Project Management Guidelines

Size: px
Start display at page:

Download "Project Management Guidelines"

Transcription

1 Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW. I. Cover Page The Project Management Plan (PMP) is a critical document that aids the Project Manager in managing the project. It is a documentation of the understanding of the expectations of cost, scope and time and provides a roadmap to the project s success. Establishing a baseline will allow the Project Manager to permanently capture and store these constraints for future use such as impact analysis of a potential change in the project. The change must be documented by stating the effect on cost, schedule and scope after proceeding through the pre-defined Change Management Process. The Project Manager should negotiate the PMP with the State Project Manager so that expectations can be set; and cost, schedule, and scope targets can be maintained. Once completed, any approved change order is stored in an appendix to the PMP. The Contractor must provide a Project Management Plan to demonstrate to the State that the Contractor has a clear understanding of the overall complexity of the project and all associated tasks to successfully implement the requirements in this RFP. The Project Management Plan must address the operational aspects of the project and must address all major sections of this RFP. The Project Management Plan must be approved by the State Contract Manager and must be continuously updated by the Contractor throughout the duration of the project. The Project Management Plan is a living document that charts the path of the project and contains the project s baseline at various points in time. As the project changes, the Project Management Plan is referenced to help determine the impact of those changes on cost, schedule, and scope. If the change is agreed upon, the plan is edited and its contents rebaselined. The project then continues under new constraints. The contents and size of the Project Management Plan will vary from project to project. The effort to create the plan must be weighed against the size and complexity of the project. A two week project may only need a 2-3 page Project Management Plan while a multi-phase, multiyear project, filled with risk and complexity may warrant a much bigger PMP. Depending upon the size of the project, the PMP should contain the following sections: II. Table of Contents III. Document Change History IV. Executive Summary

2 V. Project Work Plan VI. Facility Management Plan VII. Issues Management Plan VIII. Transition Plan IX. Communication Plan X. Weekly Status Reporting XI. Requirements Management Plan XII. Change Management Plan XIII. Issues Management Plan XIV. Risk Management Plan XV. Training Plan XVI. Maintenance and Operations Plan XVII. Administrative Completion Reporting APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award in the system development lifecycle, the State expects a Project Management Plan that describes the approach and methodology for seventeen (17) key aspects of the project management effort associated with a project as determined necessary by the Project Steering Committee, which are numbered I through XVII in the document structure listed above. A description of each key aspect, along with the associated requirements, can be found below. The Contractor will be provided the opportunity to update the Project Management Plan in Requirements and Planning Phase; and in doing so, will begin to provide a history of document issuance and change(s). Project Management Plan Requirements: The Contractor Must 1. Prepare and deliver a Project Management Plan during the Pre-Award Phase. 2. Starting in Requirements Analysis and Design Phase and for the duration of the System Development Life Cycle, provide an update to the Project Management Plan following the implementation of any change or configuration that impacts the Project Management Plan. 3. Track each deliverable of the Project Management Plan in Microsoft Project format (or a similar software package or application with Contractor provided licenses). All updates must be presented for review at the weekly status meeting.

3 4. Cooperate with the IV&V (Independent Validation and Verification) Contractor and provide access to staff, documentation, and deliverables, as directed by the State. 5. Describe the management process for obtaining approval of the deliverables, as well as any go/no-go decision points in the project. 6. Update the Project Management Plan and identify the status of all activities and milestones associated with the Project Management Plan. 7. The Project Management Plan must include a cover page that contains a title, issuance date, and version number. 8. The Project Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents. 9. The Project Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan. 10. The Project Management Plan must include an executive summary, including the purpose of the plan, and the contents of the document. 11. The Project Management Plan must include a section Project Work Plan (aka Schedule), and follow the content and requirements defined below. 12. The Project Management Plan may include a section Facility Management Plan, (if applicable) and follow the content and requirements defined below. 13. The Project Management Plan must include a section Transition Plan, and follow the content and requirements defined below. 14. The Project Management Plan must include a section Communication Management Plan, and follow the content and requirements defined below. 15. The Project Management Plan must include a section Weekly Status Reporting, and follow the content and requirements defined below. 16. The Project Management Plan must include a section Requirements Management Plan, and follow the content and requirements defined below. 17. The Project Management Plan must include a section Change Management Plan, and follow the content and requirements defined below. 18. The Project Management Plan must include a section Issues Management Plan, and follow the content and requirements defined below. 19. The Project Management Plan must include a section Risk Management Plan, and follow the content and requirements defined below. 20. The Project Management Plan must include a section Training Plan, and follow the content and requirements defined below. 21. The Project Management Plan must include a section Maintenance and Operations Plan, and follow the content and requirements defined below. 22. The Project Management Plan may include a section Certification Readiness, and follow the content and requirements defined below. 23. The Project Management Plan must include a section Administrative Completion Reporting, and follow the content and requirements defined below. Project Work Plan Requirements The Contractor must provide a Project Work Plan to help guide the project team through the execution, operations and closure phases of the project. The Project Work Plan is a set of plans to help manage

4 staff, and subcontractors if applicable, to ensure that the project is delivered on time and within budget. The Project Work Plan must be broken down into specific tasks and sub-tasks, including the identification of project deliverables, and assignment of allocated resources to each task. The Project Work Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary Overview V. Contractor s Approach a. Policies b. Procedures c. Metrics VI. Project s Critical Path a. Performance monitoring VII. Conditions and Standards for verification and compliance with any mandates (if applicable) VIII. Work Breakdown Structure a. Deliverables b. Tasks and subtasks c. Proposed Milestones d. Schedules e. Resources IX. Project Scope a. Procedures and resources b. Applications and tools X. Implementation of modules and components XI. Weekly Status Reporting

