submit to Project Office 27
28 Risk Identified as: RISK Handling Business (financial, legal, Market, Political) Process (Procedural) Project (technical) Risks are Ranked by Probability and Impact (Qualified) Only High Scored Risks have Mitigation Plans All Risk are Periodically Reviewed for Score Changes HIGH RISKS are Classified as Unacceptable and must be mitigated to lower score before Project can proceed 28
29 RISK Impact Not Calculated against the schedule. Consequences not quantified unless they effect the business decision. Any Risk that becomes a reality must be mitigated. Acceptance is considered mitigation if it does not delay the project. Documented Risks are used to justify Change Orders. 29
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
Risk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
Quantitative Risk Analysis with Microsoft Project
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
1.20 Appendix A Generic Risk Management Process and Tasks
1.20 Appendix A Generic Risk Management Process and Tasks The Project Manager shall undertake the following generic tasks during each stage of Project Development: A. Define the project context B. Identify
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Project Risk Management
Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
Risk Review Process Basics
2011 PMOC Annual Meeting FEDERAL TRANSIT ADMINISTRATION Risk Review Process Basics Michael P. Wetherell, PE - Urban Engineers David N. Sillars, PE Sillars Consulting FEDERAL TRANSIT ADMINISTRATION 2011
PROJECT RISK ASSESSMENT & MANAGEMENT
PETROSYNC S PROJECT MANAGEMENT SERIES PROJECT RISK ASSESSMENT & MANAGEMENT Your Key To Analyse & Identify Risk In Project Risk Management 1 March 4 March 2016 Bali, Indonesia Supported By Course Overview
Risk Analysis and Quantification
Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419
Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419 ABSTRACT David T. Hulett, Ph.D., Hulett & Associates, LLC Michael R. Nosbisch, CCC PSP, Project Time and Cost, Inc. This
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_risk_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition
A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise
Incorporating Risk Assessment into Project Forecasting
Incorporating Risk Assessment into Project Forecasting Author: Dione Palomino Conde Laratta, PMP Company: ICF International - USA Phone: +1 (858) 444-3969 [email protected] Subject Category: Project
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
Project Management. [Student s Name] [Name of Institution]
1 Paper: Assignment Style: Harvard Pages: 10 Sources: 7 Level: Master Project Management [Student s Name] [Name of Institution] 2 Project Management Introduction The project management also known as management
Project Risk Management Handbook: A Scalable Approach
Project Risk Management Handbook: A Scalable Approach Version 1 (June 2012) Risk Monitoring Qualitative Risk Analysis Risk Response A LETTER FROM THE CHIEF ENGINEER Welcome to the new Caltrans Project
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES OP-09/2013 Responsible Unit: PMO Focal Point OBJECTIVE: This Operational Procedures presents the guidelines for the risk assessment and allocation process in projects.
Creating A Risk Management Plan
Creating A Risk Management Plan A presentation based on the concepts taught in the Risk Management 1A course. Carlos Consulting Group Roseville, CA. (916) 521-2520 www.carlosconsulting.com 1 Objectives
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
Project Risk Management. Presented by Stephen Smith
Project Risk Management Presented by Stephen Smith Introduction Risk Management Insurance Business Financial Project Risk Management Project A temporary endeavour undertaken to create a unique product
INT 3 Schedule Risk Analysis
INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,
Acompany that consistently selects the right projects and
PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
Negative Risk. Risk Can Be Positive. The Importance of Project Risk Management
The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project and in the best interests t of
Value Engineering VE with Risk Assessment RA
Preparation Conclude & Report Value Engineering VE with Risk Assessment RA yes START Plan for VE and RA Value Engineering Job Plan 1 2 Function Information Analysis 3 Creative 4 Evaluation 5 Develop recommendations
OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.
OTC 12979 Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
Technology based Project Management Consulting (T-PMC): Innovate to Reduce Costs
Technology based Project Management Consulting (T-PMC): Innovate to Reduce Costs Graham Freeth, North African Oil and Gas Summit, Tunis, Tunisia October 2009 J P Kenny Offices World Wide Aberdeen Stavanger
Project Risk Management
PROJECT ADVISORY Project Risk Management Leadership Series 9 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes, but its content is
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
The Program Managers Guide to the Integrated Baseline Review Process
The Program Managers Guide to the Integrated Baseline Review Process April 2003 Table of Contents Foreword... 1 Executive Summary... 2 Benefits... 2 Key Elements... 3 Introduction... 4 IBR Process Overview...
