Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame
|
|
|
- Tyrone McBride
- 10 years ago
- Views:
Transcription
1 1.0 Inception 1.1 Project Request from Client / User 1.2 Assignment Preliminary Project Charter Submit Project Charter to Obtain internal project number Initial Project Authorization (PA) 1.9 Funding Client or User to generate formal request for a project Manager reviews and assigns the request to a Project Manager or discipline Manager Prepare a preliminary charter document that includes scope and total project cost estimate Submit Project Charter to Client / User for approval Written approval of Project Charter required from confirms understanding of scope Request project number form Support Staff/Accounting Generate initial project authorization based on approved Project Charter Circulate for signatures Return of signed PA with coding Transfer of funds from to PR Finance Use standard form to request project or estimate Construction costs based on experience / history Professional consulting fees including set PR management fees Additional soft costs Require confirmation that Project Charter is understood Required to move forward Initial authorization may be for seed money for consulting and management or for full funding to end of bid period Required to move to next phase NA 2.0 Initiation 2.1 Develop Project Charter 2.2 Submit to 2.3 Written Project Charter (further detailed) for inclusion into proposed documents Submit written detailed scope to Client / User for approval Written approval of Project Charter required from prior to issue Required to move forward Physical Resources - Design, Engineering & Construction Page 1 of 6
2 Establish internal Committees Consultant Selection Process 2.6 Procure Reports Establish Steering Committee and / or Building Committee Expression of Interest (EOI) Request for Proposals (RFP) Topographic survey Geotechnical boreholes and reports Hazardous materials In consultation with Senior U of G Staff and Prepare, issue, advertise, receive expressions, evaluate, award 2 to 2 to 3 to 6 weeks 3 to 6 weeks 2 to 3.0 Pre-design 3.1 Formal agreement With Consultant 3.2 Scope Development 3.3 Functional Program 3.4 Construction cost 3.5 Submit to 3.6 Periodic meetings with Client/user Periodic meetings with steering Site visits Initial confirmation of program including space allocation and requirements Initial confirmation on construction cost Submit written detailed scope, functional program and cost to Client / User for approval Written approval of program, scope and cost required from Initiate, provide for signature, return, execute by U of G Bi-weekly or as required. Confirm requirements, reviews Seek approvals and/or direction As required for confirmations Approval required to move forward 2 to Physical Resources - Design, Engineering & Construction Page 2 of 6
3 4.0 Schematic Design Periodic meetings with Client/user Bi-weekly or as required. Confirm requirements, reviews, 4.1 Develop design Periodic meetings with steering Seek approvals and/or direction Site visits As required for confirmations 4.2 Cost check Confirmation on construction cost 4.3 Submit to Submit written detailed scope, functional program and cost to Client / User for approval Submit for Site Plan Approval Submission to Board of Governors 4.7 Stakeholder Review Of schematic design documents drawings, outline spec and cost Prepare and issue documentation as required for committees PRPC, Finance, Board Submit a copy of the approved schematic design documentation to stakeholders at U of G for their review and comment Client Sign-off required to move to next phase By Consultant based on schematic design as approved if required Request a return of comments within a specific time frame. Must include any standing committees with U of G - landscape, accessibility, space 4 to 6 weeks varies 5.0 Design Development Periodic meetings with Client/user Bi-weekly or as required. Confirm requirements, 5.1 reviews, Detailed development of Periodic meetings with steering Seek approvals and/or direction schematic design 6 weeks Site visits As required for confirmations 5.2 Cost check Confirmation on construction cost 5.3 Submit to Submit design development and cost to Client / User for approval 5.3 Of design development documents Client Sign-off required to move to next drawings, outline spec and cost phase Required to move to next phase Physical Resources - Design, Engineering & Construction Page 3 of 6