5 a. Approach b. Tools c. Examples APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle the State expects an approach and methodology of the Project Work Plan which will help guide the project team for the duration for the System Development Life Cycle. The approach and methodology must cover all aspects of the Project Work Plan. PLAN AND PROCESS During the Planning phase and through Maintenance and Operations Phase, the Contractor must prepare and deliver a Project Work Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and process associated with the approach and methodology previously described in the Project Management Plan for the work plan. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section with the approved Project Work Plan. The Contractor must: 2.1 Describe its approach and methodology for the work plan management in Pre Award Phase, which will help guide the project team for the duration of the System Development Life Cycle. 2.2 Prepare and deliver the PWP during Planning Phase and update as needed for the life of the project. 2.3 Create a Work Breakdown Structure (WBS) developed in Microsoft Project, or equivalent format acceptable to the State, which includes: all deliverables; tasks and subtasks; proposed milestones; associated dependencies; and resources assigned to each task and subtask to be performed during Pre- Award Phase and through Maintenance and Operations Phase 2.4 Update the Project Management Plan and identify the status of all activities and milestones associated with the PWP, as necessary. 2.5 The PWP must include a cover page that contains a title, issuance date, and version number. 2.6 The PWP must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents. 2.7 The PWP must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan. 2.8 The PWP must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document.

6 2.9 The PWP must include a project overview that includes a narrative description of its overall management approach, policies, procedures, and project metrics The PWP must document the project s critical path and include a performance monitoring plan The PWP must include a description and organization of the Work Breakdown Structure (WBS) The PWP must describe the business processes and procedures for controlling the scope of the project The PWP must describe how changes in project scope will be presented to the State, including prioritization of changes, budget and schedule implications The PWP must describe the Contractor s approach for the phased implementation of modules and components The PWP must describe any applications and/or tools that will be used to control scope The PWP must include the approach to weekly status reporting and tools that will be used as part of the reporting methodology The PWP must include examples of the weekly status report(s) that will be used throughout all phases of the project. The report(s) must include a summarization of the progress and status of all activities, milestones and achievements, schedule risks, schedule status of all activities related to the enterprise scope of work, documented problems encountered and the resulting impact, as well as corrective measures taken. Facility Management Plan Requirements (If needed) The Contractor must provide a Facility Management Plan that will include all activities, resources and schedules supporting the establishment and maintenance of the project office and facilities for the development, implementation and operations of the Project. The Contractor will be required to provide a fully functional and operational facility for the Project. The Project Facility will house the entire Project Team including NJ State Project staff, Contractor staff, and any other Project Contractors. The Contractor must establish a primary project facility in a location approved by the State Contract Manager. The Contractor must maintain an office in New Jersey. The Contractor s proposals must include strategies to rapidly procure adequate space for key and core State and Contractor staff during the initial phases of project development. The State reserves the right to inspect all facilities at any time. Successful completion of this deliverable will ensure that the Project Team has an adequate facility in which to work. The Facility Management Plan must adhere to the following outlined structure:

7 I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary V. Roles and Responsibilities VI. Contractor s Approach VII. Approach and Methodology APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the project, the State expects an approach and methodology to facility management for the duration of the System Development Life Cycle. The approach and methodology must cover all aspects of facility management. PLAN AND PROCESS During Planning Phase, the Contractor must prepare and deliver a Facility Management Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and processes associated with the approach and methodology previously described in the Project Management Plan for facility management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for facility management with the approved Facility Management Plan. REQUIREMENTS 3.1 The Facility Management Plan must include a cover page that contains a title, issuance date, and version number. 3.2 The Facility Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents. 3.3 The Facility Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan. 3.4 The Facility Management Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document.

8 3.5 The Facility Management Plan must include the Contractor s approach and methodology to the requirements above and the process of maintaining compliance with these requirements. Transition Plan Requirements The Contractor must provide a Transition Plan to describe an approach for knowledge transfer, and for evaluating the risks and issues involved in the Project transition, and the strategies to minimize disruption to the normal business operations of the State during Project integration, implementation, and cutover activities. The Contractor must develop and implement its approach to transition planning and provide the State with the ability to monitor business operations throughout the project phases and life of the Contract. The Transition Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Documents Change History IV. Executive Summary V. Contractor s Approach VI. Major Activities and Milestones VII. Roles and Responsibilities VIII. Proposed Sequence and Schedule by Transition Phase-In IX. Communication X. Business Process Transition XI. Technical Transition XII. Staff Transition APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the Project, the State expects an approach and methodology for initiating and maintaining normal business operations during Project transition for the duration of the System

9 Development Life Cycle. The approach and methodology must cover all aspects of transition management, including transition items, transition reporting, and transition auditing. PLAN AND PROCESS During Planning Phase, the Contractor must prepare and deliver a Transition Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and processes associated with the approach and methodology previously described in the Project Management Plan for transition management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for transition management with the approved Transition Plan. REQUIREMENTS The Contractor must: 4.1 Describe its approach and methodology for initiating and maintaining normal business operations during the Project transition. 4.2 Provide the Transition Plan during Planning Phase within 30 State work days after the effective date of the Contract, to allow appropriate knowledge transfer between the incumbent project Contractor and the new Contractor. 4.3 Participate in joint review meetings with the State and the incumbent Contractor to discuss methods to minimize disruption to the normal business operations of the State during the Project transition. 4.4 Provide major activities and milestones. 4.5 Describe the method of documenting strategies and decisions. 4.6 Identify and define the impact of each business process to be transitioned from incumbent Contractor to successor Contractor. 4.7 Identify and define the impact of each technical process to be transitioned from incumbent Contractor to successor Contractor. 4.8 Identify the proposed staff transition from incumbent Contractor to successor Contractor. 4.9 Describe the process for materials, artifacts, and equipment transfers Initiate, coordinate and host an initial Project Kickoff meeting with the State within ten (10) State business days after the contract effective date or as defined by the State Describe how appropriate knowledge transfer between the current Project Contractor and the successor Project Contractor will occur Not employ any individuals who are employees of the current Fiscal Agent without prior written consent and approval by the State Provide a transition strategy that ensures knowledge transfer, evaluating the risks and issues involved in the Project transition, and the strategies to minimize disruption to the normal business operations of the State during Project integration, implementation, and cutover activities 4.14 Update the Project Management Plan and identify the status of all activities and milestones associated with the Transition Plan, as necessary.