Basic Schedule Analysis
Basic Schedule Analysis Topics Why are Schedules Important Scheduling Basics Attributes of a Valid Schedule Scheduling Best Practices Basic Schedule Analysis Tools and Techniques Sources: NASA Schedule
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
ITS Project Management Methodology
ITS Project Management Methodology Information Technology Services Project Management Group 11/17/2014 Version 2.1 Author: ITS Project Management Group Document Control Change Record Date Author Version
PROJECT RISK ANALYSIS AND MANAGEMENT
PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest
Certificate In Project Management (CIPM)
Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Certificate In Project Management (CIPM) Course Overview The Certificate
RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES
RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES August 2012 This page is left intentionally blank NEVADA DEPARTMENT OF TRANSPORTATION RISK MANAGEMENT AND RISK-BASED COST ESTIMATION GUIDELINES
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson
Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced
Risk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT
RISK MANAGEMENT PLAN FOR THE PROJECT Prepared by: Approved by: Reference: Version: Date: INTRODUCTION This document is the Risk Management
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PBL: Project Management. Competency: Project Definition
Competency: Project Definition 1. Define project management and the context of modern project management. 2. Describe how to manage projects throughout the five major process groups. 3. Define the characteristics
STAG Technical Database Section 13
Risk and Uncertainty May 2014 Transport Scotland Once printed or downloaded this document is considered to be uncontrolled. For the current version refer to the Scot-TAG section of the Transport Scotland
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Guidelines for a risk management methodology for product design
Guidelines for a risk management methodology for product design Viviane Vasconcellos Ferreira Federal University of Santa Catarina [email protected] André Ogliari Federal University of Santa Catarina
PMI Risk Management Professional (PMI-RMP) Exam Content Outline
PMI Risk Management Professional (PMI-RMP) Exam Content Outline Project Management Institute PMI Risk Management Professional (PMI-RMP) Exam Content Outline Published by: Project Management Institute,
A Risk Management Standard
A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
ISO, CMMI and PMBOK Risk Management: a Comparative Analysis
ISO, CMMI and PMBOK Risk Management: a Comparative Analysis Cristine Martins Gomes de Gusmão Federal University of Pernambuco / Informatics Center Hermano Perrelli de Moura Federal University of Pernambuco
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
SCRAM: A Method for Assessing the Risk of Schedule Compliance
SCRAM: A Method for Assessing the Risk of Schedule Compliance Adrian Pitman Defence Material Organisation Australia Angela Tuffley Red Bay Consulting Pty Ltd Australia Betsy Clark Software Metrics Inc.
Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses
Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses David T. Hulett, Ph.D. Keith Hornbacher, MBA Waylon T. Whitehead Hulett & Associates, LLC Los
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Security Risk Assessment and Mitigation Prioritization
Security Risk Assessment and Mitigation Prioritization Stephanie King, PhD, PE Weidlinger Associates, Inc. FFC Committee on Physical Security and Hazard Mitigation July 15, 2008 www.wai.com New York Massachusetts
The Cost of Risks. Essence of Risk Quantification. PALISADE @RISK Forum Calgary 2008
PALISADE @RISK Forum Calgary 2008 The Cost of Risks Essence of Risk Quantification Disclaimer: This presentation material is provided for general information. The author shall not be held accountable for
Sample Examination Questions
Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes
NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Risk Management Procedure
Purpose of this document Develop and document procedures and work instructions for Risk Management to cover the project Stages set out in the Project Process Map. The purpose of this procedure is to identify
Project Zeus. Risk Management Plan
Project Zeus Risk Management Plan 1 Baselined: 5/7/1998 Last Modified: N/A Owner: David Jones/Zeus Project Manager Page Section 1. Introduction 3 1.1 Assumptions, Constraints, and Policies 3 1.2 Related
Specialists in Strategic, Enterprise and Project Risk Management. PROJECT RISK MANAGEMENT METHODS Dr Stephen Grey, Associate Director
BROADLEAF CAPITAL INTERNATIONAL PTY LTD ACN 054 021 117 23 Bettowynd Road Tel: +61 2 9488 8477 Pymble Mobile: +61 419 433 184 NSW 2073 Fax: + 61 2 9488 9685 Australia www.broadleaf.com.au [email protected]
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
USING THE EVALUABILITY ASSESSMENT TOOL
USING THE EVALUABILITY ASSESSMENT TOOL INTRODUCTION The ILO is committed to strengthening the Office-wide application of results-based management (RBM) in order to more clearly demonstrate its results
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
PMI Lexicon of Project Management Terms
Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
The Past and Future of CPM Project Scheduling. Dr. Dan Patterson PMP Pertmaster, Acumen, PMFocus Founder
The Past and Future of CPM Project Scheduling Dr. Dan Patterson PMP Pertmaster, Acumen, PMFocus Founder Introduction Innovation not Invention Invent To create new Innovate To make better It s Not About
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