4 6.0 Construction Documents Periodic meetings with Client/user Bi-weekly or as required. Confirm requirements, 6.1 reviews, Completion of detailed Periodic meetings with steering Seek approvals and/or direction documents for bidding 6 to 8 weeks Site visits As required for confirmations 6.2 Final Cost check Confirmation on construction cost 6.3 Submit to Submit documents and cost to Client / User for approval 6.4 Of construction documents Client Sign-off required to move to next drawings, outline spec and cost phase Expression of Interest (EOI) - Issue, advertise, receive expressions, evaluate, select General 2 to 3 weeks 6.5 Contractor Selection Pre-qualification process Contractors 6.6 Stakeholder Review Manager / Director approval Building Permit Application Issue completed documents to all pertinent stakeholders for review Seek approval from Manager or Director to issue bids Submit a copy of bid documents to City for building permit Formal pre-qualification - Issue document, receive documents, evaluate, award Receive comments, review comments, initiate revisions in form of addendum or change orders as required prior to final printing of the bid documents By Consultant 3 weeks 4 to 6 weeks 7.0 Bidding 7.1 Issue 7.2 Bid Period 7.3 Receipt of bids 7.4 Evaluation of bids Issue bids documents to prequalified bidders The receipt and opening of bids received Detailed review of the bids received, make recommendations, revise total project budget based on accepted bid Use Support Staff and comply with written procedures Provide direction as required on inquiries for addendum to be issued by Consultant Comply with written procedures Comply with written procedures Physical Resources - Design, Engineering & Construction Page 4 of 6
5 7.5 Generate second PA Funding 7.8 Award Generate 2 nd Project Authorization (if required) for additional funding based on accepted bid Return of signed PA with coding Transfer of funds from to PR Finance Prepare and issue letter of intent or acceptance for signature and execution Required to move to next phase Based on accepted bid and project requirements 8.0 Construction 8.1 Completion and execution of formal contracts 8.2 Construction Period Consultant to assemble and prepare formal contracts for execution by U of G and Contractor Construction activities, contract administration, certification for payment, Periodic meetings with steering Periodic site meetings, approvals for revisions, reviews of the work Seek approvals and/or direction Varies - months to years 8.3 Commissioning Start-up of equipment and systems Training of U of G personnel and staff Varies 8.4 Closeout Final close-out of construction and Final payments to contractor, adjustments to project including financials funding Varies 8.5 Move-in Occupancy of the new spaces by Physical move by client/users into new Client spaces/building 8.6 Satisfaction Survey Survey to be sent to Client for their feedback on project and services 9.0 Warranty / Post Construction 9.1 One Year Warranty Period Correction of any outstanding deficiencies found during warranty period Formal reviews and sign-off by PR 12 months from formal acceptance Physical Resources - Design, Engineering & Construction Page 5 of 6
6 Notes:.1 Phases for all projects are generally the same..2 s will vary based on complexity of the proposed project and length of time required to receive approvals..3 The expected time frame for one activity may overlap the time frame for another activity..4 Not all Phases will require all of the activities listed. Physical Resources - Design, Engineering & Construction Page 6 of 6
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS
CARROLL COUNTY PUBLIC SCHOOLS ADMINISTRATIVE REGULATIONS BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS Administrative Procedures For Appointment of Architectural, Engineering and Construction
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
THE TOWN OF NORTH SMITHFIELD
THE TOWN OF NORTH SMITHFIELD SPECIFICATIONS FOR REQUEST FOR PROPOSALS FOR EMERGENCY PLANNING, DISASTER RECOVERY, DEBRIS MANAGEMENT, AND HAZARD MITIGATION PROGRAM SERVICES SEPTEMBER 2014 FINANCE DIRECTOR
FGP-WPMP Supplier Qualification overview