10 4.15 The Transition Plan must include a cover page that contains a title, issuance date, and version number The Transition Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Transition Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan The Transition Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document The Transition Plan must include a list of major activities and milestones to be achieved The Transition Plan must include a definition of roles and responsibilities of designated staff and/or teams that will manage and perform transition activities The Transition Plan must include an inventory of all transition items, categorize each item into phases for transition, include calendar schedule by phase-in, hardware, software and materials The Transition Plan must include all processes and procedures associated with communication of the transition, the workflow steps for each process, and examples of all associated forms The Transition Plan must include all processes and procedures associated with business process transition, the workflow steps for each process, and examples of all associated forms The Transition Plan must include all processes and procedures associated with technical transition, the workflow steps for each process, and examples of all associated forms The Transition Plan must include all processes and procedures associated with staff transition, the workflow steps for each process, and examples of all associated forms. Communication Management Plan Requirements The Contractor must provide a Communication Management Plan to document the methods and activities needed to ensure timely and appropriate collection, generation, dissemination, storage, and ultimate disposition of project information among the project team and stakeholders. The Contractor must develop and implement its approach to communications management. The Communication Management Plan must include strategies and tools that will be used throughout all project phases. The Communication Management Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary V. Roles and Responsibilities VI. Contractor s Approach

11 VII. Process and Procedures VIII. Tools APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the Project, the State expects an approach and methodology to ensure timely and appropriate collection, generation, dissemination, storage, and ultimate disposition of project information among the project team and stakeholders for the duration of the System Development Life Cycle. The approach and methodology must cover all aspects of communication management including the strategies and tools that will be used throughout all project phases. PLAN AND PROCESS During Planning Phase, the Contractor must prepare and deliver a Communication Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and processes associated with the approach and methodology previously described in the Project Management Plan for communication management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for communication management with the approved Communication Management Plan. REQUIREMENTS The Contractor must: 5.1 Describe its approach and methodology for communication management in Pre Award Phase, including timely and appropriate collection, generation, dissemination, storage, and ultimate disposition of project information among the project team and stakeholders for the duration of the System Development Life Cycle. 5.2 Prepare and deliver the Communication Management Plan during Planning Phase and at least 30 Days prior to start of Requirements Analysis and Design Phase. 5.3 Integrate fully all communication management processes into the Project Workflow Management System (if present and applicable). 5.4 Describe how communication with the different stakeholders will be accomplished, e.g., members, providers, state staff, vendors, throughout all phases of the lifecycle. 5.5 Describe the business processes and procedures for managing communication channels. 5.6 Update the Project Management Plan and identify the status of all activities and milestones associated with the Communication Management Plan, as necessary. 5.7 Provide tools for both internal and external communication throughout all project phases. 5.8 Update the Communication Plan annually or at the direction of the State. 5.9 Describe how the Communication Plan will be implemented and how it will be integrated into the overall Project Management Plan.

12 5.10 The Communication Management Plan must include a cover page that contains a title, issuance date, and version number The Communication Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Communication Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan The Communication Management Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document The Communication Management Plan must include a definition of roles and responsibilities as related to communications The Communication Management Plan must include all processes and procedures associated with communication management, the workflow steps for each process, and examples of all associated forms The Communication Management Plan must describe any applications and/or tools that will be used to track and report written, electronic and telephone inquiries. Weekly Status Reporting Plan Requirements The Contractor must provide weekly status reporting to summarize the progress and status of all activities, milestones and achievements, risks, and status of all activities related to the project s scope of work. The Contractor must provide a Weekly Status Reporting Plan to describe the methods and activities needed to ensure documentation of problems encountered and the resulting impact as well as corrective actions taken. The Weekly Status Reporting Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary V. Contractor s Approach VI. Roles and Responsibilities VII. Process and Procedures VIII. Applications and Tools APPROACH AND METHODOLOGY

13 In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the Project, the State expects an example of a status report. The approach and methodology of the weekly status reporting activities must be described in the Contractor s draft Project Work Plan (PWP) submitted as part of its bid response. PLAN AND PROCESS During Planning Phase, and throughout the life of the contract, the Contractor must prepare and deliver the PWP that includes the details of the weekly status reporting activities and complies with the requirements listed below. This Weekly Status Reporting Plan represents the detailed plan and processes associated with the approach and methodology previously described in the PWP. Upon approval of the PWP, the Contractor must begin generating required reports and provide an update to the Project Management Plan, as needed. REQUIREMENTS The Contractor must: 6.1 Provide an initial status report during Planning Phase within 30 State business days after the effective date of the Contract, and weekly thereafter or at a frequency designated by the State. 6.2 Provide an updated PWP during Planning Phase no later than twenty-four (24) hours prior to the status meeting. 6.3 Ensure attendance of appropriate staff as identified by State at all status reporting meetings. 6.4 Participate in weekly project status and other meetings as directed by the State. 6.5 Describe within the PWP the strategies to be used to summarize the progress and status of all activities, milestones and achievements, schedule risks, schedule status of activities related to the scope of work, and document problems encountered and the resulting impact as well as corrective actions taken. 6.6 Provide a meeting agenda, previous meeting minutes and supporting documentation no later than twenty-four (24) hours prior to the status meeting. 6.7 Submit status report in a format approved by the State Contract Manager. 6.8 Update Project Management Plan, as necessary. 6.9 The Weekly Status Reporting Plan must include a cover page that contains the following: a title; issuance date; and version number The Weekly Status Reporting Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Weekly Status Reporting Plan must include a history of changes that contains the following: identifies each issuance date: version number: and the list of changes made compared to the previous issuance and version of the plan The Weekly Status Reporting Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document The Weekly Status Reporting Plan must include a definition of roles and responsibilities as related to weekly status reporting.

14 6.14 The Weekly Status Reporting Plan must include all processes and procedures associated with weekly status reporting, the workflow steps for each process, and examples of all associated forms The Weekly Status Reporting Plan must describe any applications and/or tools that will be used for weekly status reporting. Requirements Management Plan Requirements The Contractor must provide a Requirements Management Plan to describe the approach and methodology that will be used to document and track the project requirements from initial proposal submission through design, testing, and certification to verify that all requirements have been fulfilled. The Requirements Management Plan must ensure that the technical requirements can be clearly traced to the business or functional requirements that they support and must include any unresolved traceability issues. The Contractor must submit an initial Requirements Traceability Matrix (RTM) as part of its proposal and must maintain the baseline requirements in order to directly associate the baseline to the configuration of the Project. Additions, modifications, and deletions to these requirements must be added and modified throughout the project so it is imperative that a current version of the RTM be maintained at all times. The Requirements Management Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary V. Contractor s Approach VI. Roles and Responsibilities VII. Repository VIII. Tools APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the Project, the State expects an approach and methodology for documenting and tracking project requirements for the duration of the System Development Life Cycle. The approach and methodology must cover all aspects of traceability management, including tracing requirements and unresolved issues, change management, and version control.

15 PLAN AND PROCESS During Planning Phase, the Contractor must prepare and deliver a Requirements Management Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and processes associated with the approach and methodology previously described in the Project Management Plan for requirements traceability management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for requirements management with the approved Requirements Management Plan and begin the process of traceability management within the Requirements Traceability Matrix (RTM). REQUIREMENTS The Contractor must: 7.1 Describe its approach and methodology for requirements management in Pre-Award Phase. The methodology will become the foundation for the Requirements Management Plan. 7.2 Prepare and deliver the Requirements Management Plan during Planning Phase and at least 30 Days prior to the start of Requirements Analysis and Design Phase. 7.3 Establish the initial Project baseline requirements that will serve as the basis for all subsequent configuration, integration, and testing activities. 7.4 Work with the State and its stakeholders to analyze and verify system functional and technical requirements and specifications, including business rules. 7.5 Use the RTM to ensure that all requirements can be traced to the supporting business rule or State objective. 7.6 Ensure that links for each unique requirement to other supporting requirements, including the RFP or deliverables, are established and maintained. 7.7 Document that all requirements have been verified and validated against the Requirements Traceability Matrix (RTM). If any external certification of requirements needs to occur (i.e. External Agency, Federal, State or local agencies, authorized third party, etc.) document that as well 7.8 Summarize its analysis and verification of the requirements, including any impacts to the Project design concept as proposed in its proposal to the State. 7.9 Secure additional documentation, such as clarifications, details and/or examples that help define a requirement and can be attached to the appropriate requirement(s) utilizing the RTM to identify the references to supporting documentation related to a requirement Document specifications for all requirements to support configuration activities through Planning Phase Provide an initial Requirements Traceability Matrix (RTM) as part of the Requirements Management Plan Use the Requirements Traceability Matrix (RTM) to document and track all phases of testing and evaluation Plan, schedule, and coordinate all necessary activities in this task, including the development of schedules, invitations, and locations for the appropriate analysis and review meetings.

16 7.14 Describe business processes and procedures that will be used for tracking requirements from design through coding, acceptance, unit and integration testing, as well as promotion into production Integrate fully all Requirement Managements processes in the Project Workflow Management System (if present and applicable) Describe how the Requirements Management Plan will be implemented and how it will be integrated into the overall Project Management Plan approach Update the Project Management Plan and identify the status of all activities and milestones associated with the Requirements Management Plan The Requirements Management Plan must include a cover page that contains a title, issuance date, and version number, as necessary The Requirements Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Requirements Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan The Requirements Management Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document The Requirements Management Plan must include a definition of roles and responsibilities associated with management of the matrix The Requirements Management Plan must describe how requirements will be stored in a repository and how the State and stakeholders will access the information The Requirements Management Plan must include a description of the tools associated with the RTM process and activities The Requirements Management Plan must include all processes and procedures, the workflow steps for each process, and examples of all associated forms. Change Management Plan Requirements The Contractor must provide a Change Management Plan to address contractual scope changes for the project. The Change Management Plan must define the approach, administrative procedures, and roles and responsibilities for submitting, evaluating, coordinating, approving or disapproving business and technical changes to the agreed upon solution. The Change Management Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents

17 III. Document Change History IV. Executive Summary V. Contractor s Approach VI. Roles and Responsibilities VII. Documenting Change a. Management Activities b. Workflow VIII. Training APPROACH AND METHODOLOGY In response to the Request for Proposal, in the System Development Life Cycle for the project, the State expects an approach and methodology for contractual change management for the duration of the System Development Life Cycle. The approach and methodology must cover all aspects of contractual change management, including document processing, reporting, archiving, and auditing. PLAN AND PROCESS During the Requirements Analysis and Design phase of the project, the Contractor must prepare and deliver a Change Management Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and processes associated with the approach and methodology previously described in the Project Management Plan for change management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for contractual change management with the approved Change Management Plan. REQUIREMENTS The Contractor must: 8.1 Describe and provide its approach and methodology for Change Management in their response to this RFP. The methodology will become the foundation for the Change Management Plan, and should include at a minimum: resources, time, solution, etc. 8.2 Prepare and deliver the Change Management Plan during the Requirements Analysis and Design phase of the project and at least 30 Days prior to start of the Development and Testing phase. 8.3 Provide an application tool for submitting, tracking and reporting on activities and outcomes associated with a change request that has the potential to create a change in contract scope, throughout the System Development Life Cycle.