FGP-WPMP Supplier Qualification overview Tengizchevroil 2014 Purpose and intent Supplier Qualification Process is: To ensure work with qualified, reliable and reputable suppliers To identify potential
MONTGOMERY COLLEGE JOB CLASS SPECIFICATION
MONTGOMERY COLLEGE JOB CLASS SPECIFICATION Title: Project Manager I (Facilities) Grade: J FLSA: Nonexempt Financial Disclosure: No Job Class Level: This includes performance level positions in the Project
Design-Build Process for Project Managers
Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel
THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL
THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL OCTOBER, 2013 TABLE OF CONTENTS 1. CHECKLIST PAGE NO. 2. CHECKLIST DETAILS A. Design Path 3 B. Property Acquisition 6 C. Outside
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under
Volume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
BIDDING REQUIREMENTS, CONTRACT FORMS, CONDITIONS OF CONTRACT
BIDDING REQUIREMENTS, CONTRACT FORMS, CONDITIONS OF CONTRACT 1. General Information 1.1. Preparation of Bidding Documents: The owner s representative shall provide master documents (these documents are
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
Planning and Construction Management Services
Planning and Construction Management Services Construction Project Management Services New construction, major renovations or improvements to building structures and systems are part of the Department's
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community
REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1
REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services
GENERAL CONTRACTOR PRE-QUALIFICATION 2014 - FOR PERIOD ENDING DEC 2017
APPLICATION for PRE QUALIFICATION GENERAL CONSTRUCTION CONTRACTORS Construction Projects up to $3,000,000 Prequalified General Contractors will be invited to submit bids for various Renovation and Construction
TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #2015-12
TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #2015-12 Sealed bids are due by 10:30 am on Friday, January 30, 2015 Bid Specs are
North American Development Bank. Model Prequalification Document: Prequalification of Contractors
North American Development Bank Model Prequalification Document: Prequalification of Contractors 2 Preface Procurement under projects financed by the North American Development Bank (the Bank), is carried
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET UCC and CPC MDOS Letters to FileNet PROJECT MANAGER STATEMENT OF WORK (SOW)
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET UCC and CPC MDOS Letters to FileNet PROJECT MANAGER STATEMENT OF WORK (SOW) A Pre-Qualification Program was developed to provide a mechanism for
DELAWARE COUNTY DIVISION OF ENVIRONMENTAL SERVICES PREQUALIFICATION AND QUALIFICATIONS-BASED SELECTION PROCEDURE FOR PROFESSIONAL DESIGN SERVICES
DELAWARE COUNTY DIVISION OF ENVIRONMENTAL SERVICES PREQUALIFICATION AND QUALIFICATIONS-BASED SELECTION PROCEDURE FOR PROFESSIONAL DESIGN SERVICES Rev. Date 4/14/2014 TABLE OF CONTENTS: Article 1: Introduction
ESCO BASE CONTRACT FOR AS-NEEDED ENERGY PERFORMANCE CONTRACTING SERVICES
ATTACHMENT A ESCO BASE CONTRACT FOR AS-NEEDED ENERGY PERFORMANCE CONTRACTING SERVICES The Energy Services Coalition offers a collection of model procurement and contracting documents that represent Best
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management
Project Management Manual for Design and Construction Projects. (Revised August 2010)
Project Management Manual for Design and Construction Projects (Revised August 2010) Table of Contents 1. Overview...5 1.1 Introduction... 6 1.2 Design and Construction Process... 7 1.3 Project Delegation
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
Supplier Performance Management Guide
Supplier Performance Management Guide DRAFT PR04-503 (Nov14) PR04-503 (Nov 14) Page 1 of 11 Contents 1 Introduction... 3 1.1 ATPACE Responsibilities... 3 2 Completing Performance Evaluations... 4 2.1 Performance
Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.
SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description
Provision of Accounts Payable Service
Oman LNG LLC Pre-Qualification of Tenderers NGF-14-761 Provision of Accounts Payable Service GUIDELINES Response to this questionnaire shall be completed in English by a senior member of your company.
LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION
LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION 1985 Edition INCLUDING ADDENDA ONE AND TWO M.J. AMike@ Foster, Jr. Governor Mark C. Drennen, Commissioner of Administration
ALABAMA STATE DEPARTMENT OF EDUCATION
ALABAMA STATE DEPARTMENT OF EDUCATION CONSTRUCTION REQUIREMENTS FOR COUNTY AND CITY PUBLIC SCHOOLS PROJECTS TOTALLY FUNDED WITH LOCAL FUNDS AND SUBMITTAL OF ALL PLANS AND SPECIFICATIONS Thomas R. Bice,
REQUEST FOR EXPRESSIONS OF INTEREST 4887 EOI NETWORK BACKUP/EMAIL ARCHIVING
4887 EOI REQUEST FOR EXPRESSIONS OF INTEREST 4887 EOI NETWORK BACKUP/EMAIL ARCHIVING Expressions of Interest will be received at the Information Counter, Main Floor, Richmond City Hall, addressed to the
Procurement Processes and Tools
Methods of Procurement Purchasing Activities Procurement Processes and Tools There are different methods of procurement, which are utilized to acquire goods or services. There are many factors which determine
Construction Manager at Risk
Request for Qualifications (RFQ) Construction Manager at Risk Beaufort County Jail and Sheriff s Office Jim Chrisman, Assistant County Manager/Finance Officer Beaufort County Government Beaufort County
Section 00 61 13 2015-03-12 Contract Security
Section Cover Page Section 00 61 13 2015-03-12 Use this Section to specify security for performance of the contract and for payment of claims for labour and material, when the estimated contract cost is
STANDARD PROCUREMENT PREQUALIFICATION DOCUMENT. (Works, Heavy Equipment, Supply and Installation Contracts)
STANDARD PROCUREMENT PREQUALIFICATION DOCUMENT (Works, Heavy Equipment, Supply and Installation Contracts) Table of Contents Page INTRODUCTION 3 SECTION I - Invitation for prequalification... 4 SECTION
ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES This Professional Design Services (this "Agreement"), made as of 20 by and between the University of Cincinnati (the "University") by the Division of Administration
The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs.
SCHOOL PLANNING/SCHOOL CONSTRUCTION PROGRAMS Effective: August 14, 2014 I. Policy Statement The Board of Education is responsible for providing safe, engaging and supportive educational and work environments
Request for Proposal Architectural/Engineering Services. Adapt/SouthRiver CHC. P a g e 1
P a g e 1 Request for Proposal Architectural/Engineering Services Adapt/SouthRiver CHC RFP for Architectural/Engineering Services P a g e 2 Introduction (SRCHC), a Federally Qualified Health Center, is
International Peace Support Training Centre Westwood Park P O Box 24232-00502 Karen, Kenya
International Peace Support Training Centre Westwood Park P O Box 24232-00502 Karen, Kenya PRE-QUALIFICATION TENDER NO. IPSTC/PREQ/2014/2015/043 FOR PROVISION OF PLUMBING SERVICES FOR 2014/2015 July, 2014
CONTRACT ADMINISTRATION. Procedures
CONTRACT ADMINISTRATION Procedures Check the Capital Project Delivery web site to ensure this is the current version. Index Section Page Introduction 1 Contract Administration Final Design PS&E / Advertising
REQUEST FOR PROPOSALS FOR LANDSCAPE ARCHITECTURAL SERVICES TOWN OF AVON, CONNECTICUT
REQUEST FOR PROPOSALS FOR LANDSCAPE ARCHITECTURAL SERVICES TOWN OF AVON, CONNECTICUT The Town of Avon is seeking written responses to a Request for Proposal (RFP) for services of a landscape architect
Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows
JOB DESCRIPTION Position: Location of position: Reporting to: Special functional relationships: Term of Appointment: Programme Manager/Procurement Specialist Suva Capital Works Manager Capital Works Programme
EXPRESSION OF INTEREST PROVISION OF TRAINING SERVICES
The Kenya Power & Lighting Co. Ltd. EXPRESSION OF INTEREST PROVISION OF TRAINING SERVICES TENDER NO. KPLC1/5BA/42U/01/11 LIST OF CONTENTS PART I INTRODUCTION PART II SUMMARY OF THE IN-HOUSE COURSES TO
STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR
REBECCA OTTO STATE AUDITOR STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR SUITE 500 525 PARK STREET SAINT PAUL, MN 55103-2139 (651) 296-2551 (Voice) (651) 296-4755 (Fax) [email protected] (E-mail)
City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308
City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308 PURPOSE: The purpose for this specification is to establish a 36 month service contract for maintenance and
Revised Work Scope Dated April 23 rd, 2015
Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March
RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.
RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as
Project Implementation: Procurement & Contract Management. April 2012
& Contract Management April 2012 & Contract Management We would like to acknowledge the contribution of the Programme Management Department in the preparation of this presentation that will introduce some
BEST PRACTICE GUIDE 3: TENDER PROCESSES AND TENDER DOCUMENTS. RDTL MINISTRY OF FINANCE Procurement Service
RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 3: TENDER PROCESSES AND TENDER DOCUMENTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement
Contracting for Services
Contracting for Services A National State Auditors Association Best Practices Document Published by the National State Auditors Association Copyright 2003 by the National State Auditors Association. All
Within the context of this policy, the following definitions apply:
BOARD OF EDUCATION POLICY 4050 PROCUREMENT OF GOODS AND/OR SERVICES Effective: July 1, 2011 I. Policy Statement The Board of Education of Howard County expects that the funds provided to them for all goods
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
:: REQUEST FOR INFORMATION :: DEMOLITION SERVICES
:: REQUEST FOR INFORMATION :: DEMOLITION SERVICES 4200 Canal Street, Suite B New Orleans, LA 70119 PROPOSAL SUBMITTAL DEADLINE: Friday, June 15, 2012 @ 2:00pm NOTE: Proposal to be submitted in one (1)
Current Work Study Schedules and Trends in Finland
Culver City Unified School District Board Work Study Session July 6, 2015 Agenda for Tonight Current & Immediate Next Steps Communication System: Review New Web Page Summer/Current Projects Building Our
REPUBLIC OF KENYA MINISTRY OF FOREIGN AFFAIRS AND INTERNATIONAL TRADE PRE-QUALIFICATION/REGISTRATION OF SUPPLIERS FY-2015-2016/2016-2017
REPUBLIC OF KENYA MINISTRY OF FOREIGN AFFAIRS AND INTERNATIONAL TRADE PRE-QUALIFICATION/REGISTRATION OF SUPPLIERS FY-2015-2016/2016-2017 CATEGORY NO: A, B, C & D TENDER No. MFA&IT/PQ/01/2015-2017 For SUPPLY
L ARAMIE C OUNTY C OMMUNITY C OLLEGE Cheyenne Wyoming
L ARAMIE C OUNTY C OMMUNITY C OLLEGE Cheyenne Wyoming Request for Proposals to provide Landscape Architect Due Date Proposal Submissions Monday, June 15, 2015 by 5:00 p.m. RFP15-15008 Solicited by: Department
Denver Water Capital Projects Contractor Prequalification REQUEST FOR QUALIFICATIONS
RFQ Term: 9/29/2015 12/1/2019 Denver Water Capital Projects Contractor Prequalification REQUEST FOR QUALIFICATIONS Denver Water (DW), in an effort to improve the administration and efficiency, has initiated
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
Supplier Performance Management Program. CEA Edmonton Buildings Committee November 13, 2012
Supplier Performance Management Program CEA Edmonton Buildings Committee November 13, 2012 Supplier Performance Management Program - Background Consulting Services Review (Dec 14, 2009): The Office of
Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing
CITY OF DEARBORN ADVERTISEMENT FOR NATURAL GAS PROVIDER TO THE CITY OF DEARBORN, MICHIGAN Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing Agent, 2951 Greenfield, Dearborn,
EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS
EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 7 E. DESIGN
PROJECT MANAGEMENT PLAN - INSTRUCTIONAL GUIDE (Part 3)
PROJECT MANAGEMENT PLAN - INSTRUCTIONAL GUIDE (Part 3) The PMP is a resource and tool for the Project Manager to enhance the overall success and delivery of OGS D&C design projects. Part 3 s purpose is
REQUEST FOR PROPOSALS
ROWAN COUNTY 130 West Innes Street Salisbury, NC 28144 Tel: (704) 216-8174 Email: [email protected] REQUEST FOR PROPOSALS FOR REPLACEMENT OF COMMERCIAL ROOFTOP AIR CONDITIONING UNIT Issued
BOND MEASURE E CONTRACTOR OUTREACH
FREMONT UNIFIED SCHOOL DISTRICT BOND MEASURE E CONTRACTOR OUTREACH May 4, 2015 INTRODUCTIONS Therese Gain, Director of Facilities, Fremont Unified School District Carol Lemos, Administrative Assistant