18 8.4 Ensure that the application supports pricing estimates and key dates for a change request. 8.5 Ensure that all contractual change request activities are represented in the Project Work Plan. 8.6 Develop a controlled change process for changes set against the baseline scope of work and define and provide for a Contractor management-level Change Control Board, with associated roles and the State s and Contractor s responsibilities, including a process for managing the change and for the review of supporting documentation such as resources, estimated timeframe, estimated time and materials costs, etc. 8.7 Maintain an audit trail of all updates/changes to the project. 8.8 Document all procedures for users of the Change Management tracking application through an online version. 8.9 Provide training for users of the Change Management tool Describe how the Change Management Plan will be implemented and how it will be integrated into the overall Project Management Plan approach, including any and all COTS tools that will be used Integrate fully all change management processes in the Project Workflow Management System (if present and applicable) Update the Project Management Plan and identify the status of all activities and milestones associated with the Change Management Plan, as necessary Describe the process of analyzing scope, time and cost to support change request activities Ensure that all change request activity status is documented and reported on a regular basis The Change Management Plan must include a cover page that contains a title, issuance date, and version number The Change Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Change Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan The Change Management Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document The Change Management Plan must include a definition of roles and responsibilities.

19 8.20 The Change Management Plan must include an inventory of all change management items The Change Management Plan must include all processes and procedures associated with documenting change management activities, the workflow steps for each process, and examples of all associated forms The Change Management Plan must include all processes and procedures associated with training staff and stakeholders, the workflow steps for each process, and examples of all associated forms. Issues Management Plan Requirements The Contractor must provide an Issues Management Plan that comprehensively documents technical and administrative issues that occur as the project progresses. The Contractor must develop and implement an Issues Management Plan that describes its approach to issue resolution and provides the State with the ability to monitor resolution of issues throughout the project phases and life of the Contract. The primary goal of the plan is to ensure that the issues are identified, evaluated, assigned for resolution, monitored, documented and communicated. The Issues Management Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary Overview V. Roles and Responsibilities VI. Contractor s Approach VII. Process and Procedures VIII. Tools IX. Workflow APPROACH AND METHODOLOGY In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the Project, the State expects an approach and methodology to issue resolution with the ability to monitor resolution of issues for the duration of the System Development Life Cycle. The approach and methodology must cover all aspects of issues management to ensure that

20 issues are identified, evaluated, assigned for resolution, monitored, resolved, documented and communicated. PLAN AND PROCESS During Requirements Analysis and Design Phase and throughout the life of the contract, the Contractor must prepare and deliver an Issues Management Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and process associated with the approach and methodology previously described in the Project Management Plan for issues management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for issues management with the approved Issues Management Plan. REQUIREMENTS The Contractor must: 9.1 Describe its approach and methodology for issues management in Pre-Award Phase, ensuring that issues are identified, evaluated, assigned for resolution, monitored, resolved, documented and communicated. 9.2 Prepare and deliver the Issues Management Plan during Requirements Analysis and Design Phase and at least 30 Days prior to start of Development and Testing Phase. 9.3 Define the procedures for the escalation of an issue. 9.4 Describe how the business processes and procedures will be implemented and integrated into the overall Project Management Plan. 9.5 Identify the criteria for determining priority, severity, resolution, and category of issues. 9.6 Provide an issues management strategy, including analysis, impact assessment, mitigation, tracking/control, resolution methodology and escalation management. 9.7 Integrate fully, all issues management processes into the Project Workflow Management System (if present and applicable). 9.8 Update the Project Management Plan and identify the status of all activities and milestones associated with the Issues Management Plan, as necessary. 9.9 The Issues Management Plan must include a cover page that contains a title, issuance date, and version number The Issues Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Issues Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan The Issues Management Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document The Issues Management Plan must include a definition of roles and responsibilities.

21 9.14 The Issues Management Plan must include all processes and procedures associated with issues management, the workflow steps for each process, and examples of all associated forms The Issues Management Plan must propose an application that will record and track issues and describe how it will be utilized by all stakeholders The Issues Management Plan must include the tools to be used for the identification, definition and evaluation of project issues related to the Project. Risk Management Plan Requirements The Contractor must provide a Risk Management Plan to comprehensively document the approach to risk analysis, risk mitigation, and risk tracking/control. The Contractor must develop and implement its approach to risk analysis (i.e., the evaluation of risks and risk interactions to assess the range of possible project outcomes), risk mitigation (i.e., the identification of ways to minimize or eliminate project risks), and risk tracking/control (i.e., a method to ensure that all steps of the risk management process are being followed and risks are being mitigated effectively) and provide the State with the ability to monitor resolution of risk throughout the project phases and life of the Contract. The Risk Management Plan must ensure a clearly established process for problem escalation and must be updated, as needed, throughout the term of the contract. The Risk Management Plan must include an annual Project risk assessment. The Risk Management Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary V. Contractor s Approach VI. Process and Procedures VII. Roles and Responsibilities VIII. Annual Risk Assessment IX. Tools X. Workflow APPROACH AND METHODOLOGY

22 In response to the Request for Proposal, which the State defines as Pre-Award Phase in the System Development Life Cycle for the Project, the State expects an approach and methodology to risk management for the duration of the System Development Life Cycle. The approach and methodology must cover all aspects of risk management, including analysis, mitigation, and tracking and control. PLAN AND PROCESS During Requirements Analysis and Design Phase, the Contractor must prepare and deliver a Risk Management Plan that complies with the general and plan requirements listed below. This deliverable represents the detailed plan and processes associated with the approach and methodology previously described in the Project Management Plan for risk management. Upon approval of the plan, the Contractor must replace in the Project Management Plan the approach and methodology section for risk management with the approved Risk Management Plan. REQUIREMENTS The Contractor must: 10.1 Describe its approach and methodology for risk management in Pre-Award Phase, for all aspects of risk management, including analysis, mitigation, and tracking and control Prepare and deliver the Risk Management Plan during Requirements Analysis and Design Phase and at least 30 Days prior to start of Development and Testing Phase Describe the business processes and procedures to be used for identifying and defining, tracking, monitoring, quantifying, prioritizing, and mitigating risks Provide a risk management strategy for risk analysis, risk mitigation and risk tracking/control, including methodology and escalation management Describe its approach to various risk factors including contractual risk, technology risk, size and complexity risks, risk assessment, personnel acquisition and retention risks, and risks to achieving customer acceptance Describe how the business processes and procedures will be implemented and integrated into the overall Project Management Plan Update the Project Management Plan and identify the status of all activities and milestones associated with the Risk Management Plan, as necessary The Risk Management Plan must describe the application and/or tools and techniques that will be used for risk identification, documentation, management, analysis, logging and risk mitigation The Risk Management Plan must include a cover page that contains a title, issuance date, and version number The Risk Management Plan must include a table of contents and associated links to permit a reader to move directly to the data content from the table of contents The Risk Management Plan must include a history of changes that identifies each issuance date, version number, and the list of changes made compared to the previous issuance and version of the plan.

23 10.12 The Risk Management Plan must include an executive summary, including the purpose of the plan, the approach and methodology, and the contents of the document. The Risk Management Plan must describe the processes and procedures that will be used for risk assessment The Risk Management Plan must include a definition of roles and responsibilities The Risk Management Plan must describe processes that will be completed annually for the Project risk assessment The Risk Management Plan must include all processes, procedures, and tools associated with risk management, the workflow steps for each process, and examples of all associated forms. Training Plan Requirements The Contractor must provide a Training Plan to describe the strategy for training the project staff, State users, providers, and other stakeholders on using any and all aspects of the Project. The Training Plan must cover both the system training for all users and providers and operations training for all subcontractors, if applicable, as well as State operations personnel. The Training Plan must describe training approaches, including video conferencing, face-to-face presentations, and self-directed tutorials. The training plan must include both initial and ongoing training strategies. Since the training requirements will vary based on the project phase, the plan must be organized by project phase. The Training plan must provide an integrated training approach covering the different modules in the Project and include training for unique module areas. The Training Plan must adhere to the following outlined structure: I. Cover Page II. Table of Contents III. Document Change History IV. Executive Summary V. Contractor s Approach VI. Roles and Responsibilities VII. Training Environment VIII. Tools IX. Documentation and Artifacts X. Reporting and Evaluation APPROACH AND METHODOLOGY

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT GERARD M. HILL CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Croup, an informa business

More information

Template K Implementation Requirements Instructions for RFP Response RFP #

Template K Implementation Requirements Instructions for RFP Response RFP # Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES 1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 - ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and

More information

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP TSE015 PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP Course Outline I. Introduction and Course Objectives A. About PMI B. PMP and CAPM

More information

Appeals Case Management System Project. Scope Management Plan. November 20, 2014

Appeals Case Management System Project. Scope Management Plan. November 20, 2014 Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF

More information

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997 Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then

More information

VA ICJIS. Program Management Plan

VA ICJIS. Program Management Plan VA ICJIS Program Management Plan 1 08/29/01 Program Management Plan VA Integrated Criminal Justice Information System (ICJIS) Program 1. Introduction. The Commonwealth of Virginia Integrated Criminal Justice

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840

STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles

More information

Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012

Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012 Minnesota Health Insurance Exchange Project (MNHI) Deliverable Definition Document (DDD) For Project Plan Date: 07-31-2012 11/9/2012 1:18 PM Page 1 of 8 1. High Level Deliverable Description The Project

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.

This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>. Guide to Preparing the SOFTWARE PROJECT MANAGEMENT PLAN R. Buckley CSc 190 Senior Project Department of Computer Science - College of Engineering and Computer Science California State University, Sacramento

More information

Crosswalk Between Current and New PMP Task Classifications

Crosswalk Between Current and New PMP Task Classifications Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the

More information

Appendix 2-A. Application and System Development Requirements

Appendix 2-A. Application and System Development Requirements Appendix 2-A. Application and System Development Requirements Introduction AHRQ has set up a Distributed Systems Engineering Lab (DSEL) to support all internal development efforts and provide a facility

More information

SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK

SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK Office of Safety and Mission Assurance NASA-GB-9503 SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK AUGUST 1995 National Aeronautics and Space Administration Washington, D.C. 20546 PREFACE The growth in cost

More information

Positive Train Control (PTC) Program Management Plan

Positive Train Control (PTC) Program Management Plan Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information

More information

Design Consultant Project Management Requirements

Design Consultant Project Management Requirements Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0

More information

Biometrics Enterprise Architecture Project Management Plan (BMEA PMP)

Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible

More information

Assessment of NCTD Program Management Framework for Positive Train Control Program

Assessment of NCTD Program Management Framework for Positive Train Control Program Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

Terms of References for Infrastructure Expert

Terms of References for Infrastructure Expert 1. BACKGROUND Terms of References for Infrastructure Expert Sustainable Development Account Moldova (SDA Moldova) (hereinafter the institution) is a public entity established by the Government of the Republic

More information

IT Project Management Practices Guide

IT Project Management Practices Guide IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) Project Status Report Week Ending: 09-19-2012 Page - 1 Executive Summary The Executive Summary provides an executive level review of general project activities,

More information

Project Knowledge Areas

Project Knowledge Areas From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.