EXPRESSION OF INTEREST FOR PRE-QUALIFICATION PROCESS TO HIRE INDEPENDENT AUDITORS
EXPRESSION OF INTEREST FOR PRE-QUALIFICATION PROCESS TO HIRE INDEPENDENT AUDITORS FOR CONDUCTION OF AUDIT OF 35 DISEASE DIAGNOSTIC LABORATORIES WORKING UNDER LIVESTOCK AND DAIRY DEVELOPMENT DEPARTMENT,
OHIO DEPARTMENT OF YOUTH SERVICES REQUEST FOR PROPOSALS
OHIO DEPARTMENT OF YOUTH SERVICES REQUEST FOR PROPOSALS ADDENDUM # 1 RFP NUMBER: DYS110104 ADDENDUM ISSUE DATE: September 3, 2010 Reference: MEDICAL TRANSCRIPTION SERVICES FOR ODYS This addendum is issued
COUNTY ASSEMBLY OF MARSABIT P.O.BOX 29 MARSABIT
COUNTY ASSEMBLY OF MARSABIT P.O.BOX 29 MARSABIT PREQUALIFICATION OF BIDDERS FOR PROVISION OF OFFICE MEDICAL INSURANCE SERVICES FOR THE FINANCIAL YEAR 2014-2015 BIDER S NAME:. CATEGORY NO:.. MBT/CA/50/2014-2015
ADDENDUM TO: REQUEST FOR PROPOSAL (RFP) COMPUTER AIDED DISPATCH/RECORDS MANAGEMENT SYSTEM (CAD/RMS)
ADDENDUM TO: REQUEST FOR PROPOSAL (RFP) COMPUTER AIDED DISPATCH/RECORDS MANAGEMENT SYSTEM (CAD/RMS) Addendum Number: 3 Date Issued: February 6, 2015 I. This addendum is hereby made as part of the bid packet
How to do Business. with Charlotte-Mecklenburg Utilities. http://cmucontracts.charmeck.org
How to do Business with Charlotte-Mecklenburg Utilities http://cmucontracts.charmeck.org How Charlotte-Mecklenburg Utilities Purchases Products and Services 2 & 3 l About Water and Sewer Projects 4 & 5
Construction Management and project process
Construction Management and project process Presented by: Vourvoutsiotis Apostolos GSO University of Applied Science Nürnberg 06.04.2000 Table of Contents Construction Management and project process Construction
REQUEST FOR PROPOSAL
REQUEST FOR PROPOSAL RFP ISSUE DATE: September 26 th, 2001 TITLE: RFP NUMBER: San José State University Website Redesign F-WR00001181-AL PURCHASING OFFICE CONTACT: DEPARTMENT OFFICIAL: Alex Lebedeff, Mary
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT CONSTRUCTION AUDIT PROGRAM
GENERAL: Some of the Districts largest capital expenditures are from new construction, facility upgrades, and renovations. A single project can run into the millions of dollars, involving engineering,
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and
AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff
11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Competitive Negotiations and Competitive Dialogue (overview based on OPM) Dialogue 2 Involve simultaneous negotiation (dialogue)
Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds
STAFF REPORT June 22, 2005 To: From: Subject: Administration Committee Deputy City Manager and Chief Financial Officer Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds Purpose:
Training Management Guidelines
Training Management Guidelines February 2009 Training Management Guidelines - February 2009 These guidelines provide a strategic approach to training and skills development in the construction industry
Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
REGIONAL MUNICIPALITY OF WOOD BUFFALO VENDOR / CONTRACTOR PERFORMANCE EVALUATION FOR SERVICES & CONSTRUCTION
REGIONAL MUNICIPALITY OF WOOD BUFFALO VENDOR / CONTRACTOR EVALUATION FOR SERVICES & CONSTRUCTION ALL FIELDS ARE MANDATORY Contractor Name: Contract Title and Number: Purchase Order Number: Contract Term:
REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Various Projects RFQ/RFP No. 15-16-02
Banning Unified School District 161 West Williams Street, Banning, CA 92220 (951) 922-2706 phone (951) 922-0227 fax January 12, 2016 REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT
Work Breakdown Structure Element Dictionary Construction
Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor
Exhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
How To Get Construction Procurement Services
Construction Procurement William C. Charvat, AIA, CSI Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 The procurement of construction services brings together the team