More information

PMP Examination Tasks Puzzle game

PMP Examination Tasks Puzzle game PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in

More information

CONFIGURATION MANAGEMENT PLAN GUIDELINES

CONFIGURATION MANAGEMENT PLAN GUIDELINES I-680 SMART CARPOOL LANE PROJECT SYSTEM ENGINEERING MANAGEMENT PLAN CONFIGURATION MANAGEMENT PLAN GUIDELINE SECTIONS: PLAN GUIDELINES 1. GENERAL 2. ROLES AND RESPONSIBILITIES 3. CONFIGURATION MANAGEMENT

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Customer Account Data Engine 2 Systems Development Guidelines; However, Process Improvements Are Needed to Address Inconsistencies September 30, Year

More information

Integrity 10. Curriculum Guide

Integrity 10. Curriculum Guide Integrity 10 Curriculum Guide Live Classroom Curriculum Guide Integrity 10 Workflows and Documents Administration Training Integrity 10 SCM Administration Training Integrity 10 SCM Basic User Training

More information

Software Project Management Plan (SPMP)

Software Project Management Plan (SPMP) Software Project Management Plan (SPMP) The basic template to be used is derived from IEEE Std 1058-1998, IEEE Standard for Software Project Management Plans. The following is a template for the SPMP.

More information

<Company Name> <Project Name> Software Development Plan. Version <1.0>

<Company Name> <Project Name> Software Development Plan. Version <1.0> Version [Note: The following template is provided for use with the Rational Unified Process. Text enclosed in square brackets and displayed in blue italics (style=infoblue)

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

CONTENTS. Preface. Acknowledgements. 1. Introduction and Overview 1 Introduction 1 Whatis the CMMI"? 2 What the CMMI* is Not 3 What are Standards?

CONTENTS. Preface. Acknowledgements. 1. Introduction and Overview 1 Introduction 1 Whatis the CMMI? 2 What the CMMI* is Not 3 What are Standards? Preface Acknowledgements xi xiii 1. Introduction and Overview 1 Introduction 1 Whatis the CMMI"? 2 What the CMMI* is Not 3 What are Standards? 3 2. Summaryof CMMI-SW 5 The CMM*-SW 5 CMMI--SW Continuous

More information

Scope of Work Microsoft Infrastructure Upgrade

Scope of Work Microsoft Infrastructure Upgrade Introduction Scope of Work Microsoft Infrastructure Upgrade The University of Texas M. D. Anderson Cancer Center (M. D. Anderson) in Houston, Texas, celebrating six decades of Making Cancer History, is

More information

Project Management Concepts, Methods, and Techniques

Project Management Concepts, Methods, and Techniques Project Management Concepts, Methods, and Techniques Claude H. Maley Uffi\ CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Croup, an Informa

More information

Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.

Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition. Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

<PROJECT NAME> PROJECT MANAGEMENT PLAN

<PROJECT NAME> PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Management Plan was controlled and tracked.

More information

Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201

Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 PURCHASE ORDER ATTACHMENT Q-201A Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 1. A qualified employee shall be selected by the Software Quality Manager

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

REQUEST FOR PROPOSALS. Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3

REQUEST FOR PROPOSALS. Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3 REQUEST FOR PROPOSALS Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3 EXHIBITS EXHIBIT 1 EXHIBIT 2 EXHIBIT 3 Glossary of Terms and Acronyms Contract Discrepancy

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2

VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2 VoteCal Statewide Voter Registration System Project Master Project Management Plan Version 1.2 October 2010 October 2010 i REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 0.1 3/12/2009

More information

POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections

POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections Policy Subject: Policy Number: Project Management 1.1.5 Date of Issue: Authority: Effective Date: May 29, 2009 Signature on File

More information

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the

More information

Construction Management System (CMS) Deliverable Review Process

Construction Management System (CMS) Deliverable Review Process Construction Management System (CMS) Deliverable Review Process State of California Department of Transportation Division of Construction December 21, 2009 Version 1.0 Approvals Name: Title: Mark Leja

More information

Request for Resume (RFR) for Project Manager (Senior) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information

Request for Resume (RFR) for Project Manager (Senior) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information Request for Resume (RFR) for Project (Senior) Section General Information RFR Number: (Reference BPO Number) Functional Area (Enter One Only) Q00R00 BPO # 060B900 in ADPICS Functional Area 0 IT Management

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

Project Management Methodology

Project Management Methodology Project Management Methodology 1/6/2015 PAGE 1 OF 28 Version 2.0 Contents INTRODUCTION... 4 1. Overview... 4 PHASE 1 PROJECT INITIATION... 5 1. Governance Model... 6 2. Project Prioritization Process...

More information

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE

More information

The Project Management Plan will be used to guide, communicate and coordinate project efforts.

The Project Management Plan will be used to guide, communicate and coordinate project efforts. F.1 General Implementation Contractor Deliverables include critical system planning and development components. Sufficient deliverables have been identified at key steps in the project to guide the project

More information

Management. Project. Software. Ashfaque Ahmed. A Process-Driven Approach. CRC Press. Taylor Si Francis Group Boca Raton London New York

Management. Project. Software. Ashfaque Ahmed. A Process-Driven Approach. CRC Press. Taylor Si Francis Group Boca Raton London New York Software Project Management A Process-Driven Approach Ashfaque Ahmed CRC Press Taylor Si Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor St Francis Croup, an Informa business

More information

City of Casper, Wyoming. Request for Proposals. for. Food Service Point of Sale Solution

City of Casper, Wyoming. Request for Proposals. for. Food Service Point of Sale Solution City of Casper, Wyoming Request for Proposals for Food Service Point of Sale Solution The City of Casper, Wyoming (hereinafter referred to as City ) is seeking qualification statements and service proposals

More information

SOFTWARE ASSURANCE STANDARD

SOFTWARE ASSURANCE STANDARD NOT MEASUREMENT SENSITIVE National Aeronautics and NASA-STD-8739.8 w/change 1 Space Administration July 28, 2004 SOFTWARE ASSURANCE STANDARD NASA TECHNICAL STANDARD REPLACES NASA-STD-2201-93 DATED NOVEMBER

More information

Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis

Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for

More information

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading

More information

IT Project: System Implementation Project Template Description

IT Project: System Implementation Project Template Description 2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation

More information

Office of Small and Disadvantage Business Utilization (OSDBU) Logistics Support Contract

Office of Small and Disadvantage Business Utilization (OSDBU) Logistics Support Contract Office of Small and Disadvantage Business Utilization (OSDBU) Logistics Support Contract 1. Introduction. The Department of Veteran Affairs (VA) Office of Small and Disadvantaged Business Utilization (OSDBU)

More information

ID Task Name Time Pred

ID Task Name Time Pred 0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive

More information

PHASE 8: IMPLEMENTATION PHASE

PHASE 8: IMPLEMENTATION PHASE PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the

More information

Independent Verification and Validation of SAPHIRE 8 Software Project Plan

Independent Verification and Validation of SAPHIRE 8 Software Project Plan INL/EXT-09-17022 Rev. 2 Independent Verification and Validation of SAPHIRE 8 Software Project Plan March 2010 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance

More information

ADVANCED CUSTOMER SUPPORT ORACLE FUNCTIONAL HELP DESK EXHIBIT

ADVANCED CUSTOMER SUPPORT ORACLE FUNCTIONAL HELP DESK EXHIBIT ADVANCED CUSTOMER SUPPORT ORACLE FUNCTIONAL HELP DESK EXHIBIT This exhibit incorporates by reference the terms of the order for Oracle Functional Help Desk services. A. Definitions. End Users means those

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

DRAFT REGULATORY GUIDE

DRAFT REGULATORY GUIDE U.S. NUCLEAR REGULATORY COMMISSION August 2012 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE Contact: K. Sturzebecher (301) 251-7494 DRAFT REGULATORY GUIDE DG-1206 (Proposed Revision

More information

Medicaid Eligibility and Enrollment (EE) Implementation Advanced Planning Document (IAPD) Template. Name of State Medicaid Agency:

Medicaid Eligibility and Enrollment (EE) Implementation Advanced Planning Document (IAPD) Template. Name of State Medicaid Agency: Name of State: Name of State Medicaid Agency: Name of Contact(s) at State Medicaid Agency: E-Mail Address(es) of Contact(s) at State Medicaid Agency: Telephone Number(s) of Contact(s) at State Medicaid

More information

Project Management Certificate (IT Professionals)

Project Management Certificate (IT Professionals) Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: Support@Nutek-us.com

More information

Eastern Illinois University EISE Configuration Management Plan

Eastern Illinois University EISE Configuration Management Plan Eastern Illinois University EISE Configuration Management Prepared by: Bill Witsman Version: 10.0 Create Date: April 13, 2005 Approval Date: Last Revision Date: December 17, 2009 CM Analyst: Project Manager:

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

Program Management Professional (PgMP) Examination Content Outline

Program Management Professional (PgMP) Examination Content Outline Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...

More information

Request for Proposal for Application Development and Maintenance Services for XML Store platforms

Request for Proposal for Application Development and Maintenance Services for XML Store platforms Request for Proposal for Application Development and Maintenance s for ML Store platforms Annex 4: Application Development & Maintenance Requirements Description TABLE OF CONTENTS Page 1 1.0 s Overview...

More information

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) is the processes required to ensure that the various elements of the project are properly coordinated. the processes required to ensure

More information

Project Management Plan for the VDI Data Center Project

Project Management Plan for the VDI Data Center Project Project Management Plan for the VDI Data Center Project Prepared by: Moe Yousof A paper submitted to the Project Management Training Program in partial fulfillment of the requirements for the Project Management

More information

8. Master Test Plan (MTP)

8. Master Test Plan (MTP) 8. Master Test Plan (MTP) The purpose of the Master Test Plan (MTP) is to provide an overall test planning and test management document for multiple levels of test (either within one project or across

More information

output: communications management plan

output: communications management plan Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project

More information

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute

More information

Regulatory Guide 1.169 Configuration Management Plans for Digital Computer Software Used in Safety Systems of Nuclear Power Plants

Regulatory Guide 1.169 Configuration Management Plans for Digital Computer Software Used in Safety Systems of Nuclear Power Plants Regulatory Guide 1.169Configuration Managemen... Page 1 of 10 September 1997 Regulatory Guide 1.169 Configuration Management Plans for Digital Computer Software Used in Safety Systems of Nuclear Power

More information

CONTENTS. List of Tables List of Figures

CONTENTS. List of Tables List of Figures Prelims 13/3/06 9:11 pm Page iii CONTENTS List of Tables List of Figures ix xi 1 Introduction 1 1.1 The Need for Guidance on ERP System Validation 1 1.2 The Need to Validate ERP Systems 3 1.3 The ERP Implementation

More information

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information